This addendum to RFQ 426528 addresses frequently asked questions regarding wastewater lift station repair services for the City of Oakland's Public Works Department, Sewer Division in California. The RFQ seeks repair services for thirteen wastewater lift stations throughout the city, including maintenance and repair of submersible Flygt pumps, control panels, piping, float switches, and associated components. The contractor must provide technicians available during regular business hours and on-call seven days per week with a mandatory one-hour response time for after-hours, weekend, and emergency calls. The awarded contract will be for an initial two-year term with an option to extend for an additional one-year period, with a not-to-exceed total amount of $250,000.00.
Regarding technician qualifications, Flygt/Xylem factory certification is preferred but documented experience repairing Flygt/Xylem lift station pumps and related equipment will be accepted. Bidders must submit proposed hourly labor rates, overtime labor rates, and miscellaneous charges with the preference that these rates remain fixed throughout the entire two-year contract term; however, if rate adjustments are necessary for the second year, the City requires 60-day notification of new prices. No dedicated technician standby coverage is required, and no estimated annual usage data regarding anticipated service calls, labor hours, or historical after-hours calls has been provided by the City at this time.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ 426528 WASTEWATER LIFT STATION REPAIR SERVICES.pdf | ||
| RFQ 426528 ADDENDUM 2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ: 426528 WASTEWATER LIFT STATION REPAIR SERVICES: ADDENDUM 1
1. The RFQ requires on-call availability seven days per week. Does this mean 24-hour availability, and what response time will be required for after-hours, weekend, or emergency calls?
Yes, we are requesting 24-hour availability with a 1-hour response time for after-hours, weekend, and/or emergency calls.
2. Is the awarded contractor expected to maintain a dedicated technician on standby, or is the requirement limited to responding to service calls within the required response time?
If dedicated standby coverage is required, is there separate compensation for that availability?
No, we do need expected a dedicated technician on standby. The requirement is limited to responding to service calls within the required response time of 1-hour.
3. Is any estimated annual usage available, such as the anticipated number of service calls, labor hours, historical after-hours calls, or the contract’s not-to-exceed value?
There is no estimated annual usage at this time. The award resulting from this
RFQ will be for a two-year (2) period with an option to extend an additional one
(1), one-year period year period at the sole discretion of the City and not to exceed total amount of $250,000.00.
4. Please clarify what is meant by “certified technicians.” Is a Flygt/Xylem factory certification required, or will documented experience repairing wastewater lift-station pumps and related equipment satisfy the requirement?
Yes, a Flygt/Xylem factory certification is preferred, however experience with repairing Flygt/Xylem lift stations pumps and related equipment will be accepted.
1. Must the proposed labor and miscellaneous rates remain fixed throughout the initial two-year term, or may bidders provide separate rates or an adjustment for the second year?
We prefer the proposed labor, and miscellaneous rates remain fixed throughout the entire contract and if it is necessary for the rates to change for the second year, we request 60-day notification of the new prices.