This RFP Addendum No. 001 provides clarifications and revisions to RFP No. 2026008 issued by Northern Wasco County People's Utility District for a McNary Fisheries Compensation Committee (MFCC) Coordinator position. The coordinator will facilitate four annual virtual meetings, administer grants and contracts, maintain committee records and website, and conduct occasional site visits to confirm project completion. The RFP originally issued a proposal due date of November 20, 2026, with award anticipated December 14, 2026, contract execution December 22, 2026, and project commencement February 1, 2027. The initial contract term runs three years (February 1, 2027 through January 31, 2030) with two optional one-year renewals by mutual written agreement. The District anticipates approximately 300 to 350 hours annually for coordinator services, with an estimated three grant awards open at contract start, though none requiring monitoring until later in 2027.

Current annual expenditure for coordinator services is approximately $25,000 to $30,000 annually, with the incumbent contractor identified as S. Scott & Associates LLC. Proposals should include hourly rates with estimated annual costs and a transition plan. The District will not utilize the Trust Fund for coordinator compensation and all services must flow through the contractor's hourly rates. Pricing will be scored based on competitiveness of fees and services, and the District does not anticipate prevailing wage requirements apply to this contract. Professional liability insurance of $2,000,000 per occurrence and $2,000,000 annual aggregate is required and non-negotiable; the District will not reduce insurance limits for sole proprietors or small firms. Travel expenses must be pre-approved and billed separately from hourly rates. The contractor may be located anywhere, including out of state, but must comply with all applicable federal, state, and local laws, including Oregon business registration and workers' compensation requirements.

View the file

Other files

File Type Posted
Personal Service Contract Sample~2.pdf PDF
Appendix 1 Rev1 Add1.pdf PDF
RFP No 2026008 - MFCC Coordinator Final.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP 2026008 Addendum No.001

Addendum Number: 001

RFP No. 2026008 – McNary Fisheries Compensation Committee (MFCC) Coordinator

Date: 11/12/2026

Addendum Overview:

This addendum is issued to provide clarifications, revisions, and additions to the original RFP documents. Please review the following carefully and incorporate the changes into your RFP submission.

RFP No. 2026008 Responses to RFIs/Questions

Question Number

Question

Response

1 Current annual expenditure for coordinator services and the current contractor's name (confirm it is a public record).

The current contractor is S. Scott & Associates LLC. The

District's annual expenditure for coordinator services is approximately $25,000 to $30,000 a year.

2 Whether the Protocols Section 5 grant-management fees (0.5 percent / 1.0 percent / $500 site visits) continue to be paid from the Trust Fund in addition to the contract, or whether all compensation now flows through the contractor's hourly rates.

The trust fund is not being utilized to pay for the coordinator services.

3 What do you expect as the estimated hours or range of hours from the contractor?

Approximately 300 – 350 hours a year.

4 Is professional liability insurance required, and if yes at what limits?

Professional liability insurance is required. Proposers should refer to the Sample Agreement, Section 5 (Insurance), on page 4. The required professional liability insurance limits are $2,000,000 per occurrence and $2,000,000 annual aggregate.

5 Who owns the Squarespace account and will the contractor receives administrator access?

The District owns the website. The Coordinator will be granted administrator permissions.

6 Is the 2026 annual report (due Jan 31, 2027) the incumbent's responsibility?

Yes. The 2026 Annual Report, due January 31, 2027, remains the responsibility of the current coordinator under the existing agreement.

7 Section 8, item 4 refers to coordinating "construction services"; confirm this is a drafting carryover and the intended reference is coordinator services?

Yes, this is a drafting error. References to "construction services" in Section 8, Item 4 should be interpreted as references to MFCC Coordinator services.

8 Would the District consider reduced insurance limits or modified coverage requirements for a sole proprietor or small consulting firm performing primarily administrative services?

The sample agreement's insurance requirements appear more extensive than the scope of work.

The District's insurance requirements will remain unchanged for this solicitation. However, insurance coverage and limits may be discussed with the apparent successful proposer, but the District offers no guarantees for any changes.

9 The scope includes approximately 1-2 site visits annually and occasional in-person meetings. Is travel time billable, and are mileage, lodging, and other necessary travel expenses reimbursable separately from the proposed hourly rate?

The District anticipates that meetings will generally be virtual. Limited travel may be required. Any travel expenses must be pre-approved by the District.

10 Appendix 1 requests hourly rates, while the RFP references an annual contract amount.

Should proposals include estimated annual hours and costs in addition to hourly rates?

Does the District anticipate time-and-materials billing or a fixed annual fee?

Please refer to revised Appendix 1 in OregonBuys for more details and submit accordingly.

11 Is there an anticipated annual budget or estimated number of coordinator hours?

Historical annual spending would also be helpful.

See 1 and 3 above.

12 Would a candidate with project management, meeting coordination and website administration experience, but without direct fisheries or grant administration experience, be considered? Does the coordinator review applications for administrative completeness while committee members handle fisheries and technical evaluations? Which annual permit and regulatory filings would the coordinator prepare, and are templates or guidance available?

Yes, that background would be considered. The MFCC does largely handle the fisheries and technical evaluations.

Members of the MFCC can help the Coordinator on any permit or regulatory filings needed. These may not end up being assigned to the Coordinator.

13 Where are site visits typically held, and should travel expenses be included in the proposed annual fee or itemized separately?

They would be held at the location(s) of the funded stream restoration project. Not all project areas will require site visits. Travel expenses would be billed separately.

14 Is there any requirement that the Coordinator reside in Oregon, Washington, or the Pacific Northwest provided the Coordinator is expected to travel for meetings and site visits as required?

No. The District does not require the Coordinator to reside in Oregon, Washington, or the Pacific Northwest, provided the Coordinator is available to perform the services outlined in the RFP, including travel for meetings and site visits as required.

15 Will the District provide an MFCC email account, Teams licensing and document storage, or should the Contractor use its own?

Contractor should use their own email or create an email specific for this role. Teams has not been used in the past and isn't necessary. File storage and exchange can be done through Google drive or other acceptable options.

16 What is the signature routing process for grant award documents (Docusign, wet signature), and who are the signatories?

Grant award documents are typically executed through

Docusign. The signatories are the grant award recipient and the MFCC.

17 Can the District share the historical annual cost or hours for coordinator services, or a budget for this contract?

See 1 and 3 above

18 Of the 4 annual MFCC meetings, are they held virtually or in person?

They are held virtually.

19 Solicitation refers to 'annual rates.' Should proposers provide hourly rates (Table 1) with an estimated annual amount, or a fixed annual fee? How will pricing be scored?

See 10 above.

Pricing will be scored based on services and associated fees and their competitiveness.

20 Where should official MFCC records be stored, and are there retention requirements?

The MFCC minutes and agendas should be uploaded to the website. The Coordinator can use a tool like Google drive for storage and should be prepared to hand off all files at the end of their contract.

The District will keep official records pertaining to MFCC activities.

21 Will the awarded contractor need Oregon business registration, an Oregon tax-compliance certification, or Oregon workers' compensation coverage if based out of state?

The awarded contractor is responsible for complying with all applicable federal, state, and local laws and regulations. Including registering with the Oregon Secretary of State, verifying city and county requirements, verifying professional or industry-specific licenses, and understanding what constitutes doing business in Oregon to avoid unintentional violations, and maintaining any required workers' compensation coverage.

22 Is there a preferred format or template for the Quarterly Committee Activity Report

No. It just needs to outline what was accomplished, significant decisions, and significant milestones/events/updates on the horizon. It should not be considered rigid, and needs may change.

23 Is there a budget or not-to-exceed amount for this contract? If not, what was spent on these services in each of the last 3 years?

See 1 above.

24 Should pricing be a fixed annual fee, or hourly rates with estimated annual hours? Section 7 and Appendix 1 ask for different things.

See 1 and 10 above.

25 Appendix 1 says rates include transportation, but Table 2 allows expenses billed at cost.

Should travel be built into our rates or listed separately?

See 10 above. Travel expenses would be billed separately.

26 Does prevailing wage (sample agreement Section 10.h) apply to these services?

The District does not anticipate that prevailing wage requirements will apply to the services contemplated under this RFP. The prevailing wage provision included in the sample agreement is a standard contract provision.

27 Coordination and grant administration used to be separate contracts. Does this contract cover both?

The coordinator is to perform both functions per the scope of work.

28 Who writes the 2026 Annual Report due January 31, 2027, one day before this contract starts?

See 6 above.

29 Which filings does "Annual Permit and Regulatory Filings" cover?

See 12 above.

30 How many funded grants will still be open and need monitoring on February 1, 2027?

There will be 3 as it stands now, however none of them have progressed to on-the-ground work yet so there is no monitoring needed until later in 2027. Even then, the monitoring needs are flexible, and photos and documentation from the awardee(s) could be sufficient in lieu of a physical site visit from the Coordinator.

31 How many meetings a year are held in person, and where?

All the MFCC meetings are virtual.

32 Do site visits only confirm that a project was completed, or do they need a technical fisheries assessment?

Just confirmation of progress or completion.

33 Who pays the mcnary.fish website subscription and hosting, the District or the coordinator?

The District.

34 Which parts of the current program would the District most like improved (for example, application intake, tracking, reporting, the website, or turnaround time)?

Application review for completeness and appropriateness.

Communications to potential grant applicants (watershed groups, others regarding the MFCC program).

35 Should proposals include a transition plan, work samples or a sample tracking log?

Proposals should include a transition plan, but can disregard work samples and sample tracking log.

36 May a firm bid with a named subcontractor as the coordinator? Is the subcontractor approved at award?

No subcontractors allowed.

37 If interviews are held, what format will they take and when?

Interviews, if conducted, will be at the District's sole discretion by early December. Interviews will be conducted virtually, and selected proposers will be notified of the interview format and schedule following the proposal evaluation process.

38 Will the District accept lower insurance limits for an administrative contract of this size?

See 8 above.

39 Exceptions are scored 0 to 10. Will proposing changes to the sample agreement lower our score, or only exceptions the District rejects?

Any proposed changes and exceptions to the Sample Agreement will be considered in scoring under this criterion and will impact the proposal's score. Acceptance of any exception is at the District's sole discretion.

40 Is there a page limit or any required form beyond Appendix 1 and the addenda acknowledgment?

No page limit was provided in the RFP. Proposals should include the information required by the RFP, including Appendix 1 and the Addenda Acknowledgment, and should be concise and relevant to the requested services.