RFP No. FA520523R0004_Minutes_Pre-proposal Conference&Site Visit_23May23.pdf
PDF 328 KB Posted
- Attached to
- Project No. QKKA214009, Repair JNCO Homes, MFH, 123, 125, 127, 129, 291, Misawa Air Base, Japan
- Solicitation number
- FA520523R0004
About this file
The document provides minutes from a pre-proposal conference and site visit for a military family housing repair project at Misawa Air Base in Japan. The Air Force seeks to repair five military family housing buildings and two pump houses through competitive proposals due by June 22, 2023. The pre-proposal meeting included briefings by the 35th Contracting Squadron on the solicitation requirements and evaluation procedures, and by the 35th Civil Engineer Squadron on the project scope and technical specifications. Attendees from nine prospective offeror firms and Air Force personnel then conducted a site visit of the housing buildings and pump houses to observe existing conditions. Questions on the solicitation are due by June 2 to inform proposal preparations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP No. FA520523R0004_Pre-proposal Conference Slides_23May23.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
35TH FIGHTER WING (PACAF)
MISAWA AIR BASE, JAPAN
23 May 23
MEMORANDUM FOR ALL PROSPECTIVE OFFERORS
FROM: 35th Contracting Squadron, Plans & Programs/Specialized Flight
Bldg. 656, Misawa Air Base, Misawa-shi, Aomori-ken, Japan
SUBJECT: Pre-proposal Conference Minutes & Record of Site Visit, Request for Proposal (RFP) No.
FA520523R0004, Project No. QKKA214009, Repair JNCO Homes, MFH 123, 125, 127, 129, 291, Misawa Air Base, Japan
1. These are minutes of the pre-proposal conference and its subsequent site visit conducted for the subject RFP on
23 May 23, in accordance with FAR 52.236-27 “Site Visit (Construction) – Alternate I” and RFP Attachment 3, Other Contract Requirements, paragraph 9. L001 “Notice of Pre-Bid/Pre-Proposal Conference”. The pre-proposal conference was held at the 35th Contracting Squadron Conference Room, Bldg. 656, Misawa Air Base, with attendance of the representatives of the following f irms and the Government’s individuals:
Firms (Listed in a lphabetical order) Government
American Engineering Corporation 35th Civil Engineer Squadron
Aomori Environmental Development Co., Ltd. Maj Shandon James, 35 CES/CEN
Daiwa House Reform Co., Ltd. Capt Jose Medina Ramirez, 35 CES/CENMC
HAZAMA ANDO CORPORATION Mr. Charles Lane, 35 CES/CENM
Kosaka Komuten Co., Ltd. Mr. Rector Hartley, 35 CES/CENMC
NIPPO CORPORATION Mr. Yasuhiro Yonaiyama, 35 CES/CENMD
Suzuki Kensetsu Kogyo Co., Ltd. Mr. Mitsuhiro Kashiwazaki, 35 CES/CENMD
Mr. Norihiro Maruyama, 35 CES/CENMD
Ms. Inok Antunes, 35 CES/CEIH
Mr. Louis Vance, 35 CES/CEIH
SSgt Kayla Arias, 35 CES/CEIH
Ms. Masako Taura, CE CES/CEIHM
35th Contracting Squadron
Maj Timothy Wilhelm, 35 CONS/CC
MSgt Joshua Blalock, 35 CONS/PKB
Ms. Miyako Fujimoto, 35 CONS/PKP
Mr. Takafumi Nosaki, 35 CONS/PKP
Mr. Kazuo Miura, 35 CONS/PKP
Ms. Shoko Suzuki, 35 CONS/PKP
Mr. Akito Miura, 35 CONS/PKP
2. Outline of Pre-proposal Conference and Site Visit conducted.
a . Pre-proposal Conference. The purpose of the conference/site visit is to enhance the “exchange of information” encouraged in FAR 15.201. The conference was opened by Mr. Akito Miura /Contract Administrator
(CA) at 0900 hours who proceeded to present the topics contained in the briefing slides (Attachment, Pre-proposal
Conference Briefing Slides). All attendees were allowed to ask questions at the pre-designated session of the slides;
however, all attendees were reminded that:
• All questions asked must be formally submitted to 35 CONS in the form of questionnaire and/or request for clarification later;
• Any technical questions deemed to be critical by the Government engineers and the Contracting Officer
(CO) must be submitted in writing to 35 CONS; and
• Information provided at this conference shall not qualify the terms and conditions of the solicitation and specifications. Terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing (ref. RFP Attachment 3, “Other Contract Requirements”, paragraph 9, L001(c)).
(1) Solicitation Briefings by 35 CONS. The CA explained the scope and requirements, and filling instructions of the solicitation including proposal preparation and proposal evaluation procedures.
(2) Questions on Solicitation. No questions were asked during the session. Accordingly, the CA turned over the briefing to 35 CES to present the technical portion of the subject project to enhance understanding of the project requirements at approximately 0920 hours.
(3) Technical Briefings by 35 CES. Capt Jose Medina Ramirez/Chief, Construction Management opened the technical briefing with the general requirements and work scope under each engineering disciplines, and followed by Mr. Yonaiyama/Architectural Engineer to provide supplemental information on the technical briefing in accordance with the project specifications and drawings.
(4) The briefing was turned over to 35 CONS after the technical briefing by 35 CES. The CA explained the example format for the question and answer (Q&A) writing process, and reminded those in attendance of the closing date/time of the Q&A and proposal submission.
(5) Closing remarks was given by Maj Timothy Wilhelm/Commander, 35th Contracting Squadron at around 0940 hours, and the party moved to the Military Family Housing (MFH) area of the project for the site visit.
b. Site Visit. Following the pre-proposal conference, the site visit was conducted at MFH Bldg. 129 from 1000 hours, and subsequently at MFH Bldg. 123 (exterior only), Pump House Bldg. 119, MFH Bldg. 291 (exterior only) and Pump House Bldg. 263 to confirm the existing condition of the buildings where required to be renovated/upgraded under this project.
All attendees observed the current state of the buildings above and received explanation by 35 CES personnel on the details of the existing condition. All photos listed below were taken during the site visit.
• MFH Bldg. 129, Unit C – Kitchen • MFH Bldg. 129, Unit C – Bedroom • MFH Bldg. 123 – Entrance
• Pump House Bldg. 119 • MFH Bldg. 291 – Entrance • Pump House Bldg. 263
(1) No question was asked by the attendees during the site visit.
(2) At the end of the site visit, all attended prospective offerors were reminded that questions should be submitted to 35 CONS in writing not later than 2 Jun 23, and the proposal closing time/date is 02:00 PM (JST) on
22 Jun 23.
3. Accordingly, the pre-proposal conference and the site visit were concluded at approximately 1100 hours.
AKITO MIURA
Contract Administrator
Approved:
MIYAKO FUJIMOTO
Contracting Officer
Attachment:
Pre-proposal Conference Briefing Slides dated 23 May 23, 23 pages (46 slides) cc: 35 CES/CENM