RFP 26 2250 Schedule B Pricing.docx
DOCX document 72 KB Posted
- Attached to
- Cadillac Place Cooling Tower 1 and 2 Repair
- Solicitation number
- RFP 171 260000002250 1
- Issued by
- Michigan
About this file
This is a Schedule B Pricing document for RFP 26-2250 related to the Cadillac Place Cooling Tower 1 and 2 Repair project in Michigan. The document establishes the pricing framework and line items for bidders to submit cost proposals for the repair and restoration of two cooling towers at the Cadillac Place facility. The pricing schedule outlines specific components, labor categories, materials, and equipment necessary to complete the cooling tower repairs, with detailed breakdowns to enable accurate cost estimation and comparison among competing bidders. Bidders are required to populate the pricing schedule with their proposed costs for each identified line item, allowing the State of Michigan to evaluate proposals on a standardized cost basis.
The Schedule B document serves as the standardized pricing template that all qualified contractors must use when submitting their bids for this project. By utilizing a uniform pricing schedule, the State ensures consistent and comparable proposals across all bidders, facilitating transparent evaluation of costs and enabling straightforward identification of the lowest responsive bid. The document does not contain contract renewal options or extended term provisions beyond the primary scope of cooling tower repairs. This pricing schedule is a critical component of the overall RFP submission package and must be completed in its entirety with all requested cost information to ensure bid compliance and responsiveness to the solicitation requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Binder1.pdf | ||
| RFP 26 2250 Schedule A - Commodities & Non-Professional Services - Bidder Box.docx | DOCX document | |
| RFP 26 1721 Standard Contract Terms - Short Form.docx | DOCX document | |
| RFP 26 2250 Proposal Instructions - Confidential Treatment - Vendor Questions Worksheet.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Michigan.gov/MiProcurement Enter company name here Schedule B - Pricing Request For Proposal No. 171 260000002250 Cadillac Place Cooling Tower Repairs
1. The Contractor must provide a pricing schedule for the proposed Contract Activities using the pricing schedule table below. The pricing schedule should be submitted in a modifiable format (e.g. Microsoft Word or Excel); however, you may also submit an additional pricing schedule in a non-modifiable format (e.g., PDF). Failure to complete the pricing schedule as requested may result in disqualification of your proposal.
2. Price proposals must include all costs, including but not limited to, any one-time or set-up charges, fees, and potential costs that Contractor may charge the State (e.g., shipping and handling, per piece pricing, and palletizing).
3. The Contractor is encouraged to offer quick payment terms. The number of days must not include processing time for payment to be received by the Contractor's financial institution.
Quick payment terms: % discount off invoice if paid within days after receipt of invoice.
4. By submitting its proposal, the Contractor certifies that the prices were arrived at independently, and without consultation, communication, or agreement with any other Contractor.
COOLING TOWER 1 PRICING
| Item |
| Item Cost |
| # of Hours/Items |
| Total Cost |
| Labor |
| $ |
| Materials |
| $ |
| Parts |
| $ |
| Equipment Rental |
| $ |
| Total Unit 1 Cost |
| $ |
COOLING TOWER 2 PRICING
| Item |
| Item Cost |
| # of Hours/Items |
| Total Cost |
| Labor |
| $ |
| Materials |
| $ |
| Parts |
| $ |
| Equipment Rental |
| $ |
| Total Unit 2 Cost |
| $ |
Grand Total Project Cost $
Please include your typical, standard company quote with your submission.
Version 2022-2 1 of 71 image1.png
File details come from the government source that posted it. Updated .