RFQ 2025-28 Clarifying Questions -1.pdf
PDF 149 KB Posted
- Solicitation number
- S-C01010-00013157
- Issued by
- Clackamas County, Mission CDP, Oregon
About this file
This document is a Response to Clarifying Questions for Request for Quotes #2025-28 (RFQ) issued by Clackamas County for the Aquatic Park Stair and Deck Repair Project at North Clackamas Aquatic Park. The document provides two key pieces of information: the depth of concrete slabs (which can be found on sheets S300 and S301) and a detailed disruptive demolition schedule for contractors. The work schedule is divided into two distinct periods - from now until June 20, 2025, and from June 21 to September 30, 2025 - specifying precise time windows for loud construction activities like demo, rebar work, and less disruptive construction/mobilization, which could potentially occur at any time.
The clarifying questions document does not provide additional pricing, funding, or comprehensive project details beyond the work schedule and slab depth information. The document is explicitly noted as a clarification document that does not alter or amend the original RFQ, serving primarily to provide supplemental information to interested contractors about the timing and constraints of the construction work at the aquatic park.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Quotes #2025-28
Aquatic Park Stair and Deck Repair Project (“RFQ”)
RESPONSE TO CLARIFYING QUESTIONS
April 9, 2025
Note that these are questions submitted by interested firms to the above referenced solicitation.
The below answers are for clarification purposes only and in no way alter or amend the RFQ as published.
1. What are the depth of the concrete slabs?
Answer: Thickness of slabs can be found on sheets S300 and S301.
2. The following information is to assist contractors with demolition and work times:
Disruptive Demolition schedule to assist with scheduling work North Clackamas Aquatic Park
Now- June 20, 2025 Demo/Rebar/Loud construction – Monday /Wednesday 8 p.m. until 9 a.m. (following day Tuesday/Thursday morning) Tuesday/Thursday 8 p.m. until 5 a.m. (following day Wednesday/Friday morning) Friday 12:30 p.m. – until 8 a.m. (Saturday morning) Saturday – 4 p.m. – until 8 a.m. (Sunday morning) Sunday 4 p.m. – until 5 a.m. (Friday morning)
Not as loud construction/mobilization – Could potentially be anytime.
June 21 – September 30, 2025 Demo/Rebar/Loud construction – Monday /Wednesday 8 p.m. until 8 a.m. (following day Tuesday/Thursday morning) Tuesday/Thursday 8 p.m. until 5 a.m. (following day Wednesday/Friday morning) Friday 4 p.m. – until 8 a.m. (Saturday morning) Saturday – 4 p.m. – until 8 a.m. (Sunday morning) Sunday 4 p.m. – until 5 a.m. (Friday morning)
Not as loud construction/mobilization – Could potentially be anytime.
End of Clarifying Questions -1