This is an RFP Addendum #2 issued by the Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration Design and Construction Division for the Fort Wilkins State Park Water/Sewer System Upgrades project. The addendum addresses two clarification questions submitted by proposers regarding the scope of work. The first clarification confirms that the separate stockade sprinkler and hydrant water system drawing water from Lake Fanny Hooe is not included in the project scope, as it has a separate water source. The second clarification addresses connections to the sewer disposal system and confirms that the Manager's residence, Crew Quarters, and Assistant Manager's residence should be assumed to remain on standalone drain fields rather than being connected to the Chamber No. 5 Flushing/Connection Chamber indicated in the 1991 Roberts, Bartow & Associates, Inc. plan set. The addendum was issued on March 25, 2019, with a proposal due date of April 4, 2019. The project is under the direction of Robert A. Adams with file number 751/19152.RAA.
No pricing terms, set-asides, incumbent information, funding sources, or contract duration details are provided in this addendum document. The addendum serves solely to clarify the project scope and resolve ambiguities in the design drawings and supporting documentation for proposers to develop accurate bid responses.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 RFP (Rev 6/16)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
REQUEST FOR PROPOSAL ADDENDUM NO. 2
This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals. Addenda will be numbered by the Project Director and distributed through www.michigan.gov/SIGMAVSS as an attachment.
TO:
ALL PROPOSERS
DATE ISSUED
3/25/2019
PROJECT NAME
Fort Wilkins State Park Water/Sewer System Upgrades.
FILE NUMBER
751/19152.RAA
PROJECT DIRECTOR
Robert A. Adams
PROPOSAL DUE DATE:
4/4/2019
ADDENDUM ITEMS:
Question #1: Do we need to plan for replacement of the separate stockade sprinkler and hydrant water system that draws water out of Lake Fanny Hooe? This system is shown on plan U-1 sheet 1 of 4. Answer: No. The stockade sprinkler and hydrant water system is not in scope and has a separate source.
Question #2: Have the Managers Residence, Crew Quarters, and Assistant Managers Residence been connected to Chamber No. 5 Flushing/Connection Chamber indicated on sheet 5 of 10 of the Roberts, Bartow & Associates, Inc plan set from 1991? If so, how many grinder pumps and electrical panels have been installed as part of this connection to the force main? If the connection has not been completed are the above mentioned building still being serviced by the septic tanks and drain fields indicated in the provided drawings? Answer: Assume that the Manager’s residence, Crew Quarters, and assistant manager’s residence is not connected to the sewer disposal system and is on a standalone drain field.