RFQ # 354-PW27-16 Addendum No.1.pdf
PDF 154 KB Posted
- Attached to
- Public Works Fleet Maintenance HVAC Addition
- Solicitation number
- 354-PW27-16
- Issued by
- Wake County, Charlotte City, North Carolina
About this file
Summary of RFQ # 354-PW27-16 Addendum No. 1
This addendum to a Request for Qualifications is issued by the Town of Cary, North Carolina, for the Public Works Fleet Maintenance HVAC Addition project. The addendum addresses questions submitted during the open question and answer period and clarifies that all other terms and conditions from the original RFQ remain in full force and effect. The primary clarification provided pertains to the deliverables section on page 7, specifying that vendors should submit a design schedule that includes design tasks and their corresponding required amounts of time, rather than a construction schedule.
No pricing information, set-asides, incumbents, or funding details are addressed in this addendum. The document serves solely to clarify scope requirements for responding vendors and does not modify compensation structures, insurance requirements, evaluation criteria, or submission deadlines established in the original RFQ.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 354-PW27-16 Public Works Fleet Maintenance HVAC Addition.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
919.469.4000 | carync.gov
PO Box 8005 Cary, NC 27512
October 30, 2026
Public Works Fleet Maintenance HVAC Addition
RFQ # 354-PW27-16
Addendum No. 1
The purpose of this addendum is to answer questions received during the open question and answer period. All other terms and conditions given in this Request for Proposals are in full force and effect.
QUESTIONS & ANSWERS
Vendor Question: In reference to deliverables on page 7, is this a design schedule or construction schedule? Should we list the design tasks and their corresponding required amounts of time?
Answer: A design schedule with tasks and their corresponding required amounts of time will be sufficient.