RFQ-24-18 Design Criteria Package Final.pdf

PDF 360 KB Posted

Attached to
Progressive Design Build - Water Recycling Facility at Pollard Rd
Solicitation number
RFSQ-09355
Issued by
Polk County, Woodlawn Beach CDP, Florida

About this file

This document is a Design Criteria Package for a Progressive Design Build contract for a Water Recycling Facility (WRF) at Pollard Road in the City of Winter Haven, Florida. The City is seeking to construct a new 12-million-gallons-per-day (MGD) WRF with provisions for future expansion up to 24 MGD, as well as future facilities for Direct Potable Reuse, Managed Aquifer Recharge, and stormwater harvesting. The WRF must meet advanced wastewater treatment standards and Class I reliability standards. The Progressive Design Build team will be responsible for the design, permitting, and construction of the new WRF, as well as the abandonment of the existing Wastewater Treatment Facility #2. The City has outlined priority items in Tier 1, desired items in Tier 2, and future items in Tier 3 for the Progressive Design Build team to consider.

The Progressive Design Build team will be required to provide a Preliminary Engineering and Phasing Plan, as well as a Basis of Design Report, prior to the final design. The team will also assist the City in obtaining necessary permits and permit modifications, including the extension of the operating permit for the existing Wastewater Treatment Facility #3. The City has a budget target of less than $200 million for the initial phase of the project.

View the file

Other files

File Type Posted
RFQ-24-18 Prog DB - Water Recycling Facility.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

23160-033-01 1 May 2024 WRF at Pollard Road Design Criteria

PROGRESSIVE DESIGN BUILD FOR WRF AT

POLLARD ROAD AND WWTF #2 ABANDONMENT

PREPARED FOR: City of Winter Haven, Water Department

PREPARED BY: Jones Edmunds & Associates, Inc.

DATE: May 20, 2024

PROJECT NO: 23160-034-01

SUBJECT: Owner’s Design Criteria

This item has been digitally signed and sealed by Edward J. French, IV, PE, Florida Professional

Engineer No. 57453 on the date indicated on the digital seal. Printed copies of this document are not considered to be signed and sealed. The signature must be verified on any electronic copies.

Jones Edmunds & Associates, Inc.

8657 Baypine Road, Suite 300

Jacksonville, Florida 32256

(904) 744-5401

The above-named professional engineer is responsible for collecting and summarizing various work performed by others to compile a synopsis of Winter Haven’s Design Criteria.

INTRODUCTION AND BACKGROUND

The City of Winter Haven intends for its new One Water Complex to consist of an initial

12-million-gallons-per-day (MGD) Wastewater Resource Facility (WRF), Reclaim Pumping

Facility (RPF), and offsite mains with provisions for:

Future expansion up to 24 MGD.

Future onsite 2.5-MGD Direct Potable Reuse (DPR) Facility expandable to 5.0 MGD.

Future 1.6-MGD Managed Aquifer Recharge (MAR) project.

Future 0.4-MGD stormwater harvesting project retrofitting the current Wastewater

Treatment Facility (WWTF) #3.

Class I reliability standards.

Capable of producing public access reclaimed water (RCW) that meets advanced wastewater treatment (AWT) requirements with the following concentrations on an annual average basis:

Five-day carbonaceous biochemical oxygen demand (CBOD5) – 5 ppm

Total Suspended Solids (TSS) – 5 ppm

Total Nitrogen (TN) – 3 ppm

Total Phosphorus (TP) – 1 ppm

The WRF design, permitting, and intended operation conforms with Chapter 62-600, FAC.

The RPF design, permitting, and intended operation conforms with Chapter 62-610, FAC, for Public Access Reuse.

Assist the Owner in completing and obtaining all applicable and necessary permits or permit modifications for the project.

23160-033-01 2

Assist the Owner in completing and filing all applicable and necessary notices of commencement and termination for the project.

Process modeling, evaluations, and hydraulic calculations demonstrating that the

Progressive Design Build Team takes full responsibility for the overall processes and systems under design and their compliance with the Owner’s requirements and regulatory compliance.

The Owner uses goods, equipment, or materials integrated into the operations that are considered strategic and requires compatibility with existing goods, equipment, or materials or such that could not be replaced or incorporated without substantial expenditures to the Owner. The Progressive Design Build Team shall coordinate with the

Owner and incorporate the Owner’s goods, equipment, and materials preferences into the project.

The existing WWTF#3 will need to remain operational until flows can be diverted to the new WRF. WWTF#3’s operating permit expires September 6, 2026, and the Progressive

Design Build Team shall assist the Owner in completing and filing all applicable and necessary documents to extend the existing operating permit 180 days before the expiration date, including all supporting documents.

The City plans to decommission WWTF#2 and redirect wastewater from WWTF#2 to the new One Water Complex for treatment. The operating permit for WWTF#2 expires in

April 2029, and the City's ability to redirect wastewater from WWTF#2 depends on obtaining permits from the Florida Department of Environmental Protection (FDEP), securing funds, and completing the transmission force mains and pump station at

WWTF#2. Review the existing WWTF#2 abandonment plan and implement a plan for the design and construction of the abandonment and wastewater transmission and conveyance to the new One Water Complex for treatment based on funding availability.

As part of the WWTF#2 abandonment, the Progressive Design Build Team shall assist the Owner in completing and filing all applicable and necessary documents and FDEP permit applications to abandon portions of the WWTF and to transfer the existing public access reuse operating permit and service area to the new WRF at the One Water

Campus including all supporting documents.

Performance, payment, and warranty bonds shall be required from the Progressive

Design Build Team.

The City is served by two treatment facilities. Both produce public access reuse water.

WWTF #2 (FLA129747) is a Type I activated sludge plant permitted for 1.7-MGD average annual daily flow (AADF), with 6.0 MGD permitted for public access reuse. It currently treats approximately 1.3-MGD AADF and discharges only to the Master Reuse System (MRS).

WWTF #3 (FL0036048) is a four-stage Bardenpho system permitted for 7.5-MGD AADF with

4.1 MGD permitted for public access reuse. It currently treats approximately 4.4-MGD

AADF. WWTF #3 was designed to meet the effluent concentration limitations for surface water discharge (D-001 at Peace Creek) and public access reuse (R-002 to the MRS).

Both facilities are nearing the end of their service lives. The Winter Haven One Water Master

Plan – Phase 2A Wastewater Treatment Facilities Consolidation Evaluation (Black and

Veatch, 2021) determined that consolidating the facilities would have the lowest life-cycle cost compared to maintaining and upgrading both facilities. Winter Haven is planning on consolidating flows at the new One Water Complex.

23160-033-01 3

Potential One Water Complex Conceptual Process Flow Diagram

23160-033-01 4

WWTF #3 Influent Flows, January 2022–April 2023

Parameter Flow (MGD) Permitted Flow

AADF 4.615 7.5

MMADF 6.185 Report

PDF 7.910 —

MinDF 4.290 —

PHF 9.971 —

1Data from Black and Veatch Technical Memorandum – Winter Haven One Water Master Plan –

Phase 2A Wastewater Treatment Facilities Consolidation Evaluation (2021).

AADF = average annual daily flow; MMADF = maximum monthly average daily flow; PDF = peak daily flow; MinDF = minimum daily flow; PHF= peak hourly flow

WWTF #3 Normalized Influent Loads, January 2022–April 2023

Parameter CBOD5 TSS

Influent Concentration MGD AADF (mg/L) 78.79 229.83

AAD Normalized (ppd/MGD) 3,033 8,846

AAD (ppd) 13,996 40,825

MMAD (ppd) 18,758 54,716

PD (ppd) 23,989 69,973

2022 2023

T o ta l

F lo w

M G

Total Flow into WWTF #2 FLW-02 Total Flow into WWTF #3 FLW-01 RCW Flow to MRS (FLW-04)

System-Wide Reclaimed Water Production

23160-033-01 5

WWTF #3 Influent Nitrogen from 2023 Annual Testing

Parameter TN Nitrate and Nitrite as N TKN1

Influent Concentration (mg/L) 4.44 0.254 4.19 1Total Kjeldahl Nitrogen.

Source: 2021 CFWI Water Resource Planning

60,000

70,000

80,000

90,000

100,000

110,000

120,000

130,000

140,000

150,000

160,000

2020 2030 2040 2050 2060 2070

Functionalized Seasonal Population [1]

(100)

A v a il a b le

W a te r (M

G

RCW Demand (MG) DPR Demand (MG)

Recharge Projects Demand (MG) Monthly Surplus or Deficit Flow (MG)

Total Sewer Flow (MG)

Projected 2050 Water Balance

Population Projections

23160-033-01 6

WASTEWATER RESOURCE FACILITY (WRF)

PRIORITIZATION AND PHASING PLAN

The Owner expects the Progressive Design Build Team to complete a Preliminary

Engineering and Phasing Plan before completing the final design of any elements. This section is not intended to be all-inclusive or binding. The Final Phasing Plan and Engineering

Report will be approved during the project based on the discussions between the

Progressive Design Build Team, the Owner, and the Owner’s Representative.

The Owner has three tiers:

Tier 1 encompasses items that are deemed necessary or essential to the project.

Tier 2 includes items that would be considered appealing to include.

Tier 3 comprises items that are needed in the future.

The tiers outline the Owner's current preferences and are intended to serve as a starting place for the Progressive Design Build Team to facilitate the planning and design process.

Tier 1:

Capable of producing public access RCW and meeting AWT standards with the following concentrations on an annual average basis:

CBOD5 – 5 ppm

TSS – 5 ppm

TN – 3 ppm

TP – 1 ppm

Class I reliability standards.

Effluent turbidity approved operating protocol so that the permit limitations for TSS and fecal coliforms will be achieved.

The facility design, permitting, and intended operation shall conform with Chapter

62-600, FAC.

Meet or exceed the Owner’s budget and schedule requirements.

Review the existing WWTF#2 abandonment plan and implement the design and construction of the wastewater transmission and conveyance to the new One Water

Complex for treatment based on funding availability.

One objective of the initial phase is for the Owner’s budget to remain below $200M.

Tier 2:

Future expansion to 24 MGD.

Effluent turbidity below 3 nephelometric turbidity units (NTU) or lower based on permit or reclaim water requirements.

Carrousel biological nutrient removal (BNR) or BNR with fine bubble aeration with MS centrifugal blowers in 5-stage configuration are the City’s preferred options.

Center-flow Ovivo clarifiers are the City’s preferred option.

Onsite reject pond.

Winter Haven is open to considering alternative treatment options during the initial phases of the 12-MGD facility that are energy-efficient; produce reliable high-quality water; keep operating costs low, long-lasting, trouble-free; and maintain ease of

23160-033-01 7 operations. Alternatives must also meet or exceed the Owner’s budget and schedule requirements.

If the Design-Builder presents an alternative for the Owner’s consideration, it shall also include a comparison in business case format along with a 50-year net present value cost analysis that includes the Owner’s preferred alternatives.

Tier 3:

Future onsite 2.5-MGD DPR Facility expandable to 5 MGD.

Future 1.6-MGD MAR project.

Future 0.4-MGD stormwater harvesting project retrofitting the current WWTF#3.

The Progressive Design Build Team shall prepare a Conceptual Master Plan layout of the 24-

MGD facility and WWTF#2 abandonment that includes options for:

Treatment processes.

Ease of operation and maintenance.

Phasing.

Growth.

Efficient land usage.

Infrastructure integration and utility planning to facilitate the WRF and WWTF#2 abandonment.

Environmental, endangered species, and archaeological impacts.

Soil impacts.

Keeping the existing facility in service and operations and maintenance planning.

Funding opportunities.

Rough construction scheduling, budget, and risk assessment for the initial phase.

Options for incorporating the use of the existing wastewater facility.

The Progressive Design Build Team shall coordinate with the Owner and, when possible, incorporate the Owner’s operational preferences into the Conceptual Master Plan, keeping ease of operation and maintenance in mind. Data collection including surveys, geotechnical explorations, environmental, and archaeological described in Appendix 1 may need to be conducted concurrently during the planning process.

RECOMMENDATIONS

The Progressive Design Build Team shall prepare final recommendations and budget estimates for the initial phase for the Owner’s evaluation and review. If the Progressive

Design Build Team presents alternatives for the Owner’s consideration, it shall include a comparison in business case format along with a 50-year net present value cost analysis that includes the Owner’s preferred alternatives. Design assignments will proceed as outlined in the RFQ.

23160-033-01 8

Appendix 1

23160-033-01 9

A survey as determined by the Progressive Design Build Team’s Engineer of Record

(EOR) to include the following:

The Progressive Design Build Team shall be responsible for determining the extent and the requirements of the needed survey suitable for the design, permitting and construction of the Project.

Flagged boring locations (if not present at the time of survey field work include going back to pick-up and adding).

Structures on the property with finished floor elevations.

Underground utilities.

Subsurface Utility Engineering (SUE).

Verified Vertical and Horizontal Location (VVH), the locations and quantity determined by the EOR.

Aboveground utilities.

Landscaping and trees.

Fencing.

Paving.

Sidewalks.

Spot elevations within the area including all grade breaks, top of banks, flow lines, toe of slope, center lines, etc.

Contour elevations not to exceed 1-foot elevations.

Flood zone classification.

Wetland lines (if not present at the time of survey field work include going back to pick-up and adding).

Water features.

Easements, servitudes, rights-of-way, and access.

Property boundaries.

Legal description.

Easements locations.

Adjacent rights-of-way.

Extend the topographic and utility survey beyond the site perimeter by 25 feet.

Include survey information for adjacent fronting rights-of-way.

Include at least two temporary benchmarks for use during construction located outside but adjacent to the proposed improvements.

Horizontal shall use the North American Datum of 1983 (NAD 83), Florida State

Plane Coordinate System, East Zone – US Survey Feet.

Elevations shall use the North American Vertical Datum of 1988 (NAVD 88).

The survey will be performed in accordance with the State of Florida Standards of

Practice, as set forth by the Board of Professional Surveyors and Mappers, Chapter

5J-17, FAC, and pursuant to Section 472.027, Florida Statutes (FS).

Deliverables shall include electronic forms in PDF and AutoCAD .dwg formats.

AutoCAD files shall use the national CAD layering standards and will include the surface, Triangular Irregular Network(TIN), and all break lines used to create the contours.

Final survey shall include four signed-and-sealed hard copies for filing and a digitally signed and sealed pdf version, as set forth in rule SJ-17.062, FAC.

23160-033-01 10

Geotechnical Engineering to include the following:

The Progressive Design Build Team shall decide the final boring and test pit locations, depths, and quantity suitable for the design, permitting and construction of the project.

The geotechnical investigation shall include borings in accordance with Appendix A of

ACI 372 as the guidelines and foundational requirements for all GSTs.

The geotechnical investigation shall include borings and test pits along the utility routes.

Borings.

Test pits.

Laboratory testing.

Site earthwork recommendations and site preparation.

Seasonal high groundwater table.

Encountered groundwater table.

Evaluation of the subsurface conditions.

Settlement potential analysis.

Bearing capacity and allowable bearing pressure of the native soils.

Evaluation of on-site soil for use as structural fill/backfill material.

Unsuitable soil expectations (silts, clays, or other deleterious materials).

Flag boring and test pit locations for inclusion into the site survey.

Boring and test pit logs.

Boring and test pit map.

Geotechnical engineering report and recommendations.

Environmental and Archaeological to include the following:

The Progressive Design Build Team shall decide the environmental and archaeological assessment needed for the project's design, permitting, and construction.

Site visits, evaluations, field surveys, and investigations.

Phase I and Phase II environmental site assessments as determined by the EOR.

Evaluation, avoidance, and mitigation of potential hazardous impacts.

Archaeological site assessments as determined by the EOR.

Evaluation, avoidance, and mitigation of potential archaeological impacts.

Evaluation, avoidance, and mitigation of wetland impacts.

Calculation of mitigation requirements for the Project in accordance with the Uniform

Mitigation Assessment Method (UMAM) as mandated by subsection 373.414(18), FS.

Identification of the final amount and coordination for the purchase of mitigation of credits with mitigation banks.

Evaluation, avoidance, and mitigation of endangered species impacts.

On-site meetings with the applicable jurisdictional permitting agencies as the

Progressive Design Build Team's Environmental Scientist determines in the best interest for the project or permitting needs.

Preparation and submittal of applicable environmental permit applications.

Permit Analysis and Preparation:

Investigate all applicable and necessary permits or permit modifications for the project.

23160-033-01 11

Provide a Technical Memorandum for the project outlining all required and necessary permitting and associated fees.

Provide a Basis of Design Report to include:

Influent sampling plan for confirming influent characteristics, loads, and modeling parameters.

Flow and loads.

Process modeling.

Capacity analysis with consideration of population projections and the phasing of flows from WWTF#2.

Owner’s goods, equipment, and materials preferences.

Process flow diagram including:

Flow lines.

Tank volumes.

Name and quantity of each component.

Name and quantity of each system.

Name and quantity of each process.

Pump stations.

Major unit treatment processes.

Residual processing and disposal systems.

Reclaimed water reuse and effluent disposal systems.

Prepare and submit WWTF#3 operating permit renewal documents:

WWTF#3’s operating permit expires September 6, 2026.

The Progressive Design Build Team shall extend the existing operating permit.

Submit the operating permit extension 180 days prior to the expiration date including all required supporting documents that shall include but not limited to the following:

o Performance reporting.

o Flow and loading analysis.

o Capacity analysis.

o Operations and conditions report.

Respond to requests for additional information as required.

jfrench@jonesedmunds.com
2024-05-20T08:11:24-0400
Jacksonville, FL
Edward J French, IV
Winter Haven Water PDB Design Criteria