RFP BPAA 2027000076 1
Issued by
Boulder County, Aurora City, Colorado

About this file

This is a Request for Proposals (RFP) issued by the Colorado Department of Agriculture on behalf of the Pesticide Disposal and Recycling Program Enterprise Board for pesticide disposal services. The solicitation seeks an experienced contractor to establish and implement a new statewide pesticide disposal program designed to provide safe, accessible disposal options for commercial and agricultural applicators. The contractor must conduct collection events to gather, sort, lab-pack, transport, and dispose of unused or unwanted pesticides while maintaining strict regulatory compliance and environmental protection standards. The RFP was published on November 17, 2026, with a deadline for written inquiries on December 1, 2026, at 10:00 a.m. Mountain Time, and proposals are due on January 5, 2027, at 9:00 a.m. via box.com submission. A virtual public bid opening is scheduled for January 5, 2027, from 10:00 a.m. to 11:00 a.m. Mountain Time. The contract is anticipated to begin on April 1, 2027, and end on December 31, 2027, with an option to renew for up to four additional one-year periods, not to exceed five years total. An Intent to Award is estimated to be published on January 31, 2027.

The initial budget for the first year is $75,000.00, based on pesticide registration fees, with the offeror responsible for submitting cost proposals including pricing per pound for disposal of liquid and dry pesticide formulations, estimated at zero to 30,000 pounds. The pricing must be all-inclusive for handling, packaging, treatment, and disposal of accepted waste pesticides. This procurement is exempt from the Colorado Procurement Code and does not contain any stated set-asides. The contractor must demonstrate a minimum of ten years' experience in pesticide disposal programs with local, state, or federal agencies, including at least five collection events, and must provide three references from pesticide disposal programs conducted within the last five years. Key personnel requirements include a degreed chemist or Certified Hazardous Materials Manager as site/project manager, field technicians with current 40-hour HAZWOPER certifications, drivers with Commercial Driver's Licenses and Hazardous Materials endorsements, and regulatory staff knowledgeable in RCRA compliance. The contractor must possess all required State of Colorado and federal handling permits (EPA, DOT, RCRA) and maintain zero significant safety incidents or environmental violations.

View the file

Other files

File Type Posted
Appendix B Personal-Services-Contract.docx DOCX document
Offeror Response Signature Page PDF.pdf PDF
Appendix A Administrative Info.pdf PDF
Offeror Response Signature Page MS Word.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Proposals

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

RFP,BPAA,2027-0076

Pesticides Disposal Services

Publish Date: 11/17/2026

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO

PROCUREMENT CODE

(§ 24-101-101, et seq., through 24-12-101, C.R.S.)

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24-

RFP Summary Sheet

The information found in this summary sheet is for reference purposes only. Vendors or other interested parties are cautioned to review the solicitation, including any later amendments, in its entirety and contact the listed Point of Contact with any questions.

1. Point of Contact: Kathy Chang, kathy.chang@state.co.us

2. Important Dates (Estimated):

A. Publication Date: 11/17/2026

B. Deadline for Questions: 12/1/2026 at 10:00 am

C. Proposal Submission Deadline: 1/5/2027 at 9:00 am

3. Overview and Goals:

A. THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-

101-101, et seq., through 24-12-101, C.R.S.)

B. The Colorado Department of Agriculture’s Pesticide Disposal Enterprise Board (the

Board) seeks a collaborative, experienced partner to help establish and implement a new, highly effective Pesticide Disposal Program. By leveraging a contractor's proven expertise in hazardous waste management and their understanding of

Colorado's unique agricultural and commercial applicator pesticide disposal needs.

While specific collection targets will evolve as the program grows, the overall goals include creating a safe and accessible disposal network for commercial and agricultural producers, maximizing safe chemical removal across the state, and supporting the Department's broader mission to protect Colorado's environment and public health.

C. Budget: The total annual budgeted amount will be based on pesticide registration fees placed on eligible pesticide products, with a projected $75,000.00 annual budget for the first year’s disposal event(s). Offerors' cost proposal should reflect services based on this amount, with the option to increase the number of events and/or services as funding allows.

mailto:kathy.chang@state.co.us

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

4. Offeror’s Experience, Qualifications and Personnel and Contract Requirements:

A. Additional Information found in Section 2 and 3.

5. Requested Proposal Format: Additional Information found in Section 5.

6. Proposal Submission Instructions: Section 2.I. of Appendix A

A. For this solicitation, proposals will be accepted using an online submission application. Hard copy and email submissions will not be accepted. Responses must be submitted through box.com.

https://colorado.app.box.com/f/e711eb762b8a4bb5a4017c4100cf95f9.

i. Offerors should submit one zip folder that contains all required proposal submission documents. Individual attachments are acceptable if they are clearly labeled.

ii. The zip folder or document must be titled with the RFP Number and the

Offeror’s name, such as: RFP,BPAA,2027-0076 ABC Corporation.

iii. Please do not encrypt your zip folder. Additional encryption may result in failure to upload or review the proposal.

iv. The solicitation submission application typically uploads proposals within five minutes. Offerors are advised to submit proposals no later than one business day prior to the solicitation deadline to ensure the proposal has been received.

v. The application does not send email confirmations if the proposal was uploaded correctly. Please email the Point of Contact for confirmation of submission.

B. Ensure all requested attachments are included.

C. Responses received after the submission deadline shall not be opened and may be rejected as a late response, unless otherwise permitted by the procurement official.

http://box.com/ https://colorado.app.box.com/f/e711eb762b8a4bb5a4017c4100cf95f9

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

D. The solicitation submission application is only for proposal submission. All inquiries, questions, comments, or concerns should be submitted to the

Procurement Contact via email and not through the solicitation submission application.

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

Offeror Response Signature Page RFP,BPAA,2027-0076 Colorado Pesticide Disposal Services

Offerors responding to this solicitation must fill out this page in its entirety, sign and return with Offeror’s response. This page must bear a physical or electronic signature, as electronic signature is defined in the "Uniform Electronic Transactions Act", section 24-71.3-102 (8), C.R.S., evincing an intent by the Offeror to be bound by its response. Failure to do so may disqualify the Offeror’s response.

The undersigned understands and agrees that misrepresentation made in this response and/or subsequent discussions or information presented to the State may be deemed sufficient cause for the refusal by the State to execute a contract as a result, and that that later discovery of any omission or misrepresentation made in the solicitation response and/or subsequent discussions or information presented to the State may be grounds for the cancellation of an existing contract.

LEGAL COMPANY NAME (OFFEROR)

OFFEROR INSERT: Full Legal Company Name

AUTHORIZED SIGNATURE

By: Name of Person Signing for Contractor

TYPED/PRINTED NAME

OFFEROR INSERT: Signer’s Full Name

TITLE

OFFEROR INSERT: Title of Signer

PHONE NUMBER

OFFEROR INSERT: Signer’s Phone Number

EMAIL ADDRESS

OFFEROR INSERT: Signer’s Email Address

CONTACT FOR CLARIFICATIONS

OFFEROR INSERT: Name of Contact

TITLE

OFFEROR INSERT: Title of Contact

PHONE NUMBER

OFFEROR INSERT: Phone Number of Contact

EMAIL ADDRESS

OFFEROR INSERT: Email Address of Contact

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

1. INTRODUCTION

A. Exempt from Procurement Code

This Request for Proposals (RFP) is administered by the Colorado Department of

Agriculture (CDA or State), on behalf of the Pesticide Disposal and Recycling

Program Enterprise Board (Board), for pesticide disposal services to support the

Board. The Board is created pursuant to 35-10.5-103(1), C.R.S., and is exempt from the Colorado Procurement Code as set forth at 24-101-105(1)(a)(V), C.R.S. As such, this request for proposals is EXEMPT from the Procurement Code and may not necessarily conform to the usual requirements of the code. Any references to the

Procurement Code or its sections that may be found in this solicitation are for illustrative purposes only and not binding upon the State or the Board. This RFP will differ in certain and stated ways and may not, and is not, required to explicitly spell out any differences from the requirements of R-24-103-203 (1 CCR 101-9).

B. Background

Historically, the Colorado Department of Agriculture has never had a formal pesticide disposal program, a void that has historically left agricultural and commercial applicators without a convenient or economical solution to safely dispose of unused or unwanted pesticides. The newly established Pesticide Disposal

Program is designed to bridge this critical gap by providing an accessible, practical, and cost-effective disposal mechanism.

C. Overview and Goals

By partnering with an experienced contractor to help build and implement this initiative from the ground up, the Department’s overall goals are to establish a successful and user-friendly system, ensure the safe and efficient removal of hazardous chemicals statewide, and protect Colorado's agricultural lands, communities, and environment.

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

The Department aims to achieve the following objectives:

● Prevent the contamination of soil, groundwater, and surface water by keeping unused pesticides out of landfills, local waterways, or illegal dump sites.

● Reduce the risk of accidental exposure or poisoning for agricultural workers, commercial applicators, and local communities by eliminating the need for storage of unused pesticides.

● Reduce the financial and logistical barriers to pesticide disposal for producers by offering a convenient, low-cost, or free mechanism for hazardous waste disposal.

● Educate applicators on proper inventory management, safe storage protocols, and smart purchasing to minimize the future accumulation of unusable pesticides.

● Monitor and report on the volume, type, and geographic origin of collected chemicals to evaluate program efficacy, identify regional needs, and guide future resource allocation.

The Offeror is expected to express their commitment to achieving:

● Execute all handling, packaging, transportation, and disposal activities with a strict commitment to zero spills, accidents, or regulatory violations, thereby protecting public safety and shielding the state from environmental liability.

● Design and manage the logistics of collection sites to minimize wait times, streamline the intake process, and provide a professional, user-friendly experience that encourages applicators to participate again in the future.

● Facilitate the legal, secure transport and final destruction of hazardous chemicals in strict accordance with state and federal environmental regulations.

● Commit to utilizing the most environmentally sound destruction and disposal methods available (such as secure, high-temperature incineration) to ensure legacy chemicals are permanently removed from the ecosystem.

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

● Provide 100% accurate, auditable, and timely reporting on chemical volumes, waste categories, and geographic participation to help the Board measure the new program's success.

● Act as a flexible, collaborative partner capable of scaling operations, adjusting logistics based on turnout, and resolving on-site challenges dynamically to guarantee the smooth implementation of the state's first formal disposal program.

D. Sole Point of Contact

i. The sole point of contact for this solicitation is Kathy Chang, Procurement

Director, who may be reached via email at kathy.chang@state.co.us.

ii. Email is the preferred method of communication. The individual listed above is the sole point of contact for this solicitation. Initiating contact with anyone other than this individual may result in Offeror disqualification.

E. Schedule of Activities

i. This Schedule of Activities is for information and planning purposes only.

Schedules for Activities listed as “Estimated” may be subject to change depending on the needs of the State. All times are considered in Mountain

Time (MT), as adjusted for daylight savings.

ii. The date of publication for this solicitation on Colorado VSS is 11/17/2026.

a. Written inquiries must be submitted to the Procurement Point of

Contact email no later than 10:00 am on 12/1/2026.

b. The estimated date for the State’s responses to vendors’ written inquiries to be published on Colorado VSS is 12/9/2026.

c. All proposals must be submitted via the unique box.com link no later than 9:00 am on 1/5/2027.

https://colorado.app.box.com/f/e711eb762b8a4bb5a4017c4100cf95f mailto:kathy.chang@state.co.us

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

d. A virtual public opening of the proposals will be held at:

Bid Opening: RFP,BPAA,2027-0076 Pesticides Disposal Services

Tuesday, January 5, 2027 · 10:00 – 11:00am

Time zone: America/Denver

Google Meet joining info

Video call link: https://meet.google.com/yvf-ijqs-gnr

Or dial: (US) +1 314-649-9739 PIN: 510 518 590#

More phone numbers: https://tel.meet/yvf-ijqs-gnr?pin=5084186051434

Attendance at this public bid opening is optional and does not impact any interested party's participation in the solicitation process.

e. The estimated date for the publication of an Intent to Award on

Colorado VSS is 1/31/2027.

F. Start Date

The desired Contract start date is 4/1/2027.

G. Anticipated Contract Term

i. The initial term of the awarded Contract is anticipated to begin on 4/1/2027 and end on 12/31/2027. This Contract may be renewed for up to 4 additional one-year periods at the sole discretion of the Board. The total duration of the

Contract, including all options, is not anticipated to exceed five (5) years.

ii. The Board may, within its sole discretion, choose not to exercise any option or extension term in the Contract for any reason. If the Board chooses not to exercise any option or extension term, it may re-procure the goods and/or services in its sole discretion.

https://meet.google.com/yvf-ijqs-gnr https://tel.meet/yvf-ijqs-gnr?pin=5084186051434

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

2. CONTRACT REQUIREMENTS

Offeror must acknowledge and agree to the below requirements:

A. Insurance Requirements: The awarded Contractor will be required to submit certificate(s) of insurance evidencing insurance coverage for, at minimum, the types and amounts of insurance as required by in the State’s Contract Template, included in this solicitation as an attachment, prior to execution of the Contract. Offerors do not need to submit this document unless they are awarded this solicitation.

B. Offeror must be in good standing. A Certificate of Good standing is required prior to contract execution. Offerors do not need to submit this document unless they are awarded this solicitation.

C. Offeror must agree to execute the contract quickly, preferably within 30 calendar days after award. A copy of the contract template is provided as Appendix

B. Preference shall be made to Offerors who agree to the State’s contract template as-is.

3. OFFEROR’S EXPERIENCE, QUALIFICATIONS AND PERSONNEL

The ideal Contractor possesses the following experience, qualifications and personnel.

A. Organizational Experience, Qualifications, and Personnel

i. Experience: The Offeror must demonstrate a proven, multi-year corporate track record specifically focused on the identification, on-site sorting, lab-packing, transportation, and final destruction of unused pesticides. Offeror must have a minimum of ten (10) years’ experience conducting pesticide disposal programs with local, state, or federal agencies, including at least five (5) one- or two-day collection events.

ii. References: Minimum of three (3) references from pesticide disposal programs conducted within the last five (5) years with local, state, or federal agencies. Offerors must demonstrate success in overseeing high-volume, multi-location collection drives, including managing site logistics, participant traffic flow, and agency coordination. Proposals must contain the primary contact's full name, professional title, email address, telephone number, and

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

a brief overview of the project. The State reserves the right to verify all submitted references.

iii. The Offeror must possess all necessary State of Colorado and federal handling permits (EPA, DOT, RCRA) and demonstrate a documented history of strict regulatory compliance, with zero significant safety incidents, spills, or environmental violations.

B. Key Qualifications & Personnel:

i. On-Site Leadership & Chemists: The on-site team must be anchored by a dedicated, seasoned Site/Project Manager or Field Supervisor who is a degreed chemist or a Certified Hazardous Materials Manager (CHMM) with hands-on experience in accurately identifying, categorizing, and safely lab-packing pesticides. This leader oversees large-scale, turnkey collection events, manages traffic flow and site security, ensures PPE/safety compliance, conducts real-time risk assessments, and maintains chain-of-custody documentation from intake to final disposal.

ii. Field Technicians & Containment Personnel: All field technicians and handling personnel must hold current 40-hour HAZWOPER certifications and up-to-date training in emergency spill response, decontamination protocols, and PPE usage (meeting OSHA requirements under 49 CFR 172.704/172.602 and 29 CFR 1910.120/1910.1200). Dedicated personnel with advanced training in emergency containment and remediation must be designated to handle and neutralize degraded, rusted, or leaking containers on-site.

iii. Transport Personnel: Drivers must possess active Commercial Driver's

Licenses (CDL) with Hazardous Materials (Hazmat) endorsements and a minimum of two (2) years of experience under DOT regulations for hauling hazardous waste.

iv. Regulatory & Intake Staff: Back-office or on-site RCRA experts must ensure strict compliance with waste manifests, Land Disposal Restrictions (LDRs), and Certificates of Destruction. Intake and greeting staff should ideally

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

include personnel with agricultural backgrounds to build trust with producers

(bilingual staff is an added benefit).

v. Permits & Certifications: The Offeror must possess all required State of

Colorado and federal handling permits (EPA, DOT, RCRA), demonstrate a documented history of strict regulatory compliance with zero significant safety incidents or environmental violations, and provide defensible documentation (manifests, Certificates of Destruction, post-event metrics).

Offerors with ISO 9000 or 14000 series certification will be given preference.

4. SCOPE OF WORK AND DELIVERABLES

Services offered by the Offeror must align with the tasks outlined in the Scope of Work and

Deliverables and adhere to all solicitation requirements. Any deviations must be explicitly detailed in the proposal and fulfill equivalent standards.

A. Project Overview

The awarded Contractor shall safely collect, properly package, transport, and dispose of registered, unused pesticides from commercial and private applicators. The baseline requirement is to conduct a one-day pesticide disposal event, with the possibility of expanding to a multi-day event based on pesticide disposal registration volumes and mutual agreement between the Contractor and the State. The awarded Contractor will serve as a turn-key provider, operating as the legal generator of all collected wastes and supplying all necessary personnel, equipment, and documentation.

B. Pre-Event Planning & Documentation

a. Immediately following the contract award and Post-Award meeting, or 30 days prior to a scheduled disposal event, the awarded Contractor must submit:

i. Health and Safety Plan: A site-specific plan consistent with EPA Orders, including EPA Order 1440.3 and Section 104(f) of the Comprehensive

Environmental Response, Compensation and Liability Act of 1986, and any other amendments that may occur during the term of this contract, as well as any other applicable federal and state laws and regulations, THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

and the "Occupational Safety and Health Publication No. 85-115," which is incorporated herein by reference for all purposes, and OSHA standards. Must include documentation of at least two (2) previous site-specific plans developed for similar events.

ii. QA/QC Plan: A site-specific Quality Assurance/Quality Control Plan for

State approval.

iii. Insurance: Certificate of Insurance including an MCS-90 endorsement

(demonstrating financial responsibility and pollution coverage for toxic-material clean-ups).

iv. Licensing: Copies of all required licenses, permits, and EPA identification numbers authorizing hazardous waste operations.

b. Prior to the scheduled events, the awarded Contractor must meet with Board staff for Board staff to provide guidance on necessary pesticide disposal event data the Board needs to collect.

c. After the event, the awarded Contractor shall provide the Department with a list of any pesticides, quantities, containers, or other materials the contractor is unable to accept.

C. Equipment & Site Preparation

a. The awarded Contractor shall provide all necessary equipment, scalable to event size. Any changes or variances in the necessary equipment must be noted in your proposal. This includes but not limited to:

i. All equipment necessary to properly unload, handle, weigh, identify, properly package, label, and transport all collected pesticides.

ii. The awarded Contractor must be able to provide all personal protective equipment required by local, state and federal regulations for hazardous waste operations and the site or project manager to assure its proper use.

iii. The required amounts of the necessary equipment shall be increased or decreased prior to collection events based on sign up numbers and agreed to by the site/project manager.

b. Necessary equipment should at a minimum include the following items listed

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

but not be limited to:

i. Heavy Equipment & Logistics

1. Warehouse Forklift: One (1) 5,000 lb. capacity warehouse-type forklift.

2. Trash Dumpsters: Twenty (20) to forty (40) yard bin or roll-off trash dumpsters.

3. Portable Toilet: One (1) unit, required if existing restroom facilities are unavailable on-site.

ii. Weighing Equipment

1. Portable Platform Scale: One (1) 4' x 4' platform scale, which must be calibrated and sealed by proper authorities within thirty

(30) days prior to the collection event.

ii. Site Protection

1. Exterior Protection: A minimum of 5,000 square feet of 60-millimeter (60mm) high-density polyethylene (HDPE) sheeting to completely cover all exterior unloading surfaces.

2. Interior Protection: If buildings are used, 6-millimeter (6mm) poly sheeting must cover all interior floors and walls up to a height of 12 feet.

ii. Traffic & Security

1. Traffic Cones: Fifty (50) standard traffic cones.

2. Event Signage: Four (4) 3' x 3' signs explicitly designating

"Commercial and Agricultural Pesticides Collection only" or similar.

3. Site Security: Dedicated site security personnel, which may be deleted by the Board for an individual collection if the location is already securely fenced or determined to be unnecessary.

ii. Safety, Operations & Waste Handling

1. Operational Equipment: All equipment necessary to properly unload, handle, weigh, identify unknown or partially identified

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

wastes, properly package, label, and transport all collected wastes.

2. Safety & PPE: All required personal protective equipment (PPE) and spill control materials necessary to safely manage and recover any unplanned release of wastes.

iii. Adjustments & Scaling

1. Dynamic Quantities: Required amounts of necessary equipment will be increased or decreased prior to collection events based on registration sign-up numbers, as agreed to by the site/project manager.

2. Changes to Agreement: Any modifications to the necessary equipment must strictly comply with the general conditions of the contract agreement.

D. Event Operations & Waste Handling

During the disposal event, the awarded Contractor must:

a. Weighing & Inventory: Establish tare weights for all drums/packing materials prior to the event to accurately determine net waste weights. Maintain a detailed inventory of all lab packs and bulk packs.

b. Identification & Segregation: Classify, segregate by compatibility, and conduct on-site testing to identify pesticides to be disposed of per 40 CFR 262.11.

c. Packaging: Transfer, package, and properly label small and leaking/damaged containers into DOT-approved shipping containers (lab packing).

d. Nonconforming Waste Policy: Refuse nonconforming items (explosives, unapproved pesticides, any pesticides contractor is unable to accept). If explosives are brought, secure the area, hold the participant, and notify regulating authorities. Acceptable nonconforming waste accepted by accident will be handled at the deliverer's expense.

E. Environmental Sampling

a. To establish baseline and impact data, the awarded Contractor shall conduct site testing utilizing ASTM Standards and EPA Methods (EPA 8081):

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

b. Take a total of 2 pre-collection samples and 2 post-collection samples (2 of each at each event site).

c. Utilize 0-6 composite sampling for soil.

d. Submit copies of all analytical reports to the State within fourteen (14) days following the final collection event.

F. Transportation, Disposal, and Post-Event Reporting

The awarded Contractor assumes full legal liability for the disposal process and must provide the following:

a. Legal Generator Status: The awarded Contractor shall act as the sole legal generator of all wastes, signing Block 3 and Block 16 (Generator Certification) of the Uniform Hazardous Waste Manifest. This responsibility cannot be subcontracted.

b. Transportation & Disposal: Load and transport all waste in DOT-compliant vehicles directly to an EPA-approved Treatment, Storage, or Disposal Facility

(TSDF) free of pending enforcement actions. Wastes must be incinerated, recycled, or (if incineration is unauthorized) disposed of in a permanent hazardous waste landfill.

c. Final Documentation: Within forty-five (45) days of final disposal or recycling, provide the State with legibly completed inventory reports, signed manifests, and written confirmation (Certificates of Destruction/Recycling) verifying the date, location, and method of final disposal.

5. REQUESTED PROPOSAL FORMAT

Proposals should cover the following areas, with an emphasis on how these areas relate to the evaluation criteria listed in this Request for Proposals. In the proposal response, please ensure the corresponding section is explicitly identified.

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

A. Contract Requirements: Offeror shall acknowledge and confirm that they meet the requirements in this section.

B. Technical/Business Proposal

i. OFFEROR’S EXPERIENCE, QUALIFICATIONS AND PERSONNEL: Offeror shall describe how they meet or exceed the Offeror’s experience, qualifications and personnel as detailed in this section. In addition to the section, please further elaborate on the following:

a. Disposal event coordination and administration. Describe Offeror’s experience with similar projects. Disposal capabilities and limitations should be provided.

b. One dedicated account representative that will serve as the main point of contact for the organization

c. Additional account representatives as needed for disposal events.

d. On site support for the duration of the disposal event. This may include management of the site and disposal event traffic flow.

ii. SCOPE OF WORK AND DELIVERABLES: Offeror shall describe how they will accomplish the Scope of Work detailed in this solicitation.

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

C. Cost Proposal/ Pricing

The cost proposal should be quoted for the first year of implementation of the

Pesticide Disposal Program. One event is planned to be held in the latter half of

2027 with an estimated event budget of $75,000.00, subject to revenues received in the 2027 registration year.

i. Offeror shall include a description of required equipment and services, personnel hourly rates as applicable, cost per collection event and price per pound for disposal of the various types of pesticides listed below for both liquid and dry formulations (see cost tables examples below). The costs should align with how Offeror will accomplish the Scope of Work detailed in this solicitation.

ii. Pricing for future years (Years 2 - 5) are to be included as estimates and based on a per event estimate. Offeror will present a budget for disposal events yearly for final approval by the Enterprise Board.

iii. Proposed pricing must remain firm during the initial term of the Contract.

iv. Pricing must include any fees associated with the delivery of the goods or services, including, but not limited to, shipping and installation if applicable.

v. Responses will be evaluated for price based on the following criteria, including but not limited to:

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24-

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

Please submit the price per pound for disposal of the various types of pesticides listed below for both liquid and dry formulations. Pricing calculations to be based upon 0 pounds to an estimated 30,000 pounds collected. The price shall be all-inclusive for proper handling, packaging (lab packs), treatment and disposal of accepted waste pesticides.

6. EVALUATION METHODOLOGY

A. Evaluation Process

A comprehensive, thorough, complete and impartial evaluation of each proposal received will be conducted.

B. Evaluation Committee

i. An Evaluation Committee will be established utilizing measures to ensure the integrity of the evaluation process. These measures include the following:

a. Selecting committee members who do not have a conflict of interest regarding this solicitation.

b. Facilitating the independent review of proposals.

c. Ensuring the fair and impartial treatment of all Offerors.

ii. The objective of the Evaluation Committee is to conduct reviews of the proposals that have been submitted, to hold frank and detailed discussions among themselves, and to recommend an Offeror for award.

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

C. Proposal Evaluation Criteria

i. The Evaluation Committee will evaluate proposals to determine if each

Offeror meets all mandatory qualification requirements; provided, however, that the Board has the discretion to waive non-material mandatory requirements in certain circumstances.

ii. Proposals will be evaluated by the Evaluation Committee using the evaluation criteria listed below. The evaluators will consider whether the Scope of Work requirements in the solicitation have been addressed, and they will review the capabilities of the Offeror, as well as the quality of the approach proposed, the price, and any other aspect determined relevant to the evaluation criteria.

iii. The evaluation criteria to be used in evaluating the proposals are as follows

(and are listed in no particular order):

a. Contract Requirements

b. Technical/Business Proposal

(a) OFFEROR’S EXPERIENCE, QUALIFICATIONS AND PERSONNEL

(b) SCOPE OF WORK AND DELIVERABLES

c. Cost Proposal/ Pricing

iv. Upon concluding the review, the Evaluation Committee shall submit its findings to the Commissioners’ Governance Committee for its review, consideration, and recommendation to the Board.

v. The Board is the final decision-maker.

D. Single proposal

If only one bid or proposal is received in response to a solicitation, consideration for an award may be made to the single bidder or offeror if approved by the

Board.

E. Award

i. A Notice of Intent to Award will be published on Colorado VSS.

THIS PROCUREMENT IS EXEMPT FROM THE COLORADO PROCUREMENT CODE (§ 24-101-101, et seq., through 24- 12-101, C.R.S.)

ii. The Board is the final decision-maker for the award.

iii. The Board reserves the right to award to multiple offerors.

File details come from the government source that posted it. Updated .