RFQ - 19AL6026Q0010.docx

DOCX document 139 KB Posted

Attached to
Painting of the CAC-s vehicular gates, hydraulic barriers, metal fences and bollards at Embassy and RR Compound.
Solicitation number
19AL6026Q0010
Issued by

About this file

This is a Request for Quotations (RFQ) issued by the U.S. Embassy in Tirana, Albania, for painting and repair services at diplomatic facilities. The solicitation number is 19AL6026Q0010, issued on August 12, 2026, with quotations due by August 31, 2026, at 4:30 p.m. local time (Tirana). The work includes painting three vehicular gates (100 square meters), two steel fences at the Main and Secondary Compound Access Centers (approximately 400 square meters), and six hydraulic barriers with 53 bollards, all using high-quality oil-based gloss white paint with primer. Additionally, the contractor must repair the damaged perimeter wall at Rilindja Ridge Housing Compound, which requires demolition, soil excavation, installation of steel rebars, concrete pouring (Grade 250), plastering, and painting. A mandatory site visit is scheduled for August 18, 2026, at 9:00 a.m., requiring advance notification by August 14, 2026. Quotations must be submitted electronically to TiranaBids@state.gov in MS-Word, MS-Excel, or PDF format, not exceeding 30MB per file.

The contractor must be registered in the System for Award Management (SAM) and provide Standard Form 18, Section A pricing, Section L representations and certifications, a performance schedule in bar chart format, and a business management/technical proposal. All work must be completed within 30 calendar days, with working hours Monday through Saturday, 8:00 a.m. to 5:00 p.m. The contractor is responsible for all labor, materials, equipment, insurances, and overhead costs, with prices quoted in Albanian Lek including 20 percent Value Added Tax as a separate line item. Award will be made to the lowest-priced, acceptable, responsible quoter. The contractor must obtain performance/payment security (50 percent of contract price), provide general liability insurance ($5,000 per occurrence/$10,000 cumulative for bodily injury and property damage), submit personnel biographies and construction schedules within five days of award, and provide a one-year warranty on all materials and workmanship. Security requirements include background investigations for all employees, daily screening upon site entry, and designated storage areas for tools and materials. Liquidated damages of $750 per calendar day apply for project delays.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EMBASSY OF THE UNITED STATES OF AMERICA

U.S. Embassy Albania Date: August 12, 2026

Dear Prospective Offeror:

Subject: Request for Quotes - 19AL6026Q0010 Painting of the CAC-s vehicular gates, hydraulic barriers, metal fences and bollards at Embassy and RR Compound.

Enclosed is a Request for Quotes (RFQ) for Painting of the CAC-s vehicular gates, hydraulic barriers, metal fences and bollards at Embassy and RR Compound. If you would like to submit a quotation, follow the instructions in Section J of the solicitation, complete the required portions of the attached document, and submit it to the address shown on the Standard Form that follows this letter.

The U.S. Government intends to award a contract/purchase order to the responsible company submitting an acceptable offer at the lowest price. We intend to award a contract/purchase order based on initial proposals, without holding discussions, although we may hold discussions with companies in the competitive range if there is a need to do so.

Quotations are due by August 31, 2026 @16:30 a.m. Local time (Tirana). No quotations will be accepted after this time. Quotations must be in English and incomplete quotations will not be accepted.

A site visit will be held on August 18, 2026 at 9:00 a.m. local time to the following address: Rilindja Ridge residences, Rruga Haki Shehu, Tirana/Albania. Please send an email to TiranaBids@state.gov with names of participants not later than August 14, 2026 at 16:30 in order to secure access.

Your quotation must be submitted electronically to TiranaBids@state.gov . It is important to make sure the submission is made in specific size and format; in MS-Word, MS-Excel, or Adobe Acrobat (pdf) file format. The file size must not exceed 30MB. If the file size should exceed 30MB, the submission must be made in separate files and attached to separate emails with less than 30MB each.

In order for a quotation to be considered, you must also complete and submit the following:

1. SF-18

2. Section A, Pricing

3. Section L Representations and Certifications

4. Additional information as required in Section J

5. Proof of SAM Registration

Offerors shall be registered in the SAM (System for Award Management) database at https://www.sam.gov prior to submittal of their offer/proposal as prescribed under FAR 4.1102. Failure to be registered at time of proposal submission may deem the offeror’s proposal to be considered non-responsible and no further consideration will be given. Therefore, offerors are highly encouraged to register immediately if they are interested in submitting a response to this requirement.

Sincerely, Chris Carlisle Contracting Officer

TABLE OF CONTENTS

SF-18 COVER SHEET

A. PRICING

B. STATEMENT OF WORK

C. PACKAGING AND MARKING

D. INSPECTION AND ACCEPTANCE

E. DELIVERIES AND PERFORMANCE

F. CONTRACT ADMINISTRATION DATA

G. SPECIAL TERMS AND CONDITIONS

H. CLAUSES

I. LIST OF ATTACHMENTS

Attachment1: Breakdown of Price by Divisions of Specifications

J. INSTRUCTIONS ON HOW TO SUBMIT A QUOTATION

K. EVALUATION CRITERIA

L. REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS

REQUEST FOR QUOTATION

(THIS IS NOT AN ORDER)

THIS RFQISIS NOT A SMALL BUSINESS SET-ASIDE
PAGE OFPAGES
3
35

1. REQUEST NUMBER

19AL6026Q0010

2. DATE ISSUED

08/12/2026

3. REQUISITION/PURCHASE REQUEST NUMBER

PR16145163

4. CERT. FOR NAT. DEF. UNDER BDSA REG. 2 AND/OR DMS REG. 1
RATING

5a. ISSUED BY US Embassy Tirana - GSO/Procurement

6. DELIVER BY Aug 31, 2026 at 16:30 local time

5b. FOR INFORMATION CALL (NO COLLECT CALLS)
7. DELIVERY

OTHER

FOB DESTINATION (See Schedule)

NAME

Irisa Hyso

TELEPHONE NUMBER

AREA CODE

NUMBER

698052807

9. DESTINATION

a. NAME OF CONSIGNEE

8. TO:

a. NAME
b. COMPANY
b. STREET ADDRESS
c. STREET ADDRESS
c. CITY
d. CITY
e. STATE
f. ZIP CODE
d. STATE
e. ZIP CODE
10. PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS (Date)
IMPORTANT: This is a request for information and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or service. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotation must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State and local taxes)

ITEM NUMBER

(a)

SUPPLIES/SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e)

AMOUNT

(f)

Painting of the CAC-s vehicular gates, hydraulic barriers, metal fence and bollards at Embassy and RR Compound. Repairing of the damaged perimeter wall at Rilindja Ridge Housing Compound as per Scope of Work.

12. DISCOUNT FOR PROMPT PAYMENT

a. 10 CALENDAR DAYS (%)
b. 20 CALENDAR DAYS (%)
c. 30 CALENDAR DAYS (%)
d. CALENDAR DAYS
NUMBER
PERCENTAGE
NOTE: Additional provisions and representationsX areare not attached.
13. NAME AND ADDRESS OF QUOTER
14. SIGNATURE OF PERSON AUTHORIZED TO SIGN QUOTATION
15. DATE OF QUOTATION

a. NAME OF QUOTER

b. STREET ADDRESS
16. SIGNER
a. NAME (Type or print)
b. TELEPHONE

c. COUNTY

AREA CODE

d. CITY
e. STATE
f. ZIP CODE
c. TITLE (Type or print)
NUMBER
AUTHORIZED FOR LOCAL REPRODUCTIONSTANDARD FORM 18 (REV. 6/1995)
Previous edition not usablePrescribed by GSA-FAR (48 CFR) 53.215-1(a)

SECTION A - PRICING

A. PRICE

The Contractor shall complete all work, including furnishing all labor, material, equipment, and services required under this purchase order for the following firm fixed price and within the time specified. This price shall include all labor, materials, all insurances, overhead, and profit.

Description
Price in ALL

Painting of three vehicular gates

Painting of two steel fences at MCAC and SCAC

Painting of six hydraulic barriers and 53 bollards

Repairing of the damaged perimeter wall at Rilindja Ridge Housing Compound

Total Price (including all labor, materials, overhead and profit)

VAT 20%

Grand Total

A.1 VALUE ADDED TAX

VALUE ADDED TAX (VAT). The Contractor shall include VAT as a separate charge on the Invoice.

SECTION B - STATEMENT OF WORK

Project Description: Painting of the CAC-s vehicular gates, hydraulic barriers, metal fence and bollards at Embassy and RR Compound. Repairing of the damaged perimeter wall at Rilindja Ridge Housing Compound.

1.0 Location of Work

The work associated with this Statement of work is to be performed on the two CAC-s at Embassy and the Rilindja Ridge housing compound Tirana, Albania.

1.0 General Requirements

The work involves repairs and painting of all identified surfaces including vehicular gates, hydraulic barriers and the steel fence.

3.0 Contracting officer’s Representative (COR)

The COR is delegated the authority to act for the Contracting Officer in matters concerning technical clarifications, inspections, acceptance of Contractor’s performance, oversight, and emergency requests. This includes certification of work in progress or completed; authorization to process payments, and the appointment of Government Technical Monitors (GTM) to assist in the administration of this contract. The COR on this contract is Mr. Arben Mane, Maintenance Supervisor for the United States Embassy in Tirana, Albania.

4.0 Security

Upon notification of being the successful bidder, the Contractor shall submit to the Contracting Officer, or to the Contracting officer’s Representative (COR), the names of all the Contractor’s employees who may be working on this project. All employees will be required to submit to the routine background investigation done by the Embassy’s Regional Security Officer (RSO) prior to working on this project. No employee will be admitted to the work site without first being cleared by the RSO.

4.1 All contractor employees will be screened each time they enter or leave both compounds. This screening will include people, personals, vehicles, toolboxes and materials.

4.2 All tools and materials, including ladders and scaffolding, shall be returned to the designated storage area at the end of each workday and secured.

5.0 Safety

The Contractor shall maintain a safe working environment.

5.1 All employees of the Contractor shall wear appropriate work shoes or boots while working on this project. Open-toe sandals are not acceptable and will not be allowed.

5.2 Contractor employees will be required to wear eye protection such as safety glasses or goggles when scraping or grinding.

5.3 The Contractor shall provide and use proper ladders and/or scaffolding for performing work on elevated surfaces.

The United States Government shall not be held responsible for injuries to Contractor employees.

6.0 Liability

If, during this project, it is determined that the employees of the Contractor were negligent, and United States Government property and/or personal property of United States Government employees is damaged because of such negligence, the Contractor will be responsible for the repair or replacement of said damaged property.

7.0 Materials

The Contractor is responsible for providing all materials associated with this contract.

7.1 All materials shall be new at the start of this project. No material shall be used which has been deemed obsolete by current industry standards.

7.2 The COR shall approve all materials before commencement of work.

7.3 The Contractor is responsible for measuring the quantities of materials required.

7.4 The Contractor shall be responsible for transportation, and transportation costs, related to the delivery of materials. This shall include, but not be limited to, freight carrier fees, road tolls, border crossing fees, fuel cost, and the movement of tools, material, and labor to and from the project site.

7.5 The Contractor shall be responsible for any cost incurred in the removal and disposal of debris generated by this project.

7.6 The use of any lead-based paints is prohibited.

8.0 Tools

The Contractor shall be responsible for providing all tools necessary for the proper completion of this project. This shall include, but not be limited to, fall protection, PPE, ladders, scaffolds, mixers, power tools, and hand tools. Use of tools owned by the United States Government will not be permitted and are not a part of this contract.

9.0 Storage

The COR will designate a specific place for on-site storage of tools and materials. Storage areas shall be always kept neat and clean.

10.0 Working Hours

Working hours should be Monday through Saturday 08:00 until 17:00. The contractor will not be permitted to work on Sundays or holidays without prior approval from COR.

11.0 Utilities

Contractor personnel shall have use of the on-site water and electricity.

11.1 The contractor’s employees shall have the use of designated staff toilets. All other toilet facilities are off limits to contractor employees.

12.0 Timetable

The contractor will have thirty (30) calendar days to complete this project.

13.0 Personnel

The Contractor shall provide both skilled and unskilled labor, as determined by the Contractor, to complete this project. At no time shall unskilled laborers be left on this project unsupervised.

14.0 Clean-up

The Contractor will be required to always maintain a clean work area. Items for installation and accumulated debris shall not be left in an area where it may become a tripping or other safety hazard. Upon completion of the job and prior to submitting the final invoice, the Contractor shall remove all excess material, tools, and debris, and shall restore the mobilization/storage area back to its original condition, which may include planting grass and shrubbery.

15.0 Quality Control

The contractor shall be responsible for quality control, which includes all materials installed, and the workmanship of his employees. Inferior material in quality, and unprofessional workmanship from the employees of the contractor will not be accepted.

16.0 Warranty

The Contractor shall warranty all materials and workmanship for a period of one year from the date of acceptance by the COR. Should any defects develop, the Contractor should respond within 48 hours and begin repairs of defects. If the Contractor fails to respond to the requirements of this paragraph, the United States Government, at its sole discretion, shall be free to select a different contractor to make the necessary repairs, which will be billed to the contractor for reimbursement.

Technical Instructions

17.0 Painting of three vehicular gates.

The total square meters of the gates to be painted is 100 square meters.

Prior to painting, the contractor should sand and then apply the primer to prevent the steel gates from rusting. The paint should be high quality oil base, gloss, white color.

18.0 Painting of two steel fences at MCAC and SCAC.

The contractor should repair and paint approx.400 square meters of steel fence. The Surface preparation is the key to a quality finish.

Prior to painting, the contractor should sand and then apply the primer to prevent the steel profiles from rusting. The paint should be high quality oil base, gloss, white color.

19.0 Painting of six hydraulic barriers and 53 bollards.

Application of paint shall be with standard tools of the trade, brushes and rollers, paint sprayers. The Contractor shall meet the following standards:

19.1 Lead based paint is prohibited.

19.2 The Contractor shall use exterior-grade oil-based paint on all surfaces. The color of the paint should be the same as the existing one.

19.3 Prior to painting, the contractor should sand and then apply the primer to prevent the bollards and barriers from rusting. All paint shall be applied at full strength.

19.4 A minimum of two coats of finished paint shall be applied to all surfaces. The first coat shall be allowed to dry for a minimum of 8 hours before applying the second coat of paint.

20. Repairing of the damaged perimeter wall at Rilindja Ridge Housing Compound.

20.1 Demolishing of the damaged wall and foundation and cleaning the site.

20.2 Soil excavation and crushed stone layer.

20.3 Installation of construction steel rebars.

20.4 Resin for installation of steel rebars on the existing column.

20.5 Build the forms and pour Grade 250 concrete.

20.6 Plaster the wall and paint with the same color.

SECTION C - PACKAGING AND MARKING

U.S. Embassy Tirana

19AL60Q0010

Rr. Stavro Vinjau, No 14 Tirana Albania

SECTION D - INSPECTION AND ACCEPTANCE

The COR, or his/her authorized representatives, will inspect from time to time the services being performed and the supplies furnished to determine whether work is being performed in a satisfactory manner, and that all supplies are of acceptable quality and standards.

The Contractor shall be responsible for any countermeasures or corrective action, within the scope of this contract, which may be required by the Contracting Officer as a result of such inspection.

D.1 SUBSTANTIAL COMPLETION

(a) "Substantial Completion" means the stage in the progress of the work as determined and certified by the Contracting Officer in writing to the Contractor, on which the work (or a portion designated by the Government) is sufficiently complete and satisfactory. Substantial completion means that the property may be occupied or used for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which:

(1) do not interfere with the intended occupancy or utilization of the work, and

(2) can be completed or corrected within the time period required for final completion.

(b) The "date of substantial completion" means the date determined by the Contracting Officer or authorized Government representative as of which substantial completion of the work has been achieved.

Use and Possession upon Substantial Completion - The Government shall have the right to take possession of and use the work upon substantial completion. Upon notice by the Contractor that the work is substantially complete (a Request for Substantial Completion) and an inspection by the Contracting Officer or an authorized Government representative (including any required tests), the Contracting Officer shall furnish the Contractor a Certificate of Substantial Completion. The certificate will be accompanied by a Schedule of Defects listing items of work remaining to be performed, completed, or corrected before final completion and acceptance. Failure of the Contracting Officer to list any item of work shall not relieve the Contractor of responsibility for complying with the terms of the contract. The Government's possession or use upon substantial completion shall not be deemed an acceptance of any work under the contract.

D.2 FINAL COMPLETION AND ACCEPTANCE

D.2.1 "Final completion and acceptance" means the stage in the progress of the work as determined by the Contracting Officer and confirmed in writing to the Contractor, at which all work required under the contract has been completed in a satisfactory manner, subject to the discovery of defects after final completion, and except for items specifically excluded in the notice of final acceptance.

D.2.2 The "date of final completion and acceptance" means the date determined by the Contracting Officer when final completion of the work has been achieved, as indicated by written notice to the Contractor.

D.2.3 FINAL INSPECTION AND TESTS. The Contractor shall give the Contracting Officer at least five (5) days advance written notice of the date when the work will be fully completed and ready for final inspection and tests. Final inspection and tests will be started not later than the date specified in the notice unless the Contracting Officer determines that the work is not ready for final inspection and so informs the Contractor.

D.2.4 FINAL ACCEPTANCE. If the Contracting Officer is satisfied that the work under the contract is complete (with the exception of continuing obligations), the Contracting Officer shall issue to the Contractor a notice of final acceptance and make final payment upon:

· Satisfactory completion of all required tests,

· A final inspection that all items by the Contracting Officer listed in the Schedule of Defects have been completed or corrected and that the work is finally complete (subject to the discovery of defects after final completion), and

· Submittal by the Contractor of all documents and other items required upon completion of the work, including a final request for payment (Request for Final Acceptance).

SECTION E - DELIVERIES AND PERFORMANCE

52.211-12 LIQUIDATED DAMAGES - CONSTRUCTION (SEPT 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, or any extension, the Contractor shall pay liquidated damages to the Government in the amount of$750 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Default clause.

CONTRACTOR'S SUBMISSION OF CONSTRUCTION SCHEDULES

(a) The time for submission of the schedules referenced in FAR 52.236-15, "Schedules for Construction Contracts", paragraph (a), is hereby modified to reflect the due date for submission as " 10 calendar days after receipt of an executed contract".

(b) These schedules shall include the time by which shop drawings, product data, samples and other submittals required by the contract will be submitted for approval.

(c) The Contractor shall revise such schedules (1) to account for the actual progress of the work, (2) to reflect approved adjustments in the performance schedule, and (3) as required by the Contracting Officer to achieve coordination with work by the Government and any separate contractors used by the Government. The Contractor shall submit a schedule, which sequences work so as to minimize disruption at the job site.

(d) All deliverables shall be in the English language and any system of dimensions (English or metric) shown shall be consistent with that used in the contract. No extension of time shall be allowed due to delay by the Government in approving such deliverables if the Contractor has failed to act promptly and responsively in submitting its deliverables. The Contractor shall identify each deliverable as required by the contract.

(e) Acceptance of Schedule: When the Government has accepted any time schedule; it shall be binding upon the Contractor. The completion date is fixed and may be extended only by a written contract modification signed by the Contracting Officer. Acceptance or approval of any schedule or revision thereof by the Government shall not:

(1) Extend the completion date or obligate the Government to do so,

(2) Constitute acceptance or approval of any delay, or

(3) Excuse the Contractor from or relieve the Contractor of its obligation to maintain the progress of the work and achieve final completion by the established completion date.

NOTICE OF DELAY

If the Contractor receives a notice of any change in the work, or if any other conditions arise which are likely to cause or are actually causing delays which the Contractor believes may result in late completion of the project, the Contractor shall notify the Contracting Officer. The Contractor’s notice shall state the effect, if any, of such change or other conditions upon the approved schedule, and shall state in what respects, if any, the relevant schedule, or the completion date should be revised. The Contractor shall give such notice promptly, not more than ten (10) days after the first event giving rise to the delay or prospective delay. Only the Contracting Officer may revise the approved time schedule.

NOTICE TO PROCEED

(a) After receiving and accepting any bonds or evidence of insurance, the Contracting Officer will provide the Contractor a Notice to Proceed. The Contractor must then prosecute the work, commencing and completing performance not later than the time period established in the contract.

(b) It is possible that the Contracting Officer may elect to issue the Notice to Proceed before receipt and acceptance of any bonds or evidence of insurance. Issuance of a Notice to Proceed by the Government before receipt of the required bonds or insurance certificates or policies shall not be a waiver of the requirement to furnish these documents.

WORKING HOURS

All work shall be performed during regular workdays from 8:00 to 19:00. Other hours, if requested by the Contractor, may be approved by the Contracting Officer's Representative (COR). The Contractor shall give 24 hours in advance to COR who will consider any deviation from the hours identified above. Changes in work hours, initiated by the Contractor, will not be a cause for a price increase.

PRECONSTRUCTION CONFERENCE

A preconstruction conference will be held after contract award to discuss the schedule, submittals, notice to proceed, mobilization and other important issues that effect construction progress. See FAR 52.236-26, Preconstruction Conference.

DELIVERABLES - The following items shall be delivered under this contract:

Description
Quantity
Deliver Date
Deliver To
Section G. Securities/Insurance
1
5 days after award
CO
Section E. Construction Schedule
1
5 days after award
COR
Section E. Preconstruction Conference
1
TBD after award
COR
Section G. Personnel Biographies
1
5 days after award
COR
Section F. Payment Request
1
1 day After Final acceptance is confirmed
COR
Section D. Request for Substantial Completion
1
15 days before inspection
COR
SectionD. Request for Final Acceptance
1
5 days before inspection
COR

SECTION F – CONTRACT ADMINISTRATION DATA

652.242-70 CONTRACTING OFFICER'S REPRESENTATIVE (COR) (AUG 1999)

(a) The Contracting Officer may designate in writing one or more Government employees, by name or position title, to take action for the Contracting Officer under this contract. Each designee shall be identified as a Contracting Officer’s Representative (COR). Such designation(s) shall specify the scope and limitations of the authority so delegated; provided, that the designee shall not change the terms or conditions of the contract, unless the COR is a warranted Contracting Officer, and this authority is delegated in the designation.

(b) The COR for this contract is Arben Mane, Facility Management Supervisor.

Payment: The Contractor's attention is directed to Section H, 52.232-5, "Payments Under Fixed-Price Construction Contracts". The following elaborates on the information contained in that clause.

Requests for payment, may be made no more frequently than monthly. Payment requests shall cover the value of labor and materials completed and in place, including a prorated portion of overhead and profit.

After receipt of the Contractor's request for payment, and on the basis of an inspection of the work, the Contracting Officer shall make a determination as to the amount, which is then due. If the Contracting Officer does not approve payment of the full amount applied for, less the retainage allowed by in 52.232-5, the Contracting Officer shall advise the Contractor as to the reasons.

Under the authority of 52.232-27(a), the 14 day period identified in FAR 52.232-27(a)(1)(i)(A) is hereby changed to 30 days.

ATTN Financial Management Office

Email: TiranaVoucherExaminers@state.gov

The Contractor shall show Value Added Tax (VAT) as a separate item on invoices submitted for payment.

SECTION G - SPECIAL TERMS AND CONDITIONS

G.1.0 PERFORMANCE/PAYMENT PROTECTION - The Contractor shall furnish some form of payment protection as described in 52.228-13 in the amount of 50% of the contract price.

G.1.1 The Contractor shall provide the information required by the paragraph above within ten (10) calendar days after award. Failure to timely submit the required security may result in rescinding or termination of the contract by the Government. If the contract is terminated, the Contractor will be liable for those costs as described in FAR 52.249-10, Default (Fixed-Price Construction), which is included in this purchase order.

G.1.2 The bonds or alternate performance security shall guarantee the Contractor's execution and completion of the work within the contract time. This security shall also guarantee the correction of any defects after completion, the payment of all wages and other amounts payable by the Contractor under its subcontracts or for labor and materials, and the satisfaction or removal of any liens or encumbrances placed on the work.

G.1.3 The required securities shall remain in effect in the full amount required until final acceptance of the project by the Government. Upon final acceptance, the penal sum of the performance security shall be reduced to 10% of the contract price. The security shall remain in effect for one year after the date of final completion and acceptance, and the Contractor shall pay any premium required for the entire period of coverage.

G.2.0 INSURANCE - The Contractor is required by FAR 52.228-5, "Insurance - Work on a Government Installation" to provide whatever insurance is legally necessary. The Contractor shall at its own expense provide and maintain during the entire performance period the following insurance amounts:

G.2.1 GENERAL LIABILITY (includes premises/operations, collapse hazard, products, completed operations, contractual, independent contractors, broad form property damage, personal injury):

(1) BODILY INJURY, ON OR OFF THE SITE, IN U.S. DOLLARS

Per Occurrence
$5,000
Cumulative
$10,000

(2) PROPERTY DAMAGE, ON OR OFF THE SITE, IN U.S. DOLLARS

Per Occurrence
$5,000
Cumulative
$10,000

G.2.2 The foregoing types and amounts of insurance are the minimums required. The Contractor shall obtain any other types of insurance required by local law or that are ordinarily or customarily obtained in the location of the work. The limit of such insurance shall be as provided by law or sufficient to meet normal and customary claims.

G.2.3 The Contractor agrees that the Government shall not be responsible for personal injuries or for damages to any property of the Contractor, its officers, agents, servants, and employees, or any other person, arising from and incident to the Contractor's performance of this contract. The Contractor shall hold harmless and indemnify the Government from any and all claims arising therefrom, except in the instance of gross negligence on the part of the Government.

G.2.4 The Contractor shall obtain adequate insurance for damage to, or theft of, materials and equipment in insurance coverage for loose transit to the site or in storage on or off the site.

G.2.5 The general liability policy required of the Contractor shall name "the United States of America, acting by and through the Department of State", as an additional insured with respect to operations performed under this contract.

G.3.0 DOCUMENT DESCRIPTIONS

G.3.1 SUPPLEMENTAL DOCUMENTS: The Contracting Officer shall furnish from time to time such detailed drawings and other information as is considered necessary, in the opinion of the Contracting Officer, to interpret, clarify, supplement, or correct inconsistencies, errors or omissions in the Contract documents, or to describe minor changes in the work not involving an increase in the contract price or extension of the contract time. The Contractor shall comply with the requirements of the supplemental documents, and unless prompt objection is made by the Contractor within 20 days, their issuance shall not provide for any claim for an increase in the Contract price or an extension of contract time.

G.3.1.1. RECORD DOCUMENTS. The Contractor shall maintain at the project site:

(1) a current marked set of Contract drawings and specifications indicating all interpretations and clarification, contract modifications, change orders, or any other departure from the contract requirements approved by the Contracting Officer; and,

(2) a complete set of record shop drawings, product data, samples and other submittals as approved by the Contracting Officer.

G.3.1.2 . "As-Built" Documents: After final completion of the work, but before final acceptance thereof, the Contractor shall provide:

(1) a complete set of "as-built" drawings, based upon the record set of drawings, marked to show the details of construction as actually accomplished; and,

(2) record shop drawings and other submittals, in the number and form as required by the specifications.

G.4.0 LAWS AND REGULATIONS - The Contractor shall, without additional expense to the Government, be responsible for complying with all laws, codes, ordinances, and regulations applicable to the performance of the work, including those of the host country, and with the lawful orders of any governmental authority having jurisdiction. Host country authorities may not enter the construction site without the permission of the Contracting Officer. Unless otherwise directed by the Contracting Officer, the Contractor shall comply with the more stringent of the requirements of such laws, regulations, and orders and of the contract. In the event of a conflict between the contract and such laws, regulations and orders, the Contractor shall promptly advise the Contracting Officer of the conflict and of the Contractor's proposed course of action for resolution by the Contracting Officer.

G.4.1 The Contractor shall comply with all local labor laws, regulations, customs, and practices pertaining to labor, safety, and similar matters, to the extent that such compliance is not inconsistent with the requirements of this contract.

G.4.2 The Contractor shall give written assurance to the Contracting Officer that all subcontractors and others performing work on or for the project have obtained all requisite licenses and permits.

G.4.3 The Contractor shall submit proper documentation and evidence satisfactory to the Contracting Officer of compliance with this clause.

G.5.0 CONSTRUCTION PERSONNEL - The Contractor shall maintain discipline at the site and at all times take all reasonable precautions to prevent any unlawful, riotous, or disorderly conduct by or among those employed at the site. The Contractor shall ensure the preservation of peace and protection of persons and property in the neighborhood of the project against such action. The Contracting Officer may require, in writing that the Contractor remove from the work any employee that the Contracting Officer deems incompetent, careless, insubordinate or otherwise objectionable, or whose continued employment on the project is deemed by the Contracting Officer to be contrary to the Government's interests.

G.5.1 If the Contractor has knowledge that any actual or potential labor dispute is delaying or threatens to delay the timely performance of this contract, the Contractor shall immediately give notice, including all relevant information, to the Contracting Officer.

G.5.2 After award, the Contractor has ten calendar days to submit to the Contracting Officer a list of workers and supervisors assigned to this project for the Government to conduct all necessary security checks. It is anticipated that security checks will take 21days to perform. For each individual, the list shall include:

Full Name Place and Date of Birth Current Address Nationality Father’s Name Title

Failure to provide any of the above information may be considered grounds for rejection and/or resubmittal of the application. Once the Government has completed the security screening and approved the applicants a badge will be provided to the individual for access to the site. This badge may be revoked at any time due to the falsification of data, or misconduct on site.

G.5.3 The Contractor shall provide an English-speaking supervisor on site at all times. This position is considered as key personnel under this purchase order.

G.6.0 Materials and Equipment - All materials and equipment incorporated into the work shall be new and for the purpose intended, unless otherwise specified. All workmanship shall be of good quality and performed in a skillful manner that will withstand inspection by the Contracting Officer.

G.7.0 SPECIAL WARRANTIES

G.7.1 Any special warranties that may be required under the contract shall be subject to the stipulations set forth in 52.246-21, "Warranty of Construction", as long as they are not in conflict.

G.7.2 The Contractor shall obtain and furnish to the Government all information required to make any subcontractor's, manufacturer's, or supplier's guarantee or warranty legally binding and effective. The Contractor shall submit both the information and the guarantee or warranty to the Government in sufficient time to permit the Government to meet any time limit specified in the guarantee or warranty, but not later than completion and acceptance of all work under this contract.

G.8.0 EQUITABLE ADJUSTMENTS

Any circumstance for which the contract provides an equitable adjustment that causes a change within the meaning of paragraph (a) of the "Changes" clause shall be treated as a change under that clause; provided, that the Contractor gives the Contracting Officer prompt written notice (within 20 days) stating:

(a) the date, circumstances, and applicable contract clause authorizing an equitable adjustment and

(b) that the Contractor regards the event as a changed condition for which an equitable adjustment is allowed under the contract

The Contractor shall provide written notice of a differing site condition within 10 calendar days of occurrence following FAR 52.236-2, Differing Site Conditions.

G.9.0 ZONING APPROVALS AND PERMITS

The Government shall be responsible for:

· obtaining proper zoning or other land use control approval for the project

· obtaining the approval of the Contracting Drawings and Specifications

· paying fees due for the foregoing; and,

· for obtaining and paying for the initial building permits.

SECTION H - CLAUSES

52.252‑2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. In addition, the full text of a clause may be accessed electronically at: Acquisition.gov this address is subject to change.

If the Federal Acquisition Regulation (FAR) is not available at the location indicated above, use the Department of State Acquisition website at e-CFR to see the links to the FAR. You may also use an Internet “search engine” (for example, Google, Yahoo or Excite) to obtain the latest location of the most current FAR.

THE FOLLOWING FEDERAL ACQUISITION REGULATION CLAUSE(S) IS/ARE INCORPORATED BY REFERENCE (48 CFR CH. 1):

CLAUSE TITLE AND DATE

52.202-1 DEFINITIONS (JUN 2020)

52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS (NOV 2023)

52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)

52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS (JAN 2026)

52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (JAN 2026)

52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)

52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED OR PROPOSED FOR DEBARMENT OR VOLUNTARILY EXCLUDED (JAN 2026)

52.216-7 ALLOWABLE COST AND PAYMENT (FEB 2026)

52.222-1 NOTICE TO THE GOVERNMENT OF LABOR DISPUTES (FEB 1997)

52.222-19 CHILD LABOR-COOPERATION WITH AUTHORITIES AND REMEDIES (FEB 2026)

52.222-50 COMBATING TRAFFICKING IN PERSONS (FEB 2026)

52.225-5 TRADE AGREEMENTS (NOV 2023)

52.225-14 INCONSISTENCY BETWEEN ENGLISH VERSION AND TRANSLATION OF CONTRACT (FEB 2000)

52.226-8 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING (MAY 2024)

52.228-3WORKERS’ COMPENSATION INSURANCE (DEFENSE BASE ACT)
(JUL 2014)

52.228-4 WORKERS’ COMPENSATION AND WAR-HAZARD INSURANCE OVERSEAS (APR 1984)

52.228-5 INSURANCE - WORK ON A GOVERNMENT INSTALLATION (JAN 1997)

52.228-11 PLEDGES OF ASSETS (FEB 2021)

52.228-13 ALTERNATIVE PAYMENT PROTECTION (JULY 2000)

52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)

52.228-15 PERFORMANCE AND PAYMENT BONDS-CONSTRUCTION (JUN 2020)

52.229-6 TAXES - FOREIGN FIXED-PRICE CONTRACTS (FEB 2013)

52.229-7 TAXES- FIXED PRICE CONTRACTS WITH FOREIGN GOVERNMENTS (FEB 2013)

52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)

52.232-8 DISCOUNTS FOR PROMPT PAYMENT (FEB 2002)

52.232-11 EXTRAS (APR 1984)

52.232-18 AVAILABILITY OF FUNDS (APR 1984)

52.232-22 LIMITATION OF FUNDS (FEB 2026)

52.232-25 PROMPT PAYMENT (JAN 2017)

52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017)

52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER - SYSTEM FOR AWARD MANAGEMENT (OCT 2018)

52.232-34 PAYMENT BY ELECTRONIC FUNDS TRANSFER – OTHER THAN SYSTEM FOR AWARD MANAGEMENT (JULY 2013)

52.233-1 DISPUTES (JAN 2026)

52.233-3 PROTEST AFTER AWARD (JAN 2026)

52.236-2 DIFFERING SITE CONDITIONS (AUG 2025)

52.236-3SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK
(AUG 2025)

52.236-5 MATERIAL AND WORKMANSHIP (AUG 2025)

52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (AUG 2025)

52.236-7 PERMITS AND RESPONSIBILITIES (AUG 2025)

52.236-8 OTHER CONTRACTS (AUG 2025)

52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS (AUG 2025)

52.236-10 OPERATIONS AND STORAGE AREAS (AUG 2025)

52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (AUG 2025)

52.236-12 CLEANING UP (AUG 2025)

52.236-13 ACCIDENT PREVENTION (AUG 2025)

52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (AUG 2025)

52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (AUG 2025)

52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (AUG 2025)

52.242-14 SUSPENSION OF WORK (APR 1984)

52.243-4 CHANGES (JUL 2025)

52.243-5 CHANGES AND CHANGED CONDITIONS (JUL 2025)

52.245-2 GOVERNMENT PROPERTY INSTALLATION OPERATION SERVICES (JUL 2025)

52.245-9 USE AND CHARGES (APR 2012)

52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)

52.246-17 WARRANTY OF SUPPLIES OF A NONCOMPLEX NATURE (JUN 2003)

52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)

52.246-26 REPORTING NONCONFORMING ITEMS (AUG 2024)

52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012)

52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)

52.249-14 EXCUSABLE DELAYS (APR 1984)

II.

FAR CLAUSES INCORPORATED IN FULL TEXT

52.213-4 TERMS AND CONDITIONS SIMPLIFIED ACQUISITIONS (NONCOMMERCIAL) (JAN 2026)

(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post acceptance rights—

(1) Within a reasonable period of time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(b) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence. Examples of occurrences include acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. When an excusable delay occurs, the Contractor shall—

(1) Notify the Contracting Officer in writing as soon as possible;

(2) Remedy the delay as quickly as possible; and

(3) Notify the Contracting Officer when the occurrence is over.

(c) Termination for the Government’s convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(d) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. The Government will send a cure notice to the Contractor, unless the reason for the termination is late delivery. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(e) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(End of clause)

III.

THE FOLLOWING DEPARTMENT OF STATE ACQUISITION REGULATION (DOSAR) CLAUSE(S) IS/ARE SET FORTH IN FULL TEXT:

CONTRACTOR IDENTIFICATION (JULY 2008)

Contract performance may require contractor personnel to attend meetings with government personnel and the public, work within government offices, and/or utilize government email.

Contractor personnel must take the following actions to identify themselves as non-federal employees:

1. Use an e-mail signature block that shows name, the office being supported and company affiliation (e.g., “John Smith, Office of Human Resources, ACME Corporation Support Contractor”);

1. Clearly identify themselves and their contractor affiliation in meetings.

3) Identify their contractor affiliation in Departmental e-mail and phone listings whenever contractor personnel are included in those listings; and

4) Contractor personnel may not utilize Department of State logos or indicia on business cards.

652.204-70 DEPARTMENT OF STATE PERSONAL IDENTIFICATION CARD ISSUANCE PROCEDURES (FEB 2015)

(a) The Contractor shall comply with the Department of State (DOS) Personal Identification Card Policy and Procedures for all employees performing under this contract who require frequent and continuing access to DOS facilities, or information systems. The Contractor shall insert the substance of this clause in all subcontracts when the subcontractor's employees will require frequent and continuing access to DOS facilities, or information systems.

(b) The DOS Personal Identification Card Policy and Procedures may be accessed at http://www.state.gov/m/ds/rls/rpt/c21664.htm.

(End of clause)

652.229-71 PERSONAL PROPERTY DISPOSITION AT POSTS ABROAD (AUG 1999)

Regulations at 22 CFR Part 136 require that U.S. Government employees and their families do not profit personally from sales or other transactions with persons who are not themselves entitled to exemption from import restrictions, duties, or taxes. Should the Contractor experience importation or tax privileges in a foreign country because of its contractual relationship to the United States Government, the Contractor shall observe the requirements of 22 CFR Part 136 and all policies, rules, and procedures issued by the chief of mission in that foreign country.

(End of clause)

652.236-70 ADDITIONAL SAFETY MEASURES (OCT 2017)

In addition to the safety/accident prevention requirements of FAR 52.236-13, Accident Prevention Alternate I, the contractor shall comply with the following additional safety measures.

(a) High Risk Activities. If the project contains any of the following high risk activities, the contractor shall follow the section in the latest edition, as of the date of the solicitation, of the U.S. Army Corps of Engineers Safety and Health manual, EM 385‑1‑1, that corresponds to the high risk activity. Before work may proceed, the contractor must obtain approval from the COR of the written safety plan required by FAR 52.236-13, Accident Prevention Alternate I (see paragraph (f) below), containing specific hazard mitigation and control techniques.

(1) Scaffolding;

(2) Work at heights above 1.8 meters;

(3) Trenching or other excavation greater than one (1) meter in depth;

(4) Earth-moving equipment and other large vehicles;

(5) Cranes and rigging;

(6) Welding or cutting and other hot work;

(7) Partial or total demolition of a structure;

(8) Temporary wiring, use of portable electric tools, or other recognized electrical hazards. Temporary wiring and portable electric tools require the use of a ground fault circuit interrupter (GFCI) in the affected circuits; other electrical hazards may also require the use of a GFCI;

(9) Work in confined spaces (limited exits, potential for oxygen less than 19.5 percent or combustible atmosphere, potential for solid or liquid engulfment, or other hazards considered to be immediately dangerous to life or health such as water tanks, transformer vaults, sewers, cisterns, etc.).

(10) Hazardous materials - a material with a physical or health hazard including but not limited to, flammable, explosive, corrosive, toxic, reactive or unstable, or any operations, which creates any kind of contamination inside an occupied building such as dust from demolition activities, paints, solvents, etc.; or

(11) Hazardous noise levels as required in EM 385-1 Section 5B or local standards if more restrictive.

(b) Safety and Health Requirements. The contractor and all subcontractors shall comply with the latest edition of the U.S. Army Corps of Engineers Safety and Health manual EM 385-1-1, or OSHA 29 CFR parts 1910 or 1926 if no EM 385-1-1 requirements are applicable, and the accepted contractor’s written safety program.

(c) Mishap Reporting. The contractor is required to report immediately all mishaps to the COR and the contracting officer. A “mishap” is any event causing injury, disease or illness, death, material loss or property damage, or incident causing environmental contamination. The mishap reporting requirement shall include fires, explosions, hazardous materials contamination, and other similar incidents that may threaten people, property, and equipment.

(d) Records. The contractor shall maintain an accurate record on all mishaps incident to work performed under this contract resulting in death, traumatic injury, occupational disease, or damage to or theft of property, materials, supplies, or equipment. The contractor shall report this data in the manner prescribed by the contracting officer.

(e) Subcontracts. The contractor shall insert this clause, including this paragraph (e), with appropriate changes in the designation of the parties, in subcontracts.

(f) Written program. The plan required by paragraph (f)(1) of the clause entitled “Accident Prevention Alternate I” shall be known as the Site Safety and Health Plan (SSHP) and shall address any activities listed in paragraph (a) of this clause, or as otherwise required by the contracting officer/COR.

1. The SSHP shall be submitted at least 10 working days prior to commencing any activity at the site.

1. The plan must address developing activity hazard analyses (AHAs) for specific tasks. The AHAs shall define the activities being performed and identify the work sequences, the specific anticipated…