Amendment 0003.pdf
PDF 615 KB Posted
- Attached to
- Ballistic Shields Federal contract opportunity
- Solicitation number
- RFP15F06723R0000173
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0002.pdf | ||
| Amendment 0001.pdf | ||
| Cover Page_RFP.docx | DOCX document | |
| RFP 15F06723R0000173 Ballistic Shields.pdf | ||
| RFP Cover Ltr RFP15F06723R0000173 Ballistic Shields.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0003 9 June 2023
Same as Blk 6
RFP15F06723R0000173
xx
12 May 2023
X 1
a. The purpose of this amendment is to post Questions and Answers.
b. Return all signed copies of amendment/s with the proposal/s.
FEDERAL BUREAU OF INVESTIGATION
PROCUREMENT SECTION
NATIONAL ACQUISITION PROGRAMS UNIT
X
Amendment 0003
RFP 15F06723R0000173
| BALLISTIC | RESISTANT | SHIELDS | |
| Pistol | Resistant | Shields | |
| Rifle | Resistant | Shields |
QUESTIONS & ANSWERS
Posted to SAM.gov on 9 June 2023
| The | following | questions | and | answers | are | provided | for | informational | purposes | only. | |||||
| Nothing | contained | in | the | below | questions | and | answers | constitutes | a | change | to | the | |||
| terms | and | conditions | of | the | solicitation. | Any | change | to | a | term | or | condition | will | be | |
| issued | through | an | amendment | to | the | solicitation. |
| Note: | In | some | instances, | questions | have | been | abbreviated | or | additional | context | has |
| been | added | to | clearly | describe | the | question | for | all | potential | Offerors. |
QUESTION 1:
Will the FBI consider an extension to the deadline?
| ANSWER | 1: | ||
| PLEASE | SEE | AMENDMENT | #1. |
QUESTION 2:
Referencing RFP Section C.4.2 SHIELD SIZES, the RFP makes mention to minimum size requirements but makes no mention of the protective surface area of each shield.
A. Does the FBI have any requirements for protective surface area or is industry at liberty to submit shields with lesser protective coverage area.
B. If there is no requirement for protective coverage area, how will the FBI ensure that the shot locations for the proposed test plan will be placed on a section with ballistic protection (as opposed to a portion that does not feature ballistic protection)?
| ANSWER | 2: | ||||||||
| IN | RESPONSE | TO | THE | ABOVE | QUESTIONS: | ||||
| (A) THE | FBI | HAS | NOT | SPECIFIED | A | PROTECTIVE | SURFACE | AREA; | HOWEVER, |
| SECTION | C.4.1.2 | NOTES | THAT, | “ALL | SHIELDS | SHALL | BE | ABLE | TO | STOP | THREAT |
| IMPACTS | AT | ONE | (1) | INCH | FROM | ANY | EDGE | (I.E., | THE | OUTERMOST | PERIMETER |
| OF | THE | TEST | ITEM)”. |
| (B) THE | FBI | IS | SEEKING | BALLISTIC | SHIELDS | THAT | STOP | BALLISTIC | THREATS | |||
| ANYWHERE | ON | THE | STRIKE | FACE | OF | THE | SHIELD | WITHIN | ONE | INCH | FROM | THE |
| EDGE. | THE | TEST | PROTOCOL, | AS | DESRIBED | IN | SECTION | M | OF | THE | SOLICIATION, | |
| DOES | NOT | ACCOUNT | FOR | OR | CONSIDER | SECTIONS | OF | A | SHIELD | STRIKE | FACE | |
| THAT | DO | NOT | OFFER | BALLISTIC | PROTECTION. |
QUESTION 3:
RFP Section C.5.5 states, “Rifle-rated, Large size shield with viewport and Rifle-rated, Large size shield without viewport shall have a weight-distribution system available as an optional accessory.” Is it the FBI’s intent that this load bearing feature be used while the shield is deployed in an offensive/defensive position?
| ANSWER | 3: | |||||||||
| YES. | PLEASE | SEE | SECTION | A | (PAGE | 6) | OF | THE | RFP. |
QUESTION 4:
Referencing RFP Section M.3.6 PHASE III, Test 4: Ballistic Resistance – High Temperature, after the shield is subjected to the high temperature soak, will the shield then be returned to ambient prior to shooting? If not, how much time after the temperature exposure, will it take for the shield to be tested?
| ANSWER | 4: | ||||||||||||
| IT | IS | THE | INTENT | OF | THE | FBI | TO | BEGIN | TESTING | OF | THE | SHIELD | IMMEDIATELY |
| UPON | REMOVAL | FROM | THE | ENVIRONMENTAL | CHAMBER. | ONCE | THE | SHIELD | IS | ||||
| REMOVED | FROM | THE | ENVIRONMENTAL | CHAMBER, | IT | WILL | NOT | BE | RETURNED | ||||
| TO | THE | CHAMBER. | THE | FBI | WILL | CONDUCT | BALLISTIC | TESTING | ON | ONE | |||
| SHIELD | AT | A | TIME | AND | WILL | CONTINUE | TESTING | ON | THAT | SHIELD | UNTIL | ||
| COMPLETION | OF | THE | TEST | OR | FAILURE | OF | THE | SHIELD. |
QUESTION 5:
Referencing RFP Section M.3.6 PHASE III, Test 4: Ballistic Resistance – Low Temperature, after the shield is subjected to the low temperature soak, will the shield then be returned to ambient prior to shooting? If not, how much time after the temperature exposure, will it take for the shield to be tested?
| ANSWER | 5: | ||||
| PLEASE | REFER | TO | ANSWER | #4 | ABOVE. |
QUESTION 6:
Will the FBI accept multiple bids?
| ANSWER | 6: | |||||||
| PLEASE | SEE | SECTION | L.5 | OF | THE | RFP | (PAGE | 77). |
| QUESTION | 7: | ||
| Section C.4.2 of the RFP states that Rifle‐rated, | Compact | size | shield shall be “no less |
than 16 inches and no greater than 18 inches in width at the widest point and no less than 28 inches in length.” Would the FBI accept a ballistic panel polyethylene shield that is 15.5” at the widest point?
| ANSWER | 7: | ||
| PLEASE | SEE | AMENDMENT | #2. |
QUESTION 8:
Will the FBI accept a rifle-rated ballistic shield in which the protection from M855 ends 1.75” from the outermost edge of the shield? Specifically, will a perforation by a M855 projectile striking the outer regions of the shield, not rated for M855, be considered a failure?
| ANSWER | 8: | |||
| PLEASE | SEE | ANSWER | #2 | ABOVE. |
QUESTION 9:
Will the FBI accept ballistic shields not manufactured in the United States?
| ANSWER | 9: | ||||||||||
| PLEASE | SEE | PART | II, | SECTION | I | (CONTRACT | CLAUSES), | I.2 | OF | THE | RFP. |
QUESTION 10:
Does the shield have to be 100% made in the USA from 100% made in the USA components? Can the shield be made in USA from imported components?
| ANSWER | 10: | |||||
| PLEASE | REFER | TO | FAR | 52.225‐1 | BUY‐AMERICAN | SUPPLIES. |
QUESTION 11:
Will the FBI pay for the samples provided?
| ANSWER | 11: | ||||||||||||
| NO. | PLEASE | NOTE | THAT | SECTION | L.9 | OF | THE | RFP | (PAGE | 80) | NOTES | THAT | |
| ONLY | THE | TOP‐SCORING | SUBMISSION(S) | WILL | BE | SUBJECTED | TO | BALLISTIC | |||||
| RESISTANCE | TESTING. | ALL | SUBMISSIONS | NOT | SUBJECTED | TO | DESTRUCTIVE | ||||||
| TESTING | WILL | BE | RETURNED | TO | THE | OFFERORS. |
QUESTION 12:
Can the FBI provide more information of what shape and size you prefer for the different shields? Can the FBI provide a drawing? Can the FBI confirm the preferred view port shape and size?
| ANSWER | 12: | ||||||||||
| PLEASE | SEE | SECTIONS | C.3 | AND | C.4.2 | OF | THE | RFP | FOR | REQUIREMENTS | FOR |
| THE | SHAPE | AND | SIZE | OF | THE | SHIELDS. |
QUESTION 13:
Can you please confirm what alternate viewing system you are referring to for the shields?
| ANSWER | 13: | |||||||||
| PLEASE | SEE | SECTION | A | – | DEFINITIONS | (PAGE | 5) | OF | THE | RFP. |
QUESTION 14:
Will the FBI accept Past Performance Questionnaires under different company names?
The owner of the businesses was the same, but the business names changed.
| ANSWER | 14: | |||||||||
| IF | THE | BUSINESSES | ARE | DIFFERENT | LEGAL | ENTITIES, | THE | PAST | ||
| PERFORMANCE | WILL | NOT | BE | ACCEPTED. | IF | THE | BUSINESS | REBRANDED | BUT | |
| REMAINED | THE | SAME | LEGAL | ENTITY, | IT | WOULD | BE | ACCEPTABLE. |
QUESTION 15:
We manufacture ballistic shields (NIJ Level II and IIIA) in various sizes, including 9”x12”, 10”x14”, 11”x16”, 18”x24”, 21”x36”. Would the FBI require five (5) samples in each size or only five (5) in each NIJ threat level?
| ANSWER | 15: | |||||||||
| PLEASE | SEE | SECTION | C.4.2 | OF | THE | RFP | FOR | SIZE | REQUIREMENTS. | |
| PLEASE | SEE | SECTION | L.5 | OF | THE | RFP | FOR | INSTRUCTIONS | FOR | PREPARING |
PROPOSALS.
QUESTION 16:
We offer a NIJ Level II shield which is strictly handgun rated. We also offer a NIJ Level IIIA shield which is both handgun and shotgun rated. Are we required to send five
(5) samples of each or are you strictly looking for NIJ Level IIIA shields?
| ANSWER | 16: | ||||||
| PLEASE | SEE | SECTION | C.4.1 | FOR | BALLISTIC | RESISTANCE | REQUIREMENTS. |
QUESTION 17:
If an alternate viewing system is submitted, will it be subjected to the drop testing outlined in Phase III, Test 2: Drop Test?
| ANSWER | 17: | ||||||||||
| THE | FBI | INTENDS | TO | REMOVE | THE | ALTERNATE | VIEWING | SYSTEM | FROM | THE | |
| SHIELD | PRIOR | TO | DROPS. | HOWEVER, | IF | THE | ALTERNATE | VIEWING | SYSTEM | IS | |
| PERMANENTLY | / | SEMI‐PERMANENTLY | ATTACHED, | IT | WILL | BE | INCLUDED | ON | |||
| THE | DROP. |
| AS | NOTED | IN | SECTION | M.3.6 | PHASE | III, | TEST | 2: | DROP | TEST, | THE | FBI | IS |
| LOOKING | FOR | ECESSIVE | DAMAGE | CAUSED | TO | THE | SHIELD. | DAMAGE | TO | THE | |||
| ALTERNATE | VIEWING | SYSTEM | ALONE | DOES | NOT | CONSTITUTE | A | FAILURE | OF | ||||
| THE | DROP | TEST. |
QUESTION 18:
Section C.4.1.1 states, “All shields shall be able to stop multiple impacts from the threat projectiles specified within their category. Those impacts may be at various angles including, but not limited to 30, 45, 60, and 90-degrees obliquity.” The test protocol in Section M only mentions 30 and 90-degree oblique test shots. Can you please clarify?
| ANSWER | 18: | ||||||||||
| THE | FBI | IS | SEEKING | BALLISTIC | SHIELDS | THAT | CAN | STOP | THREAT | ||
| PROJECTILES | AT | ANY | ANGLE | OF | INCIDENT. | WHILE | THE | EVALUATION | CALLS | ||
| FOR | TEST | IMPACTS | AT | 30 | AND | 90‐DEGREES, | IT | ALLOWS | FOR | OTHER, | NON‐ |
| STANDARD | ANGLES | IF | NEEDED. | THE | PISTOL‐RATED | AND | RIFLE‐RATED | TEST | |||
| PROTOCOL | STATES, | “ANY | UNIQUE | FEATURE | OR | PERCEIVED | WEAK | POINTS | ON | ||
| A | SHIELD | MAY | BE | TARGETED | BY | THE | EVALUATION | TEAM. | THE | TEST | IMPACTS |
| ON | THIS/THESE | FEATURES | MAY | BE | AT | ANY | APPROPRIATE | ANGLE | IN | ORDER | |
| TO | EXPLOIT | POTENTIAL | WEAKNESSES.” | (PAGES | 89 | AND | 90) |
QUESTION 19:
Section C.4.1.2 refers to threat impacts at one (1) inch from any edge. Will the 9mm Luger rounds be used for the 1” edge and viewport shot on each of the pistol shields?
| ANSWER | 19: | |||||||||||
| THE | 9MM | LUGER | ROUNDS | WILL | BE | USED | FOR | ALL | EDGE | TESTS | ON | PISTOL‐ |
| RATED | SHIELDS. | PLEASE | SEE | C.4.1.4 | FOR | VIEWPORT | REQUIREMENTS. |
QUESTION 20:
Section C.5.3 refers to shield handles being capable of withstanding the weight of a 250 lb. individual. There is no mention of the testing to be performed in Section M.
Can you please clarify?
| ANSWER | 20: | |||||||||||
| SECTION | C.5.3 | STATES, | IN | PART, | “SHIELDS | WITH | A | HANDLE | CAPABLE | OF | ||
| WITHSTANDING | THE | WEIGHT | OF | A | 250‐POUND | INDIVIDUAL | ARE | |||||
| PREFERRED.” | AS | THIS | IS | NOT | A | REQUIREMENT, | IT | IS | NOT | INCLUDED | IN | PHASE |
| III | TESTING. |
QUESTION 21:
Sections E.1.2 and E.1.3 refer to random quality assurance testing. What type of random (QA) testing are these sections referring to?
| ANSWER | 21: | |||||||||
| THE | FBI | RESERVES | THE | RIGHT | TO | TEST | ANY | SHIELD(S) | PURCHASED | UNDER |
| THESE | CONTRACTS. | TESTING | WOULD | BE | IN | ACCORDANCE | WITH | THE | ||
| EVALUATION | FACTORS | OUTLINED | IN | SECTION | M | OF | THE | RFP. |
QUESTION 22:
In Section I.2, these two sub-sections are checked:
XX (14) (i) 52.219-6, Notice of Total Small Business Aside (Nov 2020) (15 U.S.C.
644)., XX (26) 52.219-33, Nonmanufacturer Rule (SEP 2021) (15U.S.C. 637(a) (17)).
Considering those two sections are cited we would assume that a small business offeror could only provide products manufactured by a small business for this requirement. Please confirm that the FBI’s intent is all SBA. Please confirm if there will be an SBA waiver to allow the sale of any large OEM products.
| ANSWER | 22: | |||||||
| THIS | SOLICITATION | IS | A | SMALL | BUSINESS | SET‐ASIDE. | ||
| PLEASE | SEE | DEFINITIONS | UNDER | FAR | 52.219‐33 | NONMANUFACTURER | RULE. | |
| THE | FBI | HAS | IDENTIFIED | MULTIPLE | SMALL | BUSINESS | MANUFACTURERS | OF |
BALLISTIC SHILEDS THUS THE FBI DOES NOT INTEND TO REQUEST A SBA NMR
WAIVER.
QUESTION 23:
Please confirm the shipping address for the samples. The zip code specified does not registering in our system.
| ANSWER | 23: | |||||||||||
| PER | SECTION | L.10 | OF | THE | RFP | (PAGE | 81), | SAMPLES | SHALL | BE | ADDRESSED | AS |
FOLLOWS:
FEDERAL BUREAU OF INVESTIGATION
BALLISTIC RESEARCH FACILITY
ATTN: SCOTT PATTERSON
4942 FOWLER ROAD
BUILDING #6315
REDSTONE ARSENAL, AL 35898
RFP-15F06723R0000173
QUESTION 24:
In reference to Section F.2.1, will the FBI consider releasing a planned task-order (delivery with maximum quantities) schedule for each of the indicated shields?
ANSWER 24:
NO.
QUESTION 25:
Will the acceptance testing be the current NIJ 0108.01 standard?
| ANSWER | 25: | ||||||
| NO. | PLEASE | SEE | ANSWER | # | 21 | ABOVE. |
QUESTION 26:
Can you share your anticipated award date?
| ANSWER | 26: | ||||||||
| THE | FBI | INTENDS | TO | MAKE | AWARD | NLT | 29 | SEPTEMBER | 2023. |
QUESTION 27:
Will the FBI accept proposals on single shield requirement (i.e., submitting bid for small pistol rated shields only)?
| ANSWER | 27: | |||||
| PLEASE | SEE | SECTION | L.5 | OF | THE | RFP. |
QUESTION 28:
What kind of fixture will be used to support these shields during ballistic testing?
| ANSWER | 28: | ||||||||||||
| THE | FBI | INTENDS | TO | USE | A | CUSTOM | TEST | FIXTURE. | THE | FIXTURE | HAS | TWO | |
| ADJUSTABLE | POINTS | OF | CONTACT, | INCLUDING | ONE | ADJUSTABLE | HANDLE | ||||||
| CLAMP. | WHEN | POSSIBLE, | THE | SHIELD | WILL | BE | RETAINED | BY | A | MINIMUM | OF | ||
| TWO | (2) | POINTS | OF | CONTACT. |
QUESTION 29:
Can the Offeror witness the ballistic testing of their submitted samples?
ANSWER 29:
NO.
QUESTION 30:
What is the source of the 7.62 X 39 MSC threat?
| ANSWER | 30: | |||||||||||
| THE | FBI | UTILIZES | 123 | GRAIN | MILD | STEEL | CORE | PROJECTILES | MANUFACTURED | |||
| BY | ARSENAL | JSCO. | THE | PROJECTILES | ARE | HAND‐LOADED | BY | THE | FBI | TO | MEET | |
| THE | VELOCITY | REQUIREMENTS | STATED | WITHIN | THE | SOLICIATION. |
QUESTION 31:
Within a single category (e.g., Rifle-rated, size large shield without viewport), do all five (5) samples submitted have to have the same handles? Can an Offeror submit different handle options without introducing a new shield sample set?
| ANSWER | 31: | ||||||||||
| THE | SAMPLE | SHIELDS | NEED | NOT | HAVE | THE | SAME | HANDLE; | HOWEVER, | THE | FBI |
| REQUIRES | A | MINIMUM | OF | TWO | SAMPLES | OF | EACH | ACCESSORY. | OFFERORS | MAY | |
| SUBMIT | ADDITIONAL | HANDLES | AS | ACCESSORIES. |
QUESTION 32:
Provided that the shield meets the requirements of the “Buy American—Supplies” clause, would the FBI accept an alternate viewing system that is not made in America?
| ANSWER | 32: | ||||||
| SEE | FAR | 52.225‐13 | RESTRICTIONS | ON | CERTAIN | FOREIGN | PURCHASES |
QUESTION 33:
Section C.3.4 states, “Shields shall be available in black or O.D. Green (or similar).”
(a) Does this mean that the shields can be provided in either black or O.D.
Green or that they need to be available in both colors?
(b) Can you please define what would constitute similar? Do you have any pantone numbers available?
| ANSWER | 33: | |||||||||
| THE | SAMPLE | SHIELDS | SUBMITTED | FOR | EVALUATION | CAN | BE | ANY | COLOR. | |
| WHEN | PURCHASING | SHIELDS | OFF | THE | CONTRACT, | BUYERS | SHOULD | BE | ABLE | |
| TO | SPECIFY | THEIR | PREFERENCE | FOR | SHIELD(S) | IN | BLACK | OR | O.D. | GREEN. |
| THE | FBI | DOES | NOT | HAVE | A | PANTONE | NUMBER | SPECIFIED | FOR | THIS |
SOLICITATION.
QUESTION 34:
Section C.4.1 of the RFP states, in part, “shields shall stop multiple impacts from the following threat projectiles at the specified impact velocities” How many rounds is the shield required to stop?
| ANSWER | 34: | |||||||
| PLEASE | SEE | SECTION | M.3.6 | PHASE | III | BALLISTIC | RESISTANCE | TESTING. |
QUESTION 35:
Section C.3.6 of the RFP states, “Shields shall contain identifying markings on the strike face of the shield. Available markings shall include “POLICE”, “FBI”, “DEA” and “US Marshals”. Note: Orders placed by DOJ entities should have the option for agency-specific identifying markings or “POLICE”. Do we need to provide samples of each marking or is a sample of one of them acceptable?
| ANSWER | 35: | ||||||||
| THE | SAMPLE | SHIELDS | SUBMITTED | FOR | EVALUATION | CAN | HAVE | ANY | |
| MARKINGS | OR | NO | MARKINGS. | WHEN | PURCHASING | SHIELDS | OFF | THE | |
| CONTRACT, | BUYERS | SHOULD | BE | ABLE | TO | SPECIFY | THEIR | PREFERENCE | FOR |
MARKINGS.
QUESTION 36:
In reference to Section L.9, accessory samples; If an Offeror submits shields in more than one (1) category and the same accessory is available for both shield categories, shall the Offeror submit more than two (2) samples, or will two (2) samples of the accessory suffice?
| ANSWER | 36: | ||||||||||
| IN | THE | EVENT | THAT | THE | SAME | ACCESSORY | IS | AN | AVAILABLE | OPTION | FOR |
| MORE | THAN | ONE | (1) | CATEGORY | OF | SHIELD, | OFFERORS | NEED | ONLY | SUBMIT | |
| TWO | (2) | SAMPLES, | UNLESS | THE | ACCESSORY | IS | PERMANENTLY | / | SEMI‐ | ||
| PERMANENTLY | ATTACHED. | PLEASE | CLEARLY | MARK | THAT | THE | ACCESSORY | IS | |||
| INTENDED | FOR | BOTH | CATEGORIES. |
QUESTION 37:
In reference to Section C.5.1, can you define “commonly available” batteries? Are rechargeable batteries considered commonly available?
| ANSWER | 37: | ||||||||
| FOR | THE | PURPOSES | OF | THIS | SOLICITATION, | COMMONLY | AVAILABLE | ||
| BATTERIES | MAY | INCLUDE | CR123, | AA, | AAA, | 9‐VOLT, | C‐CELL, | D‐CELL, | AND |
| CR2032. | RECHARGEABLE | BATTERIES | WOULD | BE | ACCEPTABLE | PROVIDED | |||
| THEY | ARE | IN | THE | COMMONLY | AVAILABLE | SIZES | LISTED | ABOVE. |
QUESTION 38:
Are accessories beyond those listed in the pricing matrix able to be offered?
ANSWER 38:
YES.
QUESTION 39:
Can an Offeror supply more than one (1) option for an accessory (e.g., multiple handles)? If so, where would that pricing be included?
| ANSWER | 39: | |||||||||
| YES. | PLEASE | ADD | ADDITIONAL | LINE | ITEMS | TO | THE | PRICING | MATRIX. |
QUESTION 40:
If multiple versions of an accessory (e.g., handle, light, weight bearing system, etc.)
are available, which option will be utilized for ballistic testing?
| ANSWER | 40: | ||||||||
| THE | FBI | DOES | NOT | INTEND | TO | CONDUCT | BALLISTIC | RESISTANCE | TESTING |
| WITH | ALL | OPTIONAL | ACCESSORIES. | HOWEVER, | PERMANANTLY | OR | SEMI‐ | ||
| PERMANANTLY | ATTACHED | ACCESSORIES | WILL | BE | INCLUDED. | IN | ADDITION, |
| THE | FBI | RESERVES | THE | RIGHT | TO | BALLISTICALLY | TEST | SHIELDS | IN | ANY |
| CONFIGURATION | WITH | THE | ACCESSORIES | SUBMITTED. |
QUESTION 41:
In reference to PHASE III, Test 2: Drop Test, how will the shield be held before the 55-inch drop? Will it be held vertically relative to the ground or simply be suspended 55 inches above the ground by the handle where the CG of the shield will affect whether the bottom or strike face of the shield contacts the ground first?
| ANSWER | 41: | |||||||||||
| THE | INTENT | OF | THE | FBI | IS | TO | SUSPEND | THE | SHIELD | VERTICALLY | AT | (OR |
| NEAR) | 90 | DEGREES | PERPENDICULAR | TO | THE | GROUND. | AS | SPECIFIED | IN | |||
| PHASE | III, | TEST | 2: | DROP | TEST, | THE | SHIELD | WILL | BE | RELEASED | AND | |
| ALLOWED | TO | FREEFALL | TO | A | CONCRETE | SURFACE. |
QUESTION 42:
Will all optional accessories be installed on the shield during drop testing?
ANSWER 42:
NO.
QUESTION 43:
Will all optional accessories be installed on the shield during environmental testing and ballistic testing?
| ANSWER | 43: | |||||||||||
| THE | FBI | DOES | NOT | INTEND | TO | CONDUCT | THERMAL | CYCLING | OR | BALLISTIC | ||
| RESISTANCE | TESTING | WITH | ALL | OPTIONAL | ACCESSORIES. | HOWEVER, | THE | |||||
| FBI | RESERVES | THE | RIGHT | TO | UTILIZE | ANY | ACCESSORY | IN | TESTING | IF | IT | IS |
| BELIEVED | THAT | THE | ACCESSORY | COULD | CAUSE | HARM | TO | THE | SHIELD | USER. |
QUESTION 44:
Section M.3.6 PHASE III states that all rifle-rated shields will be subjected to two (2) one-inch Edge shots. Will both edge shots be at 0° obliquity? Which projectile will be used at the edge?
| ANSWER | 44: | |||||||||||
| THE | EDGE | SHOTS | WILL | BE | CONDUCTED | AT | OR | CLOSE | TO | 0‐DEGREE | ||
| OBLIQUITY. | THE | FBI | RESERVES | THE | RIGHT | TO | UTILIZE | ANY | OF | THE | THREAT | |
| PROJECTILES | REFERENCED | IN | SECTION | C.4.1 | FOR | EDGE | TESTS; | HOWEVER, | ||||
| THE | PROJECTILE | (OR | PROJECTILES) | USED | WILL | BE | CONSISTENT | ACROSS | ALL |
OFFERORS.
QUESTION 45:
For the pistol-rated shield, will at least one of the two 1 oz. slug shots be at the edge?
Will at least one of the two 1 oz. slug shots be at a corner?
| ANSWER | 45: | |||||||||
| PLEASE | SEE | ANSWER | #19 | ABOVE. | NO | CORNER | TEST | IMPACT | IS | SPECIFIED |
| UNDER | THE | PROTOCOL. |
QUESTION 46:
Carry bags are identified as an accessory. Is a soft bag required or are hard-sided containers (i.e., rigid bags) acceptable? Are bags hand-carried only or are wheeled configurations acceptable?
| ANSWER | 46: | |||||
| SEE | SECTION | C.5.6 | FOR | CARRY | BAG | REQUIREMENTS. |
QUESTION 47:
If a fastener is less than 1 inch from the shield edge, can it still be ballistically tested/shot?
| ANSWER | 47: | ||||||||||
| THE | FBI | WILL | NOT | TARGET | FASTENERS | LOCATED | LESS | THAN | ONE | (1) | INCH |
| FROM | AN | OUTER | EDGE. |
QUESTION 48:
Can each shield come fully assembled with all accessories already on it? If so, are the two extra accessories per category still required?
| ANSWER | 48: | ||||||||||
| YES, | PROVIDED | THAT | THE | FBI | HAS | AT | LEAST | TWO | SAMPLES | OF | EACH |
| ACCESSORY | FOR | CONSIDERATION. |
QUESTION 49:
Would a level III+ be the sole requirement?
| ANSWER | 49: | ||||||
| PLEASE | SEE | SECTION | C.4.1 | FOR | BALLISTIC | RESISTANCE | REQUIREMENTS. |