RFP_3626__Gateway_Park_Entrance_Addendum_No.1.pdf

PDF 213 KB Posted

Attached to
Gateway Park Entrance
Solicitation number
36-26
Issued by
Volusia County, Florida

About this file

This is an Addendum No. 1 to the Request for Proposals issued by the City of DeBary, Florida for civil and site construction services related to the Gateway Park Entrance project located in Volusia County. The project scope encompasses construction of a new direct entrance to Gateway Park from the signalized intersection of US 17/92 and Saxon Boulevard, including clearing, grubbing, demolition, earthwork, grading, roadway pavement, curb and gutter, sidewalks, ADA improvements, stormwater collection, erosion control, maintenance of traffic, pavement markings, and site lighting. The mandatory pre-proposal meeting was scheduled for November 10, 2026, with written inquiries due November 16, 2026 at 2:00 p.m. EST and sealed proposals due December 3, 2026 at 2:00 p.m. EST. City Council approval is anticipated January 6, 2027, with construction scheduled from January 6, 2027 through an estimated completion date of May 30, 2027.

The procurement carries no set-aside, preference, or local-vendor requirement. Award will be made to the lowest responsive and responsible bidder based on the Base Bid using lump sum or unit price pricing as specified in the Bid Price Sheet. Performance and Payment Bonds may be required when contract value exceeds $200,000, with bond costs included in the Total Bid Amount. Bidder eligibility requires registration with the Florida Department of State as an active entity, E-Verify compliance, and freedom from debarment and forced-labor or human-trafficking prohibitions. Required insurance includes Commercial General Liability of $1 million per occurrence and $2 million annual aggregate, Business Auto Liability of $1 million per accident, and Workers' Compensation under Florida statute. The Site Work Contractor must furnish all labor, materials, equipment, supervision, permitting, testing, coordination, and incidentals, while the City will separately contract traffic signal equipment and system work with a Signalization Contractor.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 1

November 20, 2026

RFP 36-26 - Gateway Park Entrance

The original Request for Proposal (RFP) documents shall remain in full force and effect, except as modified herein, which shall take precedence over any contrary provisions in the prior documents.

This addendum is being issued to address questions received, make revisions to the original solicitation document, and release attachments.

RFP DUE DATE & TIME has been changed to :

December 7, 2026 at 2:00 PM EST

1. Use of rip-rap as labeled on Sheet C4.0:

• The rip rap is to be used as energy dissipator for the concrete flume. Follow the plan sheet note and FDOT Standard Specifications for Road and Bridge Construction, Section 530, and additional material and installation details.

2. Approved disposal site for unsuitable materials:

• The City does not have a specific pre-approved disposal site. Any waste, insuitable, or demolished material is to be removed and disposed of in a legal manner.

3. Material quantity discrepancies:

• The Contractor will identify and report to the City, any discrepancies, for correction to be provided. The intent is to provide a fully completed, turn-key project.

4. Engineer’s opinion of probable cost:

• The City is relying on the submitted proposals through this RFP, to provide realistic project costs.

5. Site control points:

• The coordinate-correct DWG file will be provided to the awarded Contractor. Submitting a proposal requires the ability of the Contractor and/or their surveyor to be able to use this file type.

6. Trees that may pose complications:

• There are no known Specimen or Hisotric trees within the limits of this project.

7. NPDES NOI:

• The project is 0.56 acres and does not trip the NPDES threshold. Regardless, the City’s MS4 permit and City policies will still require erosion control protection, on-going maintenance, and rain monitoring for inspections. All reports are to be made available on demand and submitted to the City for project close out.

8. Permit responsibility of the Contractor:

• Design permits have been obtained from FDOT and SJRWMD, including coordination of project with

Volusia County (no formal permit issued). The Contractor will be responsible for the operational approvals and construction commencement notice(s) associated with these permits. Coordination and any specific permit inspection details can be discussed at the pre-construction meeting.

9. FDOT Certification:

• FDOT prequalification is not required, but applicable FDOT certifications are expected to meet MOT, materials, and testing protocals.

10. Special funding source for this project:

• There is no specialy funding. The City is fully financing this project.

11. Public opening:

• Yes, upon the bid due date and time, all received bids will be opened in the City Council chambers which will be open to the public. The Contractor’s name and proposed total cost will be read aloud.

12. The plans for this project show 2" asphalt in the typical section for widening , however the bid form has a pay item showing 1.5" thick asphalt;

• For pavement work outside the FDOT R/W, use 2” per the Plan Detail Sheet. For pavement within the

FDOT R/W, see the following, Item 13.

RFP 36-26 - Gateway Park Entrance

• See updated bid sheet for correction.

13. On the south side of the intersection where the median is being shortened up to accommodate the crosswalk, the pavement design calls for a small bit of widening in this area:

• Pavement within FDOT R/W should be as follows, but is to be confirmed to match existing:

i. Type SP-12.5 Structural Course (Traffic C)(3”)

ii. Type FC-9.5 Friction Course (1”) PG 76-22

iii. Optional Base Group 09

iv. 12” Type B Stabilization (LBR 40)

• See updated bid sheet for addition of these items.

14. At the pre-bid meeting, it was incorrectly mentioned that there were no drainage structures.

• Please provide drainage structures as indicated in the plans.

15. Regarding the two curb ramps within FDOT R/W:

a. It is desired by the City to avoid 1:12 (8.33%) ramp slopes. Instead extend out from the landing to provide a maximum 4.5% (1:20, 5% max) longitudinal slope.

b. Cross slopes are to be at 1.5% (2% max) and provide positive drainage.

c. Per the grading plan at the pedestrian paths, provide spill out or “high side” gutter at both curb ramps to provide a smooth wheelchair/stroller transition across the curb.

The following are the attachments released regarding the above-mentioned solicitation:

RFP 36-26 Exhibit I REVISED Bid Price Sheet

If you should have any questions regarding this addendum, please do not hesitate to contact me by email sperry@debary.org

Sincerely, Susan Perry, CPPB, CFSBO, FCCM City of DeBary Purchasing Coordinator

Acknowledgment of Addendum No. 1 by Vendor/Contractor The Vendor/Contractor hereby acknowledges receipt of the following Addendum:

This addendum shall be completed and signed by an authorized representative and returned with the solicitation submittal. The Acknowledgement of the Addendum receipt will become an integral part of the solicitation document. In acknowledging receipt of this Addendum, the undersigned understands and accepts the foregoing solicitation changes and clarifications.

All other bid terms, conditions, and specifications as originally issued remain unchanged.

Officer (or Principal) Title

Signature Date

Company Name Address

Telephone Number Fax Number mailto:sperry@debary.org

File details come from the government source that posted it. Updated .