RFP 935700-01 Addendum #1 Q&A.pdf
PDF 177 KB Posted
- Attached to
- MPCF IPI Roof Replacement
- Solicitation number
- RFP935700-01
- Issued by
- Henry County, Iowa
About this file
This document is an addendum to a Request for Proposal (RFP) issued by the State of Iowa Department of Administrative Services (DAS) for metal roof replacement of the IPI Building at the Mt. Pleasant Correctional Facility (MPCF) in Mount Pleasant, Iowa. The addendum provides clarification on the availability of existing drawings, access to the roof, and consideration of roofing options such as roof overlay with metal or single-ply. The proposal due date remains unchanged.
The RFP seeks professional design services for the metal roof replacement project. The successful design firm will be responsible for verifying the accuracy of the existing drawings, if available, and providing design solutions that meet the intent to remove and replace the metal roofing panels with like and kind. The design firm may propose alternative options, which will be considered during the design process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP935700-01 - MPCF IPI Roof Replacement.pdf | ||
| 1169309-event.pdf.crdownload | CRDOWNLOAD file | |
| RFP 935700-01 Addendum #1 Q&A.pdf | ||
| RFP935700-01 - MPCF IPI Roof Replacement.pdf | ||
| 1169309-event.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #1
Project Name: MPCF IPI Roof Replacement
DAS#9357.00
RFP935700-01
Addendum #1
Dated: September 7, 2023
This Addendum forms a part of the Request for Proposal documents. This Addendum supersedes and supplements all portions of the original Request for Proposal dated August 18, 2023, with which it conflicts.
ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE REQUEST FOR PROPOSAL. FAILURE TO
DO SO MAY SUBJECT TO DISQUALIFICATION.
1. Schedule – Proposal date does not change.
2. Questions:
a. Q. Any original drawings / plans available for use? A. Existing CAD/PDF drawings will be provided to the successful design firm if they are available. Accuracy of drawings shall be verified by the design firm.
b. Q. Access to roof – can MPCF provide a lift and operator if roof height higher than 15 feet for conventional ladder? A Yes, the facility can help with getting to the roof for design.
c. Q. Will DAS consider roof overlay with metal roof or single-ply? With single ply can do either
EPDM or thermoplastic sheet with “fake” ribs heat welded to simulate metal roof. A. The intent is to remove and replace the metal roofing panels with like and kind. If the designer comes up with other options, they can be looked at during the design process with the successful design firm.
3. Attachments:
a. NONE
END OF ADDENDUM