This document is an Addendum No. 3 to the Request for Proposal (RFP) #FP-2024-08 issued by Eastern Oregon University (EOU) Facilities & Planning Department for Design Build (DB) Services for the North & Daugherty Halls Envelope project. The addendum provides changes and clarifications to the original RFP, including the removal of the requirement for a Price Proposal and the selection process being Qualifications Based. It also modifies the requirements for describing the A/E team approach and subcontractor/subconsultant procurement.
The project involves programming, design, and construction services for the replacement of the building envelopes (siding and windows) of the North and Daugherty Halls student dormitories on the EOU campus. There is no mention of response dates, due dates, site visits, bidder's meetings, award dates, or contract term.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
North & Daugherty Halls Envelope EOU Project Number FP#-2024-08 August 7, 2024
Design Build Services RFP Addendum No. 3
Eastern Oregon University Facilities & Planning Department
ADDENDUM NO. 3
EASTERN OREGON UNIVERSITY
RFP #FP-2024-08
North & Daugherty Halls Envelope
DESIGN BUILD (DB) SERVICES
Addendum No. 3 to the Request for Proposal (RFP) is hereby submitted for use in proposal preparation and submittal.
All changes, additions, and/or deletions are hereby made as part of EOU North & Daugherty Halls Envelope as fully and completely as if the same were entirely set forth in the RFP #FP-2024-08. Changes and additions are noted in underlined italics, deletions are noted in strikethrough.
RFP #FP-2024-08
REQUEST FOR PROPOSAL
Price Proposal
All Sections that reference a Price Proposal or Attachment C as the Price Proposal (2.5.1, 3.15, 6.2.1, 6.7.1, etc.) are removed. There is no Price Proposal, selection is Qualifications Based. Attachment C is the Certa Building Envelop Condition Assessment.
Section 3.5.1.1 A/E Team Approach
Modify Section 3.5.2.2 as shown:
3.5.1.1 A/E Team Approach.
The Owner recognizes the importance of the entire design-build team, including the A/E subconsultants. Describe how the A/E team will integrate into the project and highlight the unique approaches they will bring during programming and pre-construction services that will allow the
Owner to evaluation the feasibility of various options and understand their potential impacts on cost and schedule. specialty design-build subcontractors. For those subcontractors and subconsultants not proposed as part of the Design-Build Team,
a. Describe the Design-Build Team’s overall approach to subcontractor and subconsultant procurement for the Project.
b. Identify the challenges in the selection of subcontractors and subconsultants for the Project and how the Design-Build Team will address those challenges.
c. If applicable, describe in detail the Design-Build Team’s approach to early subcontractor involvement, including proposed design-build and design-assist subcontractors, and identify which scopes of Work are candidates for design-build or design-assist subcontracts.
By: John Garlitz, Director of Facilities Date: August 7, 2024