This document is a Request for Quotes (RFQ) issued by the U.S. Consulate General, Karachi for the installation of Forced Entry and Ballistic Resistant (FEBR) windows at the U.S. Consulate in Karachi, Pakistan.

The Consulate requires a local contractor to provide all architectural and engineering services, materials, specialized labor, and tools to design and build the installation of three new FEBR windows with teller trays in the Consular CAC pass back booth. The work includes removal of the existing FEBR windows, demolition of the existing concrete wall below the windows, and installation of the new FEBR windows with deal trays. The contractor must also provide electrical, telecommunications, and fire protection services as part of the project. The solicitation outlines the required submittals, the construction schedule, payment terms, and other special requirements. Quotes are due by July 8, 2024 and the Consulate intends to award a firm-fixed price contract to the responsible offeror submitting the lowest acceptable price, without holding discussions, though discussions may be held if necessary. A site visit is scheduled for July 1, 2024.

View the file

Other files

File Type Posted
SITE VISIT NOTES.pdf PDF
15-Minute Welding Details.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

19PK4024Q5034 PR12551130 - Installation of Forced Entry and Ballistic Resistant (FEBR) Windows at U.S. Consulate, Karachi

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

19PK4024Q5034

2. TYPE OF SOLICITATION

SEALED BID (IFB)

[x] NEGOTIATED (RFP)

3. DATE

ISSUED

June 12, 2024

PAGE OF

PAGES

1/49

IMPORTANT -

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST

NO. PR12551130

6. PROJECT NO. Installation of Forced Entry and Ballistic Resistant (FE/BR) Teller Windows at US Consulate, Karachi

7. ISSUED BY CODE 8. ADDRESS OFFER TO

Contracting Officer, GSO-Procurement & Contracting Office American Embassy, Karachi Plot 3-5, New TPX Area. MT Khan Road.

Mai Kolachi, Karachi, Pakistan.

19PK4024Q5034

Contracting Officer, GSO-Procurement & Contracting Office Plot 3-5, New TPX Area. MT Khan Road.

Mai Kolachi, Karachi, Pakistan

9. FOR INFORMATION

CALL:

A. NAME

Erwin, Penelope J.

B. TELEPHONE NO. (Include area code) (NO COLLECT

CALLS)

+92-213-5275000

SOLICITATION

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

TABLE OF CONTENTS

A. Price B. Scope of Work C. Packaging and Marking D. Inspection and Acceptance E. Deliveries/Performance F. Administrative Data G. Special Requirements H. Clauses

I. List of Attachments J. Quotation Information K. Evaluation Criteria L. Representations, Certifications, and other Statements of Offerors or Quoters

11. The Contractor shall begin performance within _10_ calendar days and complete it within 120 Working Days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See _______________.)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT

BONDS?

YES NO

12B. CALENDAR DAYS

05 Days After award

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and 02 copies to perform the work required are due at the place specified in Item 8 by 1500 (hour) local time on July 08, 2024. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show

B. An offer guarantee is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e)

19PK4024Q5034 PR12551130 - Installation of Forced Entry and Ballistic Resistant (FEBR) Windows at U.S. Consulate, Karachi

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item

14)

CODE FACILITY CODE

17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within _____ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS

SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION

PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )

26. ADMINISTERED BY CODE GSO 27. PAYMENT WILL BE MADE BY

Contracting Officer, Plot 3-5, New TPX Area. MT Khan Road. Mai Kolachi, Pakistan Karachi

Financial Management Officer (FMO) Plot 3-5, New TPX Area. MT Khan Road.

Mai Kolachi, Karachi, Pakistan.

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.)

Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses,

29. AWARD (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON

AUTHORIZED TO SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE

30C. DATE

31B. UNITED STATES OF AMERICA

31C. AWARD

DATE

19PK4024Q5034 PR12551130 - Installation of Forced Entry and Ballistic Resistant (FEBR) Windows at U.S. Consulate, Karachi

TABLE OF CONTENTS

SF-18 OR SF-1442 COVER SHEET

A. PRICING

B. STATEMENT OF WORK

C. PACKAGING AND MARKING

D. INSPECTION AND ACCEPTANCE

E. DELIVERIES AND PERFORMANCE

F. CONTRACT ADMINISTRATION DATA

G. SPECIAL TERMS AND CONDITIONS

H. CLAUSES

I. LIST OF ATTACHMENTS

Attachment 1: Sample Letter of Bank Guaranty Attachment 2: Breakdown of Price by Divisions of Specifications

J. INSTRUCTIONS ON HOW TO SUBMIT A QUOTATION

K. EVALUATION CRITERIA

L. REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS

19PK4024Q5034 PR12551130 - Installation of Forced Entry and Ballistic Resistant (FEBR) Windows at U.S. Consulate, Karachi

SECTION A - PRICING

A.1 CONTRACT PRICE

U.S. Consul General Karachi requires local contractor to provide all A&E Services, materials, specialized labor, tool to Provide Design and Build services for Installation of Forced Entry and Ballistic Resistant (FE/BR) Teller Windows. This price shall include all labor, materials, all insurances, overhead and profit required under this purchase order for the following firm fixed price and within the time specified.

Total Price (including all labor, materials, overhead and profit) PKR

A.2 VALUE ADDED TAX (VAT). The Government will not reimburse the Contractor for VAT under this contract. The Contractor shall not include a line for VAT on invoices as the U.S. Consulate General, Karachi will obtain tax exemption certificate from the host government.

A.2 TYPE OF CONTRACT

This is a firm, fixed- price contract payable entirely in the currency indicated in the SF-1442. No additional sums will be payable for any escalation in the cost of materials, equipment or labor, or because of the Contractor's failure to properly estimate or accurately predict the cost or difficulty of achieving the results required. The Government will not adjust the contract price due to fluctuations in currency exchange rates. The Government will only make changes in the contract price or time to complete due to changes made by the Government in the work to be performed, or by delays caused by the Government.

The Government will make payments based on quantities and unit prices only to the extent specifically provided in the contract.

SERVICES

The Contractor shall provide all materials, equipment, labor, engineering, and construction services required for the installation of FE/BR/Blast Teller windows at the US Consulate General Karachi. The contractor is to perform the services in accordance with the terms and conditions of this solicitation, and in strict conformance with the contract clauses and any special conditions contained herein.

TYPE OF CONTRACT

This is a firm fixed-price contract payable entirely in the currency indicated by the Contractor. No additional sums shall be payable due to any escalation in the cost of materials, equipment, or labor, or because of the Contractor's failure to properly estimate or accurately predict the cost or difficulty of achieving the results required by this contract. Nor will the contract price be adjusted on account of fluctuations in currency exchange rates. Changes in the contract price or time to complete will be made only due to changes made by the Government in the work to be performed, or by delays caused by the Government, as determined and approved by the Contracting Officer.

CONTRACT PRICE

The Contractor shall complete all work, including furnishing all labor, material, equipment and services, unless otherwise specified herein, required under this contract for the firm fixed price(s) indicated below and within the time specified herein. The price(s) stated shall include any and all costs of labor, materials, equipment, services, insurance bonds or irrevocable letters of guarantee (if required), overhead, other indirect costs, and profit. Any costs not priced will be considered to be included in the overhead and other indirect costs.

19PK4024Q5034 PR12551130 - Installation of Forced Entry and Ballistic Resistant (FEBR) Windows at U.S. Consulate, Karachi

The offeror shall insert the prices, and the currency in which the offer is made, below:

CONSTRUCTION REQUIREMENTS

installation, and required services, insurance, bonds or irrevocable letters of guaranty (if required), overhead, other indirect costs, and profit.

COST OF MATERIALS / EQUIPMENT

The cost of any materials or equipment required in conjunction with the services rendered herein shall be included in the proposed firm fixed price.

SECTION B STATEMENT OF WORK

US Consulate Karachi, Pakistan

DESIGN AND BUILD

STATEMENT of WORK

For

Installation of Forced Entry and Ballistic Resistant (FEBR) Windows

INTRODUCTION:

labor, tools, materials, transportation etc. for the design and build contract of installation of three new FEBR windows at CCAC. All work will be performed within in firm fixed-price contract.

BACKGROUND:

The CCAC pass back booth currently have three windows with only one having teller tray.

Consular requested to install all three windows built with teller trays.

PROJECT DESCRIPTION AND SPECIFICS:

The US Consulate, Karachi seeks to acquire design and build services for the Installation of Teller Windows at Consular CAC pass back booth (C103-02). There are 03 Nos. FEBR windows in the consular pass back booth and only 01 window has the deal tray. The expected number of visa applicants have increased over the period of few months and there is a new requirement to provide deal tray to all three windows. The works shall include removal of existing FEBR windows, demolition of existing concrete wall below the existing FEBR windows to make way for installation of new FEBR windows with deal trays. All the 03 windows are embedded in one sub-frame. The whole sub-frame does not need to be taken out. Only a portion of the sub-frame below the bottom of windowsill must be removed. Once the portion of sub-frame is removed, install a new half sub-frame that will slide into the existing jambs and header. The jointing of old and new sub-frame will be through 15-minute FEBR welding. Later, install 03 new teller windows and center posts. The construction debris can be removed using the CAC entrance to motor pool parking towards SCAC. During the course of execution, one side of CAC will remain operational for routine customers however, additional security escorts will be required for surveillance.

Work Execution / Scope of Deliverables:

Project Site Visit

After the issuance of Notice to Proceed, the contractor shall visit the project site to verify project requirements and existing condition of the site. The contractor shall verify/measure all dimensions and layout of the property including structure(s), site, and utilities for the development of existing A&E details outlined below. The details shall be coordinated with the COR before proceeding with the works.

Architectural & Engineering Services

Architectural Scope:

This project involves dismantling of existing FEBR windows, demolition of the existing concrete wall below them and installation of new FEBR windows with deal trays as shown in the schematic drawings attached with this SOW. The contractor shall provide the 2D design drawings for all architectural/civil works, demolition plan, construction plan and submittals with samples/data sheets of all materials for approval.

Once the windows are removed, existing concrete wall below the windows will be demolished to the required height (as per approved construction plan) for new FEBR windows (with deal trays).

The gypsum drywall, countertops (with steel tube framing), fire rated insulation and metal stud framing around the FEBR window shall also be removed. Roof ceiling and adjacent dry walls shall be protected by Polyurethane sheeting (as per approved design BoQ) during demolition.

Once the new FEBR windows are installed, new metal stud framing, insulation and gypsum drywalls shall be installed as per approved design and specifications. New Stone/Corian countertops (As per approved Design BoQ) shall be installed on new steel tubing.

accessible table has a surface height of no more than 34 inches and no less than 28 working drawings for review and design acceptance including but not limited to plans, materials plan and finish schedule, sections, blow-up details of counter tops, deal trays, drywall returns and FEBR window assembly.

Vertical Acoustic panels (As per approved Design BoQ) are to be installed on applicant and Visa officer side of the FEBR windows for sound dissipation. All new drywall gypsum wall surfaces shall be painted (Approx 800 Sqft Area) with approved color scheme to match finish schedule of the finishes on adjacent walls as per approved design/technical specifications and approved submittals.

Conduits (EMT Conduits Provided by Facilities team inhouse) for phone connectivity will need to be placed in the concrete wall below the FEBR windows.

All penetrations will need to be caulking and fire stop system to meet FEBR requirements.

There is an additional requirement to provide microphone connectivity from the will be made through the concrete FEBR wall to provide a conduit through which a speaker and microphone may be connected. FEBR and fire rated caulking will be provided on both sides of this penetration.

The 2D architectural shop drawings will include finishes and acoustical panel details will be prepared by the contractor and submitted for approval.

Structural Engineering Scope:

Assessment of the adequacy of the remaining existing construction of wall (structural analysis) for the revised wall configuration with a new FEBR window. The contractor shall submit a detailed design document (100% submittal), relevant revised structural drawings design calculations comprising of analysis model and/ or outputs verifying the adequacy of the as-built construction. (Structural analysis of this concrete wall in existing vs after modification conditions.)

Review the as-built construction drawings and verify the as-built construction during the demolition of the existing FEBR windows and saw-cutting concrete to enlarge the existing opening. Notify the COR of any discrepancies.

Before commencing any work, the contractor shall provide a demolition plan (jackhammering is not allowed). (contractor will share details of their tools and equipment for prior construction acceptance)

The contractor shall submit structural calculations demonstrating the equivalence of the new post-installed anchors to Nelson welded studs shown in FEBR window shop drawings.

(Post has already placed an order for the FE/BR Windows and FEBR windows and anchoring details will come along with the offshore consignment which will be shared with the contractor respectively.

The contractor shall provide a complete design drawing illustrating connection detail between the existing FEBR window frame (1/2-inch-thick steel plate) to remain and the new FEBR window frame (1/2-inch-thick steel plate - See FEBR window shop drawing).

Provide the exact dimension of the concrete removal required for the enlarged window. Do not overcut the existing concrete wall below the windowsill. (Existing frame will remain from three sides while new windows will be installed from the bottom Critical/Precise Cutting task shall be supervised by FAC in consultation with OBO SME) Anchor detail at windowsill shall be updated to incorporate post-installed anchors in lieu of cast-in-place anchors.

Interior Design Scope:

The contractor shall Provide 2D design and propose sitting layout incorporating acoustic panels on both sides of FEBR windows.

Construction services

Civil Engineering Scope:

Initially the contractor shall remove the FEBR window as per the standard procedure (i.e Approved Construction Plan) . The contractor to provide demolition (saw-cut and removal of openings) plan before start of the work. Jack hammering is not allowed.

The contractor shall Professionally mark the layout to do the rough opening under the windowsill. Before starting any cutting operation, place protections (plywood sheets) to protect the finished floor from damage from debris. The thickness of concrete wall is 200mm with single layer of reinforcement (main and distribution) as mentioned in the structural drawings. Mark the cutlines to make 03 Nos. panels as shown on the proposed drawing. At each panel, install wall anchor followed by mounting of Standard core machine stand in compliance with safety regulations.

Fix the core bit to the machine perpendicular, adjust, and center the core bit to the marked position. The contractor shall clean up the area and move to the next location. Similar procedure shall be carried out for vertical cutting. While core cutting, 12mm x 150mm Nelson Studs shall also be encountered at the windowsill which has also to be taken out.

The contractor must remove and dispose all type of debris regularly to avoid buildup at the Consulate Compound (Collection/Disposal bins and equipment to be furnished by the contractor) . Furthermore, the contractor shall furnish details protecting concrete surface after saw-cut.

Once the rough openings are made, take out a portion sub-frame out of the enlarged opening. Install in the new half sub-frame that shall be slide into the jamb and header as well. The new sub-frame shall be 15-minute FE/BR welded by a certified welder (OBO SME Approved contractor profile).

Anchor the sub-frame (at windowsill right and left corners) with either drop-in type expansion anchors 12 mm diameter by 90 mm long or with Hilti HY150 injection or equivalent anchoring system using 12 mm diameter by 200 mm long Hilti HIT threaded rods spaced at 300 mm on center. Drill and inject Hilti HY150 into the holes to the additional new rebars (20mm) at least 150mm inside the existing wall.

Fix the rebars at the spacing as specified in the as-built structure drawings. Place the formwork under window rough opening (Material as per approved design BoQ). Remove the formwork after 24 hours and apply curing compound on the new concrete.

Also, there is a requirement of installation of microphone on the attack side of the CCAC for communication with visitors to inquire about their appointment or intent to visit the Consulate. The description is given in architectural scope of works.

Electrical Scope:

Before start of work, remove all the electrical receptacles or conduit or light fixture or any other utility available around and underneath the FEBR window.

Once the civil works are completed, install the new receptacles as per the layout complete in all respects.

There is an additional requirement of microphone that also needs to be incorporated while the conduits are placed. The description is given in architectural scope of works.

Telecommunications Scope:

The new teller windows may additionally require ethernet and intercom connections as per the new sitting plan. Following should be considered:

1. Please ensure that all new cabling is rated for the environment it is installed. For example, plenum cable in a plenum ceiling.

2. Please ensure that cabling is supported per code.

3. Please ensure that Low Voltage Systems equipment cabinets, panels and frames are properly grounded.

4. Please ensure that all cabinets and wall mountings are braced/reinforced for the seismic rating of the area.

5. Please ensure that all abandoned cabling is removed from the ceiling and walls.

6. Please ensure that all new penetrations are fire stopped to restore the barrier/partition to its fire rating.

7. Please take precaution working around active Telecom and other cabling during demolition and new installation.

8. If additional equipment will be added to the Telecom and other Equipment rooms, please make sure the electrical panel and electrical outlets are sized for the additional Power loads.

(as per maximum classified load within the approved design record)

Physical Engineering Scope:

experience of installation and handling FE/BR windows. Place the shims at every anchor location as specified in the technical submittal. AWS (American Welding Society standards) and recommendations shall be complied and applicable for the selection of welding rods and related materials, and for selection of welding methods which will yield full-strength joining of metal members to form unit frames, with ground-smooth mitered joints except as otherwise indicated. For installation of window please refer to the guidelines mentioned in technical specifications section 08667 (Interior Security and Teller Windows).

Fire Protection Scope:

There will be no disengagement required for fire sprinklers. However, while doing the core cutting under the windowsill, the smoke detectors shall be covered with the end caps to avoid firm alarm activation. At the end of each day, the end caps shall be removed from the smoke detectors. Proper ventilation shall also be ensured while core cutting is in progress (Industrial grade vacuum machine with extendable outflow hose pipe)

1.The contractor shall fire stop all penetrations (new or existing) which their cable, conduits, pathways or systems pass through.

2. The contractor shall fire stop and restore all penetrations to rating of the wall, floor slab, etc.

3. The contractor shall utilize fire stopping materials from Hilti or equivalent manufacturer.

4.The contractor shall identify the manufacturer's fire stopping system numbers they intend to utilize.

5. The contractor shall be trained by the manufacturer of the fire stop system they intend to use.

6. The contractor shall submit the manufacturer certificates of completion of the technicians they intend to utilize for the fire stop installation. Should personnel change, contractor shall submit a certificate for replacement personnel prior to commencing work.

Safety Health and Environmental Management Scope:

The contractor shall be responsible for conducting the work in a manner that ensures the employees. The contractor shall comply with the US Army of Corps of Engineers EM-385 Safety and Health Requirements (Chapter 21- Fall Protection), Chapter 22- Work Platforms and Scaffolding) and the Occupational Safety and Health Administration (OSHA Scaffold General Requirements 29 CFR 1926.451 and Aerial Lifts 29 CFR 1926) for working at elevations. It is the responsibility of the contractor to do the risk assessment, managing health and safety issues associated with this project. Based on hazard assessments, contractor shall provide personal protective equipment (PPE) to each employee. At a minimum PPE shall consist of coveralls, eye protection, gloves, body harness, safety ropes, hard hats, and safety shoes. Sandals or athletic shoes are not permitted. The contractor shall prepare and implement Activity Hazard Analysis (AHA), Hot Work Permit (if any) prior to the start of the work. The contractor must have a competent person on site for inspection of equipment, training works in the safe use of equipment and the recognition of hazards related to their use, supervision, identifying and correcting unsafe work practices for high hazard work. The contractor shall provide in the work all the necessary signs and announcements to prevent accidents according to the safety plan (that includes signals for restricted areas, electric risk, flammable materials, construction zone, danger for general risk). Signs shall be made of acrylic or galvanized sheets painted with a yellow background and with red or black letters. Also, the means of egress must be clear at all the times.

1. Pricing Table:

S. No Description of Services Quantity Unit Price PKR per UoM

Total Price PKR

PRE-CONSTRUCTION PORTION 30 days

1 3D Architectural Renderings for required A&E Services

*Optional Services

01 Job

2 Architectural design development

*Including But not limited to 2D design for all architectural/civil works demolition plan, construction plan and submittals with samples/data sheets

3 Structural Engineering/Construction Planning and Documentation

*As - Built Vs As Constructed Detailed Analysis

*Site survey findings report, completed and final product cut data sheets and all pertinent permits, licenses required for construction within 30 calendar days upon Survey Notice to Proceed (SNTP)

CONSTRUCTION PORTION 90 days

4 Construction services for New FE/BR Teller window Installation

*As per approved A&E Design

5 Electrical layout Services

6 Physical Engineering/Welding Services

*In compliance of AWS standards

01 Job

7 Telecommunication layout Services

8 Fire Caulking and protection services.

* Hilti or equivalent certified manufacturer product and technician services

*Firm Fixed price contract for stated construction services in accordance with the Project Scope referenced thru Section B, and all other documents incorporated into this contract including all Supplies, Construction services, all labor, materials, equipment, services, overhead, other indirect costs, costs for insurance, bonds, and profit. Within 90 calendar days from Construction Notice to Proceed (CNTP).

GRAND TOTAL FIRMED FIXED PRICE PKR

NOTE:

Above Services must be performed in accordance with Statement Of Work) and inclusive of all deliverables along with maintaining SITE waste/debris collection and disposal as stated through SOW Para (4)

SUBMITTAL REQUIREMENTS

Furnish design documents, design calculations, drawings/specifications in each submittal. The documents shall be in English, and metric units.

The contractor/A&E firm shall provide all MEP and construction working drawings that include but limited to

Submittals & Deliverables: 100 % Submission

All architectural working drawings.

Sections.

Elevations.

Plans.

Finish material marked on plans and material schedule.

Structural drawings and structural calculations stamped by PEC certified engineer. Provide design of structural reinforcing and connection details

Enlarged blow up architectural details of FEBR WINDOW connection to Frame tubing.

Countertop structure details. Acoustic panel installation details, Microphone access and firestopping details for exterior penetration.

Electrical drawings.

Mechanical drawings.

Welding drawings and blow-up details of connections and assemblies.

Identify the area requiring structural reinforcing.

Provide demolition plan.

Provide design of structural reinforcing and connection details.

Provide design narratives, structural drawings, and structural calculations.

Provide design narratives, drawings, and structural calculations.

All structural drawings and calculations shall be signed by a professional PEC certified engineer.

Provide samples of all products including but not limited to drywall gypsum steels studs and gypsum, fireproof 16mm gypsum, insulation/mineral wool, fabric, finish materials and panels for sound insulation, countertops, structure steel sections, primers, anticorrosive treatment, lights, embedded expansion anchors, all hardware, UL rated firestopping submittal and samples of material and firestopping hardware. including product data sheets for each item.

RFQ Submittals

Provide Bill of Quantities, Bill of Materials and Engineering estimates.

The delivery schedule for the submission of plans, elevations, sections, and details is divided into three stages, preliminary stage at 60% completion, pre-final stage at 90% completion and final submission at 100%. Each stage includes submission of the drawings/details followed by review by the COR. Refer to delivery schedule below for details.

Final Submission drawings shall be on ANSI D (559x864 mm). Line weights shall be attached to entities (ex: line, arcs, points, etc.). Submission of digital files (.dwgs) shall include in digital media CD ROM Format using proper external label with a certification that the delivery media is free of known computer viruses including the name(s) and release date(s) of the virus scanning software used to check the media. Drawings shall be developed using the metric system of measurement (SI Units). SI drawings shall use only millimeters (mm) to avoid fractions and to eliminate the repetitious suffix. Dual dimensions shall not be used. Drawings shall be in English.

Graphic Scales:

Site Plan 1:500, minimum Plans 1:100, minimum Details 1:5 thru 1:20

Sr.No. Items % of Work

No. of Copies

Drawing Size/Scale/Medium

Schedule

Preliminary Submittals

60 % 1 Editable PDF files

10 Days after the issuance of SNTP. Submittal to be reviewed by the COR and review comments to be provided for incorporation into the pre-final submittal.

2 COR Review 02 Days after submission

Pre-Final

Submittals 90 % 1 Editable PDF files

05 Days after submittal review return. Includes the development of the preliminary submittal completed including integration of the COR review comments

4 COR Review 03 Days after submission

Final

Submittals

As per SOW

Submittal Requirements

10 Days after submittal review return. This includes pre-final submittal documents with all previous review comments incorporated with the correction of all review package comments and all iterative package discrepancies

GENERAL CONDITIONS:

CO: Contracting Officer

FM: Facility Manager RSO: Regional Security Officer POSHO: Post Occupational Safety and Health Officer APOSHO: Assistant Post Occupational Safety and Health Officer

1. COR:

are met.

2. Fixed-Price Proposal:

The contractor shall provide one fixed-priced Proposal for the complete Project that includes every aspect of the Work. The contractor will be measure and verify quantities needed to complete this project prior to bid submission.

3. Period of Performance:

The period of performance for the entire design and build project is 120 calendar days from the issuance of Notice to Proceed (NTP) including 30 days for Pre-construction scope after Survey Notice to Proceed (SNTP) and 90 days for construction scope of services after Construction Notice to Proceed (CNTP)

3b Payment:

This is a firm fixed price contract with Milestones/Tasks defined for all the works to be carried out. Payment shall be made upon completion and quality acceptance of respective milestones/tasks upon the submission of a proper invoice. 10% of the invoiced amount shall be withheld from each payment as retention money and shall be released at final completion of works. The contractor shall submit the invoice to COR. Invoice template will be shared after issuance of Notice to Proceed.

4. Execution:

The Work shall be executed in a diligent and workmanlike manner in accordance with the negotiated fixed price, this Scope of Work, and the Project Schedule.

When pursuing the work, the contractor is to take extra care as not to damage existing equipment/property of U.S Consulate General Karachi. The contractor is responsible for formance of the work.

The contractor shall be responsible for repairing any damage to adjacent properties as a result of its activities on the Project Site. If the damage is not repairable, the cost will be calculated by the Facility Manager and deducted from the payment of the final invoice.

PROJECT SCHEDULE

General:

Fully develop the construction portion of the schedule and submit to the CO, COR, and Facility Manager a week before construction starts. The project schedule shall be updated on a daily basis throughout the entire contract period and until project substantial completion.

Purpose:

The purpose of the project schedule is to ensure adequate planning, coordination, scheduling, and reporting during construction activities of the project. The project schedule will assist the COR and Facility Manager in monitoring the progress of the work and evaluating proposed changes.

Software:

The software shall be compatible with Microsoft Project 2017.

Schedule Development The project schedule shall cover the entire contract period.

The contractor shall use the Critical Path Method (CPM) with limited use of lead or lag durations between schedule activities. The contractor's project schedule shall consist of procurement activities (including mobilization, submittal, and the fabrication and delivery of key and long-lead procurement items) and construction activities.

The contractor's project schedule shall consist of, but not be limited to, the following for each activity:

Identify each and every activity number with numerical designations (maximum 5-digit).

Numbering of activities shall be in increments of 10.

Concise description of the work represented by the activity (maximum 48 characters).

Avoid the use of non-standard abbreviations. The work related to each activity shall be limited to one work trade.

Activity duration in whole working, unless otherwise approved by the COR and Facility Manager, except for non-construction activities including submittals, mobilization, window shop drawings to include head, jamb and sill details, fabrication of materials, and delivery of materials and equipment.

In developing the project schedule, the contractor shall be responsible for ensuring that subcontractor work at all tiers, as well as its own work, is included in the project schedule.

The project schedule, as developed, shall show the sequence and interdependence of activities required for complete performance of the work. The contractor shall be responsible for ensuring all work sequences are logical and the project schedule shows a coordinated work plan. Proposed durations assigned to each activity shall be the contractor's best estimate of time required to complete the activity considering the scope and resources planned for the activity. Resource loading of each activity is not required unless directed by the Project Managers. Include permit requirements and constraints.

Coordination meetings:

Pre-Project Conference: The COR shall conduct an initial project conference on or near the date of notification to proceed. Agenda items shall include a review of the general plans, conditions, procedures, and work requirements as shall be necessary for the effective scheduling and prosecution of the work activities.

Further, all parties shall review security of material delivery requirements; personnel assigned, and contract communication procedures as have been established for the work project activities.

This meeting shall be scheduled and conducted at the place agreed to by the COR/FM and the Contractor.

Construction Coordination Meetings: The Contractor and COR will hold construction coordination meetings to discuss schedule and status of outstanding issues upon request of COR. Coordination meetings shall commence immediately upon mobilization to the Project Site. All parties shall seek the expeditious resolution of issues before they become problems.

Progress of the work shall be reviewed. Contractor shall revise, balance, and submit an updated project execution. This review shall be based upon a subset report of the Project Execution Schedule in which all project execution activities have been entered. This review shall include:

Status of continuing activities.

New activity starts since last meeting.

Activity planned completion dates.

Activity interruptions.

Activity completions.

Activity interruptions should include the reason for the interruption.

An activity will be considered complete only when it has been approved by the COR.

Meeting Minutes: The Contractor shall provide minutes of each meeting held under this contract the next working day after each construction coordination meeting. The COR will sign the meeting minutes upon agreeing to their accuracy. Final minutes signed by the COR and the Contractor will be submitted to the COR no later than two working days after the coordination meeting and shall become part of the final project record set.

5. Work Hours:

-hour workday with a 30-minute lunch break; Saturday and Sunday designated as non-working days. Prayer sulate gate for check-in by 0800hrs and carry original CNICs (or equivalent photo ID).

The contractor is expected to strictly comply with the above schedule. However, if urgent work the discretion CO, If any aspect of this work is deemed by the COR, FM, the RSO or the POSHO/APOSHO to be interruptive of normal Consulate operations, security or safety, the contractor shall be required to perform that portion of the work on Saturdays and Sundays.

6. Safety:

The contractor shall be responsible for conducting the work in a manner that ensures the safety of meet or exceed current EM 385 US Corps of Engineers Safety and Health Requirements Manual requirements available online.

The contractor shall be solely responsible for risk assessments, managing health, and safety issues associated with this project. Based on hazard assessments, contractors shall provide or afford each affected employee personal protective equipment (PPE) that will protect the employee from hazards. At a minimum PPE shall consist of eye protection, hard hats, and closed toe shoes. Sandals or athletic shoes are not acceptable. PPE such as chemical/leather gloves, dust masks, are recommended. These items must b

Workers may use discretion if they feel unsafe in using the equipment in a hostile environment.

The contractor must document in the bid for work how the hazard controls will be implemented and maintained during the project.

The contractor shall prepare and implement an Activity Hazard Analysis (AHA) prior to the start of work.

The Contactor must have a competent person on-site for inspection of equipment, training workers in the safe use of equipment and the recognition of hazards related to their use, supervision, and identifying and correcting unsafe work practices for high hazard work.

All contractor personnel shall wear hard hats, safety glasses, earplugs, gloves, close-toes shoes and any other Personal Protection Equipment deemed necessary by the Facility Manager.

Safety Training:

Provide specific training to supervisory personnel and all craft workers of the contractor and subcontractors in proper use and care of specific personal protective gear, equipment, and clothing.

The contractor and subcontractor employees shall be trained and supervised by qualified persons to perform, safely and confidently, recognized hazardous work operations and work performed with hazardous conditions to which they have been assigned.

Damage: Contractor will repair or replace to include but not limited to any hardscape (i.e., roads, curbs, paving stones, etc.), landscape (trees, plants, grass areas, etc.), building wall and window opening finishes (i.e., stone, concrete, gypsum board, wood and/or metal trim, etc.) buildings doors and floor coverings, wall fixtures, window cladding, replacement glazing panel, etc.

The Contractor shall not conduct any work that is beyond this Scope of Work unless directed in writing by the CO. Any work done by the Contractor beyond this SOW and accompanying risk and at no cost to the government.

7. Workforce:

The contactor must have prominent experience of handling similar design/built contracts. His competence will be evaluated by OBO SMEs.

The contractor shall provide all supervision, skilled and unskilled labor needed to perform the work.

The contractor shall be responsible for total integration of effort and control of the works. The contractor shall be responsible for planning, monitoring, coordinating, and controlling the works.

The contractor's employees shall wear clean, neat and complete uniforms when on duty. All employees shall wear uniforms approved by the Contracting Officer's Representative (COR). The contractor shall provide, to each employee and supervisor, uniforms and personal equipment. The contractor shall be responsible for the cost of purchasing, cleaning, and repair of the uniforms.

Neglect of duties shall not be condoned. This includes sleeping while on duty, unreasonable delays or failures to carry out assigned tasks, conducting personal affairs during duty hours and refusing to render assistance or cooperate in upholding the integrity of the worksite security.

The contractor shall not condone disorderly conduct, use of abusive or offensive language, quarreling, and intimidation by words, actions, or fighting. Also included is participation in disruptive activities that interfere with normal and efficient Government operations.

The contractor shall not allow its employees while on duty to possess, sell, consume, or be under the influence of intoxicants, drugs or substances which produce similar effects.

The performance standard is that the Government receives no more than one (1) customer complaint per month. The COR shall notify the Contracting Officer of the complaints so that the Contracting Officer may take appropriate action if any of the services exceed the standard. The COR shall, as a minimum, orally notify the contractor of any valid complaints.

Repeat customer complaints are not permitted for any services. If a repeat customer complaint is received for the same deficiency during the service period, the COR will contact the Contracting Officer for appropriate action under the Inspection clause.

8. Accommodations:

Government Finished Property:

Toilets: The contractor shall utilize toilets on the NCC Compound

Contractor Property:

PPE: hard hats, safety glasses, dust mask, gloves, close- steel toes boot, Ear covers working in (But not limited to) elevated heights, Welding works, Use of sharp cutting tools, Use of Hard Impact and fastening tools, Oil Lubrication usages, e.t.c

Uniforms

Tools/Implements: Contractor staff shall provide all necessary tools and implements as necessary for the execution of services. Contractor Supervisor shall ensure the safe handling of all issued necessary equipment as per COR instructions. Damages (if any) should be in serviceable condition without leakages of oil/Fuel. Any such

9. Subcontractors:

The contractor shall be responsible for the conduct and workmanship of Subcontractors engaged in the Project, and for Subcontractors compliance with the terms of this Statement of Work. The contractor is responsible for the behavior and workmanship of subcontractors while on US Government property.

EXPRESS NDAA-889 CERTIFICATION

Public Law 115-232, also known as the John S. McCain National Defense Authorization Act (NDAA) for Fiscal Year 2019, requires representations regarding Covered Telecommunications Equipment and Services. U.S. Government Procurement and Contracting staff shall use this representation with merchants / vendors to determine compliance with NDAA requirements. To comply with this Public Law the Federal Acquisition Regulation (FAR) in FAR 4.2105 requires two provisions 52.204-24 and 52.204-26 and contract clause 52.204-25 in all procurement actions.

DIRECTIONS FOR THE MERCHANT

1. Read the entire provisions and clause in the FAR at Acquistion.gov or click on the links above.

2. After you have read the provisions, please answer the questions below.

3. Upon completion of Step 2, fill out the representation below. NOTE: This representation is made by a person with the authority to bind the merchant.

4. Return completed form to the U.S. Government Procurement Agent or Contract Specialist.

52.204-26 Covered Telecommunications Equipment or Services-Representation (OCT 2020)

(a)

-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

(b) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards

(c) Representations. (1) The Offeror represents that it [ ] does, [ ] does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.

(2) After conducting a reasonable inquiry for purposes of this representation, the Offeror represents that it [ ] does, [ ] does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services.

(End of provision)

52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND

VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (AUG 2020)

(d) Representation. The Offeror represents that

(1) It [ ] will , [ ] will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation. The Offeror shall provide the additional disclosure information this section; and

(2)After conducting a reasonable inquiry, for purposes of this representation, the Offeror represents that

It [ ] does, [ ] does not use covered telecommunications equipment or services, or use any equipment, system, or service that uses covered telecommunications equipment or services. The Offeror shall provide the additional disclosure information required at paragraph (e)(2) of this

Merchant Name and Official Stamp__________________________________________________

Authorized Representative______________________________________________ (Typed Name)

Authorized Representative Signature _________________________ Date __________________

10. Modification to Contract:

The contractor shall not incur any costs beyond those described in this SOW unless directed otherwise in writing by the Contracting Officer.

Any work performed by the contractor beyond this SOW without written direction from the

11. Housekeeping:

The contractor is responsible to clean up daily. The contractor is responsible to dispose of all dirt, trash, used oil and debris outside of the property before the close of each business day. Immediately upon removal, it must be loaded into a truck and disposed of once the vehicle is full. At the end of the day even partially loaded trucks must be removed from the US Consulate compound and the contents disposed of properly at authorized dump sites.

The Contractor shall coordinate and supervise the protection, cleaning, and maintenance work at the Project site during receipt, handling, installation, lifting of generator radiator at the workplace area.

12. Stop Work:

At any time during the Project, the Contracting Officer (CO) reserves the right to Stop Work for protection of employees or visitors, security, or any other reason at his/her discretion.

13. General Submittals:

The contractor shall provide the detailed qualification of all the key personnel.

14. Close-out:

N/A.

15. Notice to proceed:

The contractor shall start the work within 10 days of Notice to Proceed.

16. Point of Contact:

The COR shall be the main point of contact for this Project. The contractor shall report to the COR on (a) status of the Project, (b) changes in Schedule, (c) accidents and safety issues, (d) disruptions to the property accessibility; and all other important information pertaining to the Project.

The contractor shall provide a representative on-site during all working hours with the authority to make all decisions on behalf of the contractor and subcontractors.

The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all services furnished under this purchase order. The Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its construction and other services.

The Contractor shall identify a Project Site Manager who shall be responsible for the overall management of the project and shall represent the Contractor on the site during construction.

Any cost associated with services subcontracted by the Contractor shall be borne by and be the complete responsibility of the Contractor under the fixed price of this contract.

The Contractor is responsible for safety and shall comply with all local labor laws, regulations, customs, and practices pertaining to labor, safety, and similar matters. The Contractor shall promptly report all accidents resulting in lost time, disabling, or fatal injuries to the COR. The Contractor shall submit a Safety Plan to the CO that also includes the use of personal protection equipment (i.e., hard hats, steel or composite toe boots/shoes, ear and eye protection, gloves, etc.), eye-wash station, and the handling of structural steel and welding in the warehouse while DOS employees and visitors continue to work in adjacent areas.

Permits and licenses: The Contractor is responsible for obtaining all construction permits and licenses required by the local authorities to execute the work.

18. Site Security:

The contractor shall comply with US Consulate Karachi security policy.

The contractor shall prepare list of all the names of personnel working for the contractor and any subcontractors, with national ID numbers and submit the list to the Facility Manager for vetting of employees by the RSO at least 10 days prior to commencement of work.

The contractor shall also provide a list of all equipment, listing the manufacturer, model, serial number of all equipment to be used on this project at least 10 days prior to the commencement of any work. Any vehicles utilized by the contractor are also considered equipment. The contractor must provide make, year, model number and license plate number.