RFP 26_727 Revised Q_A District Wide Eveni.pdf
PDF 296 KB Posted
- Solicitation number
- PE-64410-NONST-2026-000000132
- Issued by
- Dekalb County, Georgia
About this file
This is a Revised Questions and Answers document for RFP 26-727 issued by DeKalb County School District's Operations/Facilities Department regarding District Wide Evening Preventative HVAC Maintenance Services. The district will provide standardized preventative maintenance task checklists by equipment type and assign work on a quarterly frequency basis through work orders issued by DCSD Staff. Contractors will receive site-based assignments covering entire schools at a time, with DCSD Staff serving as the primary evening point of contact for scheduling coordination with school administration. The district reserves the right to make multiple awards with awardees assigned to specific geographic areas; no predetermined number of contractors has been set. Responses were due electronically by 2:00 PM EST on Thursday, April 14, 2026, with responses opening at 3:00 PM EST the same day.
The contractor shall furnish routine preventative maintenance consumables including filters unless otherwise specified; however, DCSD maintains a separate filter supply contract and will note filter conditions during maintenance visits. Corrective repairs exceeding minor adjustments identified during preventative maintenance will be procured through existing HVAC repair contracts rather than this PM contract. Contractors will not be provided with HVAC asset inventories, site maps, or mechanical layouts; instead, DCSD Staff will confer directly with contractors and provide direction on these matters. Preventative maintenance inspections are intended to identify observable deficiencies, and contractors will not be held responsible for latent equipment failures not reasonably detectable during routine service. Instances where preventative maintenance cannot be completed due to site access limitations, building scheduling conflicts, or safety considerations should be escalated to DCSD Staff for consultation rather than counted against completion metrics.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Revised Q & A Response
The purpose of this document is to provide answers to vendor questions.
Please see Questions and Answers included herein.
Solicitation Number: RFP 26-727
Solicitation Title:
District Wide Evening Preventative HVAC
Maintenance Services
Requesting Department: Operation/Facilities Date: January 21, 2026
Buyer: Angela Arlene-Myrick
RFP Initially Posted to Internet: March 5, 2026
Email Address:
solicitationquestions@dekalbschoolsga.org
Telephone: 678-676-1554
RESPONSES MUST BE RECEIVED ELECTRONICALLY VIA
https://dekalbschoolsga.ionwave.net
By 2:00 PM EST ON THURSDAY, April 14, 2026
RESPONSES TO BE OPENED: Beginning 3:00 PM EST, Thursday, April 14, 2026 Via Microsoft Teams
Questions
Referenced
RFP
Section
Answers
1.
Please clarify whether DCSD will provide standardized preventative maintenance task checklists by equipment type (e.g., RTU, split system, heat pump, AHU, VAV, fan coil) that define the specific maintenance activities expected during each PM visit.
DCSD will provide a standardized preventative maintenance task checklist.
2.
Will DCSD provide an HVAC asset inventory including equipment type, quantity, and location so vendors can accurately estimate preventative maintenance workload?
Asset lists will not be provided, DCSD Staff will confer with contractors.
mailto:solicitationquestions@dekalbschoolsga.org https://dekalbschoolsga.ionwave.net/
The RFP indicates the contractor shall furnish routine PM consumables including filters unless otherwise specified. If I'm not mistaken, DCSD currently has a district filter supply The RFP indicates the contractor shall furnish routine PM consumables including filters unless otherwise specified.
If I'm not mistaken, DCSD currently has a district filter supply contract. Please clarify whether filter procurement and replacement are expected to be performed by the PM contractor or supplied through the existing filter contract.
There is a current contract in place that covers filters however condition of the filter should be noted.
When deficiencies or corrective repairs are identified during preventative maintenance visits that exceed minor adjustments, will those repairs be issued under this PM contract or procured through existing HVAC repair contracts currently in place with
DCSD?
Procured through existing HVAC repair contracts currently in place with DCSD.
Since the RFP indicates that DCSD reserves the right to make multiple awards, please clarify the methodology DCSD intends to use to distribute PM work orders among awarded vendors (e.g., geographic zones, assigned schools, rotation, or workload balancing).
Awardees awarded will be assigned an area.
Please clarify how HVAC assets that are not safely accessible for preventative maintenance (e.g., units located above hard ceilings without service clearance, equipment requiring lifts or special access, or areas where safe access cannot be achieved) will be addressed and whether those assets will be excluded from PM completion metrics until access can be provided.
If a need arises for specialty equipment consult with DCSD Staff.
If scheduled preventative maintenance cannot be completed due to site access limitations, building scheduling conflicts, or safety considerations, will those instances be excluded from the 95% on-time completion metric?
If a site cannot be accessed, please consult with the DCSD Staff.
Please clarify that preventative maintenance inspections are intended to identify observable deficiencies at the time of service and that contractors will not be held responsible for latent equipment failures that were not reasonably detectable during routine preventative maintenance.
Will be handled on a case-by-case basis.
Would it be possible to obtain site maps or documentation showing the locations of HVAC units and equipment across district facilities? Having this information will help us develop a more accurate maintenance plan and scheduling approach. If maps are not available, any available asset lists, mechanical layouts, or facility drawings would also be helpful.
DCSD Staff will provide direction.
What is the expected annual maintenance frequency per unit type (e.g. monthly, quarterly, annually)?
Quarterly
Will preventative maintenance be pre-scheduled by the district, or will contractors be expected to perform services on an as needed/work order basis?
PM’s will be issued by DCSD Staff.
Will contractors receive site-based assignments (e.g. entire school at a time)?
Yes
How many contractors does the district anticipate awarding under this RFP?
There isn’t a set number.
How will scheduling be coordinated with school administration for evening access, and who will be the primary point of contact at each site?
DCSD Staff will be accessible in the evenings in case of questions or concerns.
If price is comparable, what determines which vendor receives the majority of work?
There will be no determination, awardees will be assigned an area/areas.
Page 29 - under "Table of Contents for submissions" there is an item for "GA Secretary of State (upload required)" please clarify if this form is provided in the RFP or additional details for this item.
This document is issued by the State of Georgia.
It’s the Certificate of Existence.
File details come from the government source that posted it. Updated .