Statement of Objective (SOO) Western Shelter Containerized Facilities
Water and Sewer Line Construction
DR-4493-PR
PROJECT BACKGROUND & DESCRIPTION
Design and installation of temporary potable water and sanitary piping for temporary structures located at Mayaguez Medical Center, Mayaguez, Puerto Rico.
FEMA has a need for build out of potable water and grey water piping with water storage and or services to empty out grey waters for temporary Western Shelter containerized kitchen, two laundry, and two-bathroom facilities at Mayaguez Medical Center’s back parking lot.
PROJECT OBJECTIVE
The Department of Homeland Security (FEMA) is requesting services for constructing and installation of potable water and grey water piping of containerized personal hygiene and kitchen facilities for the temporary Western Shelter Hospital located at Mayaguez Medical Center. This will include two options to be evaluated. Contractors may propose using existing potable water and sanitary piping at Mayaguez Medical Center or installing an independent water management system using water tanker pumps and water storage system.
PROJECT SCHEDULE
FEMA requests all work be completed and the worksite returned to pre-construction condition within four (4) calendar days of receipt of award.
REQUIREMENTS
Construction
1. Mechanical/plumbing design and installation
2. Construction, design and fabrication
3. Disposal of grey waters.
Things to Consider
1. Possible locations of containerized facilities.
2. Distance of existing potable water and sanitary piping:
a. Location 1 (approximately 75 feet from Westerns Shelter Hospital)
i. Sanitary pipe is approximately 500 feet from Location 1
ii. Potable water pipe location is approximately 350 feet from Location 1
b. Location 2 (approximately 300 feet from Western Shelter Hospital)
i. Sanitary pipe is approximately 160 feet from Location 2
ii. Potable water pipe location is approximately 25-30 feet from
Location 2
3. Contract shall develop/install process for disposal of grey waters if proposing to install water tanker and pumps.
4. Contractor is to complete all work within four calendar days of receipt of contract.
Location Address Mayaguez Medical Center Ave. Hostos #410 PR-2 Bo Sabalos
Mayaguez, PR 00681
| Draft_Statement of Objective WESTERN SHELTER PIPE SYSTEM_dated 4-6-2020 |
| Simple Diagram Water System Install |
| All pics |
| IMG_2087 |
| IMG_2088 |
| IMG_2093 |
| IMG_2094 |
| IMG_2099 |
| IMG_2103 |
| IMG_2104 |
| IMG_2105 |
| IMG_2106 |
| IMG_2116 |
| IMG_2117 |
| IMG_2118 |
| IMG_2119 |
| IMG_2124 |
| IMG_2125 |
| IMG_2126 |
| IMG_2127 |
| IMG_2128 |
| IMG_2129 |
| IMG_2130 |
| IMG_2131 |
File details come from the government source that posted it. Updated .