RFP 2024-10 Clarifying Questions 1.pdf
PDF 300 KB Posted
- Solicitation number
- S-C01010-00009465
- Issued by
- Clackamas County, Oregon
About this file
This document is a response to clarifying questions submitted by interested firms regarding Request for Proposals (RFP) #2024-10 for the Tri-City Lab HVAC and Fume Hood project, issued by Clackamas County and Oregon City in Oregon. The project scope does not include any modifications to doors, walls, or interior finishes beyond re-roofing, and the county does not anticipate a need for an architect on the design team. The full lab remodel project is expected to begin in FY 2027/28 as part of a larger Tri-City Administration remodel.
The solicitation does not provide details on pricing terms, set-asides, incumbents, funding requirements and sources, or other financial information. The document focuses on clarifying the project scope and timeline in response to questions from interested firms.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions and Answers~11.pdf | ||
| 2024-10 Notice of Intent to Award.pdf | ||
| RFP 2024-10 Tri-City Hvac Retrofit.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PH: 503-742-5400 WWW.CLACKAMAS.US
REQUEST FOR PROPOSALS #2024-10
Tri-City Lab HVAC and Fume Hood project
RESPONSE TO CLARIFYING QUESTIONS #1
February 26, 2024
Note that these are questions submitted by interested firms to the above referenced solicitation. The below answers are for clarification purposes only and in no way alter or amend the RFP as published.
1. Page 7 describes the project scope, but it’s not entirely clear if any architectural work beyond re-roofing is anticipated as part of this package. Do you anticipate any modifications to doors, walls, interior finishes, etc as part of this project?
Answer: Based on the conceptual design work completed to-date, this project is not anticipated to require modifications to doors, walls, or interior finishes.
2. Would WES like to see an architect included on the design team?
Answer: WES does not anticipate this being a large need for the final design of this project but will defer to proposers to determine whether an architect is needed to support this project.
3. Objective 6 mentions a future “lab building remodel”. When is this project anticipated to start?
Answer: Per WES’s FY 2024/25 – 2028/29 Capital Improvement Plan, the full lab remodel is anticipated to be constructed along with the Tri-City Administration remodel project which is expected to begin in FY 2027/28.
End of Clarifying Questions #1