RFP935300-01 - IMCC Electrical Service Upgrades - Addendum #2.pdf
PDF 176 KB Posted
- Attached to
- DOC IMCC Electrical Service Upgrades
- Solicitation number
- RFP935300-01
- Issued by
- Johnson County, Iowa
About this file
This document is an Addendum to a Request for Proposal (RFP) issued by the State of Iowa Department of Administrative Services (DAS) for professional design services for electrical service upgrades at the Iowa Medical Classification Center (IMCC) in Coralville, Iowa. The Addendum modifies the original RFP dated December 4, 2023, by clarifying that IMCC staff will assist the design team to open junction boxes and panels during the schematic design phase, rather than the awarded consultant needing to hire an electrician. The proposal due date remains unchanged.
The pricing terms, set asides, incumbent details, funding requirements, and other financial information are not specified in this Addendum. However, the Addendum indicates that the RFP is for the DOC IMCC Electrical Service Upgrades project, which involves professional design services for electrical service upgrades at the IMCC facility in Coralville, Iowa.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #2
Project Name:
DOC IMCC Electrical Service Upgrades
DAS#9353.00
RFP935300-01
Addendum #2
Dated: January 2, 2024
This Addendum forms a part of the Request For Proposal documents. This Addendum supersedes and supplements all portions of the original Request For Proposal dated December 04, 2023 with which it conflicts.
ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE REQUEST FOR PROPOSAL. FAILURE TO
DO SO MAY SUBJECT TO DISQUALIFICATION.
1. Proposal Schedule – Proposal due date does not change.
2. Questions:
a. Q. Based on the scope of work to add more capacity and Service/refurbish/repair/replace existing equipment, it would seem appropriate to have an electrician onsite to open junction boxes and panels to better understand existing conditions during the Schematic design. Will the awarded consultant need to hire an electrician for this scope of work? A. No, IMCC Staff will assist the design team to open the junction boxes and panels.
Attachments: NONE
END OF ADDENDUM