This document is an Addendum to a Request for Proposal (RFP) issued by the State of Iowa Department of Administrative Services (DAS) for professional design services related to electrical service upgrades at the Iowa Medical Classification Center (IMCC) in Coralville, Iowa. The RFP seeks a design firm to provide schematic design services to develop the construction budget and scope of work for the $2,800,000 electrical service upgrade project. The addendum extends the deadline for RFP questions to December 28, 2023, maintains the January 9, 2024 proposal due date, and provides a detailed design schedule with milestones such as schematic design kickoff in January 2024 and 100% schematic design review in March 2024. The addendum also addresses several technical questions related to the project, including requirements for an arc flash study, existing electrical infrastructure, and potential design approach options.
The project budget of $2,800,000 can be spent over multiple fiscal years, with the goal of completing the bulk of the work by June 2025. The project priorities are to add new electrical capacity, service/refurbish/replace existing equipment, and conduct an arc flash study. The selected design firm will provide all future design services for the electrical upgrades, with the remaining scope to be negotiated as funding allows.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #1
Project Name:
DOC IMCC Electrical Service Upgrades
DAS#9353.00
RFP935300-01
Addendum #1
Dated: December 20, 2023
This Addendum forms a part of the Request For Proposal documents. This Addendum supersedes and supplements all portions of the original Request For Proposal dated December 04, 2023 with which it conflicts.
ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE REQUEST FOR PROPOSAL. FAILURE TO
DO SO MAY SUBJECT TO DISQUALIFICATION.
1. RFP Questions, requests for clarification: Extended to 12/28/2023 by 2:00 pm.
2. Proposal Schedule – Proposal due date does not change.
3. Schematic Design Schedule:
Execution of Designer’s Contract Week of January 15, 2024
Tentative Schematic Design Kick-Off Meeting Week of January 22, 2024
50% Schematic Design and Cost Opinion By TBD
100% Schematic Design and Cost Opinion By March 21, 2024
100% Schematic Review Week of March 25, 2024
4. Questions:
a. Q. Short circuit, current coordination and arc flash studies are very intensive and require a lot of field documentation and verification. To develop the fee for the study extensive field surveying is required. Are we to provide the fee for the study at the schematic stage?
A. Yes, a budget estimate for the arc flash study should be included in the cost estimates developed during schematic design.
b. Q. Will the entire capital appropriation of 2,800,000.00 need to be completed in a fiscal year or can it be broken up into years and phases? A. The $2,800,000 can be spent over several fiscal years. The funding will revert on June 30, 2026, but the goal would be to have the bulk of the work done by June 30, 2025, to the extent feasible.
c. Q. Is there any known grounding issues or lack of grounding conductors with branch circuits? A.
Most of grounding in the facility uses raceway for grounding conductors (no ground wire in raceways). The Branch wiring uses a lot of 3 phase to one grounded conductor (White) (Gray).
d. Q. Are the items in Exhibit A listed in order of importance? A. Exhibit A is not ranked or prioritized in any certain order. The actual scope of work may be more or less than the items included in Exhibit A, depending on decisions made in schematic design. The overall priorities for the project are to:
1. Add new capacity.
2. Service/refurbish/repair/replace existing equipment.
3. Conduct an arc flash study.
e. Q. Is the entire facility included in the scope? A. The entire facility should be reviewed, but it is expected that the most work would be in the older buildings, such as the Main Building, the North
Building, R/S and East/West.
f. Q. Is it possible to change some of the dates in the design schedule? A. Yes, but changes must be proposed in a question to construction.procurement@iowa.gov before 2:00 on 12/28/23.
g. Q. Is $2,800,000 the construction budget or the project budget? A. That is the project budget, including design, construction management and other soft costs.
h. Q. Would it be acceptable to replace some of the existing panels with larger panels, rather than to add new panels? A. That may be acceptable, it would need to be discussed during design. The goal is to reduce the nuisance tripping experienced now and provide room for future growth. The facility would prefer to avoid / limit shutdowns to the greatest extent possible, which may affect this decision.
i. Q. Does the facility have an existing arc flash study or updated as-builts of all buildings? A. No, there has never been an arc flash study done. There are PDF original drawings of the buildings, but they have not been updated over the years.
j. Q. Does the facility want to start with the arc flash study and use those results to determine the scope of the project? A. No, see the priorities above. The facility would like to do an arc flash study to the extent possible with remaining funds once the other priorities have been addressed, realizing that the study may uncover additional changes that need to be made. The arc flash study should be included as a budgeting item during schematic design and may be negotiated as an additional service with the successful proposer.
k. Q. Will there be a need for architectural services? A. Possibly, but that would be negotiated as a future design service with the successful proposer. The proposed architectural staff members should be included in this proposal.
l. Q. What ceiling types exist in the buildings? A. There is a mixture of ACT, hard lid and open ceilings, depending on the security of the area. Hallways are typically ACT.
m. Q. Are there tunnels that link the buildings where new feeders could be run? A. Yes.
n. Q. Is there metering on the main switchgears? A. There is metering on the switchgear in the newer Powerhouse, but not in the original switchgear in the Main building. The facility does not have historical data from the metering that exists, and it would be the responsibility of the designer to extract any data. The facility has the ability to amp probe panels as needed.
Additional temporary metering could be negotiated as an additional service with the successful proposer.
o. Q. Has a hazardous materials survey been performed? A. No, the owner will procure that independently once the areas of work have been identified. It is anticipated there will be lead-containing paint found, so the eventual electrical contractor will likely need to be lead paint certified to efficiently make new penetrations. Any asbestos-containing material anticipated to be disturbed would be abated by a separate contract.
p. Q. Does the power system in Power house electric room have capacity for additional electrical panels requested? A. It is believed there is enough capacity for the additional panels, but this will need to be verified by the designer. Any expansion of the main service would be negotiated as additional design services.
q. Q. Does the power system in Main Building old boiler room have capacity for additional electrical panels requested? A. It is believed there is enough capacity for the additional panels, but this will need to be verified by the designer. Any expansion of the main service would be negotiated as additional design services.
r. Q. Is the panelboard proposed in R unit to be 3-phase or 1-phase? A. This will need to be determined during design. It is believed there is capacity for either and probably only 1-phase is needed, but this will need to be evaluated further.
s. Q. How many lighting contactors are to be replaced? Are they all in the same location? Is the replacement like-for-like? A. The contactors are all centrally located and anticipated to be mailto:construction.procurement@iowa.gov replaced in the same location, like-for-like unless the designer has a different recommendation.
There are approximately 20 contactors currently
t. Q. Is the Arc Flash Study to be completed by the end of 100% schematic design phase? A. No, just the estimated fee for an arc flash study needs to be included by the end of the 100% schematic design phase.
Attachments: Pre-Proposal Sign in sheet and meeting minutes.
END OF ADDENDUM
State of Iowa - Department of Administrative Services 109 SE 13th St.
Des Moines, Iowa 50319 P: (515) 281-7260
Project: 9353.00 DOC IMCC Electrical Service Upgrades
2700 Coral Ridge Ave Coralville, Iowa 52241
RFP Pre-Proposal Minutes: Meeting #1
Meeting Date Dec 12, 2023 Meeting Time 10:00 AM - 11:00 AM Central Time (US & Canada)
Meeting Location
Overview Meeting to allow prospective design firms to visit the project site, when possible, and learn more about the scope.
Microsoft Teams meeting Join on your computer, mobile app or room device Click here to join the meeting Meeting ID: 292 225 322 851 Passcode: 8BHRwY Download Teams | Join on the web Or call in (audio only) +1 515-598-7333,,813420512# United States, Iowa City Phone Conference ID: 813 420 512#
Notes
Attachments
Scheduled Attendees
Name Company Phone Number Email Attendance
Steve Bickford Iowa Medical Classification Center steve.bickford@iowa.gov
Craig Gobush Iowa Medical Classification Center daniel.gobush@iowa.gov
Jeff Curtis Samuels Group, Inc. P: (515) 288-0467 jcurtis@samuelsgroup.net
Brian Polzin Samuels Group, Inc. P: (715) 841-1982 bpolzin@samuelsgroup.net
Bill Reynolds Samuels Group, Inc. P: (515) 288-0467 breynolds@samuelsgroup.net
Rusty Richardson Samuels Group, Inc. rrichardson@samuelsgroup.net
Jennifer Kleene State of Iowa - Department of Administrative Services
P: 5157250454 jennifer.kleene@iowa.gov
Introduction
No. Mtg Origin Title Assignment Due Date Priority Status
1.1 1 Introductions Open
Description Attendance
Official Documented Meeting Minutes See the sign in sheet
State of Iowa - Department of Administrative Services Page 1 of 3 Printed On: Dec 19, 2023 03:10 PM CST
Project Overview
2.1 1 Scope Review Open
Description DAS is currently seeking design services from qualified firms for a project consisting of schematic design to develop the construction budget and scope of work for electrical service upgrades at the IMCC. IMCC has received a capital appropriation of $2,800,000.00 for electrical service upgrades and has a list of priorities but is seeking the expertise of a design professional to review the entire electrical system to provide input on a scope of work that will meet the facility’s needs and best utilize the available funding. The design firm selected through this process will also provide all related future design services for the electrical service upgrades at the IMCC, with the remaining scope of work to be negotiated as funding allows.
Official Documented Meeting Minutes Read for those in attendance
2.2 1 Schedule Review Open
Description
• Questions Due to construction.procurement@iowa.gov: December 19, 2023 by 2:00 pm
• Addendum Issued: December 28, 2023
• Proposals Due: January 09, 2024 by 2:00 pm
• Selection of Designer/Issue NOI: Week of January 08, 2024
• Execution of 803 Contract: Week of January 15, 2024
• Tentative Design Kickoff Meeting: Week of January 22, 2024
• 50% Schematic Design & Budget: February 15, 2024
• 100% Schematic Design and budget: March 21, 2024
• 100% Schematic Design Review: Week of March 25, 2024
RFP Overview
Meeting #1 - RFP Pre-Proposal Project: 9353.00 DOC IMCC Electrical Service Upgrades
State of Iowa - Department of Administrative Services Page 2 of 3 Printed On: Dec 19, 2023 03:10 PM CST mailto:construction.procurement@iowa.gov:
3.1 1 RFP Requirements Review Open
Description
• All questions to be directed to construction.procurement@iowa.gov
• DAS uses Procore online project management system for all projects, at no cost to the designer.
• DAS uses a modified ConsensusDocs 803 Form of Agreement
• DAS requires a project-specific Certificate of Insurance and specifies a Professional Liability policy of $2,000,000 with a deductible of $25,000 o Must note in proposal if deductible is different and provide a letter of financial stability from bank o Must provide COI prior to contract execution
• Ensure the following items are included in the proposal:
o Project-specific schedule o Resumes for all technical staff that will be assigned to the project o Anticipated hours and rates for each person on the design team o Lump sum broken down by schedule of values
Conclusion
4.1 1 Designer Questions Open
Description Any questions?
Official Documented Meeting Minutes Questions from the meeting are tabulated in Addendum #1 - which is scheduled to go out the no later than 12-20-23
Meeting #1 - RFP Pre-Proposal Project: 9353.00 DOC IMCC Electrical Service Upgrades
These meeting minutes are believed to be an accurate reflection of those items discussed and the conclusions that were reached during the referenced meeting.
Please contact State of Iowa - Department of Administrative Services if there are any discrepancies or questions with the content of these minutes.
State of Iowa - Department of Administrative Services Page 3 of 3 Printed On: Dec 19, 2023 03:10 PM CST
File details come from the government source that posted it. Updated .