Addendum #01 for RFP #938000-01 was issued by the Iowa Department of Administrative Services (DAS) for the DAS AGS Cabin Roof Replacement project located at 74 Monument Dr. in Arnolds Park, Iowa. The addendum provides clarification and additional details for prospective design firms, including a pre-proposal meeting summary and responses to contractor questions. The project scope includes replacement of the wood shingle roof, repairs to daubing and chinking between logs, replacement of glazing putty on windows, recommendations for log repairs/replacements, evaluation of the stone foundation and water management, and coordination with the State Historical Preservation Office (SHPO). Key dates include questions due by 3/5/2024, proposals due by 3/12/2024, design kickoff in the week of 3/25/2024, contractor bidding in July 2024, and project closeout in October 2024.
The budget will be based on the designers' recommendations, with Major Maintenance covering project costs. DAS requires a project-specific Certificate of Insurance with a $2,000,000 Professional Liability policy and a $25,000 deductible. Proposers must submit a project-specific schedule, staff resumes, anticipated hours and rates, and a lump sum breakdown by schedule of values. The design professional is expected to provide recommendations for log repairs, foundation condition, and water management, which will be reviewed with SHPO. If approved, these recommendations may be added to the project through a change order. The project will be managed using Procore's online project management system, and a modified ConsensusDocs 803 Form of Agreement will be used.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project #9380.00 Addendum #01 Page 1 of 6
Addendum #01 for RFP #938000-01
Project Name: DAS AGS Cabin Roof Replacement
DAS RFB #: 938000-01
DAS Project #: 9380.00
Date: 03/11/2023
Addendum #1:
The original Project Manual and Drawings for the project noted above are amended as noted in this
Addendum. Included in this Addendum are Specification, Architectural, & Engineering items.
Please review all sheets and incorporate them into your set of Contract Documents.
The receipt of this Addendum shall be acknowledged by inserting its number and date in the space provided on the Bid Form.
This Addendum consists of:
General Items:
1. Questions Received from contractors (2 Pages)
2. Meeting Minutes: RFP Pre-Proposal Meeting held on 2/27/2024 (3 Page)
QUESTIONS & ANSWERS:
Q1. Please confirm that the 3 items to be evaluated (log repairs, drainage & foundation) are to include cost estimates?
A1. The design professional is to evaluate, make recommendations based on the coordination with SHPO, and provide a cost opinion on these items. Based on the recommendation and
SHPO's response, the State of Iowa will negotiate additional services for construction documents, bidding, and construction administration fees.
Q2. Is there an anticipated amount of time or number of meetings that are expected for coordinating with the SHPO?
A2. The design professional is to provide a breakdown of hours/fee and anticipated meetings with SHPO for coordination of scope work on their proposal.
Q3. For the wood shingles on the roof, it appears there may have been different shake roofing in the past. Is it expected or required to match the double stacked shingles that are on the roof now? Are they accurate for the period of historic significance?
A3. The design professional is to include the replacement of shakes to match the existing. The item is to be reviewed with SHPO.
Project #9380.00 Addendum #01 Page 2 of 6
Q4. The report recommendations mentioned updates to the electrical or security systems. Will there be any updates to those systems included as a part of this project scope?
A4. No, do not include this in the project's scope.
Q5. Are there any anticipated repairs or work scope to be included for the log rafters supporting the roof?
A5. The work is currently not in the scope of work. If the design professional sees any deterioration or concerns with items outside the scope of work, please notify the Construction
Manager and Owner.
State of Iowa - Department of Administrative Services 109 SE 13th St.
Des Moines, Iowa 50319 P: (515) 281-7260
Project: 9380.00 DAS AGS Cabin Roof Replacement 74 Monument Dr.
Arnolds Park, Iowa 51331 P: (712) 336-6352
RFP Pre-Proposal Minutes: Meeting #1
Meeting Date Feb 27, 2024 Meeting Time 11:00 AM - 12:00 PM Central Time (US & Canada)
Meeting Location Virtual Video Conferencing Link https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDhlZGY2MDAtOWFlYS00Mz g3LWFiYzQtZTAwZWZjM2NlYjc3%40thread.v2/0?c ontext=%7b%22Tid%22%3a%22705e7dc3-c582- 4519-a026- 3a1c9fd5fc88%22%2c%22Oid%22%3a%22c10595 4f-766c-49c6-8c77-6c5b7e17bacc%22%7d
Overview Meeting to allow prospective design firms to visit the project site, when possible, and learn more about the scope.
Notes
Attachments
Scheduled Attendees
Name Company Phone Number Email Attendance
Jarrad Boever Boyd Jones Construction Company jboever@boydjones.biz Present
Andrew Paleczny Boyd Jones Construction Company P: (402) 553-1804 apaleczny@boydjones.biz Absent
Michael Plummer Department of Cultural Affairs P: (515) 281-4221 michael.plummer@iowa.gov Present
James Trower State of Iowa - Department of Administrative Services james.trower@iowa.gov Present
Introduction
No. Mtg Origin Title Assignment Due Date Priority Status
1.1 1 Introductions Open
Description DAS - Owner Representative
• James Trower
Boyd Jones - Construction Manager
• Andrew Paleczny (Project Manager)
• Jarrad Boever (Project Engineer)
Abbie Gardner Cabin
• Michael Plummer (Historic Site Manager
• Lee Sorenson (Site Contact)
Official Documented Meeting Minutes Also in attendance:
• Edward Matt - Genesis Architectural Design - edleom22@gmail.com
• Scotney Fenton - RDG - sfenton@rdgusa.com
State of Iowa - Department of Administrative Services Page 1 of 3 Printed On: Mar 11, 2024 01:26 PM CDT https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDhlZGY2MDAtOWFlYS00Mzg3LWFiYzQtZTAwZWZjM2NlYjc3%40thread.v2/0?context=%7b%22Tid%22%3a%22705e7dc3-c582-4519-a026-3a1c9fd5fc88%22%2c%22Oid%22%3a%22c105954f-766c-49c6-8c77-6c5b7e17bacc%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDhlZGY2MDAtOWFlYS00Mzg3LWFiYzQtZTAwZWZjM2NlYjc3%40thread.v2/0?context=%7b%22Tid%22%3a%22705e7dc3-c582-4519-a026-3a1c9fd5fc88%22%2c%22Oid%22%3a%22c105954f-766c-49c6-8c77-6c5b7e17bacc%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDhlZGY2MDAtOWFlYS00Mzg3LWFiYzQtZTAwZWZjM2NlYjc3%40thread.v2/0?context=%7b%22Tid%22%3a%22705e7dc3-c582-4519-a026-3a1c9fd5fc88%22%2c%22Oid%22%3a%22c105954f-766c-49c6-8c77-6c5b7e17bacc%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDhlZGY2MDAtOWFlYS00Mzg3LWFiYzQtZTAwZWZjM2NlYjc3%40thread.v2/0?context=%7b%22Tid%22%3a%22705e7dc3-c582-4519-a026-3a1c9fd5fc88%22%2c%22Oid%22%3a%22c105954f-766c-49c6-8c77-6c5b7e17bacc%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDhlZGY2MDAtOWFlYS00Mzg3LWFiYzQtZTAwZWZjM2NlYjc3%40thread.v2/0?context=%7b%22Tid%22%3a%22705e7dc3-c582-4519-a026-3a1c9fd5fc88%22%2c%22Oid%22%3a%22c105954f-766c-49c6-8c77-6c5b7e17bacc%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDhlZGY2MDAtOWFlYS00Mzg3LWFiYzQtZTAwZWZjM2NlYjc3%40thread.v2/0?context=%7b%22Tid%22%3a%22705e7dc3-c582-4519-a026-3a1c9fd5fc88%22%2c%22Oid%22%3a%22c105954f-766c-49c6-8c77-6c5b7e17bacc%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDhlZGY2MDAtOWFlYS00Mzg3LWFiYzQtZTAwZWZjM2NlYjc3%40thread.v2/0?context=%7b%22Tid%22%3a%22705e7dc3-c582-4519-a026-3a1c9fd5fc88%22%2c%22Oid%22%3a%22c105954f-766c-49c6-8c77-6c5b7e17bacc%22%7d mailto:edleom22@gmail.com mailto:sfenton@rdgusa.com
Project Overview
2.1 1 Scope Review Open
Description
• At a minimum, design for construction for the following:
o Replacement of wood shingle roof.
o Make repairs to the daubing and chinking between the logs.
o Replacement glazing putty on windows.
o Make recommendations for log repair / replacement with new wood to match original species and visual characteristics.
o Evaluate and make recommendations for the condition of stone foundation.
o Evaluate and make recommendations for proper water management at base of exterior walls.
o Coordination with State Historical Preservation Office (SHPO) on proposed repairs and materials.
Official Documented Meeting Minutes Clarifications -
• Evaluate and make recommendations for proper water management at base of exterior walls. (This is to include the trough gutters)
Side Notes-
• Miriam Road will be getting redone this summer so we may need to find alternate routes.
2.2 1 Schedule Review Open
Description RFP-specific dates below
Questions Due to construction.procurement@iowa.gov: 3/5/2024 @ 4:00PM Addendum Issued:
Proposals Due: 3/12/2024 @ 2:00pm Selection of Designer/Issue NOI: Week of 12/18/2023 Execution of 803 Contract: Week of 3/25/2024 Tentative Design Kickoff Meeting: Week of 3/25/2024 50% CD: To be coordinated with DAS and CM 95% CD: To be coordinated with DAS and CM Contractor Bidding: July of 2024 Execution of Contractor's Contract(s): August 2024 Submittals, Procurement and Construction: August 2024 Closeout: October 2024
RFP Overview
3.1 1 RFP Requirements Review Open
Description
• All questions to be directed to construction.procurement@iowa.gov
• DAS uses Procore online project management system for all projects, at no cost to the designer.
• DAS uses a modified ConsensusDocs 803 Form of Agreement
Meeting #1 - RFP Pre-Proposal Project: 9380.00 DAS AGS Cabin Roof Replacement
State of Iowa - Department of Administrative Services Page 2 of 3 Printed On: Mar 11, 2024 01:26 PM CDT
• DAS requires a project-specific Certificate of Insurance and specifies a Professional Liability policy of $2,000,000 with a deductible of $25,000 o Must note in proposal if deductible is different and provide a letter of financial stability from bank o Must provide COI prior to contract execution
• Ensure the following items are included in the proposal:
o Project-specific schedule o Resumes for all technical staff that will be assigned to the project o Anticipated hours and rates for each person on the design team o Lump sum broken down by schedule of values
Conclusion
4.1 1 Designer Questions Open
Description Any questions?
Official Documented Meeting Minutes Q. What all do the designers need to do with the following notes?
1.3.5.4 Make recommendations for log repair / replacement with new wood to match original species and visual characteristics.
1.3.5.5 Evaluate and make recommendations for the condition of stone foundation.
1.3.5.6 Evaluate and make recommendations for proper water management at base of exterior walls.
A. DAS would like the designer to make recommendations on what they believe would be a proper fix for the above items. DAS will take these recommendations and work with SHPO to review the full extent of these recommendations. This scope is just asking for recommendations. If these items are approved by the team and SHPO then DAS will process a change order to the selected designers to have them added to the project.
Q. What is the budget for this project.
A. The budget will be based off of the designers recommendations. Major Maintenance will be covering the costs for this project.
Meeting #1 - RFP Pre-Proposal Project: 9380.00 DAS AGS Cabin Roof Replacement
These meeting minutes are believed to be an accurate reflection of those items discussed and the conclusions that were reached during the referenced meeting.
Please contact State of Iowa - Department of Administrative Services if there are any discrepancies or questions with the content of these minutes.
State of Iowa - Department of Administrative Services Page 3 of 3 Printed On: Mar 11, 2024 01:26 PM CDT
Project #9380.00 Addendum #01 Page 6 of 6
END OF ADDENDUM #1