RFQ 19SN1025Q0039 Attachment 1 - SOW.pdf
PDF 1 MB Posted
- Solicitation number
- 19SN1025Q0039
- Issued by
-
Department of State US Embassy Singapore
About this file
This document is a Statement of Work (SOW) for construction services to renovate bathrooms at the U.S. Embassy in Singapore. The project involves comprehensive renovation of five bathrooms across different floors of the Chief of Mission Residence, including the Master Bathroom, Guest Bathroom 1, Ladies' Rep Bathroom, Men's Rep Bathroom, and VIP Bathroom. The scope of work encompasses complete demolition and reconstruction, including new fixtures, tiles, lighting, plumbing, electrical work, vanities, countertops, and painting, with specific brand and model requirements for items like toilets, sinks, faucets, and shower systems.
The renovation is structured with a base contract for two bathrooms and two optional phases for additional bathrooms. The project has a 30-calendar day performance period from the Notice to Proceed, with work to be completed as expeditiously as possible while potentially maintaining the residence's occupancy. Contractors must provide detailed proposals demonstrating alignment with the Embassy's design aesthetic, including specifications for oak cabinetry, quartz vanity surfaces, and specific tile and fixture selections. The government reserves the right to award the base contract and any or all options, with contractors required to submit a phasing plan and construction schedule for review and approval.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ 19SN1025Q0039.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of State – Embassy Singapore Facility Management
7/28/2025
CONSTRUCTION SERVICES
STATEMENT OF WORK (SOW)
FOR
CMR BATHROOM RENOVATION
U.S. Embassy Singapore
Singapore
July 28, 2025
1. INTRODUCTION
1.1 The U.S. American Embassy Singapore is seeking a renovation project that includes up to five (5) high-end bathroom installations in the Chief of Mission Residence.
1.2 The facility, the Chief of Mission Residence, is located in 8 Leedon Park neighborhood of Singapore. All inspections shall be requested through the Embassy’s Facility Manager [FM] or Contracting Officer Representative
[COR].
1.3 Work shall be completed as expeditiously as possible. The structure may be occupied during the execution of this contract. Contractor shall coordinate with Contracting Officer or the Contracting Officer Representative (COR) for work phasing and job sequencing with work commencing and completing in each room at the same time, if requested, or sequentially one bathroom at a time, if requested. Awarded contractor to submit a phasing plan with construction schedule for review and approval prior to commencement of work at the site.
1.4 For the purpose of submitting proposals, please refer to Appendix F for reference where it is structured by base and two options. The Government reserves the right to award the base and any and all of the options. Please provide in your contractor proposals supporting documents to communicate alignment with the U.S. Embassy’s design concept aesthetic, such as quartz vanity surface and oak cabinetry.
2. GENERAL REQUIREMENTS
2.1 The Contractor shall provide quantity surveyors, construction personnel, equipment, materials, tools and supervision as needed to complete the services that meet the technical requirements in this Statement of Work [SOW]. It is expected that the Contractor shall partner closely with Embassy personnel.
2.2 Contractor shall provide their warranty time period for their workmanship and all contractor provided materials.
2.3 The work shall be executed in a diligent manner in accordance with a negotiated firm fixed price and performance period. The period of performance for all Phases of the project shall be completed in 30 calendar days from the Notice to Proceed (NTP) from the U.S. Embassy. A notice to proceed is processed after Contract Award only when DBA insurance is secured by the contractor.
2.4 The Contractor shall have limited access to or be admitted into any structure outside the areas designated for the project except with permission by the Embassy. If occupied, The Contractor shall address the impact of the consequent disruption and provide for a continuing level of operation for continuous occupation of the residence during construction.
2.5 The Contractor shall be required to prepare and submit reports, bill of materials, product literature, drawings, specifications, quality control schedules, safety plan and construction costs. These documents provide the necessary interfaces, coordination, and communication between the Embassy and Contractor for the delivery of a completed project.
3. GOVERNMENT FURNISHED CONTRACTOR INSTALLED MATERIAL (GFCI)
Pursuant to Contract Clause FAR 52-245-2, Government-Furnished Property (Short Form), the Government will furnish the following materials and equipment for the installation by the Contractor. The Government Furnished Material (GFM) is stored onsite in the basement of the residence. The contractor shall move, uncrate, assemble, and install the GFM. GFM shall be uncrated and inspected by the contractor in the presence of the Contracting Officer’s Representative (COR) to determine any damaged or missing parts. If it’s determined that there are damaged or missing materials, then it will be responsibility of the Government to remedy the issue. In this situation the contractor will not be held responsible for any delays caused by the Government.
The contractor shall be responsible for damage or loss occurring after this inspection. The contractor shall notify the COR fourteen days in advance of the date the GFM is needed. Any GFM not incorporated in the work shall be returned to the Government and placed in a designed area on-site as directed by the COR.
3.1 Contractor shall provide adequate quantities of materials, in addition to the GFCI inventory of materials stored at the site, to complete the project as specified. Detailed List of Items provided at the site include:
GOVERNMENT FURNISHED MATERIALS
CLIN Description of Service GFCI
Government furnished
Contractor
Installed
Unit of
Measure
Estimated
Quantity
1 BATHROOM FIXTURES
TOILETS
1.1
TOILET (ALL BATHROOMS)
TOTO toilet, model C889DE#XW;
Y 1 5
1.2
TOILET SEAT (ALL BATHROOMS)
TOTO seat cover, model TC381VSR Y 1 5
SINKS (LAVATORIES)
1.3
SINK - medium, square, undermounted (Master
Bathroom (2) and Ladies Rep Vanity (1))
KHOLER LADENA 21", model K-2215X
Y 1 3
1.4
SINK - small, square, undermounted (Guest
Bathroom 1 (1) and VIP Bathroom (1))
KHOLER LADENA 18", model K-2214X
Y 1 2
1.5
SINK - semi recessed, square (Rep Bathrooms next to toilet (2))
KHOLER FOREFRONT SEMI-RECESSED 18",
model K-98930X-1-0
Y 1 2
SINK FAUCETS (LAVATORY FAUCETS)
1.6
SINK FAUCET - Short bronze (Master
Bathroom (2), Ladies Rep Vanity (1), VIP
Bathroom (1))
DURAVIT short, brushed bronze, model
WA1020002A04
Y 1 4
1.7
SINK FAUCET - Short steel ( Guest Bathroom 1
(1))
DURAVIT short, brushed stainless steel, model
WA10200032A04
Y 1 1
1.8
SINK FAUCET - Tall bronze (Rep Bathrooms next to toilet (2))
DURAVIT tall, brushed bronze, model
WA1040002
Y 1 2
SINK POP-UP DRAIN STOPPERS
1.9
SINK POP-UP DRAIN STOPPER - bronze
(Master Bathroom (2), Ladies Rep Vanity (1), VIP Bathroom (1), Rep Bathrooms next to toilet
(2))
GROHE, push-open stopper, brushed warm sunset, model 65807
Y 1 6
1.10
SINK POP-UP DRAIN STOPPER - steel (All
Guest Bathrooms 2nd fl. (3))
NONAME, push-open stopper, brushed stainless steel, model N43A
Y 1 1
SINK TRAPS
1.11
SINK TRAP - Bottle trap, bronze (Rep
Bathrooms next to toilet (2))
GROHE Trap, 1 1/4" brushed warm sunset, model
28 912 DLO
Y 1 2
1.12 SINK TRAP - Bottle trap, regular concealed, Y 1 5
SHOWER SYSTEMS
1.13
SHOWER SYSTEM - 2 way, bronze (Master
Bathroom and VIP Bathroom)
DURAVIT shower system, brushed bronze, model
WA4280008
Y 1 2
1.14
SHOWER SYSTEM - 2 way, steel (Guest
Bathroom 1)
DURAVIT shower system, brushed steel, model
WA5280008
Y 1 2
ACCESSORIES
1.15
BATH TOWEL BAR, bronze (Master Bathroom and VIP Bathroom)
TBD
Y 1 3
1.16
HAND TOWEL BAR, bronze (Master
Bathroom, VIP Bathroom, 2 REP Bathrooms)
TBD
Y 1 6
1.17
TOILET PAPER HOLDER w/SHELF, bronze
(Master Bathroom, VIP Bathroom, 2 REP
Bathrooms)
TBD
Y 1 4
1.18
TOILET PAPER HOLDER EXTRA,
bronze(Master Bathroom, VIP Bathroom, 2
REP Bathrooms
TBD
Y 1 4
1.19
SINGLE HOOK, bronze (Master Bathroom, VIP Bathroom, 2 REP Bathrooms)
TBD
Y 1 6
1.20
DOUBLE HOOK, bronze (Master Bathroom, VIP Bathroom, 2 REP Bathrooms)
TBD
Y 1 6
1.21 BATH TOWEL BAR, steel (Guest Bathroom 1)
TBD
Y 1 1
1.22 HAND TOWEL BAR, steel (Guest Bathroom 1)
TBD
Y 1 1
1.23
TOILET PAPER HOLDER w/SHELF, steel
(Guest Bathroom 1)
TBD
Y 1 1
1.24
TOILET PAPER HOLDER EXTRA, steel
(Guest Bathrooom 1)
TBD
Y 1 1
1.25 SINGLE HOOK, steel (Guest Bathroom 1)
TBD
Y 1 1
1.26 DOUBLE HOOK, steel (Guest Bathroom 1)
TBD
Y 1 1
2 TILE
WALL TILE (GFCI)
2.1 WALL TILE (Master, 2nd fl.)
HAFARY: PXDUCI, 60x120 XX sq ft +10%= XXX sqft total
Y PSF XXX
2.2 WALL TILE (Guest Bathroom 1)
HAFARY: XXX, 30x60 XX sq ft +10%= XXX sqft total
Y PSF XXX
2.3
WALL TILE (Ladies Rep, 1st fl.)
HAFARY: AB-MA36540P, 30x60 Ladies Rep: 132 sqft (18pcs)
132 sq ft +10% overage = 145 sqft total
Y PSF 145
2.4
WALL TILE (Mens Rep, 1st fl.)
HAFARY: AB-MA36540P, 30x60
Mens Rep: 137 sqft (28 pcs)
137+ 10% overage = 150 sqft total
Y PSF 150
2.5 WALL TILE (VIP , 1st fl.)
HAFARY: PXDUCI 60x120 XX sq ft +10%= XXX sqft total
Y PSF XXX
FLOOR TILE (GFCI)
2.6 FLOOR TILE (Master Bathroom, 2nd fl.)
HAFARY: SUBLIME IVORY MATT R, 30 x 60 77 sq ft +10%= 85 sqft total
Y PSF 85
2.7 FLOOR TILE (Guest Bathroom 1, 2nd fl.)
HAFARY: SUBLIME IVORY MATT R, 30 x 60 42sq ft +10%= 46 sqft total
Y PSF 46
2.8 FLOOR TILE (Ladies Rep, 1st fl.)
HAFARY: SUBLIME IVORY MATT R, 30 x 60 151 sq ft +10%= 166 sqft total
Y PSF 166
2.9 FLOOR TILE (Mens Rep, 1st fl.)
HAFARY: SUBLIME IVORY MATT R, 30 x 60 63 sq ft +10%= 70 sqft total
Y PSF 70
2.1 FLOOR TILE (VIP, 1st fl.)
HAFARY: SUBLIME IVORY MATT R, 30 x 60 46 sq ft +10%= 50 sqft total
Y PSF 50
Accent Tiles
2.11 ACCENT TILE (Master Bathroom, 2nd fl.)
HAFARY: OPAL TURQUOISE REV, 7.5x30 XX sq ft +10%= XX sqft total
Y PPC
2.12
ACCENT TILE (Guest Bathroom 1, 2nd fl.)
HAFARY: SUBLIME IVORY MATT R, 30 x 60
XX sq ft +10%= XX sqft total
Y PPC
2.13 ACCENT TILE (VIP, 1st fl.)
HAFARY: SUBLIME IVORY MATT R, 30 x 60 XX sq ft +10%= XX sqft total
Y PPC
4. CONTRACT ADMINISTRATION
4.1 The Contractor shall not conduct any work that is beyond this
Statement of Work and accompanying specifications unless directed in writing by the Contracting Officer [CO]. Any work done by the
Contractor beyond this SOW and accompanying specifications without direction from the CO will be at the Contractor’s own risk and at no cost to the Embassy.
4.2 The Contracting Officer shall provide a Notice to Proceed [NTP] to the
Contractor. No work shall be initiated until the NTP is issued by the CO.
4.3 The Contracting Officer may designate more than one individual to serve as the Contracting Officer's Representative [COR]. The
Contractor will provide evidence of COR appointments, including explicit authority delegated to each COR and their responsibilities.
4.4 The Embassy does not make representations or warranties of whatsoever kind or nature, either expressed or implied, as to the quality, level of completion, accuracy, extent of compliance with the standards, codes and requirements described or referred to in this
SOW, or the extent of coordination between or among the documents provided to the Contractor.
4.5 The Embassy’s review, approval, or acceptance of, nor payment for the services required under this contract shall be construed to operate as a waiver of any rights under this contract or any cause of action against the Contractor arising out of the performance of this contract.
4.6 The Embassy has the right to inspect and test all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The Office of Overseas Buildings may perform quality assurance inspections [QAI] and tests during construction to confirm the work is installed according to the SOW.
4.7 The Contracting Officer has the authority to issue a temporary stop order during the execution of any particular phase of this SOW. This authority may be executed when the Embassy requires time for official functions or is in possession of specific credible information indicating that the lives of Embassy personnel are immediately threatened and that the execution of the project will increase the Embassy's vulnerability. The Contractor shall promptly notify the CO that work has been stopped.
4.8 If any of the Contractor’s services do not conform to the contract requirements, the COR may require the Contractor to perform the services again in conformity with the contract requirements. The
Embassy may by contract or otherwise, perform the services and charge the Contractor any cost incurred by the Embassy that is directly related to the performance of such service or terminate the contract for default.
4.9 The Embassy has the right to terminate this contract of convenience at any time in whole, or from time to time, if the Contracting Officer determines it is in the interest of the Embassy.
5. RESPONSIBILITY OF THE CONTRACTOR
5.1 The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all construction and other services furnished under this contract. The Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its construction and other services.
5.2 The Contractor shall identify a Project Site Manager who shall be responsible for the overall management of the project and shall represent the Contractor on the site during construction. The Project
Site Manager shall be approved by the COR.
5.3 The Project Site Manager shall attend all project meetings, prepare
Status Reports on the project and submit them to the COR. Status
Reports shall contain meeting minutes, accomplishments, arising concerns and proposed solutions, any proposed changed orders, and any other pertinent information required to report the progress of performance.
5.4 All documentation produced for this project will become the ownership of the Embassy at the completion of this project.
5.5 The Contractor shall verify that all materials, equipment, and systems provide operational dependability. The Contractor assures the completed construction shall be easily maintained or replaced with readily available materials and services.
5.6 Any cost associated with services subcontracted by the Contractor shall be borne by and be the complete responsibility of the Contractor under the fixed price of this contract.
5.7 The Contractor is responsible for safety and shall comply with all local labor laws, regulations, customs and practices pertaining to labor, safety and similar matters. The Contractor shall promptly report all accidents resulting in lost time, disabling, or fatal injuries to the COR.
5.8 The Contractor shall be and remain liable to the Embassy in accordance with applicable law for all damages to the Embassy caused by the Contractor's negligent performance of any of the services furnished under this contract. The rights and remedies for the Embassy provided for under this contract are in addition to any other rights and remedies provided by law.
6. PRE-CONSTRUCTION REQUIREMENTS
6.1 The Contractor shall examine all the documents and visit the site to fully inform themselves of all the conditions and limitations applied to the work and submit a firm fixed price cost proposal for all the work.
No subsequent cost allowance will be made to the Contractor for neglect of the existing conditions.
6.2 Provide a statement that the Contractor’s company and all personnel are experienced in installation of plumbing, masonry, carpentry, electrical similar to type and scope required for the work.
6.3 The Contractor shall prepare and submit a Quality Control Schedule
[QCS] and Project Safety Plan [PSP] to address the project. The QCS and PSP are intended to document the entire project from beginning to end.
6.4 Submit a copy of a Contractor’s Installation Guarantee covering the work, labor and equipment for a period of 0NE [1] year at no cost to the Embassy signed by the Contractor.
6.5 Submit a Bill of Materials [BOM], product literature, samples and standard specification submittals of all materials to be used in the project provided by the contractor. The BOM's shall list the equipment and materials in sufficient detail that a purchase order for the materials and equipment can be executed without further elaboration or specifications. These documents will be used by the Embassy to approve all equipment and materials.
7. CONSTRUCTION REQUIREMENTS
7.1 No construction shall begin until approvals of the Pre-Construction
Submittals that are accepted by the COR. These submittals are to demonstrate The Contractors adaptation of design concept drawings provided by the U.S. Embassy to ensure accordance with dimensions, materials, and finishes specified and intended for each bathroom.
7.2 The Contractor shall be responsible for all required materials not provided by the Embassy, equipment and personnel to manage, administer, and supervise the project. All workmanship shall be of high quality and performed in a skillful manner as determined by the COR.
7.3 All materials and equipment incorporated into the project shall be new unless noted otherwise. The Contractor shall transport and safeguard all materials and equipment required for construction.
7.4 Equipment and materials shall be carefully handled, properly stored, and adequately protected to prevent damage before and during installation, in accordance with the manufacturer's recommendations.
Damaged or defective items shall be replaced. The contractor will be responsible for security of all materials and equipment.
7.5 Receipt Of Materials - Shipment of equipment, materials, and supplies of contractor furnished items shall be addressed to the Contractor -not the Embassy. The Contractor must be on hand to accept shipments; the Embassy will not accept shipments.
7.6 The Contractor will be provided with a storage and staging area as determined by the COR. The Contractor shall be responsible for restoring the area to its original condition at the completion of the work. The Contractor shall be responsible for repair of any damage incurred to buildings or pavement as a result of storage activities. The
Contractor is responsible for obtaining any additional off compound storage areas as required.
7.7 The Contractor shall at all times keep the work area free from accumulation of waste materials. Upon completing construction, the
Contractor shall remove all temporary facilities and leave the project site in a clean and orderly condition acceptable to the COR.
7.8 The Contractor shall perform the work at the site from 9am to 6pm, Monday to Sunday (7 days a week), unless agreed upon with the COR.
7.9 At the end of each workday, or notification of a temporary stop order, the Contractor shall lower and fixed all temporary work platforms and/or harnesses. Contractor shall notify the COR of the temporary barricade locations. Beginning the next workday, the contractor shall remove the temporary barricades before continuing the project.
7.10 Cleanup - The contractor is responsible for the disposal of all construction materials from the renovated spaces to include but not limited to old toilets, sinks, counters, cabinets, fixtures, tiles, etc. The
Contractor shall keep the work area, including storage areas, free from accumulations of waste materials on a daily basis and comply with all federal, state and local regulations pertaining to the storage, transport and disposal of wastes. The Contractor shall not use Embassy waste disposal facilities including garbage cans, trash piles or dumpsters.
7.11 Landscape Restoration - The surfaces of all unpaved areas disturbed by construction activities shall be sodded with an approved grass native to the sodded area as approved by the COR. These shall include areas which existing pavement is removed, areas where excavation takes place, and areas where existing sod is killed or compacted by construction activities. Landscape shrubs killed or damaged by construction activities shall be replaced with same species and size.
8. CRITERIA
8.1 The Contractor work shall in accordance with U.S. codes and standards. If necessary, the contractor may use local standards, but they must be at the same or higher standards than U.S. codes. The
COR will review and comment on the Contractor’s submissions using the following codes and standards:
American Society for Testing & Materials, 2003 International Building
Code, 2003 International Mechanical Code, 2003 International
Plumbing Code, 2002 National Electrical Code (NFPA)
8.2 Statement of Work for Construction Services and the following accompanying specifications:
8.3 Manufacturer’s data sheets for installation of Government Furnished
Material (GFM) and Contractor Furnished Material (CFM).
9. DELIVERABLE SCHEDULE
9.1 The Contractor shall commence work under this contract promptly, execute the work diligently, and achieve final completion and acceptance including final cleanup of the premises within the period specified.
9.2 Milestones:
Contractor Pre-Proposal Site Visit Monday, August 4, 2025
Award of Contract & Notice to Proceed approximately SEPTEMBER 26, Pre-Construction Submittals Within 10 calendar days of Contract
Award.
Construction Begins immediately, no more than 5 calendar days of NTP
Construction 30 calendar days
9.3 Project Completion: Furnish one copy of maintenance and operating information, Contractor’s workmanship and materials guarantee, and product literature of all items installed.
10. PROJECT SECURITY
10.1 The work to be performed under this contract requires that the
Contractor, its employees and sub-contractors submit corporate, financial and personnel information for review by the Embassy.
Information submitted by the Contractor will not be disclosed beyond the Embassy.
10.2 The Contractor shall submit this information including construction vehicle requirements within 10 days of the Notice to Proceed.
11. ATTACHMENTS
11.1 Statement of Work continued on the following attachments (ref. 1.4):
APPENDIX A: Master Bathroom – 2nd Floor
APPENDIX B: Guest Bathroom 1 – 2nd Floor
APPENDIX C: Ladies’ Rep Bathroom – 1st Floor
APPENDIX D: Men’s Rep Bathroom – 1st Floor
APPENDIX E: VIP Bathroom – 1st Floor
11.2 APPENDIX F: Contractor Proposal Cost Matrix per Bathroom (ref. 1.4)
APPENDIX A
Master Bathroom, 2nd Floor
Existing Plan (roughly 75 sqft.)
Note: Dimensions and as-built conditions to be collected by interested parties during pre-proposal site visit. Design concept images and/or drawings will be furnished by U.S. Embassy during pre-proposal site visit. Reference section 9.2 for contractor pre-proposal site visit date.
APPENDIX A - MASTER BATHROOM - 2nd FLOOR (~75 sqft.)
CLIN Description of Service
GFCI
Government furnished
Contractor
Installed
CFCI
Contractor furnished
Contractor
Installed
1 DEMOLITION
BATHROOM FIXTURES:
Remove and dispose all existing bathroom fixtures and accessories:
- toilet
- sink/faucet
- shower plumbing
- bathtub/plumbing
- shelves/towel bars/towel hooks
BATHROOM VANITY:
Remove all existing bathroom cabinetry, mirrors, and accessories:
TILEWORK:
Demolish and dispose all wall/floor tile
SHOWER WALL AT TOILET AND VANITY:
Demolish existing two shower walls dividing toilet and dispose all wall/floor tile.
Demolish vanity and countertop.
GYPSOM BOARD:
Demolish and dispose painted gypsum board surfaces as noted in the concept design, CEILING:
Demolish and dispose all ceiling gypsum board surfaces as noted in the concept design
LIGHTING FIXTURES:
Remove and dispose all existing light fixtures
WOODWORK:
Remove and dispose all existing wood base trim, ceiling trim and door trim; retain and reuse all existing doors;
2 NEW WORK
Install new bathroom fixtures and accessories:
- Toilet (GFCI)
TOTO toilet, model C889DE#XW;
TOTO seat cover, model TC381VSR
- Sinks (2) (GFCI), KHOLER LADENA 21", model K-2215X-0
- Faucets (2) (GFCI)
DURAVIT Short, brushed bronze, model M #M WA1020002A04
- Shower head and fittings (GFCI)
DURAVIT, Shower system, model #WA4280008
Y
GYPSOM/BACKER BOARD:
Install all new walls and ceiling necessary to provide tile installation and painted surfaces as noted in the concept design.
Install all new tile for floor and shower walls as noted in the design concept elevations and finish floor plans. Contractor to provide grout, thin set, and grout sealer (CFCI)
WALL TILE, HAFARY: PXDUCI 60 x 120 (GFCI)
FLOOR TILE, HAFARY: SUBLIME IVORY MATT R, 30 x 60
(GFCI)
NOTE: USG to advise final grout colors (CFCI)
Y Y
Reuse existing doors; replace door trim on interior bathroom doors 3.25"
(CFCI)
Ensure all window frames and door frames are sufficiently finished/varnished glossy finish to meet moisture resistance in wet areas.
Install all new light fixtures
- Vanity wall sconces (GFCI)
SPEC: TBD
- Recessed LED lighting (round, channel, and tape) as noted in concept drawing and plans (CFCI)
SPEC: TBD
MIRRORS AND ACCESSORIES
Install all new vanity mirrors and hardware accessories
- Vanity wall mirrors (GFCI)
SPEC: TBD
- Towel bars, hooks, toilet paper holders, etc. (GFCI)
SPECS: TBD
GLAZING- SHOWER DIVIDER AND DOOR:
Install new glass shower wall and door glazing to the dimensions noted in drawings, partially frosted, tempered, 3/8 inch, 10mm rated shatterproof.
(CFCI)
Contractor to provide shower door hardware to match bathroom fixture color schedule that must be pre-approved by USG. (CFCI)
SHOWER FLOOR AND DRAIN:
Rough in recessed floor for curbless but sloped shower floor in shower.
Curbless or slightly recessed shower floor with a linear drain (CFCI) along one wall with a single slope with 30 x 60 tiles (GFCI). Curbless shower floor needs to have a consistent slope towards the drain to ensure proper water drainage. The standard slope is 1/4 inch per foot. The floor shall drop 1/4 inch for every foot away from the drain to ensure water flows efficiently to the drain without pooling.
VANITY COUNTERTOPS
Contractor to provide quartz countertops with backsplash (CFCI)
USG to select color from options available by contractor sourced materials.
VANITY CABINETS
Contractor to provide vanity cabinets in oak wood species, stained, with pulls to meet the aesthetic as noted in the concept design. Soft close hardware and hinges. (CFCI)
USG to select stain color and pulls from options available by contractor sourced materials.
Note - vanity to sit on top of finished floor tile
PAINTING
Clean old paint, repair plaster, prime and smooth surface, apply (2) coat of interior semi-gloss paint. (CFCI)
NAME - NIPPON "MELTED CREAM" NP OW 2147P (SEMI-GLOSS
FINISH) or equivalent.
Painting ceilings, two coats, (eggshell) paint, no surface preparation.
(CFCI)
NAME - NIPPON "MELTED CREAM" NP OW 2147P (EGGSHELL
FINISH) or equivalent
Painting trim/baseboards, two coats, (lead-free) paint, gloss finish, following surface preparation. (CFCI)
NIPPON "MELTED CREAM" NP OW 2147P (GLOSS FINISH) or equivalent
PLUMBING
Check and test all plumbing fixtures and snake-out all interior drain lines
Abandon in-place plumbing line from bathtub
Replace P-traps for bathroom sinks (2) (GFCI)
STANDARD BOTTLE TRAP A181A
Replace bathroom sink w/washerable lever type faucet, water & drain line connection (GFCI)
Replace bathroom sink (GFCI) Y
Replace bathroom sink faucet with washerable lever type, incl. Fittings & tubing. (GFCI)
Replace toilet, V.C. elongated type with low tank. Water & drain line
Replace shower head and mixing valve assembly including water line
Y
Replace shower valve, mixing (CFCI) Y
Replace shower head (GFCI) Y
Replace hose faucet, 1/2" dia (CFCI) Y
Remove bath tub and clean out drain and properly terminate all connection.
Replace shower floor drain with linear drain in matching finish with shower fixtures (CFCI)
Contractor is to determine new shower drain type and location based on the floor slope, linear drain, single slope direction to the linear drain along one edge of the floor
Replace ceramic tiles (GFCI) in the bathroom including cement mortar waterproofing work, and include grout, thin set, and grout sealer (CFCI).
Install shower enclosure with tempered glass panels and doors from finished floor to 8'6" celling (CFCI) in accordance with design concept.
Provide glass shower hardware to match finishes within bathroom
(CFCI).
ELECTRICAL
Remove/reinstall existing electric outlets and cover plates
Replace ceiling lighting fixtures with 6 recessed LED canless ceiling lights (220v equivalent) to Kitchler Direct to Ceiling LED Down Light, slim, 4" round, model DLSL04Rxx90WHT (CFCI) as noted in design concept drawings.
Install bathroom vanity sconces (GFCI) and 20 linear feet of recessed channel LED vanity lighting (CFCI) with 220v equivalent to Kelvix
Floor Wall Ceiling channel LED lighting, model CH-0201 or CH-
Install 20 linear feet of recessed tape LED lighting (CFCI) with 220v equivalent to American lighting COB SERIES TAPE LIGHT
CARPENTRY
Replace ceiling with 1/2" thick gypsum board incl. Taping (CFCI) Y
Remove wood furring, blocking & trim etc., at ceiling in order to raise ceiling height to 8'6" where indicated in design concept.
Install new insulation in ceiling. (CFCI) Y
Remove existing GWB wall partition and ceiling include frame based on design concept drawings
Replace base board with floor tile (GFCI) up 6", fully finished tile on exposed sides per design concept drawings.
Y
Replace door stopper and holder (CFCI) Y
Replace robe hook (GFCI) Y
Replace grab bar, 18"-20" if specified in design concept (GFCI) Y
Replace soap dish (GFCI) if specified Y
Replace toilet paper holder (GFCI) Y
Replace caulking for bathrooms Y
Replace towel bar (GFCI) Y
Replace vanity cabinet (CFCI) with oak species cabinet per concept drawings (as agreed upon by USG) incl. pulls (CFCI) sink (GFCI), water
& sewer line connection 700mm W x 490mm D x760mm H (CFCI)
Y Y
Install vanity cabinet over finished tile (CFCI) Y
Replace floor water proofing for shower room (CFCI) Y
Replace floor water proofing for latrine (CFCI) Y
Replace sink counter tops with quartz countertop and backsplash to fit sinks per concept drawings (CFCI)
MASONRY
Replace 6" tall capillary water barrier and expansion joint (CFCI) Y
Demolish bathroom floor tile and replace with GFCI Y
Demolish bathroom wall tile and replace with GFCI Y
CONTRACTOR FURNISHED MATERIALS - MASTER BATHROOM
Install all new walls and ceiling necessary to provide tile installation and painted surfaces as noted in the concept design.
TILEWORK:
Install all new tile for floor and shower walls as noted in the design concept elevations and finish floor plans. Contractor to provide grout, thin set, and grout sealer (CFCI)
NOTE: USG to advise final grout colors (CFCI)
WOODWORK:
Reuse existing doors; replace door trim on interior bathroom doors 3.25" (CFCI)
Ensure all window frames and door frames are sufficiently finished/varnished glossy finish to meet moisture resistance in wet areas.
LIGHTING FIXTURES:
Install all new light fixtures
- Vanity wall sconces (GFCI)
SPEC: TBD
- Recessed LED lighting (round, channel, and tape) as noted in concept drawing and plans
(CFCI)
SPEC: TBD
Replace ceiling lighting fixtures with 6 recessed LED canless ceiling lights (220v equivalent) to
Kitchler Direct to Ceiling LED Down Light, slim, 4" round, model DLSL04Rxx90WHT (CFCI) as noted in design concept drawings.
Install bathroom vanity sconces (GFCI) and 20 linear feet of recessed channel LED vanity lighting
(CFCI) with 220v equivalent to Kelvix Floor Wall Ceiling channel LED lighting, model CH-0201 or CH-0202
Install 20 linear feet of recessed tape LED lighting (CFCI) with 220v equivalent to American lighting
COB SERIES TAPE LIGHT
SHOWER FLOOR AND DRAIN:
Rough in recessed floor for curbless but sloped shower floor in shower. Curbless or slightly recessed shower floor with a linear drain (CFCI) along one wall with a single slope with 30 x 60 tiles (GFCI).
VANITY CABINETS
Contractor to provide vanity cabinets in oak wood species, stained, with pulls to meet the aesthetic as noted in the concept design. Soft close hardware and hinges. (CFCI)
USG to select stain color and pulls from options available by contractor sourced materials.
Note - vanity to sit on top of finished floor tile
VANITY COUNTERTOPS
Contractor to provide quartz countertops with backsplash (CFCI)
USG to select color from options available by contractor sourced materials.
PAINTING: (CFCI)
WALLS: Clean old paint, repair, prime and smooth surface, apply (2) coats of interior semi-gloss paint.
NAME - NIPPON "MELTED CREAM" NP OW 2147P (SEMI-GLOSS FINISH) or equivalent
CEILINGS: apply (2) coats, (eggshell) paint, following surface preparation.
NAME - NIPPON "MELTED CREAM" NP OW 2147P (EGGSHELL FINISH) or equivalent
TRIM/BASEBOARDS: apply (2) coats (lead-free) paint, gloss finish, following surface preparation.
NIPPON "MELTED CREAM" NP OW 2147P (GLOSS FINISH) or equivalent
Replace shower valve, mixing (CFCI)
Replace hose faucet, 1/2" dia (CFCI)
Replace shower floor drain with linear drain in matching finish with shower fixtures (CFCI)
Replace ceramic tiles (GFCI) in the bathroom including cement mortar waterproofing work, and include grout, thin set, and grout sealer (CFCI).
Install shower enclosure with tempered glass panels and doors from finished floor to 8'6" celling
(CFCI) in accordance with design concept. Provide glass shower hardware to match finishes within bathroom (CFCI).
Replace ceiling with 1/2" thick gypsum board incl. Taping (CFCI)
Install new insulation in ceiling. (CFCI)
Replace door stopper and holder (CFCI)
Replace caulking for bathrooms (CFCI)
Replace floor water proofing for shower room (CFCI)
Replace floor water proofing for latrine (CFCI)
Replace sink counter tops with quartz countertop and backsplash to fit sinks per concept drawings
Replace 6" tall capillary water barrier and expansion joint (CFCI)
APPENDIX B
Guest Bathroom 1, 2nd Floor
Existing Plan (roughly 35 sqft.)
APPENDIX B - GUEST BATHROOM 1, 2nd FLOOR (~35 sqft.)
CLIN Description of Service
GFCI
Government furnished
Contractor
Installed
CFCI
Contractor furnished
- toilet
- sink/faucet
- shower plumbing
Demolish existing two shower walls dividing toilet and dispose all
- Toilet (GFCI)
TOTO toilet, model C889DE#XW;
TOTO seat cover, model TC381VSR
- Sinks (GFCI), KHOLER LADENA 18", model K-2214X
- Faucets (GFCI)
DURAVIT short, brushed stainless steel, model WA10200032A04, NONAME, push-open stopper, brushed stainless steel, model N43A
- Shower head and fittings (GFCI)
DURAVIT shower system, brushed steel, model WA5280008 concept elevations and finish floor plans. Contractor to provide grout, thin set, and grout sealer (CFCI)
WALL TILE, LSH: POL PETRA WHITE, 30x60 (GFCI)
FLOOR TILE, HAFARY: SUBLIME IVORY MATT R, 30 x 60 (GFCI)
(CFCI)
Ensure all window frames and door frames are sufficiently
- Vanity wall sconces (GFCI)
SPEC: TBD
- Recessed LED lighting (round, channel, and tape) as noted in concept drawing and plans (CFCI)
- Vanity wall mirrors (GFCI)
SPEC: TBD
- Towel bars, hooks, toilet paper holders, etc. (GFCI) drawings, partially frosted, tempered, 3/8 inch, 10mm rated shatterproof.
(CFCI)
Contractor to provide shower door hardware to match bathroom fixture color schedule that must be pre-approved by USG. (CFCI)
Curbless or slightly recessed shower floor with a linear drain (CFCI) along one wall with a single slope with 30 x 60 tiles (GFCI). Curbless shower floor needs to have a consistent slope towards the drain to ensure proper water drainage. The standard slope is 1/4 inch per foot. The floor shall drop 1/4 inch for every foot away from the drain to ensure water flows efficiently to the drain without pooling.
USG to select color from options available by contractor sourced pulls to meet the aesthetic as noted in the concept design. Soft close hardware and hinges. (CFCI)
USG to select stain color and pulls from options available by contractor sourced materials.
NAME - NIPPON "MELTED CREAM" NP OW 2147P (SEMI-GLOSS
Painting ceilings, two coat, (eggshell) paint, no surface preparation.
NAME - NIPPON "MELTED CREAM" NP OW 2147P (EGGSHELL
Painting trim/baseboards, two coat, (lead-free) paint, gloss finish, NIPPON "MELTED CREAM" NP OW 2147P (GLOSS FINISH) or
PLUMBING
Replace P-traps for bathroom sinks (GFCI)
Y
Replace shower valve, mixing (CFCI) Y
Replace shower head (GFCI) Y
Replace hose faucet, 1/2" dia (CFCI) Y
Remove bathtub and clean out drain properly Y
Replace floor drain with linear drain (CFCI) Y
Contractor is to determine new shower drain type and location based on the floor slope, linear drain, single slope direction to the linear drain along one edge of the floor
Install shower enclosure with tempered glass panels and doors from finished floor to 8'6" celling (CFCI) in accordance with design concept.
Provide glass shower hardware to match finishes within bathroom.
Replace ceiling lighting fixtures with 4 recessed LED canless ceiling slim, 4" round, model DLSL04Rxx90WHT (CFCI) as noted in design
Install bathroom vanity sconces (GFCI) and 8 linear feet of recessed
Floor Wall Ceiling channel LED lighting, model CH-0201 or CH-
Install 8 linear feet of recessed tape LED lighting (CFCI) with 220v
Replace base board with floor tile (GFCI) up 6" and finish with Schluter strip (CFCI) or pencil tile (CFCI)
USG to select Schluter strip or pencil tile trim from options available by contractor sourced materials.
Y Y
Replace door stopper and holder (CFCI) Y
Replace robe hook (GFCI) Y
Replace grab bar, 18"-20" if specified in design concept (GFCI) Y
Replace soap dish (GFCI) if specified Y
Replace toilet paper holder (GFCI) Y
& sewer line connection 700mm W x 490mm D x760mm H (CFCI)
Y Y
Install medicine cabinet in wall (CFCI) Y
Install vanity cabinet over finished tile (CFCI) Y
Replace sink counter tops with quartz countertop to fit sinks per concept drawings (CFCI)
Replace 6" tall capillary water barrier and expansion joint Y
CONTRACTOR FURNISHED MATERIALS - GUEST 1 BATHROOM
Install all new walls and ceiling necessary to provide tile installation and painted surfaces as noted in the concept design.
TILEWORK:
Install all new tile for floor and shower walls as noted in the design concept elevations and finish floor plans. Contractor to provide grout, thin set, and grout sealer (CFCI)
NOTE: USG to advise final grout colors (CFCI)
WOODWORK:
Reuse existing doors; replace door trim on interior bathroom doors 3.25" (CFCI)
Ensure all window frames and door frames are sufficiently finished/varnished glossy finish to meet moisture resistance in wet areas.
LIGHTING FIXTURES:
Install all new light fixtures
- Vanity wall sconces (GFCI)
SPEC: TBD
- Recessed LED lighting (round, channel, and tape) as noted in concept drawing and plans
(CFCI)
SPEC: TBD
Replace ceiling lighting fixtures with 4 recessed LED canless ceiling lights (220v equivalent) to
Kitchler Direct to Ceiling LED Down Light, slim, 4" round, model DLSL04Rxx90WHT (CFCI) as noted in design concept drawings.
Install bathroom vanity sconces (GFCI) and 8 linear feet of recessed channel LED vanity lighting
(CFCI) with 220v equivalent to Kelvix Floor Wall Ceiling channel LED lighting, model CH-0201 or CH-0202
Install 8 linear feet of recessed tape LED lighting (CFCI) with 220v equivalent to American lighting
COB SERIES TAPE LIGHT
SHOWER FLOOR AND DRAIN:
Rough in recessed floor for curbless but sloped shower floor in shower. Curbless or slightly recessed shower floor with a linear drain (CFCI) along one wall with a single slope with 30 x 60 tiles (GFCI).
VANITY CABINETS
Contractor to provide vanity cabinets in oak wood species, stained, with pulls to meet the aesthetic as noted in the concept design. Soft close hardware and hinges. (CFCI)
USG to select stain color and pulls from options available by contractor sourced materials.
Note - vanity to sit on top of finished floor tile
VANITY COUNTERTOPS
USG to select color from options available by contractor sourced materials.
PAINTING: (CFCI)
WALLS: Clean old paint, repair, prime and smooth surface, apply (2) coats of interior semi-gloss paint.
NAME - NIPPON "MELTED CREAM" NP OW 2147P (SEMI-GLOSS FINISH) or equivalent
CEILINGS: apply (2) coats, (eggshell) paint, following surface preparation.
NAME - NIPPON "MELTED CREAM" NP OW 2147P (EGGSHELL FINISH) or equivalent
TRIM/BASEBOARDS: apply (2) coats (lead-free) paint, gloss finish, following surface preparation.
NIPPON "MELTED CREAM" NP OW 2147P (GLOSS FINISH) or equivalent
Replace shower valve, mixing (CFCI)
Replace hose faucet, 1/2" dia (CFCI)
Replace shower floor drain with linear drain in matching finish with shower fixtures (CFCI)
Replace ceramic tiles (GFCI) in the bathroom including cement mortar waterproofing work, and include grout, thin set, and grout sealer (CFCI).
Install shower enclosure with tempered glass panels and doors from finished floor to 8'6" celling
(CFCI) in accordance with design concept. Provide glass shower hardware to match finishes within bathroom (CFCI).
Replace ceiling with 1/2" thick gypsum board incl. Taping (CFCI)
Install new insulation in ceiling. (CFCI)
Replace door stopper and holder (CFCI)
Replace caulking for bathrooms (CFCI)
Replace floor water proofing for shower room (CFCI)
Replace floor water proofing for latrine (CFCI)
Replace sink counter tops with quartz countertop and backsplash to fit sinks per concept drawings
APPENDIX C
Ladies’ Rep Bathroom, 1st Floor
Existing Plan (roughly 125 sqft.)
APPENDIX C - LADIES' REP BATHROOM, 1st FLOOR (~75 sqft.)
CLIN Description of Service
GFCI
Government furnished
Contractor
Installed
CFCI
Contractor furnished
- toilet
- sink/faucet
BATHROOM VANITIES (2):
- Toilet (GFCI)
TOTO toilet, model C889DE#XW;
TOTO seat cover, model TC381VSR
- Sinks (2) (GFCI), KHOLER LADENA 21", model K-2215X-0 (QTY 1)
KHOLER FOREFRONT SEMI-RECESSED 18", model K-98930X-1-0
(QTY 1)
- Faucets (2) (GFCI)
DURAVIT Short, brushed bronze, model M #M WA1020002A0 4 (QTY
1)
DURAVIT tall, brushed bronze, model WA1040002 (QTY 1)
GROHE, push-open stopper, brushed warm sunset, model 65807 (QTY 2)
GROHE Trap, 1 1/4" brushed warm sunset, model 28 912 DLO (QTY 1) concept elevations and finish floor plans. Contractor to provide grout, thin set, and grout sealer (CFCI)
WALL TILE: TBD 30x60 (GFCI)
FLOOR TILE, HAFARY: SUBLIME IVORY MATT R, 30x60 (GFCI)
(CFCI)
Ensure all window frames and door frames are sufficiently
- Vanity wall sconces (GFCI)
SPEC: TBD
- Recessed LED lighting (round, channel, and tape) as noted in concept drawing and plans (CFCI)
- Vanity wall mirrors (GFCI)
SPEC: TBD
- Towel bars, hooks, toilet paper holders, etc. (GFCI)
USG to select color from options available by contractor sourced pulls to meet the aesthetic as noted in the concept design. (CFCI)
USG to select stain color and pulls from options available by contractor sourced materials.
VANITY COUNTERTOPS (2)
Contractor to provide quartz countertops and backsplash (CFCI)
USG to select color from options available by contractor sourced
VANITY CABINETS (2)
Contractor to provide vanity cabinets (2) in oak wood species, stained, with pulls to meet the aesthetic as noted in the concept design. Soft close hardware and hinges. (CFCI)
USG to select stain color and pulls from options available by contractor sourced materials.
NAME - NIPPON "MELTED CREAM" NP OW 2147P (SEMI-GLOSS
NAME - NIPPON "MELTED CREAM" NP OW 2147P (EGGSHELL
NIPPON "MELTED CREAM" NP OW 2147P (GLOSS FINISH) or
Replace P-traps for bathroom sinks (2) (GFCI)
STANDARD BOTTLE TRAP A181A (QTY 1)
Replace ceiling lighting fixtures with 8 recessed LED canless ceiling slim, 4" round, model DLSL04Rxx90WHT (CFCI) as noted in design
Install bathroom vanity sconces (GFCI) and 20 linear feet of recessed
Floor Wall Ceiling channel LED lighting, model CH-0201 or CH-
Install 20 linear feet of recessed tape LED lighting (CFCI) with 220v
USG to select Schluter strip or pencil tile trim from options available by contractor sourced materials.
Y Y
Replace door stopper and holder (CFCI) Y
Replace robe hook (GFCI) Y
Replace grab bar, 18"-20" if specified in design concept (GFCI) Y
Replace soap dish (GFCI) if specified Y
Replace toilet paper holder (GFCI) Y
Replace vanity cabinets (QTY 2) (CFCI) with oak species cabinet per concept drawings (as agreed upon by USG) incl. pulls (CFCI) sink
(GFCI), water & sewer line connection 700mm W x 490mm D x760mm
H (CFCI)
Y Y
Install vanity cabinets over finished tile (CFCI) Y
Replace sink counter tops with quartz countertop to fit sinks per concept
CONTRACTOR FURNISHED MATERIALS - LADIES REP BATHROOM
GYPSOM/BACKER BOARD:
Install all new walls and ceiling necessary to provide tile installation and painted surfaces as noted in the concept design.
TILEWORK:
Install all new tile for floor and shower walls as noted in the design concept elevations and finish floor plans. Contractor to provide grout, thin set, and grout sealer (CFCI)
NOTE: USG to advise final grout colors (CFCI)
WOODWORK:
Reuse existing doors; replace door trim on interior bathroom doors 3.25" (CFCI)
Ensure all window frames and door frames are sufficiently finished/varnished glossy finish to meet moisture resistance in wet areas.
LIGHTING FIXTURES:
Install all new light fixtures
- Vanity wall sconces (GFCI)
SPEC: TBD
- Recessed LED lighting (round, channel, and tape) as noted in concept drawing and plans
(CFCI)
SPEC: TBD
Replace ceiling lighting fixtures with 8 recessed LED canless ceiling lights (220v equivalent) to
Kitchler Direct to Ceiling LED Down Light, slim, 4" round, model DLSL04Rxx90WHT (CFCI) as noted in design concept drawings.
Install bathroom vanity sconces (GFCI) and 20 linear feet of recessed channel LED vanity lighting
(CFCI) with 220v equivalent to Kelvix Floor Wall Ceiling channel LED lighting, model CH-0201 or CH-0202
Install 20 linear feet of recessed tape LED lighting (CFCI) with 220v equivalent to American lighting
COB SERIES TAPE LIGHT
VANITY CABINETS (2)
Contractor to provide vanity cabinets in oak wood species, stained, with pulls to meet the aesthetic as noted in the concept design. Soft close hardware and hinges. (CFCI)
USG to select stain color and pulls from options available by contractor sourced materials.
Note - vanity to sit on top of finished floor tile
VANITY COUNTERTOPS (2)
Contractor to provide quartz countertops with backsplash (CFCI)
USG to select color from options available by contractor sourced materials.
PAINTING: (CFCI)
WALLS: Clean old paint, repair, prime and smooth surface, apply (2) coats of interior semi-gloss paint.
NAME - NIPPON "MELTED CREAM" NP OW 2147P (SEMI-GLOSS FINISH) or equivalent
CEILINGS: apply (2) coats, (eggshell) paint, following surface preparation.
NAME - NIPPON "MELTED CREAM" NP OW 2147P (EGGSHELL FINISH) or equivalent
TRIM/BASEBOARDS: apply (2) coats (lead-free) paint, gloss finish, following surface preparation.
NIPPON "MELTED CREAM" NP OW 2147P (GLOSS FINISH) or equivalent
Replace ceramic tiles (GFCI) in the bathroom including cement mortar waterproofing work, and include grout, thin set, and grout sealer (CFCI).
Replace ceiling with 1/2" thick gypsum board incl. Taping (CFCI)
Install new insulation in ceiling. (CFCI)
Replace door stopper and holder (CFCI)
Replace caulking for bathrooms (CFCI)
Replace floor water proofing for latrine (CFCI)
Replace sink counter tops with quartz countertop and backsplash to fit sinks per concept drawings
APPENDIX D
Men’s Rep Bathroom, 1st Floor
Existing Plan (roughly 56 sqft.)
APPENDIX D - MEN'S REP BATHROOM, 1st FLOOR (~56 sqft.)
CLIN Description of Service
GFCI
Government furnished
Contractor
Installed
CFCI
Contractor furnished
Remove and dispose of all existing bathroom fixtures and accessories:
- toilet
- sink/faucet
Demolish and dispose of all wall/floor tile
Demolish and dispose painted gypsom board surfaces as noted in the
Demolish and dispose of all ceiling gypsom board surfaces as noted in the
Remove and dispose of all existing light fixtures
Remove and dispose of all existing wood base trim, ceiling trim and door
- Toilet (GFCI)
TOTO toilet, model C889DE#XW;
TOTO seat cover, model TC381VSR
- Sinks (1) (GFCI), KHOLER FOREFRONT SEMI-RECESSED 18", model K-98930X-1-0
(QTY 1)
- Faucets (1) (GFCI)
DURAVIT tall, brushed bronze, model WA1040002 (QTY 1)
GROHE, push-open stopper, brushed warm sunset, model 65807 (QTY 1) concept elevations and finish floor plans. Contractor to provide grout, thin set, and grout sealer (CFCI)
WALL TILE: TBD 30x60 (GFCI)
FLOOR TILE, HAFARY: SUBLIME IVORY MATT R, 30x60 (GFCI)
(CFCI)
Ensure all window frames and door frames are sufficiently
- Vanity wall sconces (GFCI)
SPEC: TBD
- Recessed LED lighting (round, channel, and tape) as noted in concept drawing and plans (CFCI)
- Vanity wall mirrors (GFCI)
SPEC: TBD
- Towel bars, hooks, toilet paper holders, etc. (GFCI)
USG to select color from options available by contractor sourced pulls to meet the aesthetic as noted in the concept design. (CFCI)
USG to select stain color and pulls from options available by contractor sourced materials.
NAME - NIPPON "MELTED CREAM" NP OW 2147P (SEMI-GLOSS
NAME - NIPPON "MELTED CREAM" NP OW 2147P (EGGSHELL
NIPPON "MELTED CREAM" NP OW 2147P (GLOSS FINISH) or
Replace P-traps for bathroom sink (GFCI)
Replace ceiling lighting fixtures with 4 recessed LED canless ceiling slim, 4" round, model DLSL04Rxx90WHT (CFCI) as noted in design
Install bathroom vanity sconces (GFCI) and 8 linear feet of recessed
Floor Wall Ceiling channel LED lighting, model CH-0201 or CH-
USG to select Schluter strip or pencil tile trim from options available by contractor sourced materials.
Y Y
Replace door stopper and holder (CFCI) Y
Replace robe hook (GFCI) Y
Replace grab bar, 18"-20" if specified in design concept (GFCI) Y
Replace soap dish (GFCI) if specified Y
Replace toilet paper holder (GFCI) Y
& sewer line connection 700mm W x 490mm D x760mm H (CFCI)
Y Y
Install vanity cabinet over finished tile (CFCI) Y
Replace sink counter tops with quartz counter top to fit sinks per concept
CONTRACTOR FURNISHED MATERIALS - MENS REP BATHROOM
Install all new walls and ceiling necessary to provide tile installation and painted surfaces as noted in the concept design.
TILEWORK:
Install all new tile for floor and shower walls as noted in the design concept elevations and finish floor plans. Contractor to provide grout, thin set, and grout sealer (CFCI)
NOTE: USG to advise final grout colors (CFCI)
WOODWORK:
Reuse existing doors; replace door trim on interior bathroom doors 3.25" (CFCI)
Ensure all window frames and door frames are sufficiently finished/varnished glossy finish to meet moisture resistance in wet areas.
LIGHTING FIXTURES:
Install all new light fixtures
- Vanity wall sconces (GFCI)
SPEC: TBD
- Recessed LED lighting (round, channel, and tape) as noted in concept drawing and plans
(CFCI)
SPEC: TBD
Replace ceiling lighting fixtures with 4 recessed LED canless ceiling lights (220v equivalent) to
Kitchler Direct to Ceiling LED Down Light, slim, 4" round, model DLSL04Rxx90WHT (CFCI) as noted in design concept drawings.
Install bathroom vanity sconces (GFCI) and 8 linear feet of recessed channel LED vanity lighting
(CFCI) with 220v equivalent to Kelvix Floor Wall Ceiling channel LED lighting, model CH-0201 or CH-0202
Install 8 linear feet of recessed tape LED lighting (CFCI) with 220v equivalent to American lighting
COB SERIES TAPE LIGHT
VANITY CABINET
Contractor to provide vanity cabinets in oak wood species, stained, with pulls to meet the aesthetic as noted in the concept design. Soft close hardware and hinges. (CFCI)
USG to select stain color and pulls from options available by contractor sourced materials.
Note - vanity to sit on top of finished floor tile
VANITY COUNTERTOP
Contractor to provide quartz countertops with backsplash (CFCI)
USG to select color from options available by contractor sourced materials.
PAINTING: (CFCI)
WALLS: Clean old paint, repair, prime and smooth surface, apply (2) coats of interior semi-gloss paint.
NAME - NIPPON "MELTED CREAM" NP OW 2147P (SEMI-GLOSS FINISH) or equivalent
CEILINGS: apply…