RFP 25-VSW-SAKK-019 Amendment 2.pdf
PDF 120 KB Posted
- Solicitation number
- RFP 25-VSW-SAKK-019 Water Intake and Water Transmission Line
- Issued by
- Nome Census Area, Alaska
About this file
This is Amendment 2 to RFP 25-VSW-SAKK-019 issued by the State of Alaska Department of Environmental Conservation's Village Safe Water Program for a Water Intake and Water Transmission Line project. The amendment addresses a vendor question regarding the page limit for the Project Approach section. The RFP response is due on March 4, 2025 at 2:00 PM AST.
The amendment specifically increases the page limit for #2 Project Approach in RFP Part C Evaluation Criteria from one page to two pages, in response to a vendor's concern about adequately addressing the project's complexity within the original single-page limit.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of Alaska Department of Environmental Conservation
Village Safe Water Program 555 Cordova Street
Anchorage, AK 99501 april.akers@alaska.gov
February 19, 2025
To: Vendor List
Re: Amendment 2
RFP 25-VSW-SAKK-019
Water Intake and Water Transmission Line RFP Due Date: March 4, 2025 @ 2:00 PM AST
The following are vendor questions and the department’s response:
1. Vendor: The complexity of the project is challenging to fit into a single page for the Project Approach. Would it be possible to get 2 pages to address the Project Approach for this RFP?
Department: The Page Limit for #2 Project Approach in RFP Part C Evaluation Criteria is increased to 2 pages.
Evan Patterson
Procurement Specialist mailto:april.akers@alaska.gov