Summary: Request for Proposal for Construction Management Services
This is a Request for Proposal (RFP) issued by the Central Contra Costa Sanitary District for construction management and inspection services for the Ultraviolet Disinfection Replacement Project (District Project 100012) at the District's wastewater treatment plant in Martinez, California. The original submittal deadline of October 2, 2026 was extended to November 13, 2026 at 5:00 PM PT via the PlanetBids portal. The project encompasses a 4-5 year construction period beginning mid-2027 with an overall budget of approximately $101 million. The RFP requires proposers to address preconstruction services (constructability reviews, cost estimating, scheduling) and construction phase services (construction management, inspection, and optional safety compliance officer roles). A virtual pre-proposal meeting was held on September 2, 2026, with a deadline for consultant questions set for November 2, 2026, and responses anticipated by November 6, 2026. Central San anticipates selecting the top three scoring firms for interviews in December 2026, with the Board considering the final award in January 2027 and Notice to Proceed expected in February 2027. The agreement duration is five years.
Compensation will be determined on an hourly rate basis with a firm cost ceiling established during contract negotiations. The selected consultant must submit invoices electronically via Procore or email to cppayables@centralsan.org, with payment made within 30 calendar days of invoice receipt. Central San will provide construction trailers, office facilities, utilities, Procore system administration, and electronic document access. Consultants are responsible for mobilizing staff, providing personal protective equipment, obtaining all necessary licenses and permits, and maintaining all required insurance coverage. Proposers must demonstrate minimum qualifications including ten years of business experience in wastewater consulting, prior construction management of at least five projects exceeding $25 million, completion of at least two wastewater treatment plant projects within the past five years involving civil, mechanical, electrical, and controls work, and proficiency with Procore. Key team members including the construction manager, inspectors, scheduler, cost estimator, and optional safety compliance officer must meet specific experience and certification requirements. Disqualifying factors include evidence of collusion, prior unresolved disputes with Central San, incorrect proposal information, and previous contract defaults.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| UV Improvements CM RFP Pre-submittal Meeting 9-21-26 Slides.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL (RFP)
CONSTRUCTION MANAGEMENT SERVICES
FOR THE
ULTRAVIOLET DISINFECTION REPLACEMENT,
DISTRICT PROJECT 100012
October 13, 2026
The original submittal deadline of October 2 is being extended to
November 13. Proposals already submitted may be updated, withdrawn, or retained as submitted and will be reviewed after the new deadline. Please contact Mark Wenslawski with questions.
Submittal Deadline: 5:00 PM PT, November 13, 2026 via PlanetBids
Central San Contact (Email): Mark Wenslawski
(mwenslawski@centralsan.org)
Central Contra Costa Sanitary District Request for Proposal for Construction Management Services
Table of Contents Introduction
Summary
Tentative Schedule
Scope of Services
General
Task 1. Preconstruction Services
Task 2. Construction Phase Services
Requests for Proposals (RFP)
Proposal Requirements
Desired Qualifications
Requests for Information
Pre-Proposal Meeting
Submission of Proposals
Withdrawal or Modification of Proposals
Rights of Central San
Selection Criteria
General Requirements
Anti-Collusion
Disqualification
Non-Conforming Proposal
Gratuities
Conflict of Interest
Disclosure(s)
Reserved Rights
Artificial Intelligence (AI) Use
Attachment A – Project Overview
Attachment B – Sample Agreement and Insurance Requirements
Attachment C – Proof of Insurance Coverage and Acknowledgment of Sample Agreement Terms and Conditions
Attachment D - Memorandum on Compliance and Procedures for Government Code Section 1090 for Agreements
Introduction Summary The Central Contra Costa Sanitary District (Central San) is soliciting Request for Proposals (RFP) from qualified consulting firms interested in providing services for both construction management and inspection for the Ultraviolet (UV) Disinfection Replacement Project, District Project 100012. Construction is expected to start in mid- 2027 and take four to five years, with an overall project budget of approximately $101M (See Attachment A – Project Overview). This project is located at Central San’s wastewater treatment plant in Martinez, California.
This RFP will outline the evaluation and selection process for the consultant’s qualifications, proposal, and interview. Central San anticipates selecting only the top three (3) scoring consulting firms to interview based on the sum of the qualification and proposal scores. Final selection of the top-ranked consultant will be based on the sum of the qualification, proposal, and interview scores.
This RFP does not commit Central San to pay any costs incurred in the preparation and presentation of submittals or to select any interested firms who respond.
This RFP, including this document, questions and answers, addenda, submitting proposals, and other relevant documents, will be available and managed exclusively via Central San’s bid portal, PlanetBids, at the following link:
https://vendors.planetbids.com/portal/14663/bo/bo-detail/145969
This RFP is also accessible through Central San’s construction website, www.centralsan.org/construction, under the Notice to Contractors section.
Tentative Schedule Central San has established the following target dates for evaluation and scheduling purposes. The following dates are tentative, non-binding, and are subject to change without prior notice.
• RFP Advertisement ................................................................ Sept. 8 – Nov. 13, 2026 o Pre-Proposal Meeting……………………………………………………..Sep. 2, 2026 o Deadline for Consultants to Submit Questions ................................... Nov. 2, 2026 o Anticipated Deadline to Respond to Questions ................................. Nov. 6, 2026 o Proposal Submittal Deadline ........................................................... Nov. 13, 2026
• Proposal Review & Selection o Interviews ..................................................................................... December 2026 o Board to consider award(s) .............................................................. January 2027
• Notice to Proceed ................................................................................ February 2027
• Agreement Duration .........................................................................................5 years https://vendors.planetbids.com/portal/14663/bo/bo-detail/145969 http://www.centralsan.org/construction
Scope of Services
General
A. Overview
The Construction Manager (CM), Resident Engineer (RE), and Construction Inspector (CI) are Central San representatives serving as advisors and consultants on construction matters related to the work. Activities during construction will be approached as a team effort, with Central San or its representative leading overall.
All instructions to the Contractor and all communications from the Contractor to Central San or the Design Engineer are routed through the CM. The CM is expected to make initial decisions on questions that may arise regarding the quality or acceptability of materials furnished and work performed, and the manner of performance and rate of progress of the work. The CM is also expected to interpret the Contract's intent and meaning and make initial decisions regarding the Contractor's performance under the Contract and the Contractor's entitlement to compensation.
Depending on the expertise of the selected Proposer, Central San reserves the right to implement a different arrangement of assignments and responsibilities between Central San staff and the Proposer. Whenever Central San determines that it would be in the best interests of the individual project, Central San reserves the right to: 1) use qualified Central San staff or other consultants to provide construction management services; 2) direct the Consultant to integrate qualified Central San staff into their team; or 3) add or subtract scope during contract negotiations and the duration of the contract.
B. Provided by Central San
The following will be provided by Central San to the selected Proposer:
• Construction trailers and restrooms, including office furniture and desks, fridges, microwaves, coffee machines, utilities, and maintenance of the facilities.
• Guest WIFI access is readily available at Central San’s Martinez Campus.
• Procore system administration, including creation of project utilizing the Central San Template and creation of user accounts for the Consultant under Central San’s account, which will be assigned to appropriate roles and permissions.
• Electronic document access. Central San will upload bid documents into Procore, including Front End and Technical Specifications, Drawings, Appendices, addenda (if applicable), and executed Construction Contract Documents with the Bid Schedule.
• Upon request, hard copies of Bid Documents (including ½ size drawings).
C. Procore Usage Mandate
The consultant is required to manage the entire project within Central San’s Procore account, ensuring real-time access to:
• Documents: Drawings, Specifications, Submittals
• Communication: RFIs (Request for Information), Project Emails
• Project Controls: Daily Logs, Meetings & Minutes, Inspections, Punchlist, Schedules, Photos
• Financials: Change Requests, Change Events, Payment Requests
D. On-Site vs. Remote Services
Construction Management personnel are expected to be primarily on-site during active construction. Limited remote/virtual/telework may be permitted for preconstruction activities, project closeout activities, or other tasks that do not require an on-site presence, subject to approval by Central San. Refer to each Task for specific requirements.
E. Mobilize
The Consultant shall be responsible for mobilizing all necessary staff to and from the project site(s). The Consultant shall prepare, equip, and stock the field office with any additional office equipment not covered in existing trailers and required to complete the work. The Consultant will be compensated for additional equipment as a direct cost, plus other direct costs (ODC), with an ODC markup limited to 15%.
The Consultant is responsible for providing and maintaining smartphones or smart devices with cellular service, computers or laptops, digital cameras, and any other tools or devices required by its personnel for the duration of the construction project(s), including other consumable supplies.
Vehicle use, if required, will be compensated on a mileage or daily-rate basis for authorized site and off-site use. No mileage will be paid for commuting to Central San from home or a home office.
F. Safety Equipment
The Consultant shall be responsible for providing all necessary personal protective equipment (PPE), including hard hats, boots, lights, and other safety equipment, to its team. Compensation for this equipment will be included in the hourly rate multiplier unless otherwise approved by Central San.
G. Safety Training
The Consultant shall provide all necessary safety training required for its employees, visitors, or subconsultants. Central San requires an on-site Treatment Plant Safety Awareness Training for all employees working at its facilities.
H. Licensing
For any work that requires licensing, the Consultant shall be appropriately licensed in accordance with the laws of the State of California. The cost of any required licenses or permits shall be the responsibility of the successful Proposer.
I. Weekly Progress Meetings
Appropriate Consultant staff shall attend weekly progress meetings with the Contractor, Central San staff, and the CM team throughout the construction process.
The Consultant shall prepare agendas and minutes or status reports using Procore for all weekly and other project-related meetings.
J. Overtime
Overtime shall be authorized in advance by the Central San Project Manager, except in emergency or urgent situations. In such circumstances, Consultant shall notify Central San’s Project Manager as soon as possible, but no later than one business day following the occurrence.
Consultant shall adjust personnel shift schedules, to the extent practicable, to minimize the need for overtime.
Overtime shall not be authorized or compensated for time spent commuting to or from the job site.
K. Pay Requests
Unless otherwise authorized in writing by Central San, Consultant shall submit invoices electronically using the Submittals Tool in Procore, or to cppayables@centralsan.org. Requests for payment shall include backup information as specified in the agreement. (For additional information, see Attachment B.)
Central San will only pay for actual hours worked by Consultant’s personnel.
L. Reporting Structure
The Proposer selected shall act as Central San’s primary construction representative, advisor, and contract administrator, serving as the main communication channel between Central San and the Contractor for the UV Disinfection Replacement, District Project 100012. The Construction Manager observes and administers the work, including evaluating quality, progress, and compliance with the construction contract documents; making initial decisions on contract interpretation and performance; reviewing schedules and payment requests; managing and recommending change orders; and inspecting work and materials for conformance. The Consultant also supports Central San’s final decisions and approvals, including recommendations on work acceptability, substantial/final completion, and contract matters, while not assuming responsibility for the Contractor’s means, methods, sequencing, or safety. (See Attachment B, Exhibit D, Roles and Responsibilities).
Additionally, Central San may seek additional programmatic support for all construction occurring at Central San’s Martinez campus. The Programmatic Support Consultant serves as Central San’s program-level advisor and coordinator, supporting Central San in managing and integrating its active capital construction projects while Central San retains full ownership, authority, and decision-making mailto:cppayables@centralsan.org responsibility for the Capital Improvement Program. The Programmatic Support Consultant provides program-wide oversight and support across individual Project Construction Managers, including coordination of schedules, costs, risks, constructability, project interfaces, operations/shutdowns, commissioning, reporting, and asset handover to promote consistency and alignment among concurrent projects. The Programmatic Support Consultant does not replace or direct the individual Construction Managers and has no signature authority, but instead provides the program-level information, coordination, tools, and recommendations needed by Central San and the Construction Managers to make informed decisions and successfully deliver the overall program.
The proposed organizational structure is depicted below:
Task 1. Preconstruction Services
This task includes constructability reviews, cost estimating, and scheduling. Work under Task 1 may involve a mix of on-site and remote/virtual work, as appropriate for the effort and as approved by Central San.
The Consultant shall perform reviews of construction drawings and specifications at various levels of design, as assigned by Central San, with a focus on project constructability. At a minimum, the Consultant shall provide and log comments on the plans, specifications, and construction cost estimate. Comments should, at a minimum, include feedback on measurement and payment, sequencing, schedule, temporary facilities, constructability, and contractor qualifications. Central San will ultimately decide whether to include any or all comments provided by the consultant at its discretion.
The Consultant shall assist Central San during the bid period and may help in evaluating construction bids to determine the responsiveness or pricing of bid items.
Task 2. Construction Phase Services
Work under Task 2 must be completed on-site. Remote or virtual work will not be accepted unless explicitly authorized in writing, in advance, by Central San on a case-by-case basis.
All services below are expected to be performed on a timely basis, and response times shall be included in the scope of work.
A. Construction Management
The roles and responsibilities for this task include, but are not limited to, the following:
• Prepare, facilitate, and document the following meetings:
o Preconstruction meeting o Progress meetings for the duration of construction o Shutdown coordination meetings (as needed) o Asset handover meeting(s) o Closeout meeting
• Monthly Reports: Provide a monthly progress report summarizing the progress of the construction, schedule, cost, and issues encountered.
• Means and Methods of Construction: The consultant shall not direct the means and methods of construction. Contractors are solely responsible for the means and methods of construction. Concerns or suggestions regarding a contractor’s means and methods shall be communicated to Central San or its representative.
• Communications: Coordinate and facilitate communications between the Contractor, Central San, the design engineer, utilities, regulatory agencies, and others.
• Documentation: Responsible for all document recording, tracking, and distribution, including all correspondence with the Contractor (such as submittals, requests for information (RFIs), schedules, potential change orders, emails), daily logs, inspection reports, as-builts, pre- and construction photos, etc. The consultant shall maintain a complete set of as-built drawings throughout the construction process.
• Contractor Submittals, Requests for Information (RFIs): Process each using the established document controls, provide recommendations for response, and finalize responses to the Contractor.
• Schedule Review: Review, analyze, and comment on Contractor schedules for conformance to the specified sequence of work and logic. The schedule review includes the baseline, significant schedule revisions, and a look-ahead.
• Contractor Payment Requests:
o Review, monitor, and recommend approval of the Contractor’s Schedule of Values.
o Receive Contractor’s certified payrolls, review, and provide recommendations; verify Contractor’s monthly record drawing updates.
o Process, monitor, and file stop notices, liens, or other payment notifications under the project.
o Make recommendations regarding the assessment of liquidated damages or withholdings from payments to the Contractor.
• Conflict Resolution/Potential Change Orders: The Consultant shall have the authority to initiate change orders, reject change orders proposed by the Contractor, negotiate and recommend acceptance of change orders, including change order cost verification independent of the Contractor’s estimates.
• Shutdown Requests:
o Review and evaluate the Contractor’s shutdown requests in conjunction with Central San. The consultant shall assess the reasonableness of the duration of the requested shutdown.
o The requests shall be reviewed and approved at least two weeks prior to the actual outage/shutdown.
o The consultant shall facilitate/coordinate shutdowns with the Contractor and Central San, or its representative.
o Central San is responsible for reviewing and approving the shutdown request and duration, confirming the shutdown is properly planned, implementing the shutdown, and bringing services back online after the shutdown.
• Inspection Oversight:
o Provide and coordinate daily logs and special inspections to ensure that adequate quality control and specialty consultant support are as specified in the Contract Documents.
o Collect and review inspection reports and results.
• Testing and Training:
o Coordinate required Central San staff training sessions and activities.
o Provide assistance during testing operations.
o Work with the Contractor and Central San on the development of the Testing and Startup Plan.
o Provide oversight and administration of training and testing.
o Coordinate the training with the Contractor, vendors, and Central San staff. Training sessions shall be scheduled so that key Central San staff can attend and shall accommodate plant operations shifts. Multiple training sessions for day-shift and night-shift operators may be required.
o Attend training sessions and store attendance sheets and electronic copies of training materials in Procore.
• Startup & Commissioning: Coordinate startup and commissioning activities and schedules with Central San, vendors, and the Contractor. Observe start-up and maintain copies of start-up documentation in Procore.
• Project Closeout & Asset Handover:
o Provide construction contract closeout services, including verifying record drawings, preparing punch lists, and obtaining warranties, affidavits, and operation & maintenance manuals. Ensure all project documents are furnished in electronic files via Central San’s Procore account. Utilize Procore’s Asset Registry/ Asset Management tool.
o Spare Parts: Prepare a list of required spare parts from the specifications and vendor O&M manuals or recommended spare parts lists. The consultant shall inventory spare parts as they are delivered by the Contractor and transfer spare parts to Central San. The transfer of parts shall be documented via material transmittal, signed by the Contractor, the consultant, and Central San.
o O&M Manuals: Prepare a list of anticipated O&M manuals and track the submittal and review process in Procore. The consultant shall verify that the submitted O&M manuals are the correct and latest version, and that the lessons learned and notes taken during startup and commissioning are included in the O&M manuals.
o Record Drawings: Coordinate final submittal of an organized and complete record drawings set in accordance with contract documents. Review record drawings provided by Contractor and incorporate any additional documented changes or deviations to original drawings.
o Substantial/Final Completion: Coordinate with Central San to determine dates of Substantial Completion and Final Completion.
o Warranty: Receive and forward to Central San written warranties and related documents required by the Contract.
B. Construction Inspection
The roles and responsibilities for this task include, but are not limited to, the following:
• Enforce contract documents.
• Means and Methods of Construction: Consultant shall not direct the means and methods of construction. Contractors are solely responsible for the means and methods of construction. Concerns or suggestions regarding a contractor’s means and methods shall be communicated to Central San.
• Review Contractor’s safety procedures; assess the safety precautions taken on the construction site and notify the Contractor and Central San of observed safety violations.
• Attend progress meetings.
• Construction documentation of project areas includes preconstruction photographs and videos (daily, progress, post-construction).
• Daily construction inspection duties, including reviewing and coordinating field questions and site verification work needed for technical decisions.
• Produce electronic daily logs with the following minimum information:
o document daily conditions o detailed description of work performed and completed o location of work o detailed documentation of Contractor/ subcontractor personnel and equipment on site o hours worked versus standby o noted work deficiencies, deviations, defects, or safety-related issues o special instructions or tests performed o significant deliveries o USA (underground service alert) markings o site visitors o general comments o construction photographs demonstrating work progress to date and verification of items documented in daily inspection reports. Photos shall also include all work completed during the day, site cleanliness, rejected work, and unforeseen conditions. All photos shall be taken on a smart device (i.e., smartphone or tablet) with GPS enabled and shall be date/time- and location-stamped.
• Daily logs shall be signed and issued to Central San by 1 p.m. the following day.
• Assist in the verification of progress payments and the Schedule of Values.
• Assist in coordination of any required/necessary specialty inspections (i.e., materials testing, geotechnical, electrical, etc.).
• Verify Contractor as-built drawings and keep notes.
• Coordinate with materials testing.
• Develop and create detailed punch lists.
• Final Inspection: Consultant shall have primary responsibility for conducting the final inspection. Central San will participate and provide input on the final inspection. The consultant shall be responsible for the oversight and review of the final inspection.
C. Specialty Inspection
The Consultant shall subcontract specialty inspection services through firms pre-approved by Central San. The roles and responsibilities for this task include, but are not limited to, the following:
• Inspect structural work, including concrete, reinforcing steel, anchor bolts, etc.
• Inspect critical electrical, instrumentation, and control work.
D. Safety Compliance Officer (Optional)
This Option may be exercised at the discretion of the Central San Project Manager on the assigned project.
Due to the inherently hazardous nature of wastewater collection and treatment infrastructure, the Safety Compliance Officer shall provide independent oversight of contractor health and safety practices throughout the project. The Safety Compliance Officer position may be filled with qualified staff or subcontracted and is subject to Central San approval. The Officer's responsibilities shall include, but are not limited to, the following:
• Safety Compliance Oversight: Monitor and evaluate the Contractor's compliance with applicable federal, state, and local health and safety regulations, permit requirements, and project-specific safety plans. Document and report observed deficiencies, unsafe work practices, and instances of non-compliance to the appropriate project representatives.
• Safety Inspections and Hazard Audits: Conduct routine daily and weekly site inspections and safety audits to identify hazardous conditions and verify implementation of required controls. Particular emphasis shall be placed on compliance with OSHA regulations governing Permit-Required Confined Spaces (29 CFR 1910.146), including entry procedures, atmospheric monitoring, rescue preparedness, and permit documentation.
• Hazardous Atmosphere and Chemical Exposure Monitoring: Verify that appropriate monitoring equipment, engineering controls, and work practices are implemented to protect personnel from exposure to hazardous atmospheres and chemicals commonly encountered in wastewater facilities, including hydrogen sulfide (H₂S), methane, chlorine, oxygen-deficient environments, and bioaerosols.
• Excavation, Fall Protection, and Energy Isolation Compliance: Monitor compliance with applicable excavation and trench safety requirements, fall protection standards, and Lockout/Tagout (LOTO) procedures for energized mechanical and electrical equipment. Verify that protective systems, safe access and egress, and energy isolation measures are properly implemented prior to commencement of work.
• Incident Investigation and Regulatory Reporting: Respond to and investigate workplace incidents, injuries, illnesses, property damage, and near-miss events to determine root causes and recommend corrective actions. Prepare timely incident reports and coordinate notification and reporting to the California Division of Occupational Safety and Health (Cal/OSHA) and other regulatory agencies, as required by law.
• Safety Documentation and Coordination: Maintain records of inspections, audits, corrective actions, incident investigations, and safety observations. Participate in project coordination meetings, review Job Hazard Analyses (JHAs) and Activity Hazard Analyses (AHAs), verify completion of required safety training, and communicate emerging safety concerns and recommendations to Central San and Contractor.
Requests for Proposal (RFP)
This RFP and any subsequent addenda will be accessible electronically through Central San’s electronic procurement system (PlanetBids) at:
https://vendors.planetbids.com/portal/14663/bo/bo-detail/145969
Proposal Requirements
Proposals shall be clear and concise, responsive to all RFP requirements. Subsections may be added to identify important supplemental material. The format for the proposal is given as an outline to facilitate preparations and evaluations. Submittals that do not meet the requirements of this section may be considered non-responsive.
Proposers must submit the following:
1. Identification of Proposer: The Proposal shall include the names, offices, addresses, and phone numbers of key staff who are proposed.
2. Firm Profile & Experience: Experience with similar projects and proficiency in Procore. Refer to the Desired Qualifications section.
3. Proposed Staffing Plan: Resumes of key personnel, highlighting Procore experience and relevant wastewater treatment plant experience (refer to Desired Qualifications section). Subconsultants shall be specifically identified. Proposer shall clearly state the Staffing Plan for each Task/ sub-task.
4. Fee Proposal: A breakdown of costs by Task proposed upon, including hourly rates for each member of the proposed construction management team, overhead rate, and breakdown of overhead elements, subconsultant billing rates, and markup percentage for ODCs (other direct costs), and identify all reimbursable expenses.
5. Conflicts of Interest: Proposers may not have a conflict of interest as defined under Central San Municipal Code Chapter 2.20, or as defined under state law, including the Political Reform Act or Government Code section 1090 et seq. If a firm has no conflicts of interest, a statement to that effect shall be included in the Proposal. (See Attachment D - Memorandum on Compliance and Procedures for Government Code Section 1090 for Agreements) https://vendors.planetbids.com/portal/14663/bo/bo-detail/145969 https://www.procore.com/library/rfi-construction
Proposers previously selected to work on any portion of the design shall not be eligible to also provide construction management services under this RFP for the same work.
6. Exceptions to Contract Terms and Conditions: Provide a list of any exceptions to contract terms and conditions which the Proposer will seek from the standard Central San contract language, including but not limited to indemnification, insurance, etc. (See Attachment B – Sample Agreement and Insurance Requirements). The Proposal must include the form provided in Attachment C – Proof of Insurance Coverage and Acknowledgment of Sample Agreement Terms and Conditions. Any exceptions provided to Central San after the selection process will not be accepted and will serve as grounds for rejecting the proposer or proposal.
Desired Qualifications
Proposers must demonstrate relevant expertise to successfully perform their roles and responsibilities in their contributions to the project. The Proposer's qualifications should support the scope of services presented in this RFP. All Proposers and their subconsultants shall be registered with the California Department of Industrial Relations pursuant to California Labor Code Section 1725.5.
Below are the desired qualifications for this project:
FIRMS/SUBCONSULTANTS – DESIRED QUALIFICATIONS
Firm (Prime Proposer)
• Be in business for a minimum of ten (10) years performing professional consulting services in the wastewater field in the USA.
• Have acted as the construction manager for at least five (5) wastewater treatment plant projects greater than $25M construction cost.
• Have completed at least two (2) construction management projects in the past five (5) years of wastewater treatment plant construction. This work must have included civil, mechanical, electrical, and controls work.
Alternatively, this qualification can be met by a subconsultant.
• Have project experience with a renovation of an existing facility, multiple completion deadlines, and difficult constraints, sequencing, electrical & instrumentation cutovers, and temporary power.
• Be experienced in the use of Procore.
• Have an office in Northern California, preferably in Contra Costa County.
Subconsultants
• Be in business for a minimum of three (3) years performing similar roles and responsibilities as proposed for this project.
• Subconsultants with an office in Contra Costa County.
KEY TEAM MEMBERS – DESIRED QUALIFICATIONS
Construction Manager
• Ten (10) years of experience in wastewater treatment plant construction.
• Served as construction manager for at least three (3) wastewater, water, or industrial plant projects with a similar scope of work.
• Have in the past five (5) years completed one or more project renovation of an existing facility within a publicly owned water or wastewater treatment facility; and performed constructability reviews for one (1) or more capital improvement projects involving the renovation or expansion of an existing publicly owned wastewater or water treatment facility while maintaining continuous plant operations.
• Demonstrated experience evaluating construction sequencing, temporary facilities, bypass pumping, tie-ins, operational constraints, access, maintenance of treatment, contractor means and methods, and project phasing.
• Experience identifying construction risks, schedule impacts, permitting constraints, utility conflicts, and opportunities to improve safety, cost, and constructability.
• Excellent written communication skills with demonstrated experience preparing constructability review reports and providing recommendations to owners and design teams.
• Holds a current civil professional engineer’s license in the state of California.
• Holds a construction management certificate or degree.
• Holds up-to-date OSHA training.
• A construction manager that is located from an office in Contra Costa County. Must be available to attend in-person design review meetings, field investigations, and stakeholder workshops as required throughout the project.
Construction Inspector(s) - General
• Ten (10) years of experience in wastewater, water, or industrial plant construction inspection.
• Have inspected at least two (2) projects with a similar scope of work (see project description), roles, and responsibilities within the last five (5) years.
• Relevant experience and certifications for the work being performed.
• The ability to maintain an effective working relationship with contractors, consultants, fellow employees, and other departments.
• The ability to read, write, and speak English at a level necessary for satisfactory job performance.
• Special Requirements:
o A valid California Driver's License, Class C or higher.
o Ability to climb ladders, work on scaffolding, crawl in and out of attic spaces and building crawl spaces.
o Trained and certified in: fall protection, CPR, first aid, and OSHA construction safety.
Construction Inspector(s) - Mechanical
• Knowledge and understanding of federal, state, county and local codes including but not limited to: California Mechanical Code, California Plumbing Code, California Fire Code, and Title 24 of the California Administrative Code.
• Knowledge and understanding of citing and enforcing code requirements associated with mechanical and piping systems in the construction of heavy industrial buildings and wastewater treatment facilities.
• The ability to read, understand, and apply mechanical and plumbing code requirements as they apply to construction situations.
• The ability to clearly, accurately, and completely document mechanical and plumbing code violations.
Construction Inspector(s) - Electrical
• Knowledge and understanding of federal, state, county and local codes including but not limited to: California Electrical Code, National Electrical Code, and electrical sections of Title 24, California Administrative Code.
• Knowledge and understanding citing and enforcing code requirements associated with power and electrical systems in the construction of heavy industrial buildings and wastewater treatment facilities.
• The ability to read, understand, and apply electrical code requirements as they apply to construction situations.
• The ability to clearly, accurately, and completely document electrical code violations.
Scheduler/ Schedule Analyst
• Minimum of ten (10) years of recent experience in scheduling relative to large and complex engineering/construction projects. Demonstrate relevant and requisite experience providing construction management services for similar projects.
• Relevant experience within the last five (5) years serving in the capacity of a Lead Scheduler.
• Fully knowledgeable of construction scheduling utilizing the Critical Path Method with resource and cost loading. The proposed scheduling engineer shall also demonstrate experience evaluating and analyzing time and cost impacts as they relate to Contractor’s delay claims.
• Have a high level of skill using Primavera P6 and Microsoft Project software.
• The ideal candidate will possess one or more certifications from the various industry related associates such as the Association for the Advancement of Cost International (AACEI), such as a Certified Cost Engineer/Consultant (CCE/CCC); a certified Planning and Scheduling Professional (PSP), or other similar certifications (e.g. Certified Construction Manager – CCM certified by the Construction Management Association of America – CMAA)
Cost Estimator
• Minimum of fifteen (15) years of recent experience in cost estimating relative to large and complex building projects. Demonstrate relevant and requisite experience providing construction management services for similar projects.
• Relevant experience within the last ten (10) years serving in the capacity as the Lead Cost Estimator.
• Fully knowledgeable of construction cost estimating and development of project budgets, cost models, cost projections, and value engineering analysis; development and analysis of cost estimates based on the A/E contract documents. The cost engineer shall also demonstrate experience evaluating and analyzing time and cost impacts as they relate to Contractor’s delay claims and reviewing and negotiating change orders.
• The ideal candidate will possess one or more certifications from the various industry-related associates such as a certified Planning and Scheduling Professional (PSP); a Certified Cost Engineer/Consultant (CCE/CCC) from the Association for the Advancement of Cost International (AACEI), a certified Professional Estimator (CPE) by the American Society of Professional Estimators; or similar certifications from other industry related associations (e.g. Construction Management Association of America –
CMAA)
Safety Compliance Officer
• Minimum Certifications: Certified Safety Professional (CSP), Construction Health and Safety Technician (CHST), or OSHA 30-Hour minimum.
• Industry Experience: Minimum of 5 years of dedicated construction safety experience, with at least 3 of those years on heavy civil or wastewater treatment facilities.
• Technical Competency: Proven ability to review bypass pumping plans, structural shoring systems, and hazardous atmosphere mitigation
Requests for Information
All questions or clarifications shall be submitted electronically through PlanetBids by the posted deadline. Central San’s anticipated deadline for responding to questions within 1 week of that deadline.
Pre-Proposal Meeting
A pre-proposal meeting will be hosted virtually on the web-based platform Microsoft
Teams. Login information will be posted to PlanetBids at least 5 calendar days in advance. Proposers are responsible for ensuring a successful connection to the virtual meeting.
Submission of Proposals
All proposals shall be submitted electronically through PlanetBids by the posted deadline. The e-procurement system will not accept any proposals after the specified close time.
Withdrawal or Modification of Proposals
A Proposer may withdraw or modify its proposal through PlanetBids at any time before the submittal deadline. No request for modification of the proposal will be considered after its submission and acceptance on grounds that Proposer was not fully informed to any fact or condition.
Rights of Central San
This RFP does not commit Central San to pay any costs incurred in the preparation and presentation of submittals or to select any interested firms that respond.
Central San reserves the right to award this contract not necessarily to the consultant with the lowest cost proposal, but to the consultant that will provide the best overall match to the RFP requirements that best serves the interest of Central San.
Central San will establish an evaluation panel to review the proposals and conduct interviews. The panel may short-list consultants for this RFP utilizing the same evaluation criteria in an effort to identify the highest-ranked consultants, who may then be requested to interview with the panel.
Central San reserves the right to request additional information from any consultant prior to final selection and to consider information about a consultant other than that submitted in the proposal. Central San reserves the right to accept, reject, modify, or cancel in part or in its entirety this RFP. Central San reserves the right to waive informalities or technical defects of the proposal as the best interest of Central San may require. Central San also reserves the right to reject all proposals to make a partial award. Central San shall not, in any event, be liable for any expenses or costs incurred by consultants in preparing their proposals.
Selection Criteria
Proposals will be reviewed and ranked utilizing the following criteria:
• Experience in similar projects (25%)
• Procore proficiency and technical capability (15%)
• Proposed fee and cost-effectiveness (20%)
• Project team qualifications (25%)
• References (15%)
General Requirements
Proposers previously selected to work on any portion of the design of this project shall not be eligible to also provide construction management services under this RFP for the same project.
Anti-Collusion
By submitting a proposal, each Proposer represent and warrants that its proposal is genuine and not a sham or collusive or made in the interest of or on behalf of any person not named therein; that the Proposer has not induced or solicited any other person to submit a sham proposal or any other person to refrain from submitting a proposal; and that the Proposer has not in any manner sought collusion to secure any improper advantage over any other person submitting a proposal.
Disqualification
Factors, including but not limited to, any of the following, may be considered just cause to disqualify a Proposer without further consideration:
1. Evidence of collusion, directly or indirectly, among Proposers in regard to the amount, terms, or conditions of proposals;
2. Any attempt to improperly influence any member of the evaluation team;
3. Existence of any lawsuit, unresolved contractual claim or dispute between Proposer and Central San;
4. Evidence of incorrect information submitted as part of the proposal;
5. Evidence of Proposer’s inability to successfully complete the responsibilities and obligation of the proposal; and
6. Proposer’s default under any previous contract(s) with Central San, which resulted in termination.
Non-Conforming Proposal
Proposals shall be prepared and submitted in accordance with the provisions of these RFP instructions and requirements. Any alteration, omission, addition, variance, or limitation of, from or to a proposal may be sufficient grounds for non-acceptance of the proposal, at the sole discretion of Central San.
Gratuities
No person shall offer, give, or agree to give any Central San employee any gratuity, discount or offer of employment in connection with the award of agreement by Central San. No Central San employee shall solicit, demand, accept or agree from any other person a gratuity, discount or offer of employment in connection with a Central San agreement.
Conflict of Interest
Proposers may not have a conflict of interest as defined under Central San Municipal Code Chapter 2.20, or as defined under state law including the Political Reform Act or Government Code section 1090 et seq. (See Attachment D - Memorandum on Compliance and Procedures for Government Code Section 1090 for Agreements)
Disclosure(s)
Provide a complete disclosure of any prior or ongoing incidents as to which it is alleged that the Proposer has defaulted or failed to perform, and which has led to a Proposer contract being terminated prior to adequate project completion. Identify the parties involved and the circumstances of the default or termination. Also describe any civil or criminal litigation or investigation pending that involves the Proposer or in which the Proposer has been judged guilty or liable.
If the business or person submitting this proposal has been debarred, suspended, or otherwise lawfully precluded from participating in any public procurement activity, including being disapproved as a subcontractor with any federal, state, or local government, or if any such preclusion from participation from any public procurement activity is currently pending, the Proposer shall fully explain the circumstances relating to the preclusion or proposed preclusion in the proposal. The Proposer shall include a letter with its proposal setting forth the name and address of the governmental entity, the effective date of this suspension or debarment, the duration of the suspension or debarment, and the relevant circumstances relating to the suspension or debarment. If suspension or debarment is currently pending, a detailed description of all relevant circumstances including the details enumerated above shall be provided.
If none of these issues are applicable to the Proposer, provide a statement that no disclosures are needed.
Reserved Rights
Central San may require Proposers to submit additional data or information that Central San deems necessary to substantiate the fee and fee schedule presented by the Proposer. Central San may also require the selected Proposer to revise one or more elements of its proposal in accordance with agreement negotiations.
Central San reserves the right to evaluate proposals and interview performance for a period of up to 120 days before deciding which Proposer, if any, to select. It is the intent of Central San to award an agreement within 120 days of receipt of proposals.
Artificial Intelligence (AI) Use
A. Permitted Use of Artificial Intelligence Tools. Proposer and its subconsultants may use Artificial Intelligence (“AI”) tools in performing services only to the extent such use complies with the agreement (see Attachment B – Sample Agreement and Insurance Requirements) and all applicable laws. AI tools include any software or service that generates, analyzes, predicts, or modifies content or data using machine-learning, generative, or algorithmic models.
B. No Substitution for Licensed Professional Judgment. AI tools shall not replace the professional skill, expertise, or independent judgment required of Proposer.
All engineering services must be performed under the responsible charge of a California-licensed professional engineer in accordance with the Professional Engineers Act (Bus. & Prof. Code §§ 6700–6799). AI tools may not independently generate or modify engineering calculations, design criteria, technical analyses, or other work requiring professional licensure.
C. Stamping, Sealing, and Responsible Charge. Any document or deliverable that is stamped or sealed by a licensed engineer must be based on work personally reviewed, evaluated, and approved by that engineer. AI-generated or AI-assisted content shall not be used as the basis for any stamped or sealed document unless the licensed engineer has independently verified all engineering assumptions, calculations, and conclusions for technical accuracy and code compliance.
D. Confidentiality, Data Security, and Public Records Compliance. Proposer shall not input, upload, or otherwise disclose to any AI tool any Central San confidential information, personally identifiable information, security-sensitive information, or information exempt from disclosure under the California Public Records Act, unless expressly authorized in writing by Central San. Proposer shall ensure that any AI tool used does not store, reuse, or train on Central San data in a manner that could disclose such information to third parties.
E. Verification and Disclosure of AI-Assisted Work. Any Deliverable, analysis, report, model, or other work product that is materially generated or materially assisted by an AI tool must be reviewed, verified, and approved by qualified Proposer personnel prior to submission. Verification must include confirmation of engineering assumptions, calculations, methodologies, and compliance with applicable codes and standards. Proposer shall identify AI-assisted content upon request by Central San. Use of AI for clerical functions (e.g., formatting, grammar) need not be disclosed.
F. Restrictions on Autonomous or Safety-Critical Decision-Making. AI tools shall not autonomously generate or recommend engineering decisions that could affect public health, safety, or welfare. AI tools shall not be used to autonomously perform or direct any activity requiring professional licensure or technical judgment.
G. Intellectual Property Compliance. Proposer shall ensure that any AI-generated or AI-assisted content does not infringe upon the intellectual property rights of any third party. Proposer shall indemnify, defend, and hold harmless Central San from any claims arising out of such infringement.
H. Central San’s Right to Review and Restrict AI Use. Upon request, Proposer shall provide a description of any AI tools used in connection with the Services, including the purpose of use, data inputs, and verification procedures. Central San may prohibit or limit the use of any AI tool it determines poses unacceptable risk.
I. No Additional Compensation. Use of AI tools shall not entitle Proposer to additional compensation, time extensions, or relief of any kind. Proposer remains responsible for meeting all requirements of this Agreement regardless of the tools used. Use of AI tools shall not entitle Proposer to additional compensation, time extensions, or relief of any kind. Proposer remains responsible for meeting all requirements of this Agreement regardless of the tools used.
Attachment A – Project Overview
Attachment B – Sample Agreement and Insurance Requirements
Engineer’s Name, Description, Number Page 1 of 32 4911-4436-5216 v1
AGREEMENT FOR PROFESSIONAL ENGINEERING SERVICES
BETWEEN
CENTRAL CONTRA COSTA SANITARY DISTRICT
AND
AGREEMENT NO.
THIS AGREEMENT is made this day of , _____, by and between the CENTRAL CONTRA COSTA SANITARY DISTRICT, 5019 Imhoff Place, Martinez, California (“CENTRAL SAN”) and , , (“ENGINEER”).
RECITALS:
WHEREAS, CENTRAL SAN desires to contract with ENGINEER to provide professional engineering services in connection with the project (“Project”); and
WHEREAS, ENGINEER is willing and holds itself capable and qualified to contract with CENTRAL SAN to provide such professional engineering services; and
NOW, THEREFORE, in consideration of the mutual promises, covenants, agreements and the faithful performance of the terms and conditions set forth herein, the parties hereto agree as follows:
ARTICLE 1 ENGAGEMENT OF ENGINEER AND AUTHORIZATION TO PROCEED
1.1 CENTRAL SAN hereby engages ENGINEER, who hereby accepts the engagement to perform certain professional engineering services described in Exhibit A (“Assignment”) in connection with the Project.
1.2 The date of entering the Agreement and the engagement of ENGINEER will be the date set forth on page 1 which is the date the signature of the second party to this www.centralsan.org
ROGER S. BAILEY
General Manager
J. Leah Castella
Counsel for Central San
(510) 375-4571
KATIE YOUNG
Secretary of Central San
ATTACHMENT B
Engineer’s Name, Construction Management Services, Number Page 2 of 32
Agreement is obtained. The engagement of ENGINEER shall continue until (“End Date”). If the engagement of ENGINEER is not extended by mutual written consent of CENTRAL SAN and ENGINEER, then this Agreement shall be…