About this file
This Request for Proposals is issued by the Geological Survey of Alabama (GSA) for professional drilling services to install two new groundwater monitoring wells, remediate one existing well, and conduct aquifer testing in Baldwin County, Alabama. The project aims to expand GSA's groundwater monitoring capabilities and obtain information regarding well performance and aquifer hydraulic characteristics. The two monitoring wells (Magnolia Springs well #1 and well #2) require installation to a depth of approximately 65 feet below ground surface with nominal 4-inch-diameter Schedule 80 PVC casing and factory-slotted screen with 0.010-inch openings. The existing Gulf Shores well (003DDD14003) requires sediment and debris removal to restore accessible well depth. All three wells require aquifer testing conducted as continuous pumping tests until water levels stabilize or for six hours, whichever occurs first, with measurements recorded according to a specified schedule and in compliance with ASTM D4043-17 standards. GSA intends to award one contract to a single supplier. Written questions must be submitted by November 17, 2026, at 5:00 p.m. CST, and all proposals must be submitted electronically through Alabama Buys and as printed copies by mail or courier by November 30, 2026, at 4:30 p.m. CST. The contract will commence upon the Governor's signature and continue for up to 24 months.
Proposals should be submitted on a time and materials basis with itemized costs for each well and service, including equipment rental fees, mobilization rates, daily rig costs, personnel costs, and material costs. Evaluation criteria include specialized expertise and proposed methods (25 points), time and materials cost information (20 points), available resources (15 points), past performance and ability to meet deadlines (15 points), project management techniques (10 points), experience with similar projects (10 points), and availability and familiarity with the project locale (5 points). Respondents must submit a completed Alabama Vendor Disclosure Statement and be registered in Alabama Buys to submit proposals and be awarded contracts. The submission must include a signed proposal from an authorized representative. No set-asides are identified in this RFP. Contract award is subject to availability of funds and GSA's discretion, and no final selection is binding until execution of a written negotiated agreement signed by GSA, the Chief Procurement Officer, the Legislative Oversight Committee, and the Governor. Respondents must certify compliance with Alabama boycott laws and federal immigration law requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP Non Professional Services Boilerplate 8.12.26.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSALS FOR PROFESSIONAL SERVICES BY THE
GEOLOGICAL SURVEY OF ALABAMA FOR INSTALLATION OF
MONITORING WELLS, WELL REMEDIATION, AND AQUIFER TESTING
THE GEOLOGICAL SURVEY OF ALABAMA (GSA), pursuant to this Request for Proposals for Professional Services (RFP), is soliciting proposals from qualified professional drilling companies to install two new groundwater monitoring wells, remediate an existing well, and conduct pumping and recovery tests at the three identified wells. Additional wells that may qualify for these services may be added as they are identified by GSA staff as funds allow.
The purpose of this project is to expand and improve GSA’s groundwater monitoring capabilities in Baldwin County, Alabama, and obtain information regarding well performance and aquifer hydraulic characteristics. The locations, available construction records, and specific requirements for each well are provided in the Scope of Work. The GSA intends to award one contract for the services described in this RFP.
SCOPE OF WORK
This Scope of Work outlines details of the GSA monitoring well installation, remediation, and aquifer testing project that a prospective supplier should use to prepare a response to this RFP.
Well Locations and Required Services
The wells to be addressed under this RFP, their approximate locations, and the required services are identified in the table below.
Well Designation Approximate Location Services
Magnolia Springs well #1, near Magnolia River
30.3995, -87.7426* Installation and aquifer testing
Magnolia Springs well #2, near Magnolia Springs
30.3997, -87.7762* Installation and aquifer testing
Gulf Shores / 003DDD14003 30.25564, -87.64563 Remediation and aquifer testing
*Exact locations for the two proposed monitoring wells will be designated by GSA at the start of the project.
Requirements to Install Monitoring Wells
Unless specified otherwise, the supplier shall comply with the following requirements regarding installation of the two monitoring wells identified in this RFP:
1. Each well shall be drilled to an approximate depth of 65 feet below ground surface.
Exact drilling locations will be designated by GSA at the start of the project.
2. Each well shall be constructed using nominal 4-inch-diameter Schedule 80 PVC casing and factory-slotted Schedule 80 PVC screen with 0.010-inch openings. Each well shall have approximately 10 feet of screen, with an anticipated screened interval of 55 to 65 feet below ground surface. The final screened interval shall be approved by GSA based on the water-bearing materials encountered during drilling.
3. A clean 20/40 silica sand filter pack shall surround the screen and extend at least 2 feet above the screened interval. Alternative screen slot sizes and filter-pack gradations shall require GSA approval based on formation materials encountered during drilling.
4. A bentonite seal at least 2 feet thick shall be placed above the filter pack and hydrated according to the manufacturer’s instructions before grouting.
5. Following hydration of the bentonite seal, the remaining annular space shall be grouted to ground surface using neat cement grout or a GSA-approved cement-bentonite grout.
The supplier shall identify the proposed grout formulation in its proposal. Grout shall be placed by tremie from the bottom upward using procedures that prevent damage to the PVC casing.
6. The PVC casing shall extend 3 feet above ground surface and shall be fitted with a removable well cap. A square concrete pad measuring at least 3 by 3 feet and at least 4 inches thick shall be installed around each well, with the well centered in the pad. The finished pad shall slope away from the casing to promote drainage. The GSA will install the monitoring equipment following well completion.
7. Four PVC marker posts shall be installed around each well, outside the concrete pad.
Posts shall extend approximately 3 feet above ground surface and be securely embedded in the ground. Each post shall have a capped top and high-visibility markings. Placement shall allow access for well maintenance, aquifer testing, and installation of GSA monitoring equipment.
8. Each well shall be developed after the grout has sufficiently cured and before aquifer testing, using surging and pumping or another GSA-approved method. Development shall continue until turbidity is 10 NTU or less, including following a pumping stop and restart cycle. If turbidity stabilizes above this target, the supplier shall notify GSA for approval of further development methods, duration, approximate volume removed, pumping rates, and final turbidity.
9. The supplier shall provide a well construction record for each completed well, including total depth, materials encountered during drilling, casing and screen specifications, screened interval, filter pack and seal placement, grout formulation and placement, development records, and measured static water level.
Requirements to Remediate Existing Wells
Unless specified otherwise, the supplier shall comply with the following requirements regarding remediation of the one existing well identified in this RFP:
1. The supplier shall remove accumulated sediment and debris from the Gulf Shores well, GSAID 003DDD14003, to restore accessible well depth to the extent practicable under existing well conditions. Reported depth is 413 feet below ground surface. This depth is provided for reference; actual depth, construction, and current conditions have not been verified.
2. Proposed removal methods shall be described in the proposal and are subject to GSA approval before work begins.
3. The supplier shall measure and record the accessible depth of the well before and after remediation, using a consistent, documented measuring point.
4. The supplier shall continue cleanout until the well bottom is reached or further removal is prevented by an obstruction or well condition. If further cleanout is prevented, the supplier shall notify GSA and document the condition encountered, work performed, and basis for recommending cleanout cessation. Acceptance of an alternative completion depth or termination of cleanout shall require GSA approval.
5. The supplier shall provide documentation of the methods used, work performed, accessible depths measured before and after remediation, and conditions that affected the work.
6. Remediation of the Gulf Shores well shall be completed before aquifer testing.
Requirements to Conduct Aquifer Tests
Unless specified otherwise, the supplier shall comply with the following requirements regarding aquifer testing of the three wells identified in this RFP:
1. The supplier shall install a pump capable of discharging an adequate volume of water to induce measurable drawdown in each well.
2. The supplier shall pump Magnolia Springs well #1, Magnolia Springs well #2, and the
Gulf Shores well to perform a continuous aquifer test until water levels in the well have stabilized, or for 6 hours, whichever comes first. The test will be conducted as outlined in standards described in ASTM D4043-17 “Standard Guide for Selection of Aquifer
Test Method in Determining Hydraulic Properties by Well Techniques.”
3. The supplier shall record accurate elapsed time and water level measurements throughout the test. Readings will be taken every 2 minutes for the first hour, every 5 minutes for the next hour, every 10 minutes for the next 2 hours, and every 30 minutes for the remainder of the test.
4. The supplier shall record elapsed time and recovery water level measurements following the same schedule, designated in item 3, until the water level in the well returns to static condition.
5. The supplier shall provide a report, in Word, Excel, or PDF format, to the GSA that contains the results of the aquifer test, including test date, test start time and static water level, elapsed time, water level measured, drawdown, discharge rate, estimated specific capacity, type and size of pump used, and pump setting information.
Recommended procedures to conduct the pump test and assess the groundwater recovery condition are subject to approval of the GSA Groundwater Assessment Program Director. Removal of any monitoring equipment, if there is any monitoring equipment installed prior to testing, will be the responsibility of GSA.
PROPOSAL TERMS AND CONDITIONS
Qualified Proposals
Qualifying proposals must provide all requisite information under this RFP and clearly and specifically respond to the items set forth in this RFP. Proposals should address the entire scope of work. The GSA intends to recommend to the Chief Procurement Officer (CPO), as the awarding authority, a single contract to one supplier under this RFP.
Unnecessarily elaborate brochures or other presentation materials beyond those sufficient to present a complete, concise, and effective proposal are discouraged.
Submission Requirements
1. If more than one entity is responding to this RFP under a single proposal, list all entities that are part of the proposal and/or will perform services pursuant to the Scope of Work.
For each entity listed, clearly define its areas of expertise and proposed administrative and technical duties and responsibilities as well as applicable professional licenses held by the entities and personnel proposed to perform the work. Identify the lead entity responsible for coordinating the work and contracting with GSA.
2. Suppliers are required to submit their proposals electronically through Alabama Buys. The proposal must be signed by an authorized representative of the Respondent’s organization.
Proposals received by mail or hand delivery without a corresponding submission in
Alabama Buys cannot be evaluated and will be deemed nonresponsive.
3. Suppliers are also required to submit a printed copy of their proposal by mail or hand delivery. Printed versions shall be submitted in a sealed envelope or package. All submissions become property of GSA and will not be returned. Only information submitted by the supplier through Alabama Buys may be considered during the evaluation process; if additional information is provided in the printed version that is not provided in the version submitted to Alabama Buys, said information will not be considered during evaluations.
4. Paper size shall be 8½ inches by 11 inches. Text shall not be smaller than a font size of 12.
5. The proposal shall explain the Respondent’s interest in providing the requested services, identify proposed personnel and their qualifications, and provide a comprehensive description of the proposed approach to the work. The description shall include proposed methods, equipment, project management procedures, and a schedule for completing the services.
6. The proposal shall provide examples of similar work performed by the Respondent and proposed team members. For each project, provide information regarding quality of work and ability to meet budgets, schedules, deadlines, and performance requirements.
7. The proposal should be submitted on a time/materials basis. Time/Materials items should be itemized for each well and each required service to include, but not be limited to, equipment rental fees, mobilization rates, daily rig costs, personnel costs, cost basis for third party contractor(s), and cost basis for materials.
8. Respondents shall submit a completed Alabama Vendor Disclosure Statement. The form is available at https://www.alabamaag.gov/forms.
9. Suppliers must be registered in Alabama Buys to submit a proposal and be awarded a contract (https://alabamabuys.gov/).
10. GSA reserves the right, in its sole discretion, to waive minor defects or variations of a proposal from the exact requirements set forth herein that do not give one submitter an advantage or benefit not enjoyed by other submitters.
Further Information
Any questions must be submitted in writing and emailed to the following:
Greg Guthrie
Groundwater Assessment Program Director
GGuthrie@gsa.state.al.us
Subject line shall read: “Question – RFP for Monitoring Well Installation, Existing Well
Remediation, and Aquifer Testing.”
Written questions must be submitted no later than November 17, 2026, by 5:00 p.m. CST.
Questions concerning this RFP, along with answers, will be posted in Alabama Buys.
Submission Deadline
All submissions must be received no later than November 30, 2026, by 4:30 p.m. CST.
It shall be the sole responsibility of the Respondent to ensure submission of the proposal to
Alabama Buys and physical delivery of the printed version prior to the deadline. Email or facsimile submissions will not be accepted.
Proposal submissions shall be delivered to the following U.S. Postal Service mailing address:
Geological Survey of Alabama
Attention: Cassandra Nelson
P.O. Box 869999
Tuscaloosa, AL 35486-6999 https://www.alabamaag.gov/forms https://alabamabuys.gov/ mailto:GGuthrie@gsa.state.al.us
Or to the following physical address for non-U.S. Postal Service couriers:
Geological Survey of Alabama
Attention: Cassandra Nelson, Room 202
420 Hackberry Lane
Tuscaloosa, AL 35401
Withdrawals and Modifications of Proposals
Proposals may be modified or withdrawn in writing prior to the proposal deadline specified herein.
Proposals may not be modified or withdrawn after that time and will not be returned. If a
Respondent no longer wishes to have its proposal considered subsequent to the proposal deadline, notice to that effect must be submitted in writing.
EVALUATION PROCESS
Proposals meeting the minimum requirements of this RFP will be evaluated using the following criteria. Weights are provided in parentheses and total 100 points.
1. The Respondent has specialized expertise as demonstrated by the proposed methods (25).
2. The Respondent has provided time/materials cost in the proposal (20).
3. The Respondent has the resources available to perform the requested services (15).
4. The Respondent has demonstrated evidence of past performance and ability to meet project deadlines (15).
5. The Respondent has provided project management techniques (10).
6. The Respondent has the ability and history of handling similar projects (10).
7. The Respondent has availability and familiarity with the project locale (5).
NO COMMITMENT OF FUNDS
Any contract award related to this proposed project is subject to the availability of funds and/or the needs of the GSA. Accordingly, the GSA, at its discretion, may or may not issue a final contract as a result of this RFP. Furthermore, even in the event an initial selection is made by the GSA, no selection is final until full execution of a written negotiated agreement detailing final terms and an agreed upon scope of work. If the GSA deems, at its sole discretion, that a satisfactory agreement cannot be reached in accordance with an initial selection, the GSA reserves the right to proceed with efforts to make another selection based upon proposals submitted pursuant to this RFP, issue another RFP, or terminate efforts to obtain assistance as to some or all services described herein.
Any contract issued as a result of this RFP will begin on the date of the Governor’s signature and continue for a period of up to 24 months. In addition to signatures of representatives of GSA and supplier, the contract must also be signed by the CPO, the Legislative Oversight Committee, and the Governor.
NON-DISCRIMINATION
The GSA does not discriminate on the basis of race, color, religion, age, gender, pregnancy, national origin, genetic information, veteran status, or disability in its hiring or employment practices nor in admission to, access to, or operations of its programs, services, or activities.
COMPLIANCE WITH ALABAMA BOYCOTT LAWS
In compliance with Act 2016-312, supplier hereby certifies that it is not currently engaged in, and will not engage in, the boycott of a person or an entity based in or doing business with a jurisdiction with which this state can enjoy open trade.
In compliance with Act 2023-409, supplier hereby certifies that, without violating controlling law or regulation, supplier does not and will not, during the term of the agreement engage in economic boycotts as the term “economic boycott” is defined in Section 1 of Act 2023-409.
IMMIGRATION
By submitting a proposal, the Respondent represents that he/she and the business entity he/she represents is not in violation of federal immigration law and has not knowingly employed, hired for employment, or continues to employ an unauthorized alien within the State of Alabama.
SUBMITTALS PUBLIC RECORDS
All proposals submitted in accordance with the deadline set forth in this RFP will be retained and can become public records following final selection, if any, pursuant to this RFP or final determination by GSA not to proceed with a selection pursuant to this RFP.
| Scope of Work |
| Well Locations and Required Services |
| Requirements to Install Monitoring Wells |
| Requirements to Remediate Existing Wells |
| Requirements to Conduct Aquifer Tests |
| Proposal Terms and Conditions |
| Qualified Proposals |
| Submission Requirements |
| Further Information |
| Submission Deadline |
| Withdrawals and Modifications of Proposals |
| Evaluation Process |
| No Commitment of Funds |
| Non-Discrimination |
| Compliance with Alabama Boycott Laws |
| Immigration |
| Submittals Public Records |
File details come from the government source that posted it. Updated .