RFQ 1080-27-CG CMAR Thornton and Cottonwood Improvements - Final.pdf

PDF 856 KB Posted

Attached to
RFSQ CMAR Thornton Rd & Cottonwood Ln Improvements
Solicitation number
1080-27-CG
Issued by
Pinal County, Arizona

About this file

Summary

This is a Request for Qualifications (RFQ) issued by the City of Casa Grande, Arizona, solicitation number 1080-27-CG, for a Construction Manager at Risk (CMAR) to provide preconstruction and construction services for the Thornton Road and Cottonwood Lane Improvements Project. The project scope includes intersection improvements to widen the Thornton Road and Cottonwood Lane intersection by adding a second westbound to southbound left turn lane and a northbound to eastbound right turn lane, along with sidewalk, curb and gutter, drainage modifications, irrigation pipe extensions, and traffic signal modifications. The project also encompasses Cottonwood Lane pavement rehabilitation and ADA improvements between Pinal Avenue and Thornton Road, including mill and fill, full depth replacement options, and sidewalk and ramp modifications. Statements of Qualifications must be submitted by September 29, 2026, at 2:00 p.m. local time to the City Clerk's office at 510 East Florence Boulevard, Casa Grande, Arizona 85122. The submission must include one original and two copies in a sealed envelope. No pre-submittal conference will be held. The CMAR will be selected through a qualifications-based process, with the City reserving the right to negotiate a separate Construction Phase Agreement following completion of design development and agreement on a Guaranteed Maximum Price (GMP).

The evaluation process awards a maximum of 1,000 points across five criteria: Cover Letter and Required Forms (100 points), Capabilities of the Project Team (300 points), Project Understanding and Approach (200 points), Firms Similar Project Experience, Relevance and Results (300 points), and Subcontractor Selection Plan (100 points). SOQ responses are limited to six single-sided pages and must include specific required forms as attachments that do not count toward the page limit. The City will evaluate qualifications based on the CMAR's experience with similar multi-discipline transportation projects completed within the last five years, superintendent and key personnel qualifications, understanding of project risks, project management methodologies, and subcontractor selection processes. Per Arizona Revised Statutes Section 34-603, the CMAR must provide a Payment Bond and Performance Bond in accordance with A.R.S. Section 34-222 prior to execution of the construction contract. For horizontal construction, the CMAR must self-perform not less than 45 percent of the work as required by statute. The highest-ranked firm will be selected for negotiation of preconstruction services, with the option for the City to negotiate with subsequent firms if initial negotiations are unsuccessful.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR QUALIFICATIONS

FOR

CONSTRUCTION MANAGER AT RISK

FOR THE

THORNTON RD & COTTONWOOD LN

IMPROVEMENTS

SOLICITATION NUMBER 1080-27-CG

AUGUST 2026

CITY OF CASA GRANDE, ARIZONA

REQUEST FOR STATEMENT OF QUALIFICATIONS

FOR CONSTRUCTION MANAGER AT RISK FOR THORNTON RD & COTTONWOOD LN

IMPROVEMENTS

The City of Casa Grande requests Statements of Qualifications (SOQs) for a Construction Manager at Risk (CMAR) to provide preconstruction services and complete construction services for the City’s Thornton Rd & Cottonwood Ln Improvements in the City of Casa Grande, Arizona.

Each response shall be per the SOQ instructions and scope of work package on file with the City Clerk at City Hall, 510 East Florence Boulevard, Casa Grande, Arizona, 85122. Copies can be obtained by calling the City Clerk's Office (520) 421-8600 or downloading a complete packet at the City's website: www.casagrandeaz.gov.

All responses must be submitted by 2:00 p.m. local time on September 29, 2026 to the Office of the City Clerk, 510 East Florence Boulevard, Casa Grande, Arizona 85122. The responses will be evaluated in accordance with Section Five (5) of the SOQ.

Responses must be addressed to:

Office of the City Clerk City of Casa Grande 510 East Florence Boulevard Casa Grande, Arizona 85122

The envelope must be boldly marked:

September 29, 2026 – 2:00 P.M.

STATEMENT OF QUALIFICATIONS

FOR CONSTRUCTION MANAGER AT RISK FOR

Solicitation Number 1080-27-CG

The City of Casa Grande reserves the right to waive any informalities or irregularities in this Statement of Qualifications solicitation or to reject any or all responses, to be the sole judge of the suitability of the services and materials offered, and to award a contract for the furnishing of the services it deems to be in the best interest of the City.

/s/ Larry Rains City Manager http://www.casagrandeaz.gov/

CITY OF CASA GRANDE, ARIZONA

REQUEST FOR STATEMENT OF QUALIFICATIONS

FOR CONSTRUCTION MANAGER AT RISK FOR

THORNTON RD & COTTONWOOD LN IMPROVEMENTS

TABLE OF CONTENTS

SECTION PAGE

SECTION 1 - PROJECT DESCRIPTION

SECTION 2 - SCOPE OF WORK

SECTION 3 - TERMS, CONDITIONS, AND INSTRUCTIONS

SECTION 4 - SUBMITTAL REQUIREMENTS

SECTION 5 - SUBMITTAL EVALUATION PROCESS

SECTION 6 - SELECTION PROCESS

APPENDIX A

APPENDIX B

SECTION 1 - PROJECT DESCRIPTION

The City of Casa Grande (City) is seeking a qualified Construction Manager at Risk (CMAR) to provide preconstruction services and complete construction services as the CMAR for the City’s planned THORNTON RD & COTTONWOOD LN IMPROVEMENTS hereinafter referred to as “the Project.”

This procurement is conducted pursuant to A.R.S. Section 34-603. The City intends to select a CMAR based on qualifications and to negotiate a contract for preconstruction services, followed by negotiating a Guaranteed Maximum Price (“GMP”) for construction services.

CONSTRUCTION SCOPE OF WORK

The THORNTON RD & COTTONWOOD LN project is intended to make roadway improvements based on the following objectives:

Intersection Improvements The City’s goal is to widen the Thornton Road and Cottonwood Lane intersection to improve operations by adding a second westbound to southbound left turn lane along Cottonwood Lane and a northbound to eastbound right turn lane along Thornton Road. This project will require roadway widening with sidewalk, curb & gutter; drainage catch basin replacement and pipe extensions; irrigation pipe extensions, traffic signal modifications; signing and striping modifications.

Cottonwood Lane Pavement Rehabilitation and ADA Improvements The pavement rehabilitation task will use four (4) different pavement sections along Cottonwood Lane between Pinal Avenue and Thornton Road to include: mill and fill; mill and fill with SAMI;

full depth replacement with new AC; and remove AC and replace with concrete. The scope for this portion of the project will also include: the removal and replacement of ramps; adding new ramps; removal and replacement of sidewalks; adding new sidewalk; and replacing driveways.

SECTION 2 - SCOPE OF WORK

For this Project, the CMAR will be responsible for working with the engineering design team. The CMAR will serve as the general contractor during the construction of the Project.

Before construction, the CMAR will assume the risk of delivering the Project through a Guaranteed Maximum Price (GMP) contract. The CMAR will be responsible for construction means and methods. The CMAR may also self-perform work or solicit bids from qualified subcontractors.

Prior to execution of the construction contract, CMAR shall provide the City a Payment Bond and a Performance Bond in accordance with A.R.S. Section 34-222.

The following are the minimum requirements of the CMAR:

A. During the pre-construction phase services by the CMAR may, at a minimum, be required to:

1. Work with the design team in the development of final design plans and quantities, including providing suggestions or recommendations for value engineering and other potential cost-savings opportunities.

2. Develop one or two GMP proposals to perform the work identified in the plans developed by the Project design team.

3. Identify any long-lead items required. The first GMP may be requested to procure the identified long-lead items.

4. Provide a conceptual schedule for the Project, primarily the construction phase.

B. During the Construction phase services by the CMAR may, at a minimum be required to:

1. Construct all improvements.

2. Coordinate with various City of Casa Grande departments, other agencies, utility companies, etc. This shall include meetings at a frequency agreed to with the city.

3. Arrange for procurement of materials and equipment.

4. Maintain the approved Project schedule.

5. Bid, award, and manage all construction-related contracts while meeting City requirements for procurement of subcontractor and supplier bids.

6. Provide quality controls, including 3rd party QA/QC testing and inspection.

7. Provide as-built plans sealed by an engineer. The as-built plans shall document all changes from the permitted design plans and include survey data for all found utilities.

8. Provide payment and performance bonds to ensure construction.

9. Address and obtain federal, state, and local permitting requirements.

10. Assist in the resolution of owner issues.

11. Maintain a safe work site for all Project participants.

C. Project Management

1. Project Management Plan – Prepare and submit for approval a Project Management P lan that includes:

a. Refined scope of services

b. Identify and list the Project deliverables

c. Project schedule with needed Project meetings identified, an intermediate milestone and document delivery dates established

d. Contact information for key contractor and agency staff

SECTION 3 - TERMS, CONDITIONS, AND INSTRUCTIONS

Definition of Terms Used in These Instructions

As used in these instructions, the following terms have the following meaning:

A. "Attachments" means all items required of the Submitter as a part of the Submittal.

B. "Days" means calendar days unless otherwise specified.

C. "Exhibits" means all items attached to the solicitation.

D. "Submittal" means bid, Submittal, quotation, and qualifications.

E. "Submitter" means a vendor or provider who responds to any type of solicitation.

F. "Contracts Manager" means the person duly authorized to enter into and administer contracts and make written determinations concerning the Contract or its designee.

G. "Solicitation" means an invitation for bids (IFB), a request for Submittals (RFP), or a request for qualifications (RFQ).

Inquiries

A. Solicitation Contact Person; Other Contact Prohibited. Any inquiry related to a solicitation shall be directed solely to the City of Casa Grande Project Manager identified in this Request for Qualifications. The Submitter shall not contact or direct inquiries concerning this solicitation to any other employee unless the solicitation explicitly identifies a person other than the Project Manager as a contact. All firms interested in this Project (including the firm's employees, representatives, agents, lobbyists, attorneys, and subconsultants) will refrain, under penalty of disqualification, from direct or indirect contact to influence the selection or create bias in the selection process with any person who may play a part in the selection process, including the evaluation panel, the City Manager, Deputy City Manager, Department Heads, and other staff.

This policy is intended to create a level playing field for all potential firms, to ensure that contract decisions are made in public, and to protect the integrity of the selection process.

The Project Manager/Contact Person for this Solicitation shall be:

Owen Mills, PE

Senior Project Manager

Public Works Department

Owen_Mills@casagrandeaz.gov

B. Submission of Inquiries. All inquiries are to be submitted via EMAIL ONLY to the Project Manager/Contact person listed above. Each inquiry shall clearly refer to this solicitation in the subject line of the email. A list of all inquiries received and responses by the City shall be generated and made available to all interested parties via posting on the City's website at least seven (7) days prior to the Submittal deadline.

C. Timeliness. All inquiries should be submitted at least ten (10) calendar days before the Submittal due date and time. Failure to do so may result in the inquiry not being answered.

D. No Right to Rely on Verbal Responses. Any inquiry that raises material issues and results in changes to the solicitation shall be answered solely through a written solicitation amendment or addendum. A Submitter may not rely on verbal responses to their inquiries.

Submittal Acceptance Period

By submitting a proposal pursuant to this solicitation, Submitter agrees that it shall hold its Submittal open for one-hundred twenty (120) days.

Cost of Submittal Preparation

Except as required by statute or City Code or Regulation, the City of Casa Grande shall not reimburse any Submitter the cost of responding to a solicitation.

mailto:Owen_Mills@casagrandeaz.gov

Certifications, Disclosure, and Disqualification

A. Non-collusion, Employment, and Services. By signing the Submittal Acknowledgement, or other official contract form, the Submitter certifies that:

a. Submitter did not engage in collusion or other anti-competitive practices in connection with the preparation or submission of its Submittal; and

b. It does not discriminate against any employee, applicant for employment, or person to whom it provides services because of race, color, religion, sex, national origin, or disability, and it complies with all applicable federal, state, and local laws and executive orders.

B. Disclosure. If the design consultant, construction contractor, business, or person submitting this Submittal has previously been debarred, suspended, or otherwise lawfully precluded from participating in any public procurement activity, including being disapproved as a subcontractor with any federal, state, or local government, or if any such preclusion from participation from any public procurement activity is currently pending, Submitter must fully explain the circumstances relating to the prior preclusion or proposed preclusion in the Submittal by including a letter with its Submittal setting forth the name and address of the governmental unit, the effective dates of the suspension or debarment, the duration of the suspension or debarment, and the relevant circumstances relating to the suspension or debarment or proposed suspension or debarment.

C. Disqualification. The Submittal of a Submitter who is currently debarred, suspended, or otherwise lawfully prohibited from any public procurement activity shall be rejected.

Award of Contract

Number or Types of Awards

Where applicable, the City of Casa Grande reserves the right to make multiple awards or award a contract by individual line items, by a group of line items, or to make an aggregate award, whichever is deemed most advantageous to the City of Casa Grande. If the Contracts Manager determines that an aggregate award to one submitter is not in the City of Casa Grande's interest, "all or none" Submittals shall be rejected.

Prompt Payment Discount

Prompt payment discounts of thirty (30) days or more set forth in a Submittal shall be deducted from the Submittal for the purpose of evaluating that price.

Contract Inception.

Submittal does not constitute a contract, nor does it confer any rights on the Submitter to award a contract. A contract is not created until the Submittal is accepted by the Casa Grande City Council, if required by the City Code or Regulations, and a written contract is executed by the authorized signature of the City Manager, or designee, and the Submitter.

Protests

Pursuant to Section 3.04.170 of the Casa Grande City Code, all protests shall be in writing and be filed with the City of Casa Grande Purchasing Officer. To be considered timely, a protest of a solicitation must be filed within three (3) days following the date on which the act or error complained of occurred. A protest shall include:

• The name, address, and telephone number of the protester.

• The signature of the protester or its representative.

• Identification of the purchasing agency and the solicitation or contract number.

• A detailed statement of the legal and factual grounds of the protest including copies of relevant documents; and

• The form of relief requested.

Solicitation Order of Precedence

In the event of a conflict in the provisions of this Solicitation, the following shall prevail in the order set forth below:

• Solicitation.

• Special Terms and Conditions, if any;

• Specifications, if any;

• Exhibits, if any;

• Special Instructions to Submitters, if any; and

• Uniform Instructions to Submitters, if any.

Persons With Disabilities

Persons with a disability may request a reasonable accommodation by contacting the Project Manager. Requests should be made as early as possible to allow time to arrange the accommodation. A person requiring a special accommodation may contact the Project Manager responsible for this procurement as identified on the first page of this solicitation.

SECTION 4 - SUBMITTAL REQUIREMENTS

The CMAR will be selected through a qualifications-based selection process. Firms interested in providing CMAR services must submit a Statement of Qualifications (SOQ) that meets the criteria outlined in this section. The information included in the SOQ response will be used to evaluate your firm as part of any criteria, regardless of where that information is found in the SOQ. Information obtained from the SOQ and any other relevant source, including an independent investigation by the City, may be used in the evaluation and selection process.

The TOTAL PAGE LIMIT is SIX (6) pages, single-sided for the SOQ Submittal. All SOQs shall be submitted per the instructions below. Email copies will not be accepted. The 3 required forms (Submittal Acknowledgment, Non-Collusion Affidavit, Authorization for release of Performance Information and Waiver) do not count towards the page limit, but must be attached.

A. Copies of Submittal. To be considered responsive, one (1) original and two (2) copies of the SOQ document must be submitted in a sealed envelope or box with the following SOQ description boldly marked:

September 29, 2026 – 2:00 P.M.

STATEMENT OF QUALIFICATIONS

CONSTRUCTION MANAGER AT RISK (CMAR)

SOLICITATION NUMBER 1080-27-CG

The Submittal shall include the firm’s name and address on the package. The original copy of the Submittal document must bear the original signature of an authorized representative of the submitter on the acknowledgment provided. The Submittal must be delivered to the following Location:

Location: City of Casa Grande ATTN: Office of the City Clerk 510 East Florence Boulevard Casa Grande, Arizona 85122

B. Forms. No Facsimile or Telegraphic Submittals. A Submittal shall be made either on the forms provided in this Solicitation or their substantial equivalent. Any substitute document for the forms provided in this Solicitation shall be legible and contain the same information requested on the form. A facsimile or telegraphic Submittal shall be rejected.

C. Page Parameters. A page is defined as 8½ x 11-inch. An 11 x 17-inch page is not allowed to be submitted. A portrait or landscape format is acceptable. A page with text on the front and back will count as two pages. A page with text on the front and blank on the back will count as 1 page. All proposal pages are counted from beginning to end to arrive at the maximum allowable page limit stated in the RFQ Package. All pages, including covers, table of contents, tables, figures, photographs, divider sheets, maps, etc., are counted as pages. Any additional pages, forms, documents, or attachments that cause the Submittal to exceed the total page limit will not be included in the review of the Submittal.

The Submittal shall be clear and legible. Submittal scores will be adversely affected if SOQs are not readable or the font size is too small for Selection Panel members to read.

D. Video or Multimedia Applications. No video clips or other multimedia applications are allowed.

Attached multimedia will not be included in the review of the Submittal.

E. Attachments. The SOQ required City Forms (which are provided in this RFQ in Appendix A), shall not be included in the page count. Do not add additional pages, forms, documents, or attachments, including blank pages, to the Required Forms, as any additional pages shall count toward the page count.

See Appendix A for a detailed list of attachments requested. Extra divider sheets, including pages of any sort, blank or printed (regardless of the printed material on the page), separating the main proposal from attachments should also not be included as this shall be counted as a page.

The required forms must either be typed or in ink. Erasures, interlineations, or other modifications in the Submittal must be initialed in ink by the person signing the Submittal.

Changes shall not be permitted after Submittals have been opened except as otherwise provided under applicable law.

F. Duty to Examine. It is the responsibility of each Submitter to examine the entire Solicitation, seek clarification in writing, and check its Submittal for accuracy before submitting the Submittal.

Lack of care in preparing a Submittal shall not be grounds for withdrawing it after the Submittal due date and time, nor shall it give rise to any contract claim.

G. Amendments or Addendum. Submitters shall acknowledge all amendments or addenda.

Failure to acknowledge an amendment or addenda may be grounds for rejection of the Submittal and will be considered as part of the scoring criteria as outlined in Section 5A.

H. Submittal Amendment or Withdrawal. A Submittal may not be amended or withdrawn after the

Submittal due date and time except as otherwise provided under the City's Procurement Code or other applicable law.

I. Public Record. Under applicable law, all Submittals submitted and opened are public records and must be retained by the City of Casa Grande. Submittals shall be open to public inspection after contract award. If a Submitter believes that information in its Submittal is confidential under applicable law, it shall stamp that as confidential information and submit a statement with its

Submittal detailing the reasons that information should not be disclosed. The City of Casa

Grande shall make a determination pursuant to the City of Casa Grande's Procurement Code and the Public Records laws of the State of Arizona.

J. ADA and Accessibility Compliance of Documents in Response of this RFQ. Submitter represents and warrants that all documents and all media submitted to the City in response to this RFQ shall comply with all applicable federal and state accessibility laws and regulations, and that these documents and media shall conform to the Web Content Accessibility Guidelines

(WCAG) 2.1, Level AA (or any successor standard adopted by the United States Department of Justice or other applicable authority). If documents and/or media are submitted that do not meet this requirement, the Submittal may be deemed non-responsive. If requested by the City, Submitter shall promptly correct, at no additional cost to the City, any document and/or media determined by the City to be non-compliant with accessibility requirements.

K. ADA and Accessibility Compliance of Deliverables. Submitter represents and warrants that, if selected, all deliverables, work product, services, materials, documents, websites, software, applications, digital content, and communications provided under the resulting Contract

(collectively, “Deliverables”) shall comply with all applicable federal and state accessibility laws and regulations, and that these deliverables shall conform to the Web Content Accessibility

Guidelines (WCAG) 2.1, Level AA (or any successor standard adopted by the United States

Department of Justice or other applicable authority).Submitter shall promptly correct, at no additional cost to the City, any Deliverable determined by the City to be non-compliant with accessibility requirements.

L. Exceptions to Terms and Conditions. A Submittal that takes exception to a material requirement of any part of the solicitation, including a material term and condition of any proposed contract, may be rejected.

M. Release of Project Information. The City shall solely provide the release of all public information concerning the Project, including selection announcements and contract awards. Those desiring to release information to the public must receive prior written approval from the City.

N. Non-compliant Submittals to be rejected. Submitters are advised that failure to comply with the following criteria will be grounds for disqualification and will be strictly enforced:

● Receipt of Submittal by the specified cut-off date and time.

● Failure to deposit the Submittal in the appropriate location.

These failures will result in disqualification, and no action of the City, including late acceptance by the City Clerk, shall act to waive or otherwise affect the disqualification.

O. City Rights. The City of Casa Grande reserves the right to reject any or all Submittals and except as set forth in subsection (N) above, to waive any informality or irregularity in any Submittal received, to be the sole judge of the merits of the respective Submittals received, and to cancel any solicitation if deemed to be in the interest of the City to do so.

P. Pre-Submittal Conference. A pre-Submittal conference will not be held.

SECTION 5 - SUBMITTAL EVALUATION PROCESS

The SOQ shall be prepared to address the following evaluation factors. The maximum points to be awarded will be 1000 points. Please format your response in the order outlined below to maximum the points to be awarded for each element in the evaluation process.

EVALUATION FACTOR - MAXIMUM POINTS (1,000)

A. Cover Letter and Required Forms (100)

1. Provide a general description of the team that is proposing to provide construction management and general construction services. (40 total points)

2. Provide the following for the CMAR: (50 total points)

a. List contracts terminated in the last three (3) years and cause for the termination. (25)

b. List claims received in the last five (5) years, the cause and resolution. (25)

3. A signed statement declaring the Submitter has read all issued addenda (if any have been issued). (10 total points)

4. The Required Forms are expected to be completed and prepared accurately. A deduction of 10-points will be made for each form that is omitted or contains inaccurate information.

B. Capabilities of the Project Team (300)

1. Provide an organization chart showing key CMAR and subcontractor personnel. (30 total points)

2. Provide the following for the Superintendent: (160 total points)

a. Years of experience as a superintendent (5 points each up to 5 years = 25)

b. Number (list) of projects relevant to this Project while serving as a superintendent (15 point each up to 5 projects = 75)

c. Description of three (3) most relevant projects in the last three (3) years (50)

d. Relevant licenses and certifications (10)

e. Contact information (address, phone number and email) (10)

3. Provide the following for the Key Team Members (omitting the Superintendent); (100 total points)

a. Years of experience in their role (5 years = 20)

b. Number of projects relevant to this Project while serving in that role (5 projects = 40)

c. Description of one (1) most relevant project in the last three (3) years (20)

d. Relevant licenses and certifications (10)

e. Contact information (address, phone number and email) (10)

C. Project Understanding and Approach (200)

1. Discuss (list) your company’s: (140 total points)

a. Understanding of the scope, schedule and cost risks. (70)

b. Approach to addressing these scope, schedule and cost risks. (70)

2. Describe the project management methodologies and system used by the CMAR to ensure conformance to the: (60 total points)

a. Schedule (15)

b. Budget (15)

c. Quality assurance/quality control processes (15)

d. Securing stakeholder participation and buy-in (15)

D. Firms Similar Project Experience, Relevance and Results (300)

1. Describe your CMAR’s experience for three (3) multi-discipline transportation projects substantially completed within the last five (5) years including information on the schedule and budget to complete the work in relation to original contract requirements, with an explanation for deviations. Provide the superintendent’s and key personal’s roles on these projects. A ten (10) point deduction for subsection a. “relevance” will be made for each project listed that does not include the proposed superintendent proposed for this project. A five (5) point deduction for subsection a. “relevance” will be made for each project listed that does not include two or more of the key personnel proposed for this project. (250 total points)

a. Relevance (similarity with this projects scope of work) of the list (80)

b. Schedule (as bid in the GMP and actual) (60)

c. Budget (as provided with the GMP and actual) (60)

d. Deviation explanations (50)

2. Supply at least two (2) owner references for the above three (3) projects with up-to date contact names, email addresses, and phone numbers. (25)

3. List up to five (5) additional “relevant” multi-discipline transportation projects where the firm/team provided either CMAR, agency construction management, or general construction services in the last five (5) years, either completed or ongoing. Up to two (2) projects that do not have the same scopes of work will be given half the value of relevant matching projects scopes of work. The third (3rd) or additional project that does not have a similar or same scope of work will result in points deduction, up to ten (10) points. (25)

E. Subcontractor Selection Plan (100)

1. Describe the Primes Plan: (25 total points)

a. Describe which tasks the firm proposed to perform with its forces and which major tasks will be executed by subcontractors. (5)

b. Describe the selection process to be used in selecting key subcontractors and suppliers.

Methods available are either by qualifications-based selection only or by a combination of qualifications and price. (20)

2. Describe the Subcontractors and Suppliers: (75 total points)

a. Identify key subcontractors by firm name or specialty to be selected for your SOQ or early in the design process to engage with the design team in a design-assist role. Provide their contact information (address and phone number). (5)

b. Describe their; i) experience, ii) relevance and/or iii) certificates of the subcontractor or supplier, as justification to support those recommendations. (20)

c. Identify the key person with the subcontractor and/or supplier and their; i) experience, ii) relevance and/or iii) certificates of the key person, as justification to support those recommendations. (40)

d. Describe the lab or other testing equipment needed and provided for this Project. (10)

Format Content MAXIMUM

POINTS

TOTAL NUMBER

OF PAGES

Evaluation Criteria

A. Cover Letter 100

B. Capabilities of the Project Team 300

C. Project Understanding and Approach 200

D. Firms Similar Project Experience, Relevance and Results

E. Subcontractor Selection Plan 100

Total 1000 6

F. Interview

The city will not conduct an interview for the selection of a CMAR contractor for this Project.

SECTION 6 - SELECTION PROCESS

A selection committee shall be formed and will consist of at least one person who is a senior management employee of a licensed contractor, at least one person who is an architect or an engineer who is registered pursuant to ARS Section 32-121, representatives of the City of Casa Grande, and other members that the City of Casa Grande deem appropriate for the review of the Statements of Qualifications.. This Committee will read, review and evaluate each SOQ Submittal independently based on the published evaluation criteria and point allocations. Scores shall be tabulated and a "final list" will be constructed based on the score of the evaluations. The City may, however, call firms to clarify information received in the Submittal if deemed necessary to ensure a fair and thorough evaluation process. Final selection shall be based upon the results of the evaluation of statements of qualifications and performance data submitted. Firms on the final list shall be ranked based on the total points received, and the City will enter into negotiations with the highest-ranking firm.

Upon completion of the evaluation process, the City shall enter into negotiations with the highest-ranked firm for a Preconstruction Services Agreement. Following completion of design development and agreement upon a Guaranteed Maximum Price (GMP), the Parties will execute a separate Construction Phase Agreement, subject to City Council approval where required.

If negotiations with the highest-ranked firm are unsuccessful, the City may terminate negotiations and proceed to negotiate with the next highest-ranked firm.

A ‘draft’ sample of the forms of Contract to be executed is included in Appendix "B" in this solicitation.

If the City is unable to successfully negotiate a contract with the highest-ranking firm, the City may then negotiate with the second or third most qualified until a contract is reached or may terminate the selection process.

APPENDIX A

REQUIRED SUBMITTAL FORMS

Note: One completed original copy of each of the following forms MUST be provided with the Statement of Qualifications submittal package.

SUBMITTAL ACKNOWLEDGMENT

To the City of Casa Grande:

The undersigned hereby submits and agrees to furnish services in compliance with all terms, conditions, specifications, addendums, and amendments in the Solicitation. Signature also certifies acknowledgement of the material terms of the City of Casa Grande’s Sample Contract.

The undersigned also acknowledges that the City intends to procure execution of the final Contract using electronic signatures.

COMPANY NAME:

ADDRESS:

CITY/STATE/ZIP:

PHONE:

FAX:

CONTACT PERSON:

EMAIL for CONTACT PERSON:

AUTHORIZED COMPANY SIGNATURE AND TITLE:*

Signature: ___________________________

Name: ____________________

Title: _____________________

E-Mail Address: ______________________

* If a different person will be executing the contract, please fill out the name, title, and email:

Name: ____________________

Title: _____________________

E-Mail Address: ______________________

NON-COLLUSION AFFIDAVIT

State of ) ) ss.

County of )

__________________________________________________________ , affiant, (Name) the ______________________________________________________________ of

(Title)

(Contractor/Bidder) who is the person or other entity that makes the accompanying Submittal, having first been duly sworn, deposes and says:

That such Submittal is genuine and not sham or collusive, nor made in the interest of, or on behalf of, any persons not herein named, and that the Submitter has not directly or indirectly induced or solicited any other Submitter to put in a sham bid, or any other person, firm, company or corporation to refrain from making a submittal, and that the Submitter has not in any manner sought by collusion to secure for itself an advantage over any other Submitter.

(Title)

Subscribed and sworn to before me this ______ day of ___________________ , 2025

Notary Public:

My Commission Expires: ____________________

Authorization for Release of Performance Information and Waiver

I, ______________________, the undersigned, on behalf of ___________________ (this company), being duly authorized to do so, do hereby consent and authorize all those companies and government entities listed in my Submittal to the City of Casa Grande, and any other government entity for whom this company has performed pre-construction and/or construction services, to disclose and release to the City of Casa Grande, or its representatives, information, records and opinions concerning this 'company's performance. The purpose of this disclosure is to provide references and background material to the City of Casa Grande. This company hereby waives any claim it may have against the City of Casa Grande or any company or entity providing information to the City of Casa Grande by reason of any information being disclosed or opinions provided regarding the actions or performance of this company.

This authorization shall be effective for one year, and a copy of this authorization shall be as valid and effective as the original.

Dated: ______________________

By: _________________________

Title: _________________________

APPENDIX B

SAMPLE CONTRACT FORM

(Revised February 2026)

CONSTRUCTION MANAGER AT RISK

Pre-Construction Services

PROJECT TITLE:

THIS AGREEMENT, made and entered by and between the City of Casa Grande, an

Arizona municipal corporation, hereinafter designated “CITY” and , hereinafter designated the "Construction Manager At Risk" or “CM@Risk.”

RECITALS

WHEREAS, CITY intends to design and build a structure and related facilities to be known as the to be located at in the City of Casa Grande; and

WHEREAS, the Project will be performed in two phases. Phase I will include the pre-construction services and the preparation and submission of the Guaranteed Maximum

Price (GMP). Phase II will include the construction of the ; and

WHEREAS, this is a CM@Risk contract for Phase I of the Project, which requires that the CM@Risk be selected on the basis of demonstrated competence and qualifications for the type of professional services to be rendered without regard to fees and thereafter to negotiate a contract for those services at a fair and reasonable fee with the best qualified firm and at the end of Phase 1, at the CITY’s discretion, the CITY may enter into a separate Construction Agreement with the CM@Risk for construction phase services;

and

WHEREAS the CITY has published a Request for Qualifications seeking the submission of

Statements of Qualification to act as CM@Risk to furnish professional pre-construction services during Phase 1 of the Project identified and described in that Request for

Qualifications; and

WHEREAS, the undersigned CM@Risk submitted a Statement of Qualification that was evaluated by the CITY; and

WHEREAS, the CITY, through its awarding authority, has made an award of the work to the undersigned CM@Risk, and pursuant to the terms of the Request for Qualifications this form is to be executed to form and memorialize the contractual relationship between the parties; and

WHEREAS, CM@Risk has represented to the CITY that CM@Risk (i) is experienced in providing pre-construction services for projects of similar size and complexity to the

Project; (ii) is authorized and licensed, per AR.S. § 34-603(I)(2), to perform the type of labor and services for which it is being engaged in the State and locality in which the

Project is located; (iii) is qualified, willing and able to perform pre-construction services for the Project; and (iv) has the expertise and ability to provide pre-construction services which will meet the CITY’s objectives and requirements and which will comply with the requirements of all governmental, public, and quasi-public authorities and agencies having or asserting jurisdiction over the Project; and

WHEREAS, the Mayor and CITY Council of the City of Casa Grande are authorized and empowered by the provisions of the CITY Charter and state law to execute Agreements for Professional Services; and

WHEREAS, to undertake the design of said Project the CITY has entered into a contract with a Project Designer as defined in Article 1.

NOW THEREFORE, for and in consideration of the mutual covenants, considerations, and conditions hereinafter contained, it is agreed by and between the CITY and

CM@Risk, as follows:

ARTICLE 1- TERMS AND DEFINITIONS

“Addenda” means written or graphic instruments issued prior to the submittal of the

GMP Proposal(s), which clarify, correct, or change the GMP Proposal(s) requirements.

“Agreement” or “Contract” is this written document signed by the CITY and

CM@Risk covering the pre-construction phase of the Project, and including other documents itemized and referenced in or attached to and made part of this Agreement.

“Change Order” means a written order signed by an authorized representative of the

CITY and which approves changes in the total compensation or time allowed for completion of services consistent with the authorization provided by the Mayor and City

Council and the Casa Grande City Code.

“City”, “Owner” or “OWNER” means the City of Casa Grande, Arizona, an Arizona municipal corporation. Regulatory activities handled by the City of Casa Grande

Development Services, Planning and Fire Departments or any other CITY department are not subject to the responsibilities of the CITY under this Contract.

“CITY’S Contingency” means the fund to cover cost growth during the project used at the discretion of the CITY usually for costs that result from the CITY’S direct changes or unforeseeable site conditions. The amount of the CITY’S Contingency may be set solely by the CITY and will be in addition to the project costs included in the CM@Risk’s GMP packages. Use and management of the CITY’S Contingency is described in Section 3.9.

The CITY’S Contingency is an amount to cover changes initiated by the CITY, which may be incorporated into the GMP as an allowance at the CITY’S discretion.

“CM@Risk Contingency” means an agreed upon amount, either lump sum or a percentage of the Cost of the Work, that is included in the GMP and to be used by the

CM@Risk in accordance with the General Provisions in the construction contract, exclusive of CITY initiated changes and unknown site conditions. Generally, Contractor’s Contingency recognizes that the Drawings and the Specifications may still be less than 100% complete after the CITY’S final acceptance of the GMP. The amount of the CM@Risk’s Contingency will be negotiated as a separate line item in each GMP package. Use and management of CM@Risk’s Contingency is described in Section 3.9.

“CM@Risk’s Representative” means the person, firm, corporation, or other approved legal entity with which the CITY has entered into this Agreement and designated as such in this Contract.

“Construction Documents” are the plans, specifications, and drawings prepared by the

Project Designer after correcting for permit review requirements and incorporating addenda and approved change orders.

“Construction Fee” means the CM@Risk’s administrative costs, home office overhead, and profit, whether at the CM@Risk’s principal or branch offices. This includes the administrative costs and home office costs and any limitations or exclusions that may be included in the General Conditions for the construction phase.

“Construction Work” means the entire completed construction services or the various separately identifiable parts thereof, required to be furnished during the construction phase. Construction Work includes and is the result of performing or furnishing labor and furnishing and incorporating materials, resources and equipment into the construction, and performing or furnishing services and documents as required by the Contract

Documents for the construction phase.

“Contract Amount” means the final approved not-to-exceed budget for this Agreement as identified in Article 6.

“Contract Documents” means the following items and documents in descending order of precedence executed by the CITY and the CM@Risk: (i) all written modifications, addenda and Change Orders; (ii) this Pre-construction Agreement, including all exhibits and attachments; (iii) the CM@Risk Construction Agreement; (iv) written Supplementary

Conditions; (v) Construction Documents; (vi) GMP Plans and Specifications.

“Contract Time(s)” means the number of days or the dates related to the contract time for the Pre-Construction Phase Services Contract.

“Cost of the Work” means the direct costs necessarily incurred by the CM@Risk in the proper performance of the Work. The Cost of the Work shall include direct labor costs, subcontract costs, costs of materials and equipment incorporated in the completed construction, costs of other materials and equipment, temporary facilities, building permit fees, materials testing, and related items. The Cost of the Work shall not include the

CM@Risk’s construction fee, general conditions fee, taxes, bonds, or insurance costs.

“Data Sheet” means the sheet listing Project information contained in the RFQ.

“Day” means calendar day(s) unless otherwise specifically noted in the Contract

Documents.

“Deliverables” means the work products prepared by the CM@Risk in performing the scope of work described in Exhibit A of this Agreement. Major deliverables to be prepared and provided by the CM@Risk during the pre-construction phase may include but are not limited to: Construction Management Plan, Project Schedule, Schedule of

Values, alternative system evaluations, procurement strategies and plans, cost estimates, construction market surveys, cash flow projections, GMP Proposals, Subcontractor procurement plan, Subcontractor agreements, Subcontractor bid packages, Supplier agreements, and others as indicated in this Agreement or required by the Project Team.

“Drawings (Plans)” are documents, which visually represent the scope, extent and character of the Work to be furnished and performed by the CM@Risk during the construction phase and which have been prepared or approved by the Project Designer and the CITY. Drawings include such documents that have reached a sufficient stage of completion and released by the Project Designer solely for the purposes of review and/or use in performing constructability or biddability reviews and in preparing cost estimates

(e.g. conceptual design Drawings, preliminary design Drawings, detailed design

Drawings at 30%, 60%, 90% or 100%), but “not for construction”. Drawings do not include shop drawings.

“Effective Date of this Agreement” is the date specified in this Agreement on which the

Agreement becomes effective, but if no such date is so specified, the date on which the

CITY executes this Agreement.

“General Conditions Costs” means the costs incurred by the CM@Risk during the construction phase includes, but is not limited to the following types of costs; payroll costs for contract administrator or construction manager but not both for Construction

Work conducted at the site, payroll costs for the superintendent and full-time general foremen, payroll costs for management personnel resident and working on the site, workers not included as direct labor costs engaged in support (e.g. loading/unloading, clean-up, etc.), administrative office personnel, costs of offices and temporary facilities including office materials, office supplies, office equipment, minor expenses, utilities, fuel, sanitary facilities and telephone services at the site, costs of liability insurance premiums not included in labor burdens for direct labor costs, costs of bond premiums, costs of consultants not in the direct employ of the CM@Risk or Subcontractors, fees for permits and licenses.

“GMP Plans and Specifications” means the plans and specifications provided pursuant to Section 3.9 upon which the Guaranteed Maximum Price Proposal is based.

“Guaranteed Maximum Price” or “GMP” means the sum of the maximum cost for the construction of this Project, including but not limited to, the CM@Risk’s construction fee, general conditions fee, taxes, bonds, insurance costs, and any contingency as proposed and approved pursuant to Section 3.9.

“Legal Requirements” means all applicable federal, state and local laws, codes, ordinances, rules, regulations, orders and decrees of any government or quasi-governmental entity having jurisdiction over the Project or Site, the practices involved in the Project or Site, or any Work.

“Notice to Proceed” is a written notice given by the CITY to the CM@Risk fixing the date on which the CM@Risk will start to perform the CM@Risk’s obligations under the

Pre-Construction Services Agreement.

“Payment Request” means the form that is accepted by the CITY and used by the

CM@Risk in requesting progress payments or final payment and which will include such supporting documentation as is required by the Contract Documents and or the CITY.

“Pre-Construction Services” means advice given during the design phase. Pre-construction services shall be contracted for between the CITY and the CM@Risk, as required by A.R.S. §34-603(E)(1). Services may include the following: design review, project scheduling, constructability reviews, alternate systems evaluation, cost estimates, GMP preparation, and subcontractor bid phase services.

“Product Data” means illustrations, schedules, performance charts, instructions, brochures, diagrams and other information furnished by the CM@Risk to illustrate materials or equipment for some portion of the work.

“Project Designer” means the Architect or Engineer of record responsible for the design and design service for a particular project. For this Contract, the Project Designer is

“Project Team” means the pre-construction phase services team consisting of the

Project Designer, CM@Risk, Contract Administrator, CITY’s representatives and other stakeholders who are responsible for making decisions regarding the Project.

“Schedule of Values (SOV)” means the Document specified in the construction phase, which divides the Contract Price into pay items, such that the sum of all pay items equals the Contract Price for the construction phase Work, or for any portion of the Work having a separate specified Contract Price. The SOV may or may not be output from the

Progress Schedule depending on whether the Progress Schedule is cost-loaded or not.

“Shop Drawings” means drawings, diagrams, schedules and other data specially prepared for the Work by the CM@Risk or a Subcontractor, Sub-subcontractor, manufacturer, supplier or distributor to illustrate some portion of the Work.

“Specifications” means the section(s) of the Contract Documents for the construction phase consisting of written technical descriptions of materials, equipment, construction systems, standards and workmanship as applied to the Work and certain administrative details applicable thereto.

“Subcontractor” means any person or entity retained by CM@Risk as an independent contractor to perform a portion of the Work and shall include material, men and suppliers. All subcontractors shall be selected in accordance with the Subcontractor selection plan set forth in Section 2.9 of this Agreement.

“Subconsultant” is the person, firm or corporation having an Agreement with the

CM@Risk to furnish services required as its independent professional associate or consultant with respect to the Project.

“Substantial Completion” means when the Work, or when an agreed upon portion of the Construction Work, is sufficiently complete so that the CITY can occupy and use the

Project or a portion thereof for its intended purposes. This may include, but is not limited to: (a) approval by CITY Fire Marshall and local authorities (Certificate of Occupancy);

(b) issuance of elevator permit; (c) demonstration to the CITY that all systems in place, functional, and displayed to the CITY or its representative; (d) installation of all materials and equipment; (e) CITY review and acceptance of all systems; (f) CITY review and acceptance of draft O&M manuals and record documents; (g) CITY operation and maintenance training completed; (h) HVAC test and balance completed [provide minimum 30 days prior to projected substantial completion]; (i) completed landscaping and site work; and (j) final cleaning.

“Supplier” means a manufacturer, fabricator, supplier, distributor, materialmen or vendor having a direct contract with CM@Risk or with any Subcontractor to furnish materials or equipment to be incorporated in the construction phase Work by CM@Risk or any Subcontractor.

“Total Float” Number of Days by which the pre-construction phase services or construction phase Work or any part of the same may be delayed without necessarily extending a pertinent schedule milestone in the Project Schedule.

“Work” for this contract means the entire completed pre-construction construction services.

ARTICLE 2 - PROJECT TEAM - CM@RISK KEY PERSONNEL

The CM@Risk will be an integral member of the Project Team, as defined herein, consisting of CM@Risk, representatives from the CITY, the Project Designer, and other consultants, as required.

2.1 Key Personnel

Prior to the start of these Contract Services, the CM@Risk shall submit to the CITY for approval detailed résumés of key personnel, including any Sub consultants, that will be involved in performing the services described in this Agreement to be provided by

CM@Risk. Unless otherwise informed, the CITY hereby acknowledges its acceptance of personnel to perform such services under this Agreement.

2.2 Prior Approval for Change

At any time hereafter that the CM@Risk desires to change key personnel while performing under this Contract, the CM@Risk shall submit the qualifications of the proposed substituted personnel to the CITY for prior approval.

2.3 Key Personnel Listed

Key personnel shall include,…