This document is a Request for Proposals (RFP) issued by the Oregon Institute of Technology (Oregon Tech) to procure equipment for the advancement of manufacturing research and development. Oregon Tech was awarded a grant from the Economic Development Administration (EDA) (EDA Award Number: 07-01-07446) and is seeking proposals to select a vendor to provide eleven (11) pieces of specialized equipment, including an automatic hardness tester, grinding/polishing machine, automatic cut-off machine, electro-hydraulic hot mounting press, metallography microscopes, densitometer, dynamometer, additive manufacturing machine, waterjet, and laser cutter. The RFP provides detailed technical specifications for each piece of equipment. Proposals are due by January 24, 2022 at 1:00 PM PT, and the anticipated contract start date is on or around February 18, 2022.
The RFP outlines pricing terms, which require that bid pricing be FOB Scappoose, Oregon and include all taxes, tariffs, delivery, and setup costs. The equipment must be new, and the successful bidder will be required to provide warranties, maintenance information, and safety plans. The RFP also includes federal requirements related to the EDA grant funding, such as the Buy America provision.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP 2021-10 Notice of Cancellation.pdf | ||
| Questions and Answers - 69000-00001638.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSALS
RFP # 2021-10
EDA Grant Capital Equipment
EDA Award Number: 07-01-07446
ISSUE DATE: December 22, 2021
CLOSING DATE: January 24, 2022
CLOSING TIME: 1:00 P.M., Pacific Time (PT)
Ver. 08/2021
TABLE OF CONTENTS
Page
Section I - Information Regarding Proposal
Introduction
General Information
Schedule of Events
General Provisions
Term of Contract
Delivery of Proposals
Background
Scope of Work
Section II - Information Required from Proposers
Proposal Form and Content
Required Proposal Content
Evaluation Criteria
Section III – Questionnaire for Proposers
Section IV – Contract Terms and Required Documents
Notice of Interest
Bidder/Proposer Non-Discrimination and Oregon Tax Laws Certification
Exhibit A – Oregon Tech Sample Contract
OREGON INSTITUTE OF TECHNOLOGY
REQUEST FOR PROPOSALS
RFP #2021-10
Section I - Information Regarding Proposal
INTRODUCTION
The Oregon Institute of Technology (“Oregon Tech”) was awarded a grant from the Economic
Development Administration (“EDA”) to procure equipment for the advancement of manufacturing research and development (EDA Award Number: 07-01-07446). Accordingly, Oregon Tech is now seeking proposals to select a vendor to provide eleven (11) pieces of equipment as specified in this
Request for Proposals (“RFP”).
IMPORTANT NOTICE
It will be the responsibility of potential proposers to refer daily to the Public University Procurement
Website (https://www2.wou.edu/nora/orpu.bid.home) to check for any available addenda, response to clarifying questions, cancellations or other information pertaining to this RFP.
GENERAL INFORMATION
Issuing Office: The Office of Sponsored Projects and Grants Administration at Oregon Tech is the
Issuing Office and is the sole point of contact for clarifications regarding technical specifications in this
RFP. The Oregon Tech Procurement and Contract Services Office is the sole point of contact regarding the RFP process. All correspondence pertaining to these two matters should be appropriately addressed to the contact persons below:
Content and Technical Specifications
Dr. Abdy Afjeh, Ph.D., P.E., ASME Fellow, Vice Provost, Research and Academic Affairs
Telephone: (503)821-1279
Email: Abdy.Afjeh@oit.edu
RFP Process Questions:
Vivian Chen, J.D., Director of Procurement, Contracts, and Risk
Telephone: (503) 821-1266
Email: Vivian.Chen@oit.edu
SCHEDULE OF EVENTS
The timing and sequence of events resulting from this RFP will be ultimately determined by Oregon
Tech. The following schedule is illustrative of optimal timing goals:
RFP Issue Date ........................................................................ 12/22/2021
Deadline for Protest of Specifications .................................... 01/10/2022 (5:00 P.M., PT) https://www2.wou.edu/nora/orpu.bid.home mailto:Abdy.Afjeh@oit.edu mailto:Vivian.Chen@oit.edu
All Clarifying Questions Due ................................................. 01/10/2022 (5:00 P.M., PT)
Notice of Interest Deadline ..................................................... 01/10/2022 (5:00 P.M., PT)
Closing Date (Proposals Due) ................................................. 01/24/2022 (1:00 P.M., PT)
Finalist Presentations (if required) ......................................... 02/04/2022
Deadline for Protest of Award ................................................ seven (7) calendar days after date on Notice of Award letter
Anticipated Contract Begin Date ............................................ On or around 02/18/2022
GENERAL PROVISIONS
Oregon Tech reserves the right to reject any and all proposals received as a result of this RFP. Oregon
Tech Policy Chapter 580-61 and 580-62 govern the procurement process for Oregon Tech.
1. Modification or Withdrawal of Proposal. Any proposal may be modified or withdrawn at any time prior to the closing deadline, provided that a written request is received by the Procurement and Contract
Services Office, prior to the Closing Date. The withdrawal of a proposal will not prejudice the right of a
Proposer to submit a new proposal.
2. Notice of Interest. The Notice of Interest (form attached below) should be submitted to the
Procurement and Contract Services Office by 5:00 P.M., PT, on the date indicated in the Schedule of
Events, via email. In the Notice of Interest, the Proposer must provide the name of the primary contact person, plus that person’s current telephone number and email address for communication of information about the RFP. Proposers that complete and return the Notice of Interest will receive the same supplementary information. Submission of the Notice of Interest is not a mandatory requirement for
Proposers to submit a proposal.
3. Requests for Clarification and Requests for Change: Proposers may submit questions regarding the specifications of the RFP. Questions must be received in writing on or before 5:00 P.M., PT, on the date indicated in the Schedule of Events, at the Procurement and Contract Services email address as listed in the Contact Information section of the RFP. Requests for changes must include the reason for the change and any proposed changes to the requirements.
The purpose of this requirement is to permit Oregon Tech to correct, prior to the opening of proposals, RFP terms or technical requirements that may be unlawful, improvident or which unjustifiably restrict competition.
Oregon Tech will consider all requested changes and, if appropriate, amend the RFP. Oregon Tech will provide reasonable notice of its decision to all Proposers that submit a Notice of Interest and on the Public
University Procurement Website (https://www2.wou.edu/nora/orpu.bid.home).
No oral or written instructions or information concerning this RFP from Oregon Tech managers, employees or agents to prospective Proposers shall bind Oregon Tech unless included in an Addendum to the RFP.
4. Protests of the RFP/Specifications: Protests must be in accordance with Oregon Tech Policy Section
580-061-0145. Protests of Specifications must be received in writing on or before 5:00 P.M., PT, on the date indicated in the Schedule of Events, or within seven (7) business days of issuance of any addendum, at the Procurement and Contract Services email address as listed in the Contact Information section of the
RFP. Protests may not be faxed. Protests of the RFP specifications must include the reason for the protest and any proposed changes to the requirements.
5. Addenda: If any part of this RFP is amended, addendum will be provided on the Public University
Procurement Website (https://www2.wou.edu/nora/orpu.bid.home), with a copy to all parties who submit the Notice of Interest.
6. Post-Selection Review and Protest of Award: Oregon Tech will name the apparent successful
Proposer in a “Notice of Intent to Award” letter. Identification of the apparent successful Proposer is procedural only and creates no right in the named Proposer to award of the contract. Competing Proposers will be notified in writing of the selection of the apparent successful Proposer(s) and shall be given seven
(7) calendar days from the date on the “Notice of Intent to Award” letter to review the file and evaluation report at the Procurement and Contract Services Office and file a written protest of award, pursuant to
Oregon Tech Policy Section 580-061-0145. Any award protest must be in writing and must be delivered by email to the address for the Procurement and Contract Services Office as listed in the Contact
Information section of the RFP.
Oregon Tech will consider any protests received and:
(A) reject all protests and proceed with final evaluation of, and any allowed contract language negotiation with, the apparent successful Proposer and, pending the satisfactory outcome of this final evaluation and negotiation, enter into a contract with the named Proposer; OR
(B) sustain a meritorious protest(s) and reject the apparent successful Proposer as nonresponsive, if such Proposer is unable to demonstrate that its proposal complied with all material requirements of the solicitation and Oregon public procurement law; thereafter, Oregon Tech may name a new apparent successful Proposer; OR
(C) reject all proposals and cancel the procurement.
The Oregon Tech Vice President for Finance and Administration or designee will timely respond to the protest after receipt. This decision shall be final.
7. Acceptance of Contractual Requirements: Failure of the selected Proposer to execute a contract and deliver required insurance certificates within ten (10) calendar days after notification of an award may result in cancellation of the award. This time period may be extended at the sole discretion of Oregon
Tech.
8. Public Records: Proposals are deemed confidential until the “Notice of Intent to Award” letter is issued. This RFP and one copy of each proposal received in response to it, together with copies of all documents pertaining to the award of a contract, will be kept and made a part of a file or record which will be open to public inspection. If a proposal contains any information that is considered a TRADE
SECRET under ORS 192.501(2), SUCH INFORMATION MUST BE LISTED ON A SEPARATE
SHEET CAPABLE OF SEPARATION FROM THE REMAINING PROPOSAL AND MUST BE
CLEARLY MARKED WITH THE FOLLOWING LEGEND:
“This information constitutes a trade secret under ORS 192.501(2), and shall not be disclosed except in accordance with the Oregon Public Records Law, ORS Chapter
192.”
The Oregon Public Records Law exempts from disclosure only bona fide trade secrets, and the exemption from disclosure applies only “unless the public interest requires disclosure in the particular instance.”
ORS 192.500(1). Therefore, non-disclosure of documents or any portion of a document submitted as part of a proposal may depend upon official or judicial determinations made pursuant to the Public Records
Law.
9. Investigation of References: Oregon Tech reserves the right to investigate all references in addition to those supplied references and investigate past performance of any Proposer with respect to its successful performance of similar services, its compliance with specifications and contractual obligations, its completion or delivery of a project on schedule, its lawful payment of subcontractors and workers and any other factor relevant to this RFP. Oregon Tech may postpone the award or the execution of the contract after the announcement of the apparent successful Proposer in order to complete its investigation.
10. RFP Proposal Preparation Costs and Other Costs: Proposer costs of developing the proposal, cost of attendance at an interview (if requested by Oregon Tech) or any other costs are entirely the responsibility of the Proposer, and will not be reimbursed in any manner by Oregon Tech.
11. Clarification and Clarity: Oregon Tech reserves the right to seek clarification of each proposal, or to make an award without further discussion of proposals received. Therefore, it is important that each proposal be submitted initially in the most complete, clear and favorable manner possible.
12. Right to Reject Proposals: Oregon Tech reserves the right to reject any or all proposals, if such rejection would be in the public interest, as determined by Oregon Tech.
13. Cancellation: Oregon Tech reserves the right to cancel or postpone this RFP at any time or to award no contract.
14. Proposal Terms: All proposals, including any price quotations, will be valid and firm through a period of sixty (60) calendar days following the Closing Date. Oregon Tech may require an extension of this firm offer period. Proposers will be required to agree to the longer time frame in order to be further considered in the procurement process.
15. Oral Presentations: At Oregon Tech’s sole option, Proposers may be required to give an oral presentation of their proposal to Oregon Tech, a process which would provide an opportunity for the
Proposer to clarify or elaborate on the proposal, but will in no material way change Proposer’s original proposal. If the evaluating committee requests presentations, the Issuing Office will schedule the time and location for said presentation. Any costs of participating in such presentations will be borne solely by
Proposer and will not be reimbursed by Oregon Tech. Note: Oral presentations are at the discretion of the evaluating committee and may not be conducted; therefore, written proposals should be complete.
16. Usage: It is the intention of Oregon Tech to utilize the services of the successful Proposer(s) to provide the goods and services as outlined in the below Scope of Work.
17. Sample Contract: Submission of a proposal in response to this RFP indicates Proposer’s willingness to enter into a contract containing substantially the same terms listed in Exhibit A – Oregon Institute of
Technology Goods and Services Contract, attached hereto and made a part hereof. No action or response to the sample contract is required under this RFP. Any objections to the sample contract terms should be raised in accordance with Paragraphs 3 and 4 of the “General Provisions” of this RFP, pertaining to requests for clarification or change or protest of the RFP/specifications, and as otherwise provided for in this RFP.
18. Review for Responsiveness: Upon receipt of all proposals, the Issuing Office or designee will determine the responsiveness of all proposals before submitting them to the evaluation committee. If a proposal is incomplete or non-responsive in significant part or in whole, it will be rejected and will not be submitted to the evaluation committee. Oregon Tech reserves the right to determine if an inadvertent error is solely clerical or is a minor informality which may be waived, and then to determine if an error is grounds for disqualifying a proposal. The Proposer’s contact person identified on the proposal will be notified, identifying the reason(s) the proposal is non-responsive.
19. Rejections and Withdrawals. Oregon Tech reserves the right to reject any or all proposals or to withdraw any item from the award.
20. RFP Incorporated into Contract. This RFP will become part of the Contract between Oregon Tech and the selected contractor(s). The contractor(s) will be bound to perform according to the terms of this
RFP, their proposal(s), and the terms of Exhibit A.
21. Communication Blackout Period. Except as called for in this RFP, Proposers may not communicate with members of the Evaluation Committee about the RFP until the apparent successful
Proposer is selected, and all protests, if any, have been resolved.
22. Prohibition on Commissions. Oregon Tech will contract directly with persons/entities capable of performing the requirements of this RFP. Contractors must be represented directly. Participation by brokers or commissioned agents will not be allowed during the proposal process.
23. Ownership of Proposals. All proposals in response to this RFP are the sole property of Oregon
Tech, and subject to the provisions of Oregon Revised Statutes (ORS) 192.410-192.505 (Public Records
Act).
24. Clerical Errors in Awards. Oregon Tech reserves the right to correct inaccurate awards resulting from its clerical errors.
25. Rejection of Qualified Proposals. Proposals may be rejected in whole or in part if they attempt to limit or modify any of the terms, conditions or specifications of the RFP or the Oregon Tech Sample
Contract.
26. Collusion. By responding, the Proposer states that the proposal is not made in connection with any competing Proposer submitting a separate response to the RFP and is in all aspects fair and without collusion or fraud. Proposer also certifies that no officer, agent, or employee of Oregon Tech has a pecuniary interest in this proposal.
27. Evaluation Committee: Proposals will be evaluated by a committee consisting of representatives from Oregon Tech. Oregon Tech reserves the right to modify the Evaluation Committee make-up in its sole discretion. The committee’s recommendations will be forwarded to the Vice President for Finance and Administration, or designee, for final approval.
28. Commencement of Work: The Proposer shall commence no work until all insurance requirements have been met, the Protest of Awards deadline has been passed, any protest have been decided, a contract has been fully executed, and a Notice to Proceed has been issued by Oregon Tech.
29. Best and Final Offer: Oregon Tech may request best and final offers from those Proposers determined by Oregon Tech to be reasonably viable for contract award. However, Oregon Tech reserves the right to award a contract on the basis of initial proposal received. Therefore, each proposal should contain the Proposer’s best terms from a price and technical standpoint. Following evaluation of the best and final offers, Oregon Tech may select for final contract negotiations/execution the offers that are most advantageous to Oregon Tech, considering cost and the evaluation criteria in this RFP.
30. Federal Participation Disclosure; Required Federal Contract Provisions. This project will be partially funded with Federal funds from the United States Department of Commerce, Economic
Development Administration and therefore is subject to the Federal laws and regulations associated with that program, including the provisions outlined in Appendix II to 2 CFR Part 200 - Contract Provisions for Non-Federal Entity Contracts Under Federal Awards.
31. Buy America Provision. Equipment or products to be acquired under this RFP shall be American made, to the greatest extent practicable.
32. Approved Equivalent Product. The manufacturers’ names, trade name, brand names, information and/or catalogue numbers listed in a scope of work are for information purposes only and not intended to limit competition. Proposers may offer any brand for which they are an authorized representative, which meets or exceeds the specification for any item(s). Please indicate in the attached Bid Price Form the manufacturers’ name and product/model number. Proposers shall submit with their Proposal, sketches, and descriptive literature, and/or complete specifications. Proposers shall also explain in detail the reason(s) why the proposed equivalent will meet the specifications and not be considered an exception thereto. Proposals, which do not comply with these requirements, are subject to rejection.
TERM OF CONTRACT
The Contract is expected to begin on or about February 18, 2022, and conclude upon full delivery and setup of all equipment. The benefit of any warranties made by the manufacturer shall be assigned to
Oregon Tech. Oregon Tech intends to reserve the right upon thirty (30) days’ notice to the Contractor to terminate the Contract for its convenience.
DELIVERY OF PROPOSALS
The complete proposal (including all attachments) must be emailed and must be electronically received by 1:00 P.M. PT, Monday, January 24, 2022. Email subject line must be “Response to RFP#2021-
10.” Proposer must telephone and confirm electronic receipt of the complete emailed document(s) with the Procurement and Contract Services Office before the above time and date deadline. Proposals delayed or lost by email system filtering or failures may be considered at Oregon Tech’ sole discretion.
It is the responsibility of the Proposer to ensure that proposals arrive by the closing date and time. NO
LATE PROPOSALS WILL BE ACCEPTED. Proposals may not be submitted by telephone or fax.
Proposals must be e-mailed to:
Email: Purchasing@oit.edu
Proposals will be publicly opened by a designee in the Procurement and Contract Services Office on the
Closing Date.
BACKGROUND
Oregon Tech was awarded a grant from the Economic Development Administration to procure equipment for the advancement of manufacturing research and development. The research and development efforts are intended to help manufacturers of any size become more competitive by introducing advanced mailto:Purchasing@oit.edu techniques, technologies, and processes, and to carry out world-leading research into advanced machining, additive manufacturing, automation, and advanced materials that are of practical use to industry. The required specifications of each equipment are described below along with an example product (in brackets) for each that meets the required specifications for that equipment.
SCOPE OF WORK
Individual Machine Requirements:
1. Automatic Hardness Tester [Example: Struers Duramin 650 AC3]
Machine must be a Semi-Automatic and Fully Automatic Universal Tester.
Machine must be capable of Vickers, Knoop, Brinell and Rockwell hardness testing:
i. Bid must include Vickers indenter
ii. Bid must include Brinell indenter
iii. Bid must include Rockwell diamond indenter
iv. Bid must include 1/16” Rockwell ball indenter
Machine must include multiple objectives:
i. 2.5x
ii. 10x
Machine must have automatic contour scanning.
Machine must be capable of conducting weld measurements.
Machine must be capable of preforming Fracture Toughness (Kc) testing.
Machine must cover a range of different loads, covering a range from 1 kgf to 3000 kgf.
Machine must have a motorized test head.
Machine must have a motorized XY-stage.
Machine must have an anti-collision system.
Bid must include all software necessary for operation.
Bid must include calibration and calibration certificate.
2. Grinding/Polishing Machine [Example: Struers Tegramin]
Machine must have the capability to grind/polish samples in an 8” diameter specimen holder and smaller.
Machine must have two pumps, the first must be a pump capable of dosing diamond suspension and lubricant suspension. The second pump must be capable of dosing oxide suspension.
Machine must come with bowl liners (quantity 3).
Machine must come with a magnetic fixation disc capable of use with MD-System products.
Machine must come with a stainless-steel specimen holder for mounted and unmounted specimens between 27mm and 55mm.
Machine must come with a leveling device for fixation of materialographic specimens in specimen holders.
Machine must have a filter or other method for collecting of removed abrasives and materials, water and drainage will be available, so this does not need to be recirculatory machine.
3. Automatic Cut-Off Machine [Example: Struers Discoplan TS]
Machine must be an automatic cut-off machine with an automatic X and Y axis table.
Machine must have variable speed and variable automatic feed capable of selecting optimized parameters based on user input of material hardness.
Machine must be capable of using 12” cutting wheels.
Machine must have a laser that helps operators visualize the cut line on the part.
Machine must come with several clamps and clamping methods to support a variety of potential parts:
i. Quick clamp vise type tool for securing parts on the right side of the cut off wheel. This must include grooved jaw blocks for improved workpiece gripping.
ii. Quick clamp vise type tool for securing parts on the left side of the cut off wheel.
This must include grooved jaw blocks for improved workpiece gripping.
iii. Vertical clamp, vertical clamp riser block, and various swivel shoes for irregular part clamping.
Bid must include a 100-liter cooling system with built in static filter and a (if possible) a magnetic rod that can be inserted into the tank to collect magnetic particles that are too fine to be picked up by the static filter.
Bid must include a table that the cut off machine can sit on, so the cooling unit and filter system can be stored below. Include and tubes or hoses to ensure that the system can be hooked up in this condensed configuration.
4. Electro-Hydraulic Hot Mounting Press [Example: Struers CITOPRESS]
Machine must be capable of mounting up to two samples at a time, either independent or synchronous.
Machine must have controllable parameters including:
i. Temperature
ii. Pressure
iii. Heating Time
iv. Cooling Time
Machine must have a user interface that also allows for easy operator interface based on known cylinder diameter and resin.
Machine must have dual phase heating and pressure for fragile or porous specimens.
Bid must include mounting units with a cylinder diameters and chamfered rams at the following diameters:
i. 1 ½”
ii. 50mm
Bid must include the ability to save at least 10 user defined mounting method parameter sets
5. Inverted Metallography Microscope [Example: Zeiss Inverted AX10 Observer 7 Materials]
Machine should be a microscope capable of inspecting materials for example, non-metallic inclusions and grain sizes.
Machine should have motorized z-focus.
Machine should have an automatic Component Recognition that will recognize the settings for objectives and filter set.
Machine should be capable of the following contrasting techniques:
i. Brightfield
ii. Darkfield
iii. circular differential interference contrast (C-DIC)
iv. Polarization Contrast
v. Polarization with Lambda Plate
Machine must be capable of porosity and inclusion detection and measurement.
Machine must have a 6-position reflector turret motor ACR for P&C modules reflector modules exchangeable without removal of reflector turret.
Machine must have a Reflected-light illuminator.
Machine must have a 360-degree rotatable analyzer slider.
Machine must come equipped with a camera closely capable of a creating an image 2752
(H) x 2208 (V) at 6 Mega Pixels with a Pixel size of 4.54 μm x 4.54 μm.
Machine must have a minimum 130mm x 85mm scanning stage.
Bid must include any hardware or computing devices beyond a general computing desktop or laptop necessary for operation.
Bid must include all software necessary for operation.
6. Densitometer [Example: Mettler Toledo Excellence]
Machine must be capable of measuring density between 0.000 and 3.000 Density (g/cm3).
Machine must have an accuracy of +/-0.0005
Machine must have a resolution of 0.0001
Machine must have automatic temperature control .
Machine must have a digital readout.
Machine must be able to export results to a USB stick via a CSV file.
Machine must have automatic bubble detection.
Machine must have automatic viscosity correction.
Bid must include a drying unit used for cleaning and drying cell prior to measurements.
7. Dynamometer [Example: Kistler]
Machine should be a rotating dynamometer capable of being put into a CNC Milling or
MillTurn machine spindle and measuring forces on a rotating tool.
Machine must be capable of measuring the three orthogonal forces F x, Fy and Fz as well as torque M z during cutting production processes, especially during milling and drilling.
Machine must be capable of measurements up to 30 kN.
Machine must work at speed up to 12,000rpm.
Machine must have thru-coolant capability
Machine must be able to attach to the machine on the spindle side with Capto C6, Capto
C8, HSK 63, HSK 100, CAT40, and CAT50.
Machine must be able to attach on the tools side with ER32, ER40, PowRgrip, Tendo, and MEGA Chuck.
Bid must include the following spindle adapters:
i. HSK100
ii. CAT40
Bid must include the following tool holders:
i. ER32 (collets should not be included)
Bid must include any hardware or computing devices beyond a general computing desktop or laptop necessary for operation.
Bid must include all software necessary for operation.
8. Upright Metallography Microscope [Example: Leica M205C]
Machine should be a microscope capable of analyze metallic structures, composites, ceramics, polymers, and liquid crystals
Machine should be capable of the following contrasting techniques:
i. Brightfield
ii. Darkfield
iii. circular differential interference contrast (C-DIC)
iv. Polarization Contrast
Machine must have a fully motorized in X, Y, and Z for Z-stacking and Tiling/stitch, positioning.
Machine must have Extended Depth of Focus and Autofocus.
Machine must come equipped with a camera closely capable of a creating an image 2752
(H) x 2208 (V) at 6 Mega Pixels with a Pixel size of 4.54 μm x 4.54 μm.
Bid must include any hardware or computing devices beyond a general computing desktop or laptop necessary for operation.
Bid must include all software necessary for operation.
9. Additive Manufacturing Machine [Example: Renishaw]
The machine should be a Powder Bed Fusion system, as defined in ASTM F2792:
Standard Terminology for Additive Manufacturing Technologies: "An additive manufacturing process in which thermal energy selectively fuses regions of a powder bed."
The machine must have a build volume equal to or larger than 200mm x 200mm x
200mm.
The machine's thermal energy source should be a single pulsed Laser with a minimum power of 400W. Laser beam diameter must not exceed 75µm.
The machine must be capable of running an argon build environment. In the interest of efficiency and minimizing operating costs; gas consumption rate must not exceed fifty
(50) liters per hour during normal operation.
Oregon Tech will be permitted to source non-machine vendor supplied metal powder for processing in the machine, provided that the powder has similar characteristics to that of the machine vendor's powder.
The vendor must provide parameter sets for all their fully validated and released metal powder materials. The parameter sets must be adjustable (open parameters) by the machine user. The vendor must offer the option as a service, separate from the RFP, training on how to adjust these parameters.
The vendor must include a wet separator vacuum for proper and safe powder disposal.
10. Water Jet [Example: Sugino Waterjet cutter]
The machine must have a working area capable of cutting a 1000mm x 2000mm piece of material.
The machine must have a Fanuc 32i or comparable NC control capable of receiving 3 axis simultaneous code.
The machine must have a pump with minimum 49,000 psi.
The machine must have an abrasive and kerf collection (removal) system capable of pumping out and depositing abrasive into a reusable abrasive bag inside a storage hopper.
If manufacturer does not offer an abrasive collection unit, the bidder must note this and ensure the machine can be modified after purchase to add this system.
The machine must have an abrasive supply unit with electronic sensors to detect abrasive starvation or a blockage.
The machine must have a high flow ‘supply’ water filter system.
Machine must be supplied with a manual of all codes used for normal machine operations.
Bid must include all software necessary for operation.
11. Laser Cutter
The machine must have a working area of slightly larger than 48” x 96” to accommodate a wide range of standard materials
Machine must have a 155-watt or greater laser capable of cutting steel sheet metal and nonmetals such as acrylic, wood, foam, fiberglass and more
Machine must have a water chiller capable of colling the 155-watt or greater laser tube for more stable and longer cutting
Machine must have an oxygen regulation kit
Manufacturer must include CO2 laser lens cleaning kit
Bid must include all software necessary for operation
Requirements for all Machines
1. Machine must come with applicable safety plan including Lock-Out Tag-Out (LOTO), Safety
Data Sheets (SDS) for all supplied chemicals and gasses, and Job Safety Analysis (JSA) detailing suggested Personal Protective Equipment (PPE) and common hazards during various machine operations.
2. Machine Manufacturer must supply hard copies and electronic copies of maintenance manuals
3. Bid must include all items necessary for individual machine function.
4. Bid must include fluids in appropriate amounts necessary for initial startup of machine.
5. Bid must include filters appropriate for initial startup of machine.
6. Beyond rigging, successful Bidder will ensure that, factory representatives for individual machines must have all tools onsite at Oregon Tech’s campus in Scappoose (Oregon
Manufacturing Innovation Center Research and Development (OMIC R&D) facility) to accomplish installation of machine
7. Building is equipped for the below voltages, phases, and frequencies if machine cannot operate using the supplied power a transformer or phase changer as necessary must be included in the quote:
480/277 VAC 3ph/4w 60Hz
400 VAC 3ph/4w 60Hz (available for Additive Manufacturing Machine only as needed)
208/120 VAC 3ph/4w 60Hz
240/120 VAC 1ph/3w 60Hz
8. All machines must be UL listed, if machine is CE listed machine manufacturer must work with
UL, local county inspectors and an electrician to swap breakers and electrical components to get the machine UL listed once it arrives at Oregon Tech’s campus in Scappoose, Oregon (the OMIC
R&D facility). Machine manufacturer is responsible for this activity and all coordination.
Machine manufacturer will be responsible for ensuring the machine functions after the changes have been made.
9. All machines must be equipped with air filtering necessary for operation if requirements exceed
ISO 8573 Class 2 for Particulates, Class 4 for Water and Class 2 for Oil.
10. Bid must include shipping to Oregon Tech’s campus in Scappoose (OMIC R&D facility), seller must assume FOB until machine arrival at the Oregon Tech’s OMIC R&D facility in Scappoose, Oregon.
11. Bid must include all shipping costs.
12. Bid must include builder standard machine buy-off demonstration at Oregon Tech’s campus in
Scappoose (OMIC R&D facility), if applicable.
13. Bid must exclude training and maintenance.
14. Successful Bidder must immediately work with Oregon Tech staff at OMIC R&D to fully understand installation and building requirements of individual machines, including machine footprint, external systems footprint, foundation requirements, location of power and data entry into machine, air needs, water needs, chiller needs, and other pertinent information.
Section II – Information Required from Proposers
PROPOSAL FORM AND CONTENT
Proposals that do not contain all the information requested in this and other sections may be rejected as non-responsive.
Submission Format
1. The proposal should be written on standard size (8½” x 11”) paper, using generally accessible word processing and document formats conducive to cut-and-paste transfer of information to contracts or other summary documents. MSOffice Suite and Adobe Acrobat documents are preferred.
2. Proposers should structure responses as outlined in this RFP. Proposals should be prepared so that responses are specifically addressed in the same order as the requested information identified below and on the Questionnaire. Pages should be numbered consecutively.
REQUIRED PROPOSAL CONTENT
1. You must complete the Bidder/Proposer Non-Discrimination and Oregon Tax Laws
Certification sheet, signed by an authorized company official.
2. The proposal must also include the following:
a. Title Page or Cover Letter. The title page or cover letter should indicate the date, subject, name of the Proposer, address, current telephone number, e-mail address, name and title of the Proposer’s contact person as well as a signature of an authorized official with the authority to negotiate and contractually bind the Proposer.
b. Questionnaire. Complete and specific answers to the Questionnaire for Proposers. Please respond by restating each question and thereafter providing your answer in order beginning with question 1.
c. Bid Price Form. Please fully complete the Bid Price Form attached to this RFP.
3. Summary Statement. The Proposer may, but is not required to, provide a summary statement as to its qualifications, as well as briefly describe (no more than five hundred (500) words) any special considerations the Oregon Tech should consider.
EVALUATION CRITERIA
Proposals will be evaluated for completeness and compliance with this RFP. Proposals considered complete will be evaluated to determine if they comply with the administrative, contractual, and technical requirements of the RFP. If the proposal is unclear, Proposers may be asked to provide written clarification. Proposals that do not specifically address the scope of work or do not include the complete proposal content may be rejected.
Proposals will be evaluated based on the following criteria and questions outlined in the Questionnaire for
Proposers:
1. Background Information 5 points
2. Equipment Specifications 40 points
3. Cost Summary 40 points
4. Quality of Proposal 10 points
5. References Review 5 points
Total Possible: 100 points
Section III – Questionnaire for Proposers
Please submit your responses in order beginning with question 1 by restating the question, then providing your answer. Use additional sheets as necessary. Be specific with names and numbers.
1. Background Information
Description of past experience in the successful provision of similar goods and services, compliance with specifications, and contractual obligations for higher education, or public institutions. Please provide name, address, and current telephone numbers of contact person for such projects.
Identify specific person(s) who would be responsible and include a brief resume for each. Please list references for each person identified including name, address, and current telephone number of an appropriate reference contact person.
2. Equipment Specifications
Please submit sketches, descriptive literature, and/or complete technical specifications for each piece of equipment outlined in the Scope of Work. Please also explain in detail the reason(s) why each piece of proposed equipment specifically meets the required specifications provided in the Scope of Work and not be considered an exception thereto.
All equipment must be new. No used or refurbished equipment will be considered. Warranty duration information must be provided for each piece of equipment. All equipment must be provided as soon as reasonably possible. Provide the annual cost of equipment maintenance, if offered by manufacturer.
3. Cost Summary
Using the attached Bid Price Form, please provide the manufacturer, product/model number, and price for each piece of equipment outlined in the Scope of Work. Bid pricing must be FOB Scappoose, Oregon and include all taxes, tariffs, delivery, and setup costs.
4. References Review
Provide three (3) references from clients your firm has served in the past three (3) years, including one (1) client that has newly engaged the firm in the past three (3) years and one (1) long-term client (i.e., over three (3) years). Provide the name, address, and current telephone number of each reference.
Section IV – Contract Terms and Required Documents
Notice of Interest
Name of Consultant/Firm: ______________________________________________________
Check One:
_________ Yes, this firm will submit a proposal in response to this RFP. Please forward any addenda to the RFP to my attention.
_________ No, this firm does not anticipate submitting a proposal in response to this request.
Comments:
Signature: Date:
Name: Title:
Address:
City/State/Zip: Phone: ( )
E-mail:
Please email this Notice of Interest no later than January 10, 2022 at 5:00 P.M. PT to
Purchasing@oit.edu.
mailto:Purchasing@oit.edu
BIDDER/PROPOSER
NON-DISCRIMINATION AND OREGON TAX LAWS CERTIFICATION
I, the undersigned, have read all of the terms and conditions of this Request for Proposals, and I understand that if awarded the contract, I and the firm represented herein shall be bound by its terms and conditions and representations made in this response. I certify that the named firm has not discriminated against minority, women, or emerging small business enterprises in obtaining any required subcontracts.
Certified Minority, Women, or Emerging Small Business
For statistical purposes only, please indicate if your firm is an Oregon certified minority, women, or emerging small business (check all applicable): DBE MBE WBE ESB
Certificate of Compliance with Oregon Tax Laws
I, the undersigned, (check one):
hereby certify under penalty of perjury that I am not in violation of any Oregon Tax
Laws.
hereby certify under penalty of perjury that I am authorized to act on behalf of the firm herein named and to the best of my knowledge, such firm is not in violation of any
Oregon Tax Laws.
For purposes of this certification, “Oregon Tax Laws” means a state tax imposed by Oregon Revised
Statues (ORS) 320.005 to 320.150 and 403.200 to 403.250, ORS Chapters 118, 314, 316, 317, 318, 321, and 323; the elderly rental assistance program under ORS 310.630 to 310.706; and local taxes administered by the Oregon Department of Revenue under ORS 305.620.
Business Designation (check one): Corporation Partnership Sole Proprietorship
Governmental/Non-Profit Limited Partnership Limited Liability Partnership
Limited Liability Company
Print Name: Title:
Firm Name:
Address:
BID PRICE FORM
RFP #2021-10
EDA Award Number: 07-01-07446
Bid pricing response must be FOB Scappoose, Oregon and include all taxes, tariffs, delivery, and setup costs.
Machine Manufacturer Product/Model
Number
Price
1 Automatic Hardness Tester $
2 Grinding/Polishing Machine $
3 Automatic Cut-Off Machine $
4 Electro-Hydraulic Hot
Mounting Press
5 Inverted Metallography
Microscope
6 Densitometer $
7 Dynamometer $
8 Upright Metallography Stereo
Microscope
9 Additive Manufacturing
Machine
10 Water Jet $
11 Laser Cutter $
TOTAL
Proposed Delivery Date and Time After Award of Contract:
Print Name: Title:
Firm Name:
Address:
Exhibit A
Oregon Tech Sample Contract
[Please see attached.]
OREGON INSTITUTE OF TECHNOLOGY
GOODS AND SERVICES CONTRACT
CONTRACT #
This Goods and Services Contract (“Contract”) is between the Oregon Institute of Technology, hereafter called “Oregon Tech” and , hereafter called “Contractor”. Oregon Tech’s Representative for this
Contract is .
WHEREAS, the Oregon Tech and Contractor desire that Contractor provide the goods and/or services as more particularly described in the “Statement of Work” section of this Contract.
NOW, THEREFORE, the Parties agree as follows:
1. Effective Date and Duration. This Contract shall become effective upon signature of both parties. Unless earlier terminated or extended, this Contract shall expire on . However, such expiration shall not extinguish or prejudice Oregon Tech’s right to enforce this Contract with respect to: (i) any breach of a Contractor warranty; or (ii) any default or defect in Contractor performance that has not been cured.
2. Statement of Work. Contractor will . Contractor agrees that it and its employees will comply with the Oregon Tech Tobacco-Free Campus Policy.
3. Consideration: Subject to the provisions of ORS 293.462, Oregon Tech agrees to pay
Contractor, from available and authorized funds, a sum not to exceed $ , for accomplishing the work required by this Contract. If any interim payments to Contractor are made, such payments shall be made only in accordance with the schedule and requirements contained in this
Contract. Invoices should be submitted to: Oregon Institute of Technology, Accounts Payable –
Snell Hall, 3201 Campus Drive, Klamath Falls, OR 97601 or baoapay@oit.edu.
a. If this box is checked, Contractor is authorized to request reimbursement of its travel related expenses in accordance with the Oregon Tech Contractor Reimbursement Policy as outlined in Exhibit C. Travel expense reimbursement is not in addition to the above indicated contract not to exceed amount.
4. Terms and Conditions. The terms and conditions of this Contract are contained on the following page titled “General Contract Provisions.”
5. Notices. Notices to Oregon Tech shall be directed and mailed as follows: Procurement and
Contract Services, 27500 SW Parkway Ave., Wilsonville, OR 97070.
6. Contract Documents. This Contract consists of the following documents which are listed in descending order of precedence and are attached and incorporated by reference, this Goods &
Services Contract, Exhibit A (Schedule of Fees), Exhibit B (Insurance Requirements) and Exhibit
C (Contractor Travel Reimbursement Policy).
mailto:baoapay@oit.edu
7. Contractor Data.
Name (tax filing):
Address:
Phone No.:
Email:
MWESB Certification #: _______________________
DBE MBE WBE ESB
Citizenship, if applicable: Non-resident alien YES NO
Business Designation: (Check one):
_ Corporation Partnership Limited Partnership Limited Liability Partnership
__ Sole Proprietorship Governmental/Non-Profit Limited Liability Company
OREGON INSTITUTE OF TECHNOLOGY
GOODS AND SERVICES CONTRACT PROVISIONS
1. Compliance with Applicable Law: Contractor shall comply with all federal, state, county, and local laws, ordinances, and regulations applicable to the work to be done under this Contract.
Contractor specifically agrees to comply with all applicable requirements or federal and state civil rights and rehabilitation statutes, rules, and regulations. Contractor shall also comply with the Americans with Disabilities Act of 1990 (Pub. L. No. 101-336), title VI of the civil Rights Act of 1964, Section V of the Rehabilitation Act of 1973, ORS 659.425, and all regulations and administrative rules established pursuant to those laws. Contractor further agrees to make payments promptly when due, to all persons supplying to such Contractor, labor or materials for the prosecution of the work provided in this Contract; pay all contributions or amounts due the Industrial Accident Funds from such Contractor responsibilities incurred in the performance of this Contract; not permit any lien or claim to be filed or prosecuted against the state on account of any labor or material furnished; pay to the Department of Revenue all sums withheld from employees pursuant to ORS 316.167. If Contractor fails or refuses to make any such payments required herein, the appropriate Oregon Tech official may pay such claim. Any payment of a claim in the manner authorized in this section shall not relieve the Contractor or Contractor’s surety from obligation with respect to unpaid claims. Contractor shall promptly pay any person or entity that furnishes medical care to Contractor’s employees those sums which Contractor agreed to pay for such services and all money Contractor collected or deducted from employee’s wages to provide such services.
2. Disclosure of Tax ID or Social Security Number: Contractor must provide Contractor’s Social
Security number unless Contractor provides a federal tax ID number. The number is requested pursuant to ORS 305.385 and OAR 150-305-100. Social Security numbers provided pursuant to this authority will be used for the administration of state, federal and local tax laws. If required, this information will be reported to the Internal Revenue Service (IRS) under the name and taxpayer ID number submitted. (See I.R.S. 1099 for additional instructions regarding taxpayer ID numbers.) Information not matching IRS records could subject Contractor to 28% backup withholding.
3. Insurance: Contractor shall provide insurance as indicated on Exhibit B, attached hereto and by this reference made a part hereof. Insurance policies, which cannot be excess to a self-insurance program, are to be issued by an insurance company authorized to do business in the State of Oregon. The Oregon Institute of Technology and its trustees, officers and employees shall be included as additional insureds in said insurance policy. If any of the liability insurance is arranged on a “claims made” basis, “tail” coverage will be required at the completion of this Contract for a duration of 24 months.
4. Indemnity, Responsibility for Damages: Contractor shall be solely responsible for all damage to property, death, illness, bodily injury, loss, expense (including reasonable attorney’s fees and costs), arising or resulting from or in any way related to (a) Contractor’s breach of its obligations under this Contract or (b) any act or omission of Contractor, or any of its subcontractors, members, managers, directors, officers, trustees, agents, contractors, or employees. Contractor shall save, defend, indemnify, and hold harmless Oregon Tech and its board members, trustees, directors, officers, agents, contractors, employees, and members (collectively, the “Indemnified Parties”) from and against any and all Damage (defined below) or Proceeding (defined below), arising or resulting from or in any way related to a Claim (defined below). The term “Damage” means any and all damage to property, death, illness, bodily injury, demands, losses, damages, liabilities, or expenses, including, without limitations, attorney’s fees and costs, however incurred, including at trial, mediation, arbitration, in any bankruptcy proceeding, on appear, and any petition for review. The term “Proceeding” means any and all third-party claims, suits, actions, and proceedings, of any kind or nature, including, without limitation, any lawsuit, mediation, arbitration, bankruptcy proceeding, appeal, or any petition for review. The term “Claim” means (a) Contractor’s breach of its obligations under this Contract, (b) any act or omission of Contractor, its subcontractors, members, managers, directors, officers, trustees, agents, contractors, or employees, or (c) any material breach of a representation or warranty of Contractor contained in this Contract or related to this Contract or the work to be provided or actually provided by Contractor under this Contract. Contractor’s obligations under this Paragraph shall survive the expiration or termination of this Contract for any reason.
In the event any Proceeding is brought against any of the Indemnified Parties by reason of any Claim, upon the request of Oregon Tech, Contractor shall resist or defend such Proceeding with counsel satisfactory to Oregon Tech, and Oregon Tech agrees to thereafter reasonably assist, at Contractor’s expense, in such defense. Thereafter, Contractor shall have control of the defense and settlement thereof, but neither Contractor nor any attorney engaged by Contractor shall defend the Proceeding in the name of Oregon Tech, settle any portion of the Proceeding, nor purport to act as legal representative of Oregon Tech, without the prior written consent of Oregon Tech. At any time Oregon Tech may, at Contractor’s expense, provide its own defense or assume its own defense from Contractor if Oregon Tech reasonably determines that (a) Contractor is prohibited from defending Oregon Tech, (b) Contractor is not adequately defending Oregon Tech’s interests, or (c) an important governmental principle is at issue.