RFP No. 3-B157-P-00205-00
RESTRICTIVE NOTICE
THE DRAWINGS AND SPECIFICATIONS INCLUDED IN THIS SOLICITATION ARE THE PROPERTY OF UCHICAGO ARGONNE, LLC AND MAY ONLY BE FOR THE EXPRESS PURPOSE OF PREPARING A RESPONSE TO THIS SOLICITATION. FURTHER DISSEMINATION OF DRAWINGS AND SPECIFICATIONS OTHER THAN TO POTENTIAL INDIVIDUAL SUBCONTRACTORS AND/OR SUPPLIERS IS PROHIBITED, AND MAY SUBJECT THE DISSEMINATOR TO CIVIL PENALTIES. THIS NOTICE SHALL BE MADE KNOWN TO AND BE APPLICABLE TO ALL POTENTIAL INDIVIDUAL SUBCONTRACTORS AND/OR SUPPLIERS. DRAWINGS AND SPECIFICATIONS MAY NOT BE PLACED ON THE
INTERNET WITHOUT THE PRIOR WRITTEN PERMISSION OF UCHICAGO ARGONNE, LLC.
05/01/2023
To All Prospective Offerors:
Subject: Request for Proposal (RFP) No. 3-B157-P-00205-00 100 Area Demolition (Coal Plant)
UChicago Argonne, LLC (“Argonne” or “Laboratory”) operator of Argonne National Laboratory under Prime Contract No. DE-AC02-06CH11357 with the U.S. Department of Energy (DOE), has a requirement for (SCOPE OF WORK). With this RFP, you are invited to furnish a firm fixed-price proposal for this requirement.
All work is to be performed in accordance with the drawings listed in the specifications and specifications entitled, “100 Area Demolition”, Rev 0, dated 05/01/2023. (Enclosure No. 1B)
For your company’s information and use in preparing its proposal, we are providing the following applicable provisions.
1. DESCRIPTION AND LOCATION OF WORK
The work consists of the furnishing of all materials, labor, supervision, equipment, tools, and appurtenances necessary to demolish, remove and dispose of the Coal Handling Plant at Argonne National Laboratory 100 Area. The work includes but not limited to Pre-Construction documentation assembly and submission, asbestos abatement and removal, demolition of conveyers as well as above and below grade structures. Backfill and compaction of remaining subgrade structure is required. The Contractor is responsible for implementing work in compliance with approved Contractor health and safety program, Job Safety Analysis, engineering demolition survey, and Laboratory Integrated Safety Management System.
All work is to be performed in accordance with the drawings listed in the specifications and specifications entitled, “100 Area Demolition”, Rev 0, dated 05/01/2023. (Enclosure No. 1B)
Rob K. Kman Procurement Specialist 3
Financial Management and Procurement Services Procurement Department Argonne National Laboratory 9700 South Cass Avenue, Bldg. 201 Lemont, IL 60439 kman@anl.gov
(630) 252-6488 mailto:kman@anl.gov
2. SMALL BUSINESS SIZE STANDARDS
This accusation is not a Small Business set-aside. However, for informational purposes, the applicable annual receipts for the preceding three (3) years not exceeding $39.5 Million (NAICS CODE 236220).
3. PRE-PROPOSAL MEETING
A hybrid Pre-Proposal Meeting is scheduled for Monday May 8, 2023 at 8:00am CST in Building 214 Room No. 234 and can also be accessed by the following TEAMS link: (Click here to join the meeting). The meeting provides an opportunity to discuss and clarify this RFP. However, nothing said or represented in the meeting shall be deemed to modify RFP requirements unless followed by a written amendment. Prospective offerors are requested to submit questions relative to the RFP in advance of the meeting so the contract specialist may prepare responses. Offerors’ participation at this meeting is strongly recommended.
The first Site Tour is scheduled for immediately following the Pre-Proposal meeting on Monday May 8, 2023 at approximately 9:30am CST. A second Site Tour is scheduled for Tuesday May 9, 2023 at 1:30pm CST. All General Contractors shall coordinate their subcontractor attendance for the site tour.
All General Contractors participating in the site tour shall email the Procurement Official Rob Kman (kman@anl.gov) no later than Friday May 5, 2023 at 3:00pm CST. The following information shall be provided for all site tour attendees:
Name, Company, Mobile Number, Email Address, and U.S. Citizen (Yes or No). Offerors’ participation at this site tour is strongly recommended. Attendees of the Site tours should meet at Building 116 in the Coal Yard Area.
4. EXPLANATION OR INTERPRETATION OF RFP DOCUMENTS
Any prospective offeror desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing to the Procurement Official Procurement Official Rob Kman (kman@anl.gov) by 3:00pm local prevailing time on Thursday May 18, 2023. Oral explanations or instructions given before the award of a contract will not be binding. Any information given by Argonne to a prospective offeror concerning a solicitation will be furnished promptly by Argonne to all other prospective offerors as an amendment to the solicitation, if that information is necessary in submitting proposals or if the lack of it would be prejudicial to other prospective offerors.
5. PERIOD OF PERFORMANCE
Work on site will commence within ten (10) calendar days after the effective date of the contract and will be completed not later than March 29, 2024 for the work defined in the specifications and drawings. The estimated date of award in on or before Wednesday, June 7, 2023.
6. INSURANCE
Certificates of insurance of the types and in the amounts set forth in “Bonds and Insurance” clause in the enclosed Appendix A, Argonne Terms and Conditions for Fixed-Price Construction Contracts (Enclosure No. 1. B.), will be required of your company before physical work at the site commences. In accordance with paragraph (g) of “Bonds and Insurance” clause, all policies shall provide by appropriate https://teams.microsoft.com/l/meetup-join/19%3ameeting_NjM4NjQ5MjEtMmQ5OS00Y2MwLTgwYzgtNjY5NjE2NDA2Yjc5%40thread.v2/0?context=%7b%22Tid%22%3a%220cfca185-25f7-49e3-8ae7-704d5326e285%22%2c%22Oid%22%3a%229b72af6c-8726-4904-ac4c-034d30a8e406%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_NjM4NjQ5MjEtMmQ5OS00Y2MwLTgwYzgtNjY5NjE2NDA2Yjc5%40thread.v2/0?context=%7b%22Tid%22%3a%220cfca185-25f7-49e3-8ae7-704d5326e285%22%2c%22Oid%22%3a%229b72af6c-8726-4904-ac4c-034d30a8e406%22%7d language that UChicago Argonne, LLC, the University of Chicago, and the United States Government are additional insureds, that the insurance afforded by such policies is primary insurance, and that all rights of the insurer for contribution from other insurers of UChicago Argonne, LLC, the University of Chicago and the United States Government are waived.
7. DAVIS-BACON COMPLIANCE
The minimum wages paid laborers and mechanics engaged in construction work within the scope of this request shall be in accordance with the U.S. Department of Labor minimum wage determination in effect on the date of the solicitation (see the applicable Labor Standards clauses in the enclosed Appendix A - Enclosure No. 1. B.). The appropriate determination will be attached to the contract as “Appendix-Wage Rates.” A sample copy of “Appendix-Wage Rates” setting out the wage rates now in effect is included with this RFP (Enclosure No. 1. F.). Enclosure No. 5, below, provides a detailed explanation for the method in which contractors are required to submit certified payrolls. Argonne currently holds the licensing agreement with LCPtracker and the use of its system will be free to all contractors and/or subcontractors
8. ILLINOIS OCCUPATION AND USE TAXES
Any resulting contract will be exempt from Illinois Occupation and Use Taxes.
9. NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS
All offers shall be in compliance with FAR 52.225-9 Buy American – Construction Materials, FAR 52.225-140 Notice of Buy American Requirement – Construction Materials, and FAR 52.225-11 Buy American – Construction Materials under Trade Agreements of Appendix A. In accordance with the terms of Appendix A, all offerors shall appropriately identify and notify the Procurement Official of any foreign construction material planned for use under this requirement as soon as it is anticipated and with the submission of the offer. Form ANL-BAA-CM (February 21, 2022) is included with the RFP for use if needed.
10. PAYMENT BOND
If the contract exceeds $35,000.00, the successful offeror will be required to furnish Argonne with a
Payment Bond (Enclosure No. 1. G.) within (10) calendar days after the effective date of the contract in a form and with sureties satisfactory to Argonne. (see the “Bonds and Insurance” clause and the “Additional Bond Security” clause in the enclosed Appendix A (Enclosure No. 1. B.).
11. PERFORMANCE BOND
If the contract exceeds $150,000.00, the successful offeror will be required to furnish Argonne with a
Performance Bond (Enclosure No. 1. H.) within (10) calendar days after the effective date of the contract in a form and with sureties satisfactory to Argonne. (see the “Bonds and Insurance” clause and the “Additional Bond Security” clause in the enclosed Appendix A (Enclosure No. 1. B.).
12. SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS
(1) Proposals and modifications to proposals shall be submitted electronically to the Procurement
Specialist Rob K. Kman (kman@anl.gov).
(2) The first page of the proposal must show--
(i) The solicitation number;
(ii) The name, address, and telephone and email address of the offeror; and
(iii) Name, title, and signature of person authorized to sign the proposal.
(3) Late proposals and revisions.
Any proposal received at the designated email in the solicitation after the exact time specified for receipt of offers will not be considered unless it is received before award is made and it is in the best interest of the Laboratory.
(4) Proposals submitted in response to this solicitation shall be in English and in U.S. dollars, unless otherwise permitted by the solicitation.
(5) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
(6) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Laboratory Procurement Official.
13. SAFETY PERFORMANCE REQUIREMENTS
Offerors and their subcontractors shall have a record of good safety performance in order to be determined responsible and, therefore, eligible for contract award by the Laboratory.
14. PRE-AWARD SURVEY
The Laboratory may conduct a pre-award survey to confirm any information furnished by the apparent successful offeror. The Laboratory may also require other evidence such as, but not limited to, said offeror’s managerial, financial, technical, safety and other capabilities, the existence of which the Laboratory determines is necessary for the successful performance of the contract.
The apparent successful offeror must affirmatively demonstrate its responsibility, and, if requested by the Laboratory, the responsibility of its proposed subcontractors.
15. SUBCONTRACTING PLAN (IF APPLICABLE)
The Laboratory will require submittal of a subcontracting plan in accordance with Clause entitled, “Small Business Subcontracting Plan” of the Appendix A Argonne Terms and Conditions for Fixed Price Construction Contracts from the successful offeror. The Laboratory will examine the plan to determine its acceptability. The accepted plan will be incorporated into any resultant contract. The requirement for submittal of a subcontracting plan does not apply if the successful offeror is a small business concern. The Procurement Official will notify the successful offeror when the small business plan should be submitted.
16. PROPOSAL SUBMITTAL INSTRUCTIONS AND OTHER ADMINISTRATIVE ITEMS
Enclosure No. 1, below, represents the anticipated contractual vehicle format, including standard terms and scope of work.
These enclosures are provided for your company’s information and review only. Unless otherwise negotiated, it is anticipated that said terms will be incorporated into any resultant agreement. Request for waivers or deviations from any terms or conditions must be specified in writing along with justifications for deletion or waiver. Excessive exceptions may be grounds to deem an offer non-responsive.
Your attention is directed to the enclosed documents which constitute requirements for this RFP and should be fully complied with as indicated. Note that this is a Request for Proposal, not a contract.
Argonne will award a contract to the responsible offeror whose offer, by conforming to the solicitation, will be most advantageous to Argonne, considering only price and the price-related factors specified elsewhere in the solicitation.
Argonne reserves the right to accept or reject any or all proposals if that is determined to be in the best interest of Argonne. Award may be made without discussion; and hence, your company’s proposal should be submitted initially on the most favorable terms. It is brought to your company’s attention that the authorized Argonne Procurement Official is the only individual who can legally commit Argonne to the expenditure of funds in connection with this proposed procurement. This RFP does not commit Argonne to pay any cost for the preparation and submission of a proposal.
Your proposal should be submitted in accordance with Instructions for Preparation of Proposals and Notice to Offerors dated May 1, 2023 (Enclosure No. 5). Your pricing proposal shall be submitted on the enclosed Proposal Form dated May 1, 2023. (Enclosure No. 7) and should include acknowledgment of all amendments/addenda issued under this RFP. Electronic submission of offers is required.
The following three (3) documents shall be fully executed and returned with your proposal:
• Enclosure No. 2 - “Pre-Award Information” including “Booklet of Representations and
Certifications”, ANL 70-B. If any item in Enclosure No. 2 does not apply, please mark N/A.
• Enclosure No. 3 - Argonne National Laboratory Contractor Safety Information Questionnaire, PFS-525.
• The 3 separate part Best Value proposal documents:
o Part I Technical Proposal shall contain adequate information addressing all technical criteria identified in Enclosure No. 4.
o Part II Business/Management Proposal shall contain financial capability statement including requested documentation, acceptance of the proposal period, list of authorized representatives, Subcontracting Plan, and identification of any exception/deviation.
See details in Enclosure No. 5.
o Part III Cost/Price Proposal shall contain the completed Enclosure No. 7.
Your proposal should be submitted electronically to Rob K. Kman (kman@anl.gov) on or before 3:00pm CST, Friday May 26, 2023.
Your offer should be effective for a period of One Hundred Twenty (120) days from the proposal due date. If you have any questions pertaining to this RFP, contact Rob K. Kman (kman@anl.gov) Phone (630-252-6488).
Enclosure No. 1: (Contract Articles and Special Provisions applicable to any resultant contract):
A. Sample Fixed-Price Construction Contract, ANL-21(February 23, 2011) amended for RFP No. 3-B157-
00205-00.
B. Appendix A, Argonne Terms and Conditions for Fixed-Price Construction Contracts, ANL-526 (04-07-
2023).
C. Appendix B, Affirmative Action Requirements, PD-115 (May 2001).
D. Appendix C, Drawings and Specifications entitled, “100 Area Demolition”, Rev 0, dated 05/01/2023.
E. Appendix D-8-Construction, Intellectual Property Provisions - Construction Requiring Delivery of Data
PD-101 (June 2020)
F. Appendix E, Wage Rates General Decision Number IL20230008, Modification No. 2, dated 1-20-23, General Decision Number IL20230011, Modification No. 3, dated 4-7-23, G. Form ANL-22, Payment Bond (October 31, 2006). (Do not complete at this time, for reference only)
H. Form ANL-24, Performance Bond (October 31, 2006). (Do not complete at this time, for reference only)
I. Certificate of Labor Compliance, ANL-564 (5/97). (Do not complete at this time, for reference only)
J. U.S. Department of Labor Payroll Form, WH-347 (Nov 1998) and Instructions for completion. (Do not complete at this time, for reference only)
K. Applicable Safety Documents
a) Activity Hazards Analysis Rev.3
b) Construction Safety Program Requirements Rev. 4_AU2, dated March 21, 2023
c) Site-Specific Construction Safety Plan Rev.2 _AU2, dated March 21, 2023
d) Summary of Argonne Specific Requirements Rev. 2_AU2
L. Model Small Business Subcontracting Plan, PD-135 (January 20, 2023). (The Procurement Official will advise when this submission is required). (IF APPLICABLE).
Enclosure No. 2: “Pre-Award Information” including “Booklet of Representations and Certifications”, ANL 70-B (06/06/2022).
Enclosure No. 3: Argonne National Laboratory Contractor Safety Information Questionnaire, PFS-525 (8/05).
Enclosure No. 4: Evaluation Criteria dated 05/01/2023.
Enclosure No. 5: Instructions for Proposal dated 05/01/2023.
Enclosure No. 6: LCP Tracker System Information dated March 17, 2015.
Enclosure No. 7: Proposal Form dated 05/01/2023.
Sincerely, Rob K. Kman Procurement Specialist 3/Procurement Official kman@anl.gov
(630) 252-6488
SOURCE TITLE AND DATE
Appendix B Appendix B - Affirmative Action Requirements (05/03/01) Appendix D8 Construction Appendix D8 Construction Intellectual Propert (06/29/20) Special CI-SBSubcontract Plan
Small Business Subcontracting Plan MODEL (01/20/23)
Appendix A-Construction Appendix A Fixed-Price Construction Terms and (04/07/23)
(THIS PAGE IS INTENTIONALLY LEFT BLANK)