RFP 2025_08 Ag Extension Building Renovation.pdf

PDF 392 KB Posted

Attached to
2026-08 Ag Extension Building Renovation
Solicitation number
PE-74600-NONST-2026-000000027
Issued by
Georgia

About this file

This is a Request for Proposal (RFP) issued by Walker County Government in Georgia for exterior building improvements and ADA accessibility upgrades at the Ag Extension Building located at 109 S Duke Street, LaFayette, Georgia. The scope of work includes full exterior window replacement (30 windows totaling approximately 29 windows at 2' x 6' and 1 window at 6' x 6'), structural lintel replacement above all window openings, front door replacement with an ADA-compliant automatic opening system (7' x 7'), side door replacement (32" x 80"), exterior awning replacement to match the Walker County Courthouse, ADA ramp installation at the front entrance, and exterior brick repair and painting. All windows shall be Low-E, aluminum frame, double pane units meeting current energy code requirements, with Enduring Bronze trim to match the building exterior. Sealed proposals must be received by 2:00 p.m. on April 21, 2026, at Walker County Government Administration Building, 101 South Duke Street, LaFayette, GA 30728. An on-site visit for interested contractors is scheduled for 10:30 a.m. on April 6, 2026, with participants meeting first at the Walker County Government Administrative Building. Written inquiries regarding the project must be submitted by April 8, 2026, at 9:00 a.m. EDT, with responses published by April 10, 2026. Work must be substantially completed by August 31, 2026, to minimize disruption to building operations.

Proposals must include itemized pricing based on the proposed methodology, a formal proposal breakdown of expenses, contractor registration and references, supporting project narrative and documentation, Georgia Security and Immigration Compliance Act affidavits for both contractors and subcontractors, and IRS Form W-9. Walker County prefers vendors with a minimum of three years' construction experience and requires submission of documentation for two similar projects completed within the past five years, at least three references for similar projects, firm qualifications and experience, and a proposed project timeline. Contractors must obtain all required permits and pay for inspections, comply with all applicable building codes and ADA regulations, and provide performance and payment bonds in an amount equal to the contract award if exceeding $100,000. Liquidated damages are assessed at $500 per day for delays beyond the substantial completion date. Insurance requirements include Workers' Compensation, Public Liability Insurance of at least $1,000,000 per occurrence, Motor Vehicle Liability Insurance of at least $500,000 combined single limit, and Professional Liability Insurance of at least $1,000,000, with Walker County listed as additional insured. Proposals remain firm for sixty days after opening, and retainage of 10 percent is reserved until final completion and acceptance. Walker County reserves the right to reject any or all proposals and to waive technicalities or minor irregularities.

View the file

Other files

File Type Posted
Pre_bid Questions and Answers 2025_08.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Walker County

Request for Proposal

2026-08

Walker County Ag Extension Building Renovation

Bid Posted: March 25, 2026

Bid Opening: 2:00 p.m. on April 21, 2026 101 S. Duke Street

LaFayette, GA 30728

Inquiries:

Inquiries regarding this project and the bidding process should be sent by email to:

j.pursley@walkerga.us. Only inquiries received in writing will receive a response. All such written inquiries must be submitted by April 8, 2026 at 9:00 a.m. EDT. Walker County will publish a response to all inquiries on its website at walkercountyga.gov/public-notices by April 10, 2026.

https://walkercountyga.gov/public-notices/ https://walkercountyga.gov/public-notices/

INTRODUCTION:

Walker County Government (hereinafter referred to as “WCG”) is soliciting proposals from qualified vendors for exterior building improvements and ADA updates at 109 S Duke Street, LaFayette, GA. Work will include full exterior window replacement, structural lintel replacement, ADA accessibility upgrades, exterior awning replacement, exterior brick repair and exterior painting.

1 - SCOPE OF SERVICES:

The following are the specifications requested for this project.

1.1 Exterior Window Replacement

• Remove and properly dispose of all existing exterior windows.

• Verify all field measurements prior to fabrication or ordering of new windows.

• Provide and install new exterior windows o 29 windows (approximately 2’ x 6’, exact dimensions to be field verified) o 1 window (approximately 6’ x 6’, exact dimensions to be field verified) o Window trim should be Endearing Bronze to match exterior building paint

• Install 30 windows to ensure they are weather-tight, properly flashed, insulated, and sealed.

• New windows shall be Low-E, aluminum frame, double pane that meets current energy code requirements

• Repair and finish exterior surfaces as required to provide a complete and professional installation.

1.2 Lintel Replacement

• Remove existing lintels above all window openings.

• Provide and install new structurally adequate lintels above each window opening.

• Ensure proper structural bearing and compliance with current building codes.

• Repair, restore, and repoint surrounding masonry as required to match existing conditions.

1.3 Front Door Replacement (ADA Compliant)

• Remove the existing front entry door, frame (if required), and associated hardware.

• Provide and install a new ADA-compliant automatic opening door system, including:

o Required clear opening width o ADA-compliant threshold o Accessible lever-style hardware o Proper maneuvering clearances o Aluminum frame o Size is 7’ x 7’

• Ensure installation meets current ADA accessibility standards and applicable building codes.

• Door frame shall be aluminum, as in a store front type door, to match the Walker County Government Administration Building (final color to be approved by the Owner)

1.4 Side Door Replacement

• Remove the existing side door, frame (if required), and associated hardware.

• Provide and install a new door that meets applicable building codes.

• Size is 32” x 80”

• Door frame shall be aluminum, as in a store front type door, to match the

Walker County Government Administration Building (final color to be approved by the Owner)

1.5 Exterior Awning Replacement

• Remove and properly dispose of existing exterior awnings.

• Provide and install two new exterior awnings to match the Walker County

Courthouse (103 S Duke Street, LaFayette)

• Ensure proper structural attachment, weather sealing, and secure mounting.

1.6 ADA Ramp Installation

• Construct and install a new ADA-compliant ramp at the front entrance.

• Ramp shall meet current ADA code requirements, including but not limited to:

o Maximum allowable slope ratio o Required landings o Handrails (where required) o Edge protection

• Ensure proper tie-in and transition to existing sidewalks and entry points.

1.7 Exterior Brick Repair and Painting

• Repair, replace, and repoint exterior brick and masonry areas as required.

• Clean and prepare all exterior brick surfaces prior to painting.

• Prime surfaces as necessary to ensure proper paint adhesion.

• Paint exterior brick (Malabar) and exterior trim (Endearing Bronze) to match the

Walker County Government Administration Building (final color to be approved by the Owner).

• Provide uniform coverage and a professional finish consistent with industry standards.

Additional Notes:

• Contractor shall provide all labor, materials, and equipment required for the above work.

• Work must comply with all applicable building codes and standards, including ADA regulations.

• Contractor shall obtain and pay for all required permits and inspections

• Final finishes (paint colors, flooring material selections, tile type) will be approved by the project owner prior to installation.

• Contractor responsible for cleanup and disposal of construction debris.

COMPLETION TIME:

The Contractor shall provide a proposed construction schedule prior to beginning work.

The schedule shall include the estimated start date, major project milestones, and projected completion date.

Work shall be substantially completed by August 31st to minimize disruption to building operations.

By submitting a proposal, Contractor agrees to the following:

Contractor and Walker County recognize that time is of the essence and that Walker County will suffer financial loss if the Work is not completed within the times specified above. The parties also recognize the delays, expense, and difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered by Walker County if the Work is not completed on time. Accordingly, instead of requiring any such proof, Walker County and Contractor agree that as liquidated damages for delay (but not as a penalty), Contractor shall pay Walker County $500.00 for each day that expires after the time specified above for Substantial Completion until the Work is substantially complete.

After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Time or any proper extension thereof granted by Walker County, Contractor shall pay Walker County $500.00 for each day that expires after the time specified above for completion and readiness for final payment until the Work is completed and ready for final payment.

OTHER REQUIREMENTS:

The successful contractor will be responsible for providing an executed E-Verify S.A.V.E.

document. Sub-contractors that are part of the project team must be clearly identified in the submission, including roles, resumes of key personnel and project references. The Contractor is responsible for obtaining E-Verify Affidavits from its subcontractors and submitting verification to WCG prior to executing a contract with any subcontractor.

All work must pass required inspections and obtain approvals from the Authority Having Jurisdiction.

An on-site visit for interested contractors will be conducted at 10:30 a.m. on April 6, 2026. Visitors should first meet at the Walker County Government Administrative Building, located at 101 S Duke Street in LaFayette, GA.

I. CONTENT AND FORMAT OF PROPOSALS

WCG will evaluate all written submittals. It is incumbent upon the proposers to demonstrate within their proposals how each requirement will be satisfied. All Proposals must meet the specifications outlined in this Proposal. WCG reserves the right to investigate the qualifications and experience of the proposers, or to obtain new proposals. Proposals not sufficiently detailed or are in an unacceptable form may be rejected by WCG. Dates and documentation included in the proposal become public record upon selection of a proposal by the Walker County Board of Commissioners.

Interested firms must follow the process outlined in the following pages in submitting their proposal. WCG prefers to accept proposals from vendors with three (3) years’ experience minimum; however, this factor and the following will be reviewed to assist WCG in deciding the most favorable vendor. Along with the Bid Schedule, please submit the following:

a. A discussion of the history of the firm, including the number of years in business

b. Documentation of two (2) similar or comparable projects completed within the past five (5) years, including photographs of each project.

c. Firm’s proposed project team including qualifications and experience of each member with projects of this nature; provide a minimum of 2 projects;

d. Provide at least three (3) references for similar projects (including numbers and addresses);

e. Proposed methodology for the development and completion of the project.

Describe in detail your approach and scope and how the proposal will satisfy all criteria of the project;

f. Proposed project timeline;

g. Provide itemized pricing based upon your proposed methodology

II. ASSEMBLE IN THIS ORDER

a. FORMAL PROPOSAL: BREAKDOWN OF EXPENSES

b. CONTRACTOR REGISTRATION & REFERENCES

c. SUPPORTING PROJECT NARRATIVE & DOCUMENTATION

d. GEORGIA SECURITY & IMMIGRATION COMPLIANCE ACT AFFADAVIT (Contractor & Subcontractors)

e. IRS Form W-9

FORMAL PROPOSAL: Locate this page at the front when assembling documents for your proposal. Contractor may attach an itemized estimate of products/services behind this page.

For furnishing all labor, materials, tools and equipment necessary to complete the scope outlined for Walker County Ag Extension Building Renovation

PROPOSAL SCHEDULE

RFP #2026-08

Walker County Ag Extension Building Renovation

No. Item Description Total

1.1 EXTERIOR WINDOW REPLACEMENT $

1.2 LINTEL REPLACEMENT $

1.3 FRONT DOOR REPLACEMENT $

1.4 SIDE DOOR REPLACEMENT $

1.5 EXTERIOR AWNING REPLACEMENT $

1.6 ADA RAMP INSTALLATION $

1.7 EXTERIOR BRICK REPAIR & PAINTING $

TOTAL:

RFP #2026-08

Walker County Ag Extension Building Renovation

CONTRACTOR’S RESPONSE:

Date of Proposal: ____________________

The undersigned agrees, if this bid/proposal is accepted within sixty (60) days after the date of the opening, to furnish all supplies or services in strict accordance with provisions of this RFP at the price in the Proposal Schedule.

Prices are to remain firm for sixty (60) calendar days after the date of the opening.

I certify that this bid/proposal is made without prior understanding, agreement, or connection with any corporation, firm or person submitting a bid/proposal for the same supplies or services and is in all respects fair and without collusion or fraud. I understand that collusive bidding is a violation of state and federal law and can result in fines, prison sentences, and civil damage awards. I agree to abide by all conditions of this bid/proposal and certify that I am authorized to sign this proposal for the vendor.

Signature: _______________________________ Title: _________________

Printed name: ____________________________

WALKER COUNTY GOVERNMENT

101 S. DUKE STREET

LAFAYETTE, GA 30728

OFFICE: 706-638-1437

CONTRACTOR REGISTRATION Date: ________________

Name of Contractor: ____________________________

Does your company have employees: Yes No How many: ___________

Is your company licensed to do business in the State of Georgia: Yes No

City or County of Business License: ________________________________

Business Information:

Contact Name: ______________________________________________

Complete Street Address: _______________________________________

City/State/Zip: ______________________________________________

Mailing address (if different from above): ____________________________

City/State/Zip: ______________________________________________

E-mail: _____________________________ Phone: _________________

Website: ____________________________ Fax: ___________________

Organized As: Individual Partnership Corporation Limited Liability Company Other (Circle one)

Federal EIN: ________________________________________________

Summary of Products/Services provided to the County: ___________________

Does your company practice Buy American Sourcing Preferences as outlined in the Code of Federal Regulations, 2 CFR Part 184: Yes No Not Applicable (Circle one)

Applicant Signature: ________________________ Date: ______________

Printed Name: ____________________________ Title: ______________ Walker County Government prefers to accept proposals from vendors with three (3) years’ construction experience.

Number of years in construction business: ____________________________

Firm’s facilities and equipment:

Firm Name: ____________________________________________

Address: ______________________________________________

Equipment: ____________________________________________

Firm’s experience with similar projects: Provide a minimum of 2 projects:

Project: _______________________________________________

Location Address: ________________________________________

Point of Contact: _________________________________________

Project: _______________________________________________

Location Address: ________________________________________

Point of Contact: _________________________________________

References:

1) Company/Organization: ____________________________________

Address: _______________________________________________

Contact: _______________________________________________

E-mail: ___________________________ Phone: _______________

2) Company/Organization: ____________________________________

3) Company/Organization: ____________________________________

Describe in detail your approach and scope and how the proposal will satisfy all criteria of the project: ________________________________________________

Attach the following:

A. List of subcontractors and their contact information

GEORGIA SECURITY AND IMMIGRATION COMPLIANCE ACT AFFIDAVIT

Systematic Alien Verification for Entitlements (SAVE) Program

Contract No. and Name: RFP 2026-08: Walker County Ag Extension Building Renovation

Contractor’s Name: _____________________________________________________________

STATE OF GEORGIA

CONTRACTOR AFFIDAVIT

By executing this affidavit, the undersigned contractor verifies its compliance with O.C.G.A. § 13-10-91, stating affirmatively that the individual, firm, or corporation which is contracting with Walker County and attests to the following:

a) The Contractor has registered with, is authorized to use and uses the federal work authorization program commonly referred to as E-Verify, or any subsequent replacement program;

b) The Contractor will continue to use the federal work authorization program throughout the contract period, including any renewal or extension thereof;

c) The Contractor will notify Walker County in the event the Contractor ceases to utilize the federal work authorization program during the contract period;

d) The Contractor understands that ceasing to utilize the federal work authorization program constitutes a material breach of Contract;

e) The Contractor will contract for the performance of services in satisfaction of such contract only with subcontractors who present an affidavit to the Contractor with the information required by O.C.G.A. § 13-10-91(a),

(b) and (c);

f) The Contractor acknowledges and agrees that this Affidavit shall be incorporated into any contract(s) subject to the provisions of O.C.G.A. § 13-10-91 for the project listed above to which Contractor is a party after the state hereof without further action or consent by Contractor;

g) Contractor acknowledges its responsibility to submit copies of any affidavits, drivers’ licenses, and identification cards required pursuant to O.C.G.A. § 13-10-91 to Walker County within five business days of receipt.

EEV / E-verifyTM User Id (Account) Number Date of Authorization

BY: Authorized Officer or Agent Date (Contractor Name)

Title of Authorized Officer or Agent of Contractor

Printed Name of Authorized officer or Agent

SUBSCRIBED AND SWORN BEFORE ME ON THIS THE

______ DAY OF _____________________, 20_____

Notary Public

My Commission Expires: _____________________________

GEORGIA SECURITY AND IMMIGRATION COMPLIANCE ACT AFFIDAVIT

Systematic Alien Verification for Entitlements (SAVE) Program

Contract No. and Name: RFP 2026-08: Walker County Ag Extension Building Renovation

Contractor’s Name: _____________________________________________________________

STATE OF GEORGIA

SUBCONTRACTOR AFFIDAVIT

By executing this affidavit, the undersigned contractor verifies its compliance with O.C.G.A. § 13-10-91, stating affirmatively that the individual, firm, or corporation which is contracting with Walker County and attests to the following:

a) The Contractor has registered with, is authorized to use and uses the federal work authorization program commonly referred to as E-Verify, or any subsequent replacement program;

b) The Contractor will continue to use the federal work authorization program throughout the contract period, including any renewal or extension thereof;

c) The Contractor will notify Walker County in the event the Contractor ceases to utilize the federal work authorization program during the contract period;

d) The Contractor understands that ceasing to utilize the federal work authorization program constitutes a material breach of Contract;

e) The Contractor will contract for the performance of services in satisfaction of such contract only with subcontractors who present an affidavit to the Contractor with the information required by O.C.G.A. § 13-10-91(a),

(b) and (c);

f) The Contractor acknowledges and agrees that this Affidavit shall be incorporated into any contract(s) subject to the provisions of O.C.G.A. § 13-10-91 for the project listed above to which Contractor is a party after the state hereof without further action or consent by Contractor;

g) Contractor acknowledges its responsibility to submit copies of any affidavits, drivers’ licenses, and identification cards required pursuant to O.C.G.A. § 13-10-91 to Walker County within five business days of receipt.

EEV / E-verifyTM User Id (Account) Number Date of Authorization

BY: Authorized Officer or Agent Date (Contractor Name)

Title of Authorized Officer or Agent of Contractor

Printed Name of Authorized officer or Agent

SUBSCRIBED AND SWORN BEFORE ME ON THIS THE

______ DAY OF _____________________, 20_____

Notary Public

My Commission Expires: _____________________________

Terms and Conditions:

1. Identification: All proposals submitted for this RFP must be returned in a sealed envelope with the following information in the lower left-hand corner of the envelope:

RFP 2026-08: Walker County Ag Extension Building Renovation

All proposals must be submitted in hard copy, one original and one copy, as well as an additional copy on digital media by 2:00 p.m. on April 21, 2026, at the Walker County Government Administration Building located at 101 South Duke Street, P.O. Box 445, LaFayette GA 30728. Submittals received after this time and date will not be considered.

Submittal envelopes should be properly labeled with the RFP number and project title.

All proposers must fill out and sign a Completed Affidavit of Contractor’s E- Verify Compliance and any applicable Affidavit for subcontractors and submit it with your proposal.

All proposers must fill out and sign an IRS Form W-9 and submit it with your proposal.

2. Withdrawal of Proposal: Proposals may be withdrawn by written request only if the request is received PRIOR to the time and date set for the opening of RFPs.

Negligence on the part of the vendor submitting a proposal in preparing their proposal confers no right of withdrawal or modification of their proposal once the proposal has been opened. No proposal may be withdrawn for a period of ninety (90) days after time has been called on the date of opening.

3. Bonds: Construction bidders are required to post performance and payment bonds in an amount equal to the contract award, if the award is over $100,000.

4. Award of Contract: Award will be made to the responsible bidder/proposer whose bid/proposal, conforming to the request for proposals, will be most advantageous to WCG; price and other factors considered. WCG reserves the right to reject any and/or all bids/proposals submitted and to waive any technicalities or minor irregularities in bids/proposals received. A written award shall be deemed to result in a binding contract without further action by either party.

5. Exceptions to Specifications: Any award resulting from this request for proposals shall bind the proposer to all terms, conditions, and specifications set forth in this request for proposals. Proposers whose proposals do not conform should note on a separate page if necessary and/or on the proposal schedule. While WCG reserves the right to make an award to a nonconforming proposer, when in the best interest of WCG, such awards will not be readily made, and proposers are urged to conform to the greatest extent possible. No exceptions will be considered to have been taken by proposer unless it is properly set out as provided above. No exception will be deemed to have been taken by WCG unless incorporated in an award resulting from this request for proposals and so stated.

6. Proposal Results: Interested parties may request, in writing, a tabulation after award has been approved by the Walker County Board of Commissioners by sending a self-addressed, stamped envelope with their request to: Walker County Clerk, P.O. Box 445, LaFayette, GA 30728.

7. Payment: Payments will be made upon all items completed each month or completion of all work and acceptance by WCG on invoices submitted and approved by the appropriate WCG representative(s). All invoices must have a Purchase Order (PO) number and shall be itemized. All invoices submitted will be closely monitored for accuracy. Any invoice found to be incorrect will be returned to the vendor for correction.

8. Taxes: Items on this order are exempt from Federal Excise Tax and Georgia Sales and Use tax. A certificate will be furnished if requested. WCG is exempt from taxes, but the successful proposer shall pay all taxes required of him by law and WCG cannot exempt others from tax.

9. Retainage: WCG reserves the right to retain 10% of the amount of each payment until final completion and acceptance of all work covered by the contract documents.

10. Inquiries Regarding Payment: All inquiries regarding payment of invoices are to be directed to Accounts Payable, (706) 638-1437 or: Walker County Government, Attn:

Accounts Payable, P.O. Box 445, LaFayette, GA 30728.

11. Execution of Contract: Subsequent to the award, the successful proposer will be presented with a “Notice of Award”. The date of presentation shall be deemed to be the postmark or sent date, if emailed. The successful proposer’s proposal and this request for proposals shall serve as the contract for this project.

12. Certificate of Insurance: The Contractor agrees to procure all of the insurance specified below and list WCG as an additional insured:

A. Workers’ Compensation Insurance for all employees who are engaged in work under the contract.

B. Public Liability and Motor Vehicle Liability Insurance: The Contractor shall take out and maintain during the life of this contract, such public liability and motor vehicle liability insurance as shall protect him while performing work covered by this contract from claims for damages which may arise from operations by himself or by any other person directly or indirectly employed by him and the amounts of such insurance shall be as follows:

i. Public Liability Insurance in an amount not less than $1,000,000.00 on account of one occurrence.

ii. Motor Vehicle Liability Insurance on all motor vehicles owned, leased or otherwise used by the Contractor in an amount not less than $500,000.00

(combined single limit) for bodily injury including death and property damage combined.

C. Professional Liability Insurance: The Contractor shall procure and maintain during coverage in the amount not less than $1,000,000.00.

13. Insurance Conditions:

A. The insurance company must be licensed to do business in the state of Georgia.

B. The Contractor shall furnish to WCG a certificate of insurance covering the work as required above as evidence that the insurance required will be maintained in force for the entire duration of the work performed under this agreement.

C. The cancellation of any policy of insurance required by this agreement shall meet the requirements of notice under the laws of the State of Georgia as presently set forth in O.C.G.A. 33-24-44.

D. Each policy of insurance required under this agreement shall provide for notice requirements under the laws of the State of Georgia as set forth in O.C.G.A. 33-24-44 and by endorsement shall provide that WCG will receive a copy of said notice of cancellation.

E. A certificate of insurance with a cancellation provision which provides for less notice than that required by O.C.G.A. 33-24-44, or which provides that failure to give the written notice will not impose any responsibility upon the insurer, shall constitute a basis for insurance rejection of the insurance by WCG.

F. In addition to its agreement to obtain and maintain the insurance as set forth herein above, the Contractor agrees to indemnify and hold harmless WCG, its officers, agents and employees from any and all claims against the WCG, its officers, agents, and employees, which arise out of any act or omission of the Contractor or any consultant employed by the Contractor or any of their officers, agents or employees, and any and all claims which result from any condition created or maintained by the Contractor or any consultant employed by the Contractor or any of their officers, employees or agents, which condition which a result of work performed under the contract.

14. Cancellation of Insurance: If the insurance is canceled, the contractor shall deliver to WCG new policies of insurance. Should the Contractor neglect to obtain and maintain in force such insurance and deliver such policy or policies, then it shall be lawful for WCG to obtain and maintain such insurance at Contractors expense.

15. Inclusion: All items and/or services standard, expected, necessary, and/or routine to such a project as this and not actually stated in this request for proposals will be the responsibility of the successful proposer to provide at no other cost to WCG unless so stated on the successful proposer’s proposal as additional cost items and accepted by WCG at the time of the award.

16. Regulatory Agencies: Successful proposer will be responsible for all required permits or licenses required by the regulatory agency of the county, state, or federal governments. Further, successful proposer will be responsible for meeting all requirements of any regulation(s) or guideline(s) of any of the said governments or any independent agency recognized by said governments as publisher of any such regulation(s) or guideline(s).

17. Domestic Preference: To the greatest extent practicable and consistent with law, there shall be a preference for the purchase, acquisition, or use of goods, products, or materials produced in the United States (including but not limited to iron, aluminum, steel, cement, and other manufactured products)

For purposes of this section:

(1) “Produced in the United States” means, for iron and steel products, that all manufacturing processes, from the initial melting stage through the application of coatings, occurred in the United States.

(2) “Manufactured products” means items and construction materials composed in whole or in part of non-ferrous metals such as aluminum; plastics and polymer-based products such as polyvinyl chloride pipe; aggregates such as concrete; glass, including optical fiber; and lumber.

18. Independent Contractors: The proposer represents to WCG that he is fully experienced and properly qualified to perform the functions provided herein and that he is properly equipped, organized, and financed to perform such functions. The proposer shall finance his own operations hereunder, shall operate as an independent contractor and not as an agent of WCG and nothing contained in this request for proposals or a contract resulting from same shall be construed to constitute the proposer or any of his employees, servants, agents, or subcontractors as a partner, employee, servant, or agent of the county nor shall either party have any authority to bind the other in any respect; it being intended that each shall remain an independent contractor.

19. Assignment of Contractual Rights: It is agreed that the successful proposer will not assign, transfer, convey, or otherwise dispose of a contract that results from an award stemming from this request for proposals or his right, title, or interest in or to the same, or any part thereof, without written consent of WCG.

20. Starting Time: Work will commence within thirty (30) calendar days after being issued a “Notice to Proceed” on the project and commence in a routine, orderly manner until completion and acceptance by WCG.

21. Change Orders: Any and all change order requests by the successful proposer must be approved through the WCG Procurement Policy. For any work performed outside the contract agreement for which compensation over and above the agreement occurs, there must be an accompanying approved change order. If work is done before change order approval, the change may be rejected or denied for compensation.

22. Indemnity: Successful proposer agrees to defend, indemnify, and hold harmless WCG from any and all courses of action or claims of damages arising out of or related to proposer’s performance or actions or those of his employees or agents, under said contract.

23. Cancellation for Cause: Should either party fail to comply with the terms and conditions of this contract, the aggrieved party must give, in writing, to the other party any complaint for non-compliance to the terms and conditions of this contract. The other party shall have fifteen (15) calendar days to correct the matter. If corrected to the satisfaction of both parties within the fifteen (15) calendar days and stated in writing, then the contract will continue uninterrupted. Failure to correct the matter will result in termination of this contract at the end of thirty (30) calendar days following the date of the initial letter of complaint.

24. Changes to Contract: No change will be made to this contract except by written modification by WCG.

File details come from the government source that posted it. Updated .