RFQ27007137 Field House Roof SOW.pdf
PDF 320 KB Posted
- Attached to
- CCRI Field House Roof Replacement Knight Campus
- Solicitation number
- RFQ27007137
- Issued by
- Providence County, Rhode Island
About this file
This is a Scope of Work document for a Request for Proposal issued by the Community College of Rhode Island (CCRI) for the complete roof replacement of the Field House at the Knight Campus. The project involves removing the existing membrane roofing system and all flashing materials, then installing a new 30-year membrane roofing system with updated flashing, mechanical and electrical disconnects and reconnects, and plumbing drain resetting. Prospective vendors may view the roof online or visit the site to assess replacement requirements, though roof access is not available. The initial contract period begins upon issuance of the CCRI Purchase Order for one year, with renewal options for up to one additional 12-month period based on vendor performance and fund availability. Construction is scheduled to begin on-site April 12, 2027, with substantial completion required by October 10, 2027, and final completion by October 25, 2027. Vendors must possess a commercial roofing license issued by the Rhode Island Contractors' Registration and Licensing Board.
The solicitation requires bid surety bonds, payment and performance bonds, and insurance coverage including general liability of $1,000,000 per occurrence, workers compensation of $100,000 per accident, and automobile liability of $1,000,000 per occurrence. The project includes two allowances totaling $40,000: a $30,000 allowance for unforeseen concealed work directed by CCRI and a $10,000 allowance for manufacturer-required testing for warranty validity. Liquidated damages are assessed at $750 per day for schedule delays. Unit pricing has been removed from the project manual. The AIA A101-2017 Standard Form of Agreement and AIA A201-2007 General Conditions of the Contract for Construction, with State of Rhode Island revisions, govern the contract terms.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ27007137 Drawings.pdf | ||
| RFQ27007137 Project Manual.pdf | ||
| RFQ27007137_Nov_17_26_solicitation_doc.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2021-1 Page 1 of 3 Revised 06/10/2022
AGENCY SOLICITATION SPECIFICATIONS
RFQ –REQUEST FOR PROPOSAL PUBLIC WORKS
HEADER
TITLE: RFQ27007137 CCRI Field House Roof Replacement Knight Campus.
PRE-BID/ PROPOSAL CONFERENCE: NO
Vendors can go online to view the roof to see the extent of the requirements for its replacement or visit the site to look at the perimeter. Access to the roof will not be possible.
BONDING REQUIREMENTS
Bid Surety Bond Required: YES Payment and Performance Bond Required: YES
CONTRACT TERMS
The initial contract period will begin upon issuance of CCRI Purchase order for one (1) year. Contracts may be renewed for up to [1] additional 12-month periods based on vendor performance and the availability of funds.
Insurance Requirements (#14 in Instructions to Vendors on Requirements tab) In accordance with this solicitation, or as outlined in Section 13.19 of the General Conditions of Purchase, found at https://rules.sos.ri.gov/regulations/part/220-30-00-13 and General Conditions
- Addendum A found at https://www.ridop.ri.gov/documents/general-conditions-addendum-a.pdf, the following insurance coverage shall be required of the awarded vendor(s):
General Requirements:
14a) ☒ Liability - combined single limit of $1,000,000 per occurrence, $1,000,000 general aggregate and $1,000,000 products/completed operations aggregate.
14b) ☒ Workers compensation - $100,000 each accident, $100,000 disease or policy limit and $100,000 each employee.
14c) ☒ Automobile liability - $1,000,000 each occurrence combined single limit.
AIA Contract
Rhode Island custom AIA contract designated below outlining the scope and special terms and conditions covering the work, executed by an authorized representative of your company.
https://rules.sos.ri.gov/regulations/part/220-30-00-13 https://www.ridop.ri.gov/documents/general-conditions-addendum-a.pdf
2021-1 Page 2 of 3 Revised 06/10/2022
Vendor shall obtain the Rhode Island custom AIA contract at:
https://documentsondemand.aia.org/?filter=Rhode.
9a) ☒ AIA A101-2017 Standard Form of Agreement Between Owner and Contractor with State of Rhode Island revisions dated 7-25-19.
9g) ☒ AIA A201-2007 General Conditions of the Contract for Construction with State of Rhode Island Revisions dated 9-10-19.
SECTION A. BACKGROUND
The Community College of Rhode Island is the largest community college in New England, providing high-quality academic programs and career-oriented training for full- and part-time students, recent high school graduates, and adult learners.
Named the 2019 Two-Year College of the Year by Education Dive magazine, CCRI enrolls more than 13,000 students in credit-bearing degree and certificate programs and an additional 8,500 individuals in Workforce Development programs and adult education courses annually.
With campuses in Warwick, Providence, Newport, and Lincoln and satellite campuses in Westerly and Woonsocket, CCRI meets Rhode Islanders where they are, offering an outstanding college education that leads to strong learning outcomes, successful degree attainment, and job placement opportunities. Students can choose from more than 90 majors and programs and seven academic career paths. CCRI also offers online, hybrid, and in-person options in addition to seamless transfer opportunities for students looking to continue their education at a four-year college or university.
The Community College offers extensive community programming as well, opening its facilities for public use, sponsoring programs on issues of public concern, and offering workshops and seminars for businesses, government agencies, and individuals seeking to improve their skills or enhance their lives.
The purpose of this RFP is to completely remove the existing membrane roofing system and replace with a new 30-year membrane system at the Knight Campus at the Community College of Rhode Island Field House per the attached Construction Drawings.
SECTION B: SCOPE OF WORK AND REQUIREMENTS
The work includes but is not limited to the complete removal of the existing roofing system including all flashing materials. Replace with a new 30 year membrane roofing system, flashing, including all mechanical, electrical disconnects and reconnects, resetting plumbing drains, etc. A proposed substitution to the basis of bid manufacturer can be requested during the question period to be considered and or accepted in the Addendum.
**Vendor must posses a commercial roofing license Issued by the RI Contractors’ Registration and Licensing Board. Please enter your number under the contractor registration in OSP.
SECTION C: CONTRACT TIME
https://documentsondemand.aia.org/?filter=Rhode
2021-1 Page 3 of 3 Revised 06/10/2022
Start of onsite construction: April 12, 2027
Substantial completion: October 10, 2027
Final completion: October 25,2027
SECTION D: ALLOWANCES
1. ADD Allowance - unforeseen concealed work to be repaired as direction by CCRI. $30,000
2. Add Allowance - Manufacturer's required testing for Warranty validity.
$10,000
Total Allowances $ 40,000
SECTION E: LIQUIDATED DAMAGES
$750.00/Day
SECTION F: Unit Pricing
1. None – Unit price will be removed from Project Manual under Addendum 1
| SECTION A. BACKGROUND |
| SECTION B: SCOPE OF WORK AND REQUIREMENTS |
| SECTION C: CONTRACT TIME |
| SECTION D: ALLOWANCES |
| SECTION E: LIQUIDATED DAMAGES |
| SECTION F: Unit Pricing |
File details come from the government source that posted it. Updated .