RFQ REDM2425-09 Q&A Response.pdf
PDF 108 KB Posted
- Solicitation number
- RFSQ-12988
- Issued by
- Leon County, Florida
About this file
This document is a Request for Qualifications (RFQ) for Construction Manager at Risk Services for the Northwest Region, issued by a Florida state department. The RFQ seeks qualified construction management firms to provide continuing contract services for various potential projects across the region, with no guaranteed minimum number of task orders. Projects may include secure or restricted environments, and are expected to potentially incorporate energy efficiency goals, resiliency standards, or LEED-type certifications.
The solicitation requires physical thumb drive submissions with PDF documents, and each task order will require a separate Guaranteed Maximum Price (GMP) and performance/payment bond. While the department prefers CM at Risk project experience, they will evaluate submitted project experiences from various delivery methods. No specific scoring preferences exist for small businesses or minority-owned firms, and financial capacity will be evaluated subjectively by the Selection Committee without defined metrics. The contract will utilize the latest version of the CM101 form, and distance to project sites will be measured using Google Maps to determine evaluation points.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Construction Manager at Risk Services for the Northwest Region
RFQ-REDM-2425-09
FAILURE TO FILE A PROTEST WITHIN THE TIME PRESCRIBED IN SECTION 120.57(3),
FLORIDA STATUTES, OR FAILURE TO POST THE BOND OR OTHER SECURITY REQUIRED
BY LAW WITHIN THE TIME ALLOWED FOR FILING A BOND SHALL CONSTITUTE A
WAIVER OF PROCEEDINGS UNDER CHAPTER 120, FLORIDA STATUTES.
The Department’s responses to timely submitted questions are below.
Question Number Question Response
1.
Can you provide a list of anticipated project types or locations expected under this continuing contract?
A list of future projects is not available. Please reference Section 2, Project Scope of the RFQ for a description of possible projects
2.
Will any projects occur within secure or restricted environments (e.g., correctional, law enforcement, or other critical infrastructure)?
Yes.
3.
Are any of the projects expected to include energy efficiency goals, resiliency standards, or LEED-type certification?
Yes.
4.
Will selected firms be guaranteed a minimum dollar value or number of task orders under this continuing contract?
No.
5.
Are there any scoring preferences or program considerations for small businesses, WOSB, or MBE-certified firms?
No. The CM Evaluation form is referenced in Section 14 of the
RFQ.
6.
How is "financial capacity to project scope" defined in terms of scoring or eligibility? Are there thresholds or metrics used?
The Selection Committee will review the submission and provide their Evaluation based on their review. No metrics are utilized.
7.
Are joint ventures permitted under this RFQ? If so, what documentation is required to demonstrate joint compliance and legal structure?
Please see Section 1, General Desciption of the RFQ.
8.
Will each task order issued under this continuing contract require a separate GMP and performance/payment bond?
Yes.
9.
Can you confirm that the Construction Manager Agreement to be executed is the version posted on the DMS Building Construction website?
Yes, however, Section 19 and Exhibits M, N, and O will be removed.
10.
Will future solicitations under this contract or similar RFQs allow for electronic submission via the Vendor Information Portal (VIP), or is physical thumb drive submission still required?
No. All Requests for Qualifications solicited will require a submission using a thumb drive and pdf. See Section 9, Response Instructions of the RFQ.
11.
Will relevant project experience include CM-at- Risk only, or can similar project delivery methods such as General Contractor, design-build or CM-Build also be submitted?
The Department would prefer CM at Risk projects but will evaluate whatever information and projects are provided.
12.
For the “Proposed Office Distance to Site” evaluation factor, what city or address should we use as the project site reference?
The Construction Procurement Liaison will use Google Maps to determine the distance to use in the Evaluation Form. If the Respondent is within the Region, the maximum points allowed will be provided. If the Respondent is outside the Region, the Respondents address in the CM-01 will be used and measured to the closest point in the solicited Region.
13.
You specifically state to use the Form CM101 Version dated 1/21, but the version currently on the DMS Website is dated 8/2024. Can you clarify if 8/2024 is the correct version, and if not, can you provide the requested version?
Please use the latest form.