RFP_Alondra_Mosaic_(Bid_2024-003)_-_QA_Response.pdf

PDF 221 KB Posted

Attached to
ARTISTIC SERVICES FOR MOSAIC DESIGN, FABRICATION, AND INSTALLATION
Solicitation number
2024-003
Issued by
Los Angeles County, East Los Angeles CDP, Lake Los Angeles CDP, Los Angeles City, California

About this file

This is a Q&A document for RFP Bid No. 2024-003 issued by the San Gabriel & Lower Los Angeles Rivers and Mountains Conservancy (RMC) for artistic services related to mosaic design, fabrication, and installation. The RFP was released on November 14, 2024, with questions due within seven business days of advertisement. The project has a firm installation deadline of April 1, 2025, with no extensions possible. The scope requires the contractor to submit qualifications including up to ten projects, with five completed within the past five years. The work involves installing mosaic artwork on a horizontal concrete slab substrate with a 1-inch recess to accommodate tile and mortar setting bed.

The anticipated budget for the contract is $30,000, inclusive of materials and labor, though this amount is not binding and may be amended during negotiations. The selection process awards up to 30 points for the lowest cost proposal, but final selection will be based on the highest overall score combining technical and cost proposal scores. Evaluation factors include reasonableness, bid estimates, hourly rates, administrative/subconsultant markup, and timeline feasibility. If negotiations with the highest-scoring proposer fail, RMC will proceed with the next highest-scoring bidder.

View the file

Other files

File Type Posted
2024-003_RFP_Alondra_Gateway_Mosaic_-_Extended.pdf PDF
std1000.pdf PDF
2024-003_RFP_Alondra_Gateway_Mosaic.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP Q&A Posted on November 26, 2024

RFP QUESTION RESPONSES

State of California

San Gabriel & Lower Los Angeles Rivers and Mountains Conservancy (RMC)

REQUEST FOR PROPOSALS (RFP) – BID NO. 2024-003

ARTISTIC SERVICES FOR

MOSAIC DESIGN, FABRICATION, AND INSTALLATION

As stated in the RFP released on November 14, 2024, questions regarding this RFP must be received no later than seven (7) business days after the RFP advertisement.

Similar questions have been compiled as one question, and questions may have been paraphrased by the RMC for clarity. It is the responsibility of the Proposer to access the RMC website or the CaleProcure website for any changes or Addenda that may be posted.

Q1. Due to the size of the mosaic, is there a possibility installation may take place later than April 2025?

A1. The hard deadline is 04/01/2025, there is no installation possible past this date.

Q2. Could the budget of $30,000 be negotiated?

A2. The anticipated budget for the ensuing contract is $30,000, inclusive of materials and labor. This budget was established through the overall planning and design process. This amount is not binding, and the executed Agreement may be amended to accommodate costs or schedule conflicts.

RMC will initiate contract negotiations with the highest-scoring and most responsive proposer. In the event that a satisfactory agreement cannot be negotiated, RMC will terminate negotiations with that bidder and begin negotiations with the next highest-scoring bidder, and so on. Please see Section VIII. Contract Administrative Process of the RFP for additional details.

Q3. It appears the RFP is not requesting past work of conceptual design or images. Is that correct?

A3. A written statement of the contractor(s)’s qualifications is required to submit up to ten (10) projects, including images and details of previously completed works. Of these projects, up to five (5) projects must have been completed in the past five (5) years. Submission may include concept designs, implemented designs, or other work that will support the contractor(s)’s qualifications and experience, and demonstrate their ability to fulfill the Scope of Work. Please see Sections IV. Scope of Work and V. Minimum Requirements of the RFP for additional details.

RFP Q&A Posted on November 26, 2024

Q4. If a structure is already built and/or designed, what is the substrate surface upon which the artist will permanently adhere their mosaic artwork to? Is it vertical or horizontal area?

A4. The substrate is a concrete slab. There will be a 1” recess to accommodate for the tile and mortar setting bed. The work surface is a horizontal area. Please see the image below.

Q5. Will the lowest proposed bid be awarded the contract?

A5. The Lowest Cost Proposal will receive the highest number of points (30 points). However, all proposals will be evaluated by certain factors including but not limited to reasonableness, bid is within estimate, bid cover a wide range, hourly rates, admin/subconsultant markup, and realistic to timeline and budget. Award will be made to the responsible proper earning the highest overall score (technical score plus cost proposal score). Please see Section VII. Selection Criteria of the RFP for additional details.

All other terms and conditions set forth in the Request for Proposal shall remain in full force and effect.

Salian Garcia Budgets and Administration Officer sgarcia@rmc.ca.gov mailto:sgarcia@rmc.ca.gov

File details come from the government source that posted it. Updated .