RFQ 8246 Attachment 2 BPA PWS Deliverable List.docx

DOCX document 64 KB Posted

Attached to
ENTERPRISE PROGRAM, PROJECT, INTEGRATION SERVICES (EPPIS) Federal contract opportunity
Solicitation number
RFQ-8246
Issued by
Department of the Treasury Internal Revenue Service

About this file

This document outlines a schedule of deliverables for a Blanket Purchase Agreement (BPA) to provide Enterprise Program, Project, Integration Services (EPPIS) to the Internal Revenue Service. The contractor shall provide 64 deliverables across 19 task areas, including transition management support, release management support, project management support, ELC support, program integration, technical integration, business analysis support, requirements engineering support, configuration and change management support, change management and control support, organizational readiness support, organizational change management support, engineering and architecture support, enterprise testing support, cybersecurity support, applications development support, enterprise operations support, cloud services activities, and cloud services. Deliverables include program documentation, reports, meeting materials, plans, requirements, test results, and recommendations. Due dates will be determined in each task order, and all deliverables shall be categorized as "Official Use Only."

View the file

Other files for this federal contract opportunity

Other files attached to ENTERPRISE PROGRAM, PROJECT, INTEGRATION SERVICES (EPPIS), newest first.
File Type Posted
Attachment 6 RFQ 8246 QA Responses.xlsx XLSX spreadsheet
RFQ 8246 Attachment 3 BPA Provisions and Clauses.docx DOCX document
RFQ 8246 Attachment 5 BPA Quality Assurance Surveillance Plan QASP.docx DOCX document
RFQ 8246 Attach 1 BPA Performance Work Statement corrected PWS.docx DOCX document
RFQ 8246 Attachment 7 Past Performance Questionnaire PPQ.docx DOCX document
RFQ 8246 EPPIS Cover Letter Ammendment 1.docx DOCX document
RFQ 8246 EPPIS Cover Letter.doc DOC document
RFQ 8246 Attachment 4 Pricing corrected Matrix.xlsx XLSX spreadsheet
RFQ 8246 EPPIS Attachment 4 Pricing corrected Matrix.xlsx XLSX spreadsheet
RFQ 8246 Attachment 6 Small Business Participation Plan SBPP.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Schedule of Deliverables - ATTACHMENT 2 The contractor shall provide the deliverables as described in the table below. All contractor deliverables or work products shall remain categorized as "Official Use Only.” The release of any portion must be authorized in writing by the Government. The deliverables and work products will be provided in electronic format and shall comply with all applicable standards of Section 508 of the Rehabilitation Act. The below table defines the Task Order deliverables at a high level and should not be considered all inclusive. Each Task Order will identify the specific deliverables required for that Task Order and the final format and content requirements will be mutually developed and agreed upon among the IRS Program Manager (PM), the contractor and the contracting officer’s technical representative (COR). The Task Order shall also specify the required delivery dates and timeframes.

Task Area 1, Transition Management Support

Deliverable No.
Deliverable
Due Date/Frequency
1
Program vision and charter
TBD*
2
Program meeting agendas presentations and minutes
TBD
3
Process and procedure documentation
TBD
4
Analysis of alternatives
TBD
5
Program reports
TBD
6
Program risk and issue register
TBD
7
Strategic roadmaps and operating models
TBD
8
Contingency plans
TBD

Task Area 2, Release Management Support

Deliverable No.
Deliverable
Due Date/Frequency
9
Integrated release plan
TBD
10
Release dependencies list
TBD
11
Release risk and issue register
TBD
12
Release status reports
TBD
13
Release meeting agendas, presentations, and minutes
TBD
14
Lessons Learned
TBD

Task Area 3, Project Management Support

Deliverable No.
Deliverable
Due Date/Frequency
15
Project management documentation
TBD
16
Project schedules
TBD
17
Project status reports
TBD
18
Process and procedure documentation
TBD
19
Project meeting agendas, presentations, and minutes
TBD
20
Lessons learned
TBD

Task Area 4, ELC Support

Deliverable No.
Deliverable
Due Date/Frequency
21
Artifact strategy
TBD

Task Area 5, Program Integration

Deliverable No.
Deliverable
Due Date/Frequency
22
Stakeholder engagement process and interaction model
TBD
23
Program integrated master schedule
TBD

Task Area 6, Technical Integration

Deliverable No.
Deliverable
Due Date/Frequency
24
Technical dependencies, integration points and impact analyses
TBD
25
Non-functional requirements
TBD
26
Dependencies List identifying the intersection of functional and non-functional requirements
TBD
27
Technical integration plans
TBD

Task Area 7, Business Analysis Support

Deliverable No.
Deliverable
Due Date/Frequency
28
Business process descriptions, process flows, diagrams and presentations
TBD
29
Business process impacts and recommendations
TBD
30
Best practices for business process analysis and reengineering
TBD

Task Area 8, Requirements Engineering Support

Deliverable No.
Deliverable
Due Date/Frequency
31
Program requirements, functional and non-functional
TBD
32
System, project and build-to requirements
TBD
33
Requirements traceability reports
TBD

Task Area 9, Configuration and Change Management Support

Deliverable No.
Deliverable
Due Date/Frequency
34
Configuration items list
TBD
35
Implementation packages
TBD
36
Audit plans and reports
TBD

Task Area, 10, Change Management and Change Control Support

Deliverable No.
Deliverable
Due Date/Frequency
37
Change request process
TBD
38
UWR/CR Analysis
TBD

Task Area 11, Organizational Readiness Support

Deliverable No.
Deliverable
Due Date/Frequency
39
Organizational readiness plans and reports
TBD

Task Area 12, Organizational Change Management Support

Deliverable No.
Deliverable
Due Date/Frequency
40
Organizational change assessments
TBD
41
Organizational change plans and reports
TBD
42
Communication plans
TBD
43
Training plans
TBD

Task Area 13, Engineering and Architecture Support

Deliverable No.
Deliverable
Due Date/Frequency
44
Technical analyses and assessments
TBD

Task Area 14, Enterprise Testing Support

Deliverable No.
Deliverable
Due Date/Frequency
45
Test plans
TBD
46
Test results reports
TBD
47
Test integration analysis and recommendations
TBD

Task Area 15, Cybersecurity Support

Deliverable No.
Deliverable
Due Date/Frequency
48
Security and privacy requirements
TBD
49
Security and privacy risk management plans and reports
TBD
50
Defect analysis reports and recommendations
TBD
51
Security test plans
TBD
52
Security test results reports
TBD

Task Area 16, Applications Development Support

Deliverable No.
Deliverable
Due Date/Frequency
53
Requirements management plans
TBD
54
Test plans
TBD
55
Technical review results and recommendations
TBD
56
Communications plans
TBD
57
Risk management plans
TBD

Task Area 17, Enterprise Operations Support

Deliverable No.
Deliverable
Due Date/Frequency
58
Best practices recommendations
TBD
59
Knowledge transfer plans
TBD
60
Technical review results and recommendations
TBD

Task Area 18, Cloud Services Activities

Deliverable No.
Deliverable
Due Date/Frequency
61
Knowledge transfer plans
TBD
62
Transition plans
TBD

Section 8.1.1, Kickoff Meeting

Deliverable No.
Deliverable
Due Date/Frequency
63
Kickoff Meeting (Task Order Level)
TBD

Section 6.1.1, Kickoff Meeting

64
Kickoff Meeting (BPA Level)
Within 5 business days of contract award

8.1.2, Quality Control Plan (QCP)

65
Quality Control Plan
Within 30 calendar days of contract award
Task Area 19, Cloud Services
Task Area 19, Cloud Services
Task Area 19, Cloud Services
Deliverable No.
Deliverable
Due Date/Frequency
66
Cloud Strategy Plan
TBD
67
Cloud Transition Plan
TBD
68
Cloud Implementation Plan
TBD

*TBD – To Be Determined