RFQ946500-01 - DAS TMVC Floor Slab Repair.pdf
PDF 2 MB Posted
- Attached to
- DAS TMVC Floor Slab Repair
- Solicitation number
- RFQ946500-01
- Issued by
- Taylor County, Iowa
About this file
This Request for Quote (RFQ946500-01) is issued by the Iowa Department of Administrative Services (DAS) for floor slab repair services at the Toolesboro Mounds Visitor Center located at 6568 Toolesboro Ave, Highway 99, Wapello, Iowa 52653. The project scope includes removing existing carpeting, poly jacking the existing concrete floor slab to address settlement issues, and installing new luxury vinyl tile (LVT) flooring and vinyl base throughout the building. A pre-quote site meeting is scheduled for March 25, 2026, at 11:00 AM. Quotes must be submitted via the Iowa IMPACS Procurement System by April 2, 2026, at 2:00 PM Central Time. All questions regarding the solicitation must be received by email no later than March 26, 2026, at 2:00 PM Central Time. Work is required to be completed no later than May 15, 2026. The State intends to make one award for this project and reserves the right to reject any or all quotes without penalty.
Pricing shall be submitted on the designated Exhibit A pricing form with all costs delivered to the site (FOB Destination, Freight Pre-Paid). The procurement will result in a Consensus 802 Agreement, and respondents must provide a Performance and Payment Bond in accordance with Section 10.8 of that agreement. Insurance requirements include specified limits, additional insured requirements, and waiver of subrogation as detailed in the sample Certificate of Insurance (Exhibit D). Work hours are restricted to 7:00 AM to 5:30 PM, Monday through Friday, with no work permitted on State of Iowa recognized holidays. The Owner intends to occupy the facility upon substantial completion, and the contractor must coordinate operations to minimize disruption. The State will provide electrical power and water to the contractor on site, and the contractor is responsible for disposing of all debris and removed materials.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ946500-01 - Addendum 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
March 11, 2026
To: All Potential Respondents
From: Construction Procurement
Subject: RFQ946500-01 DAS TMVC Floor Slab Repair (Toolesboro Mounds Visitor Center)
Request for Quote
The State of Iowa is conducting a Request for Quote for a contractor to remove existing carpeting; poly jack the existing concrete floor slab and install new LVT flooring and vinyl base throughout the building. See Exhibit B for additional detail.
The WORK REQUIREMENTS shall be completed no later than May 15, 2026.
The Project is located at 6568 Toolesboro Ave, Hwy 99, Wapello, IA 52653
A Pre-quote on site meeting will be held March 25, 2026 @ 11:00 AM.
Please upload your quote on the Exhibit A pricing form of this solicitation utilizing the Iowa IMPACS Procurement
System (https://bids.sciquest.com/apps/Router/PublicEvent?CustomerOrg=DASIowa) prior to April 2, 2026 at
2:00 PM (CT).
All questions regarding this solicitation must be received by email by 2:00 PM (CT) ON March 26, 2026.
Contract Terms and Conditions
This procurement will result in a Consensus 802 Agreement. By submitting a quote, respondent agrees to the contract terms and conditions available at https://das.iowa.gov/sites/default/files/procurement/pdf/ConsensusDoc802.pdf
Performance Bond
Respondent must provide a Performance and Payment Bond in accordance with Section 10.8 of Consensus 802
Agreement.
Insurance Requirements
See sample Certificate of Insurance attached as Exhibit D for required limits, additional insured requirements and waiver of subrogation.
Exhibit A Pricing Form
TMVC Floor Slab Repair
6568 Toolesboro Ave, Hwy 99, Wapello, IA 52653
Request for Quote RFQ946500-01
Due April 2, 2026, at 2:00 PM (CT)
Please submit this completed form with your Quote to:
Iowa IMPACS Procurement System
(https://bids.sciquest.com/apps/Router/PublicEvent?CustomerOrg=DASIowa)
This form is to be completed in ink or typewritten.
Only pricing on this form or an exact copy of this form will be accepted.
Pricing Form shall be signed by an officer of the firm with authority to bind Respondent to Contract.
Respondent acknowledges receipt of the following Addenda (if issued) which are part of the RFQ documents:
Addendum No. _______________ Date_____________________
Addendum No. _______________ Date _____________________
Freight Terms: FOB Destination, Freight Pre-Paid
The State reserves the right to reject any or all quotes without penalty and to waive minor deficiencies and informalities if, in the judgement of the State, it's best interests will be served.
Respondents must submit pricing for all scope of work items indicated per the attached Exhibit B. The State reserves the right to evaluate pricing. The State intends to make one Award for this project.
BP-01 - TMVC Floor Slab Repair:
Total $_________________________________________________________________________________
*Please note all pricing is to be delivered price. That is why we are stating FOB Destination, Freight Pre-Paid. *
Signature _______________________________________________
Name (Print) ____________________________________________
Title __________________________________________________
Company _______________________________________________
Address ________________________________________________
City, St., Zip ____________________________________________
Phone #____________________ Fax #_______________________
E-mail _________________________________________________
Exhibit B Scope of Work
6568 Toolesboro Ave, Hwy 99, Wapello, IA 52653
BP-01 – TMVC Floor Slab Repair:
All work on Sheets C-101 Cover Sheet, C-102 Specifications, A-101 Demo Floor Plan, A-102 Floor Plans.
Contractor to remove existing carpeting; poly jack the existing concrete floor slab and install new LVT flooring throughout the building.
M
AR
K D
AT
E
D
ES
C R
IP
TI
O N
PROJECT NO:
DRAWN BY:
COPYRIGHT
DATE:
SHEET TITLE
C-101
COVER SHEET
G25-004
LM
3/11/2026
T O
O
LE
S B O
R O
A V E
H W
Y
W A
PE
LL
O
IA
C
U se rs \L en aM ic ha le k\
O ne
D ri ve
H or iz on A rc hi te ct ur e\
D oc um en ts
H or iz on
A rc hi te ct ur e\ Pr oj ec ts \G en er al P ro je ct s\
G
-0
G
-0
T M
V C S tr uc tu ra l E va lu at io n\
M od el a nd D es ig n\ To ol es bo ro
I nd ia n
M ou nd s.
pl n
D A
S
.0
T
M V
C F
LO
O
R S
LA
B
R
EP
A
IR
C O
N
ST
R U
C
TI
O N
D O
C U
M
EN
TS
0%
C D
IS
SU
ED
F
O R
B
ID
D
IN
G
M
IC
H A
EL
H
O R
IZ
O N
-A R C H
IT
EC
TU
R E.
C O
M
PH
3)
-4
W
W W
.H O
R
IZ
O N
-A R C H
IT
EC
TU
R E.
C O
M
6" TYPICAL, UNLESSOTHERWISE NOTED
OFFICE
1/A-201
D0 1.1
B2
C3
D4
A1
1.01.01
D01.1
S01
W01
GRAPHIC
SYMBOLS INDICATES SECTION
LOCATION ON SHEET
INDICATES SHEET
ON WHICH DRAWING
IS SHOWN
SECTION / DETAIL MARKER DETAIL / ENLARGED PLAN MARKER
INTERIOR ELEVATION MARKER
INDICATES ELEVATION
LOCATION ON SHEET
INDICATES SHEET
ON WHICH DRAWING
IS SHOWN
ELEVATION / SECTION MARKER
INDICATES ELEVATION
LOCATION ON SHEET
INDICATES SHEET
ON WHICH ELEVATION
IS SHOWN
XX
YY
XX
XX
YY
DETAIL / ENLARGED PLAN MARKER
INDICATES DETAIL
LOCATION ON SHEET
INDICATES SHEET
ON WHICH DETAIL
IS SHOWN
SPACE DESIGNATION
WINDOW MARKER
DOOR IDENTIFIERS
SPACE NAME
SPACE NUMBER
WALL TYPE MARKER 4C
SKYLIGHT MARKER
DOOR IDENTIFIER
(ELEVATIONS/SECTIONS)
ENLARGED PLAN REFERENCE
KEYNOTE IDENTIFIER
XX
YY
DOOR
IDENTIFIER
(PLANS)
KEYNOTE; SEE KEYNOTE LEGEND
ON DRAWING'S LAYOUT
ALTERNATE KEYNOTE;
SEE KEYNOTE LEGEND
ON DRAWING'S LAYOUT
(SEE PARTITION LEGEND)
1.01.01
VERIFY SCALE
BAR IS ONE (1) INCH LONG ON
ORIGINAL DRAWING
IF BAR IS NOT ONE (1) INCH LONG,
ADJUST SCALE ACCORDINGLY
ABBREVIATIONS
A.D. AREA DRAIN
ABV. ABOVE
ADA ACCESSIBLE / AMERICANS
WITH DISABILITIES ACT
ADJ. ADJUSTABLE
A.o.R. AREA OF REFUGE
ALUM. ALUMINUM
ALT. ALTERNATE
A.F.F. ABOVE FINISHED FLOOR
AC. ACOUSTIC / ACOUSTICAL
A.F. ALUMINUM FACE
APPX. APPROXIMATE /
APPROXIMATELY
BD. BOARD
BLK. BLOCK / BLOCKING
BLDG. BUILDING
B.O. BOTTOM OF
B.O.S. BOTTOM OF STEEL
CAB. CABINET
C.C. CENTER-TO-CENTER
CLG. CEILING
CLOS. CLOSET
C.M. CONSTRUCTION MANAGER
CMU CONCRETE MASONRY UNIT
C.J. CONTROL JOINT
CONC. CONCRETE
CORR. CORRIDOR
COL. COLUMN
CONT. CONTINUE / CONTINUOUS
CONTR. CONTRACTOR
DIA. DIAMETER
DTL. DETAIL
DN DOWN
DWG. DRAWING
DEPT. DEPARTMENT
DBL. DOUBLE
DIM. DIMENSION
DR. DOOR
EXIST. EXISTING
EQ. EQUAL
E.C. ELECTRICAL CONTRACTOR
EL. ELEVATION
ELEV. ELEVATOR
ELEC. ELECTRIC / ELECTRICAL
EXP. EXPANSION
EXT. EXTERIOR
EA. EACH
F.D. FLOOR DRAIN
F.E. FIRE EXTINGUISHER
F.E.C. FIRE EXTINGUISHER
CABINET
FIN. FINISH / FINISHED
FLR. FLOOR
F.O. FACE OF
FT. FEET / FOOT
FLUOR. FLUORESCENT
GYP. GYPSUM
GALV. GALVANIZED
GA. GAUGE
G.C. GENERAL CONTRACTOR
HR. HOUR
H.P. HIGH POINT
HVAC HEAT, VENTILATION, AIR-
CONDITIONING
HORIZ. HORIZONTAL
HT. HEIGHT
INSUL. INSULATION / INSULATING
I.D. INSIDE DIAMETER
INCAND. INCANDESCENT
JAN. JANITOR
JT. JOINT
LBS. POUNDS
LAV. LAVATORY
LAM. LAMINATE
L.P. LOW POINT
MAX. MAXIMUM
MFR. MANUFACTURER /
MANUFACTURED
MTL. METAL
MIN. MINIMUM
MIRR. MIRRORED
MTD. MOUNTED
M.O. MASONRY OPENING
MISC. MISCELLANEOUS
MECH. MECHANICAL
N.I.C. NOT IN CONTRACT
NO. NUMBER
N.T.S. NOT TO SCALE
O.C. ON CENTER
O.D. OUTSIDE DIAMETER
OPP. OPPOSITE
OPG. OPENING
P.C. PLUMBING CONTRACTOR
P.F. PANEL FACE
PR. PAIR
P.T. PRESSURE TREATED
PL. LAM PLASTIC LAMINATE
QTY. QUANTITY
R RISER
R.W.C. RAIN WATER CONDUCTOR
REINF. REINFORCING / REINFORCED
REQ. REQUIRED
R.O. ROUGH OPENING
REV. REVISED / REVISION
REFL. REFLECTED
REC. RECESSED
RAD. RADIUS
S.S. STAINLESS STEEL
ST. STREET
SIM. SIMILAR
STL. STEEL
SQ. SQUARE
SAN. SANITARY
SUSP. SUSPENDED
STD. STANDARD
SPEC. SPECIFICATION
TEL. TELEPHONE
T.O. TOP OF
T.O.S. TOP OF STEEL
T.O.W. TOP OF WALL
TOIL. TOILET
TYP. TYPICAL
THK. THICK
TMP. TEMPERED
T.S.G. TEMPERED SAFETY
GLASS
U.O.N. UNLESS OTHERWISE
NOTED
U.L. UNDERWRITERS
LABORATORIES
VEST. VESTIBULE
V.C.T. VINYL COMPOSITION
TILE
W/ WITH
W.C. WATER CLOSET
WD WOOD
& AND
@ AT
± PLUS OR MINUS
° DEGREE
� ANGLE
[ CHANNEL
# NUMBER
□ SQUARE
Ø ROUND / DIAMETER
� / C.L. CENTER LINE
� / PL. PLATE
∏ U-BAR
∟ LEG-BAR
SHEET INDEX
ID
C-101
C-102
A-101
A-102
Name
COVER SHEET
SPECIFICATIONS
DEMO FLOOR PLAN
FLOOR PLANS
PROJECT LOCATION
N
SCALE: 1" = 50'1 SITE KEY
0 20' 50' 100'
BUILDING INFORMATION
APPLICABLE BUILDING CODE - 2015 IEBC AND IPC
CLASSIFICATION OF WORK - REPAIR
POLYURETHANE UNDERSLAB JACKING REPAIR AND FLOORING
REPLACEMENT FOR THE PURPOSE OF MAINTINING
COMPONENTS IN SOUND CONDITION WITH RESPECT TO
EXISTING LOADS OR PERFORMANCE REQUIREMENTS.
CONFORMANCE REQUIREMENT (601.2) - THE WORK SHALL NOT
MAKE THE BUILDING LESS CONFORMING THAT IT WAS BEFORE
THE REPAIR WAS UNDERTAKEN.
PROJECT DIRECTORY
OWNER
IOWA DEPARTMENT OF ADMINISTRATIVE SERVICES (DAS)
109 EAST 13TH STREET
DES MOINES, IA 50319
OWNER'S REPRESENTATIVE: BRANDON ADAMS
PHONE: 515.201.2197
EMAIL: BRANDON.ADAMS@IOWA.GOV
ARCHITECT
HORIZON ARCHITECTURE
3116 ALPINE COURT IOWA CITY IA 52245
PHONE: (563) 506-4965
CONTACT: MICHAEL NOLAN, AIA
EMAIL: MICHAEL@HORIZON-ARCHITECTURE.COM
DAS 9465.00 TOOLESBORO MOUNDS VISITORS CENTER
SLAB REPAIR AND FLOORING REPLACEMENT
WAPELLO, IA
K D
AT
E
D
ES
C R
IP
TI
O N
PROJECT NO:
DRAWN BY:
COPYRIGHT
DATE:
SHEET TITLE
C-102
SPECIFICATIONS
G25-004
LM
3/11/2026
T O
O
LE
S B O
R O
A V E
H W
Y
W A
PE
LL
O
IA
C
U se rs \L en aM ic ha le k\
O ne
D ri ve
H or iz on A rc hi te ct ur e\
D oc um en ts
H or iz on
A rc hi te ct ur e\ Pr oj ec ts \G en er al P ro je ct s\
G
-0
G
-0
T M
V C S tr uc tu ra l E va lu at io n\
M od el a nd D es ig n\ To ol es bo ro
I nd ia n
M ou nd s.
pl n
D A
S
.0
T
M V
C F
LO
O
R S
LA
B
R
EP
A
IR
C O
N
ST
R U
C
TI
O N
D O
C U
M
EN
TS
0%
C D
IS
SU
ED
F
O R
B
ID
D
IN
G
M
IC
H A
EL
H
O R
IZ
O N
-A R C H
IT
EC
TU
R E.
C O
M
PH
3)
-4
W
W W
.H O
R
IZ
O N
-A R C H
IT
EC
TU
R E.
C O
M
024119 Selective Structure Demolition Toolesboro Floor Repair Wapello , Iowa
G25-004 - Toolesboro Floor Repair 024119 - 1 Selective Structure Demolition
SECTION 024119
SELECTIVE STRUCTURE DEMOLITION
PART 1 GENERAL
1.01 SUMMARY
A. Related Documents:
1. Drawings and general provisions of the Contract apply to this Section.
2. Review these documents for coordination with additional requirements and information that apply to work under this Section.
B. Section Includes: Selective demolition as follows:
1. Remove architectural, structural, plumbing, fire protection, mechanical and electrical materials and equipment as indicated or required for new construction.
2. Fire sprinkler and domestic water mains shall remain in operation.
3. Remove materials from site, and dispose of legally.
4. Disconnect, remove, cap and identify utilities for later reconnection.
1.02 SUBMITTALS
A. Product Data: Manufacturer's data sheets on each product to be used.
B. Shop Drawings: Indicate removal sequence and location of salvageable items.
C. Project Record Documents: Accurately record locations of capped utilities.
1.03 QUALITY ASSURANCE
A. Regulatory Requirements:
1. Comply with requirements of applicable codes, rules and regulations.
2. Obtain required permits from AHJ.
3. Do not close or obstruct roadways or sidewalks without permits.
4. Maintain building and room egress and access at all times. Do not reduce required egress width to exits.
5. Minimize interference with corridors, exits, sidewalks, roadways and public thoroughfares.
6. Comply with applicable procedures if hazardous or contaminated materials are discovered or suspected.
B. Hazardous Materials Remediation Work:
1. If Hazardous Materials are suspected, immediately inform Architect and Owner’s Representative. No known hazardous materials are present in scope of work.
1.04 PROJECT CONDITIONS
A. Protect adjacent work to remain, and items to be turned over to Owner, from damage.
B. Existing Conditions:
1. If lead, asbestos or other hazardous materials are found or suspected, immediately stop work in the suspected area and advise the Owner and Architect. Do not recommence work in the area until advised by the Owner that the area has been cleared for work.
C. Owner will occupy adjacent areas during the course of the Work. Work under this Section shall not affect Owner's operation of adjacent areas.
1.05 SEQUENCING
A. Submit schedule indicating proposed sequence of operations for selective demolition work to
Owner for review prior to start of work. Include coordination for shutoff, capping, and continuation of utility services, and details for dust and noise control.
1. Provide detailed sequence of demolition and removal work to ensure uninterrupted progress of Owner's operations.
2. Coordinate the scheduling of work of Section with the work of other sections.
024119 Selective Structure Demolition Toolesboro Floor Repair Wapello , Iowa
G25-004 - Toolesboro Floor Repair 024119 - 2 Selective Structure Demolition
PART 2 NOT USED
PART 3 EXECUTION
3.01 EXAMINATION
A. Inspect and verify the existing conditions and become familiar with the extent of the Work.
B. Examine the site to determine proper access within the limitations of the Contract. Conduct operations so as not to interfere with adjacent roads, driveways, walks, buildings, corridors, means of access and egress, and work areas.
3.02 PREPARATION
A. Interfaces With Other Work: Coordinate extent of selective demolition work with limits of existing work to remain, and with demolition and modification requirements shown on the Drawings.
B. Protection:
1. Protect existing materials, appurtenances and equipment which are not to be demolished.
Existing materials, appurtenances and equipment, building exterior and interior, and landscaping altered or damaged during demolition work shall be repaired or replaced by the Subcontractor to match existing undisturbed conditions at no additional cost to the Owner.
2. Prevent movement of structure; provide bracing and shoring as required.
3. Provide proper and permanent support to adjacent structure for all piping, conduits and cables to remain.
4. Provide and maintain temporary weather protection during interval between demolition and removal of existing construction on exterior surfaces and installation of new construction to ensure that no water leakage or damage, or wind damage occurs to structure or interior areas of existing building.
5. Provide and maintain temporary barriers and security devices at doorways.
6. Use periodic light water mist, temporary enclosures, and other suitable methods to limit dust and dirt. Comply with applicable environmental protection regulations.
7. Provide and maintain temporary partitions to prevent spread of dust, odors and noise to permit continued Owner occupancy.
8. Maintain path of travel for debris removal dust free and clean at all times.
9. Maintain ventilation system dust free at all times.
10. Cover and protect windows and walls that are adjacent to areas to be demolished.
11. Protect smoke alarms and fire sprinklers from dust intrusion.
12. Maintain parking areas, driveways, exterior walkways, exit paths, and landscaping in a clean, undisturbed condition. Any debris caused by selective demolition work shall be removed each day.
C. Field verify the exact location of existing concealed utilities. Use caution if working in or about concealed or exposed utilities.
1. Disconnect, remove, and cap designated utility lines within demolition areas. Mark locations of disconnected utilities. Identify utilities and indicate capping locations on Project Record Documents.
3.03 EXECUTION
A. Minimize interference with adjacent occupied building areas, materials and equipment.
B. Remove items in an orderly and careful manner.
1. Remove only as much material as is required for new construction work to be conveniently performed.
2. Cut surfaces so as to minimize the amount of new surfaces required to match existing.
Make cuts plumb, true, level and straight, or as otherwise required to provide proper surfaces to receive new work and repairs.
3. Cut asphalt and concrete by power saw in neat, sharp straight lines. Repair broken edges or as directed by the Owner.
024119 Selective Structure Demolition Toolesboro Floor Repair Wapello , Iowa
G25-004 - Toolesboro Floor Repair 024119 - 3 Selective Structure Demolition
C. Remove miscellaneous abandoned appurtenances that will be exposed to view, unless indicated otherwise.
D. Investigate and measure the nature and extent of unanticipated items that conflict with intended function or design. Submit written report with accurate detailed information to the Owner and Architect. While awaiting instructions from the Owner, rearrange selective demolition schedule as necessary to continue overall job progress without delay.
E. Eliminate dust. Install dust barriers as required to keep dust out of corridors and adjacent areas. Use walkoff mats designed to remove dust at the corridor side of doors to rooms where demolition work is being done.
1. Activities which generate silica dust, such as concrete saw cutting, jackhammering, chipping, or abrasive blasting, shall incorporate engineering controls to eliminate visible emissions.
2. Do not use silica sand or other substances containing more than 1 per cent crystalline silica as abrasive blasting material
3. Use concrete and masonry saws that provide water to the blade.
4. Prevent human exposure to dust using methods such as removing dust with water, high efficiency particulate air (HEPA) filters, and wet sweeping. Do not use compressed air or dry sweeping.
F. Stop work and notify the Owner immediately if structure or other items to remain appear to be endangered. Do not resume work until directed by the Owner.
G. Do not disrupt service to existing fire sprinkler lines. If disruption becomes necessary, coordinate with the Owner.
H. Remove, store and protect materials to be re-installed or retained so as to prevent damage.
I. Remove and promptly dispose of vermin infested materials.
3.04 DISPOSAL AND CLEANUP
A. Material removed under this Contract which is not to be salvaged or reused in the Project shall become the property of the Contractor and shall be promptly removed from the job site. Do not store or permit debris to accumulate at the site.
B. Unless indicated otherwise, remove demolished material from site in a timely manner. Dispose of materials legally off site. Do not burn or bury materials on site.
C. Upon completion, clean the entire area of demolition residue satisfactory for the continuation of the Work. Remove temporary work.
3.05 SCHEDULES
A. Remove the following materials from the site and dispose of legally.
1. Demolition materials.
END OF SECTION
096500 Resilient Flooring Toolesboro Floor Repair Wapello , Iowa
G25-004 - Toolesboro Floor Repair 096500 - 1 Resilient Flooring
SECTION 096500
RESILIENT FLOORING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Resilient tile flooring.
B. Resilient base.
C. Installation accessories.
1.02 REFERENCE STANDARDS
A. ASTM F1700 - Standard Specification for Solid Vinyl Floor in Modular Format such as Tile(s) or
Plank(s); 2025.
B. ASTM F1861 - Standard Specification for Resilient Wall Base; 2021 (Reapproved 2025).
1.03 SUBMITTALS
A. Product Data: Provide data on specified products, describing physical and performance characteristics; including sizes, patterns and colors available; and installation instructions.
B. Selection Samples: Submit manufacturer's complete set of color samples for Owner's initial selection.
1.04 DELIVERY, STORAGE, AND HANDLING
A. Upon receipt, immediately remove any shrink-wrap and check materials for damage and the correct style, color, quantity and run numbers.
B. Maintain temperature in storage area between 55 degrees F (13 degrees C) and 90 degrees F (72 degrees C).
C. Protect roll materials from damage by storing on end.
1.05 FIELD CONDITIONS
A. Store materials for not less than 48 hours prior to installation in area of installation at a temperature of 70 degrees F (21 degrees C) to achieve temperature stability. Thereafter, maintain conditions above 55 degrees F (13 degrees C).
PART 2 PRODUCTS
2.01 TILE FLOORING
A. Vinyl Tile: Printed film type, with transparent or translucent wear layer; acoustic interlayer or backing.
1. Manufacturers:
a. AHF Products; Nod to Nature LVT, LooseLay and DryBack:
www.ahfcontract.com/#sle.
b. Architessa; Luxury Vinyl Plank: www.architessa.com/#sle.
c. Armstrong Flooring; Unify: www.armstrongflooring.com/#sle.
d. Flexco Corporation; Delane Solid Vinyl Tile: www.flexcofloors.com/#sle.
e. Substitutions: See Section 016000 - Product Requirements.
2. Minimum Requirements: Comply with ASTM F1700, Class III.
3. Plank Tile Size: 8 by 40 inch (203 by 1016 mm).
4. Wear Layer Thickness: 0.020 inch (0.50 mm).
5. Total Thickness: 0.20 inch (5 mm).
6. Tile Edge: Interlocking shape.
7. Color: To be selected by Owner from manufacturer's full range.
2.02 RESILIENT BASE
A. Resilient Base: ASTM F1861, Type TP, rubber, thermoplastic; style as scheduled.
1. Height: 4 inches (100 mm).
096500 Resilient Flooring Toolesboro Floor Repair Wapello , Iowa
G25-004 - Toolesboro Floor Repair 096500 - 2 Resilient Flooring
2. Thickness: 0.125 inch (3.2 mm).
3. Finish: Satin.
4. Length: Roll.
5. Color: To be selected by Owner from manufacturer's full range.
2.03 ACCESSORIES
A. Subfloor Filler: White premix latex; type recommended by adhesive material manufacturer.
B. Primers, Adhesives, and Seam Sealer: Waterproof; types recommended by flooring manufacturer.
C. Moldings, Transition and Edge Strips: Same material as flooring.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that surfaces are flat to tolerances acceptable to flooring manufacturer, free of cracks that might telegraph through flooring, clean, dry, and free of curing compounds, surface hardeners, and other chemicals that might interfere with bonding of flooring to substrate.
B. Verify that wall surfaces are smooth and flat within the tolerances specified for that type of work, are dust-free, and are ready to receive resilient base.
C. Cementitious Subfloor Surfaces: Verify that substrates are ready for resilient flooring installation by testing for moisture and alkalinity (pH).
1. Obtain instructions if test results are not within limits recommended by resilient flooring manufacturer and adhesive materials manufacturer.
3.02 PREPARATION
A. Prepare floor substrates as recommended by flooring and adhesive manufacturers.
B. Remove subfloor ridges and bumps. Fill minor low spots, cracks, joints, holes, and other defects with subfloor filler to achieve smooth, flat, hard surface.
C. Prohibit traffic until filler is fully cured.
3.03 INSTALLATION - GENERAL
A. Starting installation constitutes acceptance of subfloor conditions.
B. Install in accordance with manufacturer's written instructions.
C. Loose-Laid Installation: Set flooring in place in accordance with manufacturer's instructions.
D. Install edge strips at unprotected or exposed edges, where flooring terminates, and where indicated.
1. Metal Strips: Attach to substrate before installation of flooring using stainless steel screws.
E. Scribe flooring to walls, columns, cabinets, floor outlets, and other appurtenances to produce tight joints.
3.04 INSTALLATION - TILE FLOORING
A. Mix tile from container to ensure shade variations are consistent when tile is placed, unless otherwise indicated in manufacturer's installation instructions.
B. Lay flooring with joints and seams parallel to building lines to produce symmetrical pattern.
C. Install loose-laid tile, fit interlocking edges tightly.
3.05 INSTALLATION - RESILIENT BASE
A. Fit joints tightly and make vertical. Maintain minimum dimension of 18 inches (45 mm) between joints.
B. Miter internal corners. At external corners, use premolded units. At exposed ends, use premolded units.
096500 Resilient Flooring Toolesboro Floor Repair
Wapello , Iowa
G25-004 - Toolesboro Floor Repair 096500 - 3 Resilient Flooring
C. Install base on solid backing. Bond tightly to wall and floor surfaces.
D. Scribe and fit to door frames and other interruptions.
3.06 CLEANING
A. Remove excess adhesive from floor, base, and wall surfaces without damage.
B. Clean in accordance with manufacturer's written instructions.
3.07 PROTECTION
A. Prohibit traffic on resilient flooring for 48 hours after installation.
END OF SECTION
314300 CONCRETE RAISING Toolesboro Floor Repair Wapello , Iowa
G25-004 - Toolesboro Floor Repair 314300 - 1 CONCRETE RAISING
SECTION 314300
CONCRETE RAISING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Lifting settled concrete with polyurethane foam.
B. Repairing cracks in concrete slabs with fast set polyurethane resin.
C. Repairing drill holes with fast set polyurethane resin.
1.02 REFERENCE STANDARDS
A. ASTM D638 - Standard Test Method for Tensile Properties of Plastics; 2022.
B. ASTM D1621 - Standard Test Method for Compressive Properties of Rigid Cellular Plastics;
2016 (Reapproved 2023).
C. ASTM D1622 - Standard Test Method for Apparent Density of Rigid Cellular Plastics; 2020.
D. ASTM D-1042D - Standard Test Method for Linear Dimensional Changes of Plastics Caused by
Exposure to Heat and Moisture.
E. NSF/ANSI 61-5 - Drinking Water System Components - Heath Effects.
1.03 SUBMITTALS
A. Product Data: Manufacturer's data sheets on each product to be used, including:.
1. Preparation instructions and
2. Storage and handling requirements and recommendations.
3. Installing methods.
1.04 DELIVERY, STORAGE, AND HANDLING
A. Deliver and store products in manufacturer's unopened packaging bearing the brand name and manufacturer's identification until ready for installation.
B. Keep lids on tightly to prevent moisture from entering containers. Avoid direct contact with product. Use caution when opening as pressure may build up in containers.
C. Handling: Handle materials to avoid damage.
1.05 FIELD CONDITIONS
A. Maintain environmental and ambient conditions within limits recommended by manufacturer for optimum results. Do not install products under ambient conditions outside manufacturer's recommended limits.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Alchateck, Advanced Construction Technologies, AP Lif 430; alchateck.com.
B. PolyPier, Terrathane; polypier.com.
C. PolyLevel; polylevel.com.
D. Substitutions: Architect approved equal
2.02 MATERIALS
A. Plural component, high strength, high density, structural polyurethane foam.
1. Mix Ratio A:B = 1:1 by volume
2. Compressive StrengthASTM D1621: 50psi
3. Tensile StrengthASTM D638 : 70 psi
4. Closed Cell Content: 90 percent minimum
5. Enviornmental Safety NSF ANSI 61-5
6. Polyurethane foam must be certified to meet NSF/ANSI 61-5 to ensure the product is safe for the environment.
314300 CONCRETE RAISING Toolesboro Floor Repair
Wapello , Iowa
G25-004 - Toolesboro Floor Repair 314300 - 2 CONCRETE RAISING
B. Fast Set Polyurethane Resin
1. For repairing cracks in concrete slabs.
2. For repairing drill holes in concrete slabs.
3. Mix Ratio A:B = 1:1 by volume
2.03 ACCESSORIES
A. Mechanical Purge Gun fitted with proper mixing chamber for Geotechnical Foam Injection.
1. Injection nozzles in the mixing chamber shall be machined to allow a laminar flow with less velocity than would be used for spray applications.
B. Injection ports as recommended by manufacturer.
PART 3 EXECUTION
3.01 PREPARATION
A. Ensure job site is ready for work. Located all utilities and drainage pipes. Inspect drainage pipes before and after job to ensure there are no cracks or defects that foam material can enter. Use sewer inspection camera
B. Condition materials overnight to 60 degrees F (15 degrees C) to 90 degrees F (32 degrees C) or as recommended by manufacturer.
C. Protect surfaces from foam that can be blown out of injection holes, cracks, and joints.
D. Sawcut joints if necessary prior to injection to prevent or release slabs from binding.
E. Install foam to lift edge level with adjacent slab.
3.02 INSTALLATION
A. Install in accordance with manufacturer's written instructions.
B. Repair cracks in concrete with cementitious grout or epoxy after injection.
C. Remove injection ports and fill injection holes with cementitious grout or epoxy.
D. Grind excess resin from face of concrete with wire brush or cup wheel if neccessary. Avoid scarring concrete.
3.03 PROTECTION
A. Protect adjacent work area using plastic sheeting if necessary.
B. Protect cementitious grout or epoxy until cured.
END OF SECTION
K D
AT
E
D
ES
C R
IP
TI
O N
PROJECT NO:
DRAWN BY:
COPYRIGHT
DATE:
SHEET TITLE
A-101
DEMO FLOOR
PLAN
G25-004
LM
3/11/2026
T O
O
LE
S B O
R O
A V E
H W
Y
W A
PE
LL
O
IA
C
U se rs \L en aM ic ha le k\
O ne
D ri ve
H or iz on A rc hi te ct ur e\
D oc um en ts
H or iz on
A rc hi te ct ur e\ Pr oj ec ts \G en er al P ro je ct s\
G
-0
G
-0
T M
V C S tr uc tu ra l E va lu at io n\
M od el a nd D es ig n\ To ol es bo ro
I nd ia n
M ou nd s.
pl n
D A
S
.0
T
M V
C F
LO
O
R S
LA
B
R
EP
A
IR
C O
N
ST
R U
C
TI
O N
D O
C U
M
EN
TS
0%
C D
IS
SU
ED
F
O R
B
ID
D
IN
G
M
IC
H A
EL
H
O R
IZ
O N
-A R C H
IT
EC
TU
R E.
C O
M
PH
3)
-4
W
W W
.H O
R
IZ
O N
-A R C H
IT
EC
TU
R E.
C O
M
3 1/2" 36' 3 1/2"
1/
2"
1/ 2"
'-1
1/
2"
1/ 2"
36'-7"
'-7
DEMOLISH AND DISPOSE
OF CARPET FLOORING
OWNER TO REMOVE DISPLAYS, PROTECT
DURING REMOVAL FOR REINSTALLATION
AFTER SLAB REPAIR IS COMPLETE AND
FLOORING IS INSTALLEDDEMOLISH AND DISPOSE
OF CARPET FLOORING
SALB HEAVING AT COLD JOINT, PREP SLAB
FOR POLYJACKING
SLAB HEAVING AT COLD JOINT, PREP SLAB
FOR POLYJACKING
DEMOLISH AND DISPOSE OF
WOOD BASE BOARD, TYP
DEMOLISH AND DISPOSE OF
WOOD BASE BOARD AT
WALLS AND DISPLAYS
N
SCALE: 1/2" = 1'-0"1 DEMOLITION PLAN
0 1' 2' 4'
K D
AT
E
D
ES
C R
IP
TI
O N
PROJECT NO:
DRAWN BY:
COPYRIGHT
DATE:
SHEET TITLE
A-102
FLOOR PLANS
G25-004
LM
3/11/2026
T O
O
LE
S B O
R O
A V E
H W
Y
W A
PE
LL
O
IA
C
U se rs \L en aM ic ha le k\
O ne
D ri ve
H or iz on A rc hi te ct ur e\
D oc um en ts
H or iz on
A rc hi te ct ur e\ Pr oj ec ts \G en er al P ro je ct s\
G
-0
G
-0
T M
V C S tr uc tu ra l E va lu at io n\
M od el a nd D es ig n\ To ol es bo ro
I nd ia n
M ou nd s.
pl n
D A
S
.0
T
M V
C F
LO
O
R S
LA
B
R
EP
A
IR
C O
N
ST
R U
C
TI
O N
D O
C U
M
EN
TS
0%
C D
IS
SU
ED
F
O R
B
ID
D
IN
G
M
IC
H A
EL
H
O R
IZ
O N
-A R C H
IT
EC
TU
R E.
C O
M
PH
3)
-4
W
W W
.H O
R
IZ
O N
-A R C H
IT
EC
TU
R E.
C O
M
3 1/2" 36' 3 1/2"
1/
2"
1/ 2"
'-1
1/
2"
1/ 2"
36'-7"
'-7
A-102
OWNER TO
REINSTALL CENTER
DISPLAY OVER NEW
FLOORING
RAISE SLAB WITH FOAM
INJECTION, SHOWN HATCHED
DISPLAY TO REMAIN IN PLACE
DISPLAY TO REMAIN IN PLACE
TYP
3 1/2" 36' 3 1/2"
1/
2"
1/ 2"
'-1
1/
2"
1/ 2"
36'-7"
'-7
OWNER TO
REINSTALL CENTER
DISPLAY OVER NEW
FLOORING
NEW LVT FLOORING
THROUGHOUT
DISPLAY TO REMAIN IN PLACE,
INSTALL NEW FLOORING UP TO
DISPLAY AND BEHIND DISPLAY
IN STORAGE CLOSET
DISPLAY TO REMAIN IN PLACE,
INSTALL NEW FLOORING UP TO
DISPLAY AND BEHIND DISPLAY
IN STORAGE CLOSET
NEW VWB
THROUGHOUT
NEW VWB THROUGHOUT,
INCLUDING AT DISPLAYS
SETTLED CONCRETE EXISTING 4" CONCRETE SLAB
CONTROL JOINT
GRAVEL SUBSTRATE
GRADE
POLYURETHANE FOAM TO
FILL VOIDS
REMOVE INJECTION PORTS AND
FILL INJECTION HOLES WITH
CEMENTITOUS GROUT OR EPOXY
N
SCALE: 1/2" = 1'-0"1 FLOOR PLAN
0 1' 2' 4'
SCALE: 1/4" = 1'-0"2 FINISH PLAN
0 2' 4' 8'
SCALE: 1/2" = 1'-0"3 POLY FOAM JACKING SECTION
0 1' 2' 4'
Exhibit C Facility Work Requirements
6568 Toolesboro Ave, Hwy 99, Wapello, IA 52653
PROJECT INFORMATION
A. Facility Name/Location: Toolesboro Mounds Visitor Center, 6568 Toolesboro Ave., Wapello, IA 52653
B. DAS Project # 9465.00
C. Owner: The State Historical Society of Iowa
D. Owner’s Representative: Brandon Adams, Iowa Department of Administrative Services, 109 SE 13th
Street, Des Moines, IA 50319
E. Construction Manager: Brian Polzin, The Samuels Group, 2929 Westown Parkway, Suite 200, West
Des Moines, Iowa 50266
WORK HOUR RESTRICTIONS
A. Work hours are from 7:00 AM to 5:30 PM, Monday through Friday unless arrangements are made in advance. No work shall be allowed on days recognized by State of Iowa as holidays.
CONTRACTOR USE OF SITE AND PREMISES
Construction Operations:
Provide access to and from site as required by law and Owner:
1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period: provide temporary exit signs if exit routes are temporarily altered.
2. Do not obstruct roadways, sidewalks, or other public ways without permission of Owner and permit if required.
Facility may be occupied at times during construction. Contractor personnel shall always conduct themselves in an agreeable manner. Failure to do so may result in removal from the work site.
OWNER OCCUPANCY
A. Owner intends to occupy the Project upon Substantial Completion.
B. Cooperate with Owner to minimize conflict and to facilitate Owner’s operations.
C. Schedule the Work to accommodate Owner occupancy.
RULES FOR CONSTRUCTION WORKERS
A. The staff of the State of Iowa has a responsibility to protect the public by providing a secure environment. All work site rules must be followed to the letter, at all times.
B. Hot Work Permit Processes and Fire Watch, when necessary, will be adhered to for this project.
C. All State properties are tobacco free. No smoking will be permitted or tolerated on campus unless in designated areas.
D. You are permitted access only to the work site and no other area of the property.
E. No drugs, alcohol, or firearms are allowed on the work site.
F. Do not leave money, drugs, alcohol, or firearms in your personal vehicle.
G. Company and personal vehicles are to be parked and locked in designated work.
H. Secure all tools at the end of the day.
I. Maintain control of all tools, supplies, and debris at all times during the work hours.
J. Never leave keys in any vehicle.
K. Secure all tools at the end of each day.
L. All delivery vehicles must go directly to the job site.
M. Owner to provide electrical power and water to the contractor on site.
O. Contractor may use the bathroom within the facility.
P. All debris / carpeting to be disposed of by the contractor.
Q. Security system will be disabled for the duration of the project.
Exhibit D Sample Certification of Insurance
6568 Toolesboro Ave, Hwy 99, Wapello, IA 52653