About this file
This is a Request for Proposal (RFP) issued by the Michigan Department of Military and Veterans Affairs for the construction of an open pavilion at Camp Grayling Joint Maneuver Training Center (JMTC). The RFP seeks a licensed residential builder to construct a 40'x30' pavilion over an existing concrete slab that is 30'x36' with a 4-inch nominal thickness. The RFP was issued on June 18, 2019, with questions due by June 25, 2019, and proposals due by July 5, 2019 at 3:00 PM Eastern. The anticipated contract start date is July 15, 2019, with all work to be completed within 90 days. Site visits are available upon request through the Solicitation Manager.
The project requires contractors to provide all permits, labor, materials, and equipment necessary for construction according to specified requirements, including low pitch beams, support columns, footings, connector plates, roof decking, shingles, and landscaping. Bidders must submit a copy of their Michigan Builders License, detailed bill of materials, project timeline, and subcontractor information with their bid. The evaluation criteria includes technical factors weighted at 80 points minimum to be considered for pricing evaluation, with specific scoring for product requirements (20 points), bid submission requirements (15 points), warranties (10 points), subcontractor disclosure (15 points), prior state experience (15 points), and prior experience (25 points). The project must comply with state and local building codes, with no electrical or plumbing work required.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF MICHIGAN
Department of Military and Veterans Affairs
Construction of Open Pavilion at Camp Grayling Joint Maneuver Training Center (JMTC) Request for Proposal No. 190000002527
Solicitation Manager Name: Elizabeth Noffsinger
Direct Phone: 989-344-6190 Email: noffsingere@michigan.gov
This is a Request for Proposal (RFP) for:
Construction of Open Pavilion at Camp Grayling Joint Maneuver Training Center (JMTC)
RFP Timeline
Event Time Date RFP issue date N/A 6/18/2019 Siti visits available upon request. Contact Proposal Manager listed above to schedule
Deadline for bidders to submit questions about this RFP
3:00 p.m. Eastern 6/25/2019
Anticipated date State will post answers to bidder questions on www.michigan.gov/SIGMAVSS
6/28/2019
Proposal deadline* 3:00 p.m. Eastern 7/5/2019 Anticipated contract begin date N/A 7/15/2019
*A bidder’s proposal received at 3:00:01 p.m. Eastern is late and subject to disqualification.
This RFP is subject to change. Check www.michigan.gov/SIGMAVSS for current information.
http://www.michigan.gov/SIGMAVSS
Version 6 Revised: 5/2019
PROPOSAL INSTRUCTIONS
1. PROPOSAL PREPARATION. The State recommends reading all RFP materials prior to preparing a proposal, particularly these Proposal Instructions and the Vendor Questions Worksheet. Bidders must follow these Proposal Instructions and provide a complete response to the items indicated in the table below.
References and links to websites or external sources may not be used in lieu of providing the information requested in the RFP within the proposal. Include the bidder’s company name in the header of all documents submitted with your proposal.
RFP Structure and Documentation
Document Description Bidder Response Instructions
Cover Page Provides RFP title and number, important dates, and contact information for Solicitation Manager
Informational
Proposal Instructions Provides RFP instructions to bidders Informational
Confidential Treatment Form Required verification on whether bidder’s proposal contains confidential information
Bidder to complete and submit by proposal deadline
Vendor Questions Worksheet Questions to bidders on background and experience
Bidder to complete and submit by proposal deadline
Schedule A – Statement of Work
Statement of work Bidder to complete and submit by proposal deadline
Schedule A-Exhibit 1 Drawings *Informational
Schedule B – Pricing Pricing for goods and services sought by the State through this
RFP
Bidder to complete and submit by proposal deadline
Contract Terms Provides legal terms for a contract awarded through this RFP
Deemed accepted by bidder unless information required in Section 8, Evaluation Process is submitted by proposal deadline
2. CONTACT INFORMATION FOR THE STATE. The sole point of contact for the State concerning this RFP is listed on the Cover Page. Contacting any other State personnel, agent, consultant, or representative about this RFP may result in bidder disqualification.
3. MODIFICATIONS. The State may modify this RFP at any time. Modifications will be posted on www.michigan.gov/SIGMAVSS . This is the only method by which the RFP may be modified.
4. QUESTIONS. Bidder questions about this RFP must be emailed to the Solicitation Manager no later than the time and date specified on the Cover Page. In the interest of transparency, only written questions are accepted. Answers to questions will be posted on www.michigan.gov/SIGMAVSS. Submit questions using the format below; a Microsoft Excel format or similar is suggested.
Q # Document and Section Page # Bidder Question
5. DELIVERY OF PROPOSAL.
Electronic – The bidder must submit its proposal, all attachments, and any modifications or withdrawals electronically through www.michigan.gov/SIGMAVSS. The price proposal should be saved separately from http://www.michigan.gov/SIGMAVSS all other proposal documents. The bidder should submit all documents in a modifiable (native) format (examples include, but are not limited to: Microsoft Word or Excel and Google Docs or Sheets). In addition to submitting documents in a modifiable format, the bidder may also submit copies of documents in PDF.
Attachment file size is limited to 6 MB per document. Bidder’s failure to submit a proposal as required may result in disqualification. The proposal and attachments must be fully uploaded and submitted prior to the proposal deadline. Do not wait until the last minute to submit a proposal, as the SIGMA VSS system requires the creation of an account and entry of certain information, in addition to uploading and submitting the materials. The SIGMA VSS system will not allow a proposal to be submitted after the proposal deadline identified in the solicitation Closing On/Closing Date fields (Summary view/Detail view), even if a portion of the proposal has been uploaded.
Questions on how to submit information or how to navigate in the SIGMA VSS system can be answered by calling (517) 373-4111 or (888) 734-9749. The Solicitation Manager will not provide assistance related to the submittal of the proposal and all attachments on the day of the proposal deadline. Responsibility for a complete submission lies with the bidder.
If there is difficulty uploading the bid documents to SIGMA please, email the documents to the Solicitation Manger listed on the first page, Documents must be received by the end date and time. Bids received after that time and date may not be considered for award.
6. MANDATORY MINIMUM REQUIREMENTS. To avoid disqualification, the bidder must provide documentation to support the following:
• A COPY OF MICHIGAN BUILDERS LICNESE HELD BY VEDNOR OR SUBCONTRACTOR
Must be submitted with the bid
• Only proposals meeting the mandatory minimum requirements will be considered for evaluation.
7. EVALUATION PROCESS. The State will evaluate each proposal based on the following factors:
Technical Evaluation Criteria Weight
1. Product Requirements-Schedule A, Statement of Work, Sections 1.1 20
2. Bid Submission Requirements – Schedule A, Statement of Work, Section 1.2
3. Warranties – Schedule A, Statement of Work, Section 1.3 10
4. Disclosure of Subcontractors- Schedule A-Statement of Work
Section 3.4 V
5. Vendor Questions Worksheet-Prior experience with the State of Michigan
6. Vendor Question Worksheet-Prior Experience 25 Total 100
Proposals receiving 80 points or more technical evaluation points will have pricing evaluated and considered for award.
The State may utilize all bidder information, without regard to a proposal’s technical score, to determine fair market value for goods or services sought. The State is not obligated to accept the lowest price proposal. If applicable, the State’s evaluation will include consideration of a bidder’s qualified disabled veterans/service -disabled veteran owned business(QVD/SDVOB) status under MCL 18.1261(8). Additional information on the SDVOB preference is available at: https://www.michigan.gov/dtmb/0,5552,7-358-82550_85746_48677- 412612--,00.html.
The State strongly encourages strict adherence to the Contract Terms. The State reserves the right to deem a bid non-responsive for failure to accept the Contract Terms. Nevertheless, the bidder may submit proposed changes to the Contract Terms in track changes (i.e., visible edits) with an explanation of the bidder’s need for each proposed change. Failure to include track changes with an explanation of the bidder’s need for the proposed change constitutes the bidder’s acceptance of the Contract Terms. General statements, such as that the bidder reserves the right to negotiate the terms and conditions, may be considered non-responsive.
http://www.legislature.mi.gov/(S(12rtpbjmznw1mn4opquus2gz))/mileg.aspx?page=getObject&objectName=mcl-18-1261 https://www.michigan.gov/dtmb/0,5552,7-358-82550_85746_48677-412612--,00.html https://www.michigan.gov/dtmb/0,5552,7-358-82550_85746_48677-412612--,00.html
The State may but is not required to conduct an on-site visit to tour and inspect the bidder’s facilities; require an oral presentation of the bidder's proposal; conduct interviews, research, reference checks, and background checks; and request additional price concessions at any point during the evaluation process.
8. NOTICE OF DEFICIENCY. The State reserves the right to issue a Notice of Deficiency to bidders if the State determines after the proposal deadline that a portion of the RFP was deficient, unclear, or ambiguous.
Failure to respond to a Notice of Deficiency timely may be cause for disqualification.
9. CLARIFICATION REQUEST. The State reserves the right to issue a Clarification Request to a bidder to clarify its proposal if the State determines the proposal is not clear. Failure to respond to a Clarification Request timely may be cause for disqualification.
10. RESERVATIONS. The State reserves the right to:
a. Disqualify a bidder for failure to follow these instructions.
b. Discontinue the RFP process at any time for any or no reason. The issuance of an RFP, your preparation and submission of a proposal, and the State’s subsequent receipt and evaluation of your proposal does not commit the State to award a contract to you or anyone, even if all the requirements in the RFP are met.
c. Consider late proposals if: (i) no other proposals are received; (ii) no complete proposals are received; (iii) the State received complete proposals, but the proposals did not meet mandatory minimum requirements or technical criteria; or (iv) the award process fails to result in an award.
d. Consider an otherwise disqualified proposal, if no other proposals are received.
e. Disqualify a proposal based on: (i) information provided by the bidder in response to this RFP; (2) the bidder’s failure to complete registration on www.michigan.gov/SIGMAVSS ; or (3) if it is determined that a bidder purposely or willfully submitted false or misleading information in response to the RFP.
f. Consider prior performance with the State in making its award decision.
g. Consider overall economic impact to the State when evaluating proposal pricing and in the final award recommendation. This includes but is not limited to: considering principal place of performance, number of Michigan citizens employed or potentially employed, dollars paid to Michigan residents, Michigan capital investments, job creation, tax revenue implications, and economically disadvantaged businesses.
h. Consider total-cost-of-ownership factors (e.g., transition and training costs) when evaluating proposal pricing and in the final award recommendation.
i. Refuse to award a contract to any bidder that has failed to pay State taxes or has outstanding debt with the State.
j. Enter into negotiations with one or more bidders on price, terms, technical requirements, or other deliverables.
k. Award multiple, optional-use contracts, or award by Contract Activity.
l. Evaluate the proposal outside the scope identified in Section 8, Evaluation Process, if the State receives only one proposal.
11. AWARD RECOMMENDATION. The contract will be awarded to the responsive and responsible bidder who offers the best value to the State, as determined by the State. Best value will be determined by the bidder meeting the minimum point threshold and offering the best combination of the factors stated in Section 8, Evaluation Process, and price, as demonstrated by the proposal. The State will post a Notice of Recommendation for Award on www.michigan.gov/SIGMAVSS .
12. DEBRIEF MEETING AND BID PROTEST. The State will post a Notice of Recommendation for Award, which will provide instructions on how to request a debrief meeting
If you wish to initiate a protest of the award, you must submit your written protest to the Solicitation Manager no later than 2 calendar days after posting the Notice of Recommendation for Award, or by 9:00 a.m. the next business day if that date falls on a state holiday or weekend. The State reserves the right to adjust this timing and will publish any change on the SIGMA VSS system.
Additional information about the protest process is available at www.michigan.gov/micontractconnect under the “Programs and Policies” link.
13. STATE ADMINISTRATIVE BOARD. Contracts equal to $500,000 or greater than require approval by the State Administrative Board. The State Administrative Board’s decision is final; however, its approval does http://www.michigan.gov/SIGMAVSS http://www.michigan.gov/micontractconnect not constitute a contract. The award process is not complete until the awarded contractor receives a contract fully executed by all parties.
14. GENERAL CONDITIONS. The State will not be liable for any costs, expenses, or damages incurred by a bidder participating in this solicitation. The bidder agrees that its proposal will be considered an offer to do business with the State in accordance with its proposal, including the Contract Terms, and that its proposal will be irrevocable and binding for a period of 180 calendar days from date of submission. If a contract is awarded to the bidder, the State may, at its option, incorporate any part of the bidder’s proposal into a contract. This RFP is not an offer to enter into a contract. This RFP may not provide a complete statement of the State’s environment, or contain all matters upon which agreement must be reached. Other than verified trade secrets, proposals submitted via www.michigan.gov/SIGMAVSS are the State’s property.
15. CONFIDENTIAL TREATMENT FORM AND THE FREEDOM OF INFORMATION ACT. All portions of the bidder’s proposal and resulting contract are subject to disclosure as required under Michigan’s Freedom of Information Act (FOIA), MCL 15.231, et seq. However, some information may be exempt from disclosure.
Under MCL 18.1261(13)(b), records containing “a trade secret as defined under section 2 of the uniform trade secrets act, 1998 PA 448, MCL 445.1902,” are exempt from disclosure under FOIA. In addition, “financial or proprietary information” submitted with a bidder’s proposal is exempt from disclosure under FOIA. A bidder’s failure to comply with this Section is grounds for rejecting a bidder’s proposal as non-responsive. As a part of its proposal, each bidder must follow the procedure below.
a. SUBMIT A COMPLETED “CONFIDENTIAL TREATMENT FORM” (CT FORM) WITH YOUR BID.
Completion and submission of the CT Form is required regardless of whether the bidder seeks confidential treatment of information. Failure to submit a completed CT Form may be cause for disqualification from the solicitation process.
i. Complete and sign Section 1 of the CT Form if the bidder does NOT request confidential treatment of information contained in its proposal; or
ii. Complete and sign Section 2 of the CT Form if the bidder requests confidential treatment of certain information. Bidder must also submit a “Public Copy” of the proposal with the trade secret, financial, and proprietary information redacted and clearly labeled as the “Public Copy.”
b. FOIA REQUESTS. If a FOIA request is made for a bidder’s proposal, the Public Copy may be distributed to the public along with the bidder’s CT Form. The CT Form is a public document and serves as an explanation for the redactions to the Public Copy. Do not put any trade secret, financial, or proprietary information in the CT Form. Do not redact the CT Form itself.
c. NO ADVICE. The State will not advise a bidder as to the nature or content of documents entitled to protection from disclosure under FOIA or other laws, as to the interpretation of such laws, or as to the definition of trade secret or financial or proprietary information. Nothing contained in this provision will modify or amend requirements and obligations imposed on the State by FOIA or other applicable law.
d. FAILURE TO REQUEST CONFIDENTIAL TREATMENT. Failure to request material be treated as confidential as specified herein relieves the State, its agencies, and personnel from any responsibility for maintaining material in confidence.
e. Bids containing a request to maintain an entire proposal as confidential may be rejected as non-responsive. Bidders may not request confidential treatment with respect to resumes, pricing, and marketing materials. The State reserves the right to determine whether material designated as exempt by a bidder falls under MCL 18.1261 or other applicable FOIA exemptions. If a FOIA request is made for materials that the bidder has identified as trade secret, financial, or proprietary information, the State has the final authority to determine whether the materials are exempt from disclosure under FOIA.
f. Bidder forever releases the State, its departments, subdivisions, officers, and employees from all claims, rights, actions, demands, damages, liabilities, expenses and fees, which arise out of or relate to the disclosure of all or a portion of bidder’s proposal submitted under this RFP. Bidder must defend, indemnify and hold the State, its departments, subdivisions, officers, and employees harmless, without limitation, from and against all actions, claims, losses, liabilities, damages, costs, attorney fees, and expenses (including those required to establish the right to indemnification), arising out of or relating to any FOIA request, including potential litigation and appeals, related to the portion of bidder’s proposal submitted under this RFP that bidder has identified as a trade secret, or financial or proprietary information. The State will notify bidder in writing if indemnification is sought. The State is entitled to: (i) regular updates on proceeding status; (ii) participate in the defense of the proceeding; (iii) employ its own counsel; and to (iv) retain control of the defense, or any portion thereof, if the State deems necessary. Bidder will not, without the State’s written consent (not to be unreasonably withheld), settle, compromise, or consent to the entry of any judgment in or otherwise seek to terminate any claim, action, or proceeding. If a State employee, official, or law is involved or challenged, the State may control the defense of that portion of the claim. Any litigation activity on behalf of the State, or any of its subdivisions under this Section, must be coordinated with the Department of Attorney General. An attorney designated to represent the State may not do so until approved by the Michigan Attorney General and appointed as a Special Assistant Attorney General.
CONFIDENTIAL TREATMENT FORM (CT FORM)
INSTRUCTIONS. Complete either Section 1 or Section 2 of this CT Form and sign where indicated. This CT Form must be signed by the individual who signed the bidder’s proposal. A completed CT Form must be submitted with your proposal, regardless of whether your proposal contains confidential information. Failure to submit a completed CT Form with your bid is grounds for rejecting the proposal as non-responsive. See Section 16 of the Proposal Instructions for additional information.
Section 1. Confidential Treatment Is Not Requested
This section must be completed, signed, and submitted with the proposal if bidder does not request confidential treatment of any material contained in the proposal.
By signing below, the bidder affirms that confidential treatment of material contained in the proposal is not requested.
RFP Number RFP Title
Signature Date
[Printed Name] [Title] [Company]
Section 2. Confidential Treatment Is Requested
The section must be completed, signed, and submitted with the proposal if bidder requests confidential treatment of any material contained in the proposal. Submission of a completed CT Form is required to request confidential treatment.
Provide the information in the table below. Bidder may add rows or additional pages using the same format shown in the table. Bidder must specifically identify the information to be protected as confidential and state the reasons why protection is necessary. The CT Form will not be considered fully complete unless, for each confidentiality request, the bidder: (1) identifies whether the material is a trade secret (TS), financial information (FI), or proprietary information (PI); (2) explains the specific legal grounds that support treatment of the material as TS, FI, or PI; and (3) provides the contact information for the person at bidder’s organization authorized to respond to inquiries by the State concerning the material. Bidders must not simply cite to an applicable act or case name; rather, bidders must provide a complete justification as to how the material falls within the scope of an applicable act or relevant case law.
CONFIDENTIAL TREATMENT FORM (CT FORM)
RFP page #, paragraph #, and section #
State whether the material is a trade secret (TS), financial information (FI), or proprietary information
(PI)
Explain the specific grounds in State or other applicable law which supports treatment of the material as TS, FI, or PI. Do not simply cite to the applicable act. Provide a complete justification as to how the material falls within the scope of the applicable act or relevant case law.
Provide the bidder contact information
By signing below, the bidder affirms that confidential treatment of material contained in its proposal is requested and has attached to this form a redacted “Public Copy” of the bidder’s proposal.
RFP Number RFP Title
Signature Date
[Printed Name] [Title] [Company]
VENDOR QUESTIONS WORKSHEET
Provide a detailed response to each question. “You” and “company” refers to the bidder.
Information Sought Bidder Response
1. Contact Information Bidder’s sole contact person during the RFP process.
Include name, title, address, email, and phone number.
Person authorized to receive and sign a resulting contract. Include name, title, address, email, phone number and vendor customer code in SIGMA VSS.
2. Company Background Information Legal business name and address. Include business entity designation, e.g., sole proprietor, Inc., LLC, or
LLP.
What state was the company formed in?
Phone number Website address Number of years in business and number of employees Legal business name and address of parent company, if any Has there been a recent change in organizational structure (e.g., management team) or control (e.g., merger or acquisition) of your company? If the answer is yes: (a) explain why the change occurred and (b) how this change has affected your company.
Discuss your company’s history. Has growth been organic, through mergers and acquisitions, or both?
Has bidder ever been debarred, suspended, or disqualified from bidding or contracting with any entity, including the State of Michigan? If yes, provide the date, the entity, and details about the situation.
Has your company been a party to litigation against the State of Michigan? If the answer is yes, then state the date of initial filing, case name and court number, and jurisdiction.
Within the last 5 years, has your company or any of its related business entities defaulted on a contract or had a contract terminated for cause? If yes, provide the date, contracting entity, type of contract, and details about the termination or default.
State your gross annual sales for each of the last 5 years.
If receiving a contract under this RFP will increase your gross revenue by more than 25% from last year’s sales, explain how the company will scale-up to manage this increase.
Describe partnerships and strategic relationships you think will bring significant value to the State.
State the physical address of the place of business that would have primary responsibility for this account if bidder is awarded a contract under this RFP.
3. Qualified Disabled Veteran/Service Disabled
Veteran-Owned Business Program Under MCL 18.1261, a “qualified disabled veteran” means a business entity that is 51% or more owned by 1
Enter YES or NO.
http://www.legislature.mi.gov/(S(b2idoibk3wwdcrok5bm0s021))/mileg.aspx?page=getObject&objectName=mcl-18-1261 or more veterans with a service-connected disability. A “service-connected disability” means a disability incurred or aggravated in the line of duty in the active military, naval, or air service as described in 38 USC 101(16).
Are you a qualified disabled veteran?
To demonstrate qualification as a qualified disabled veteran, you must provide:
(a) Proof of service and conditions of discharge (DD214 or equivalent);
(b) Proof of service-connected disability (DD214 if the disability was documented at discharge or Veterans Administration Rating Decision Letter or equivalent if the disability was documented after discharge); and
(c) Legal documents setting forth the ownership of the business entity.
In lieu of the documentation identified above, you may provide proof of certification by the National Veterans Business Development Council.
Enter the names of documents submitted with your proposal to demonstrate status as a qualified disabled veteran.
4. Participation in RFP Development or Evaluation Did your company, an employee, agent, or representative of your company, or any affiliated entity participate in developing any component of this solicitation? For purposes of this question, business concerns, organizations, or individuals are affiliates of each other if, directly or indirectly: (1) either one controls or has power to control the other or (2) a third party controls or has the power to control both. Indicia of control include, but are not limited to, interlocking management or ownership, identity of interests among family members, shared facilities or equipment, and common use of employees.
If you entered “YES”, you are not eligible for contract award or to work as a subcontractor for the awarded vendor.
If you are awarded a contract under this solicitation, in order to provide the goods or services required under a resulting contract, do you intend to partner or subcontract with a person or entity that assisted in the development of this solicitation?
If you entered “YES,” you are not eligible for contract award. An awarded vendor may not partner or subcontract with anyone to provide goods and services required under a resulting contract if that subcontractor or partner assisted in the development of this solicitation.
Will your company, or an employee, agent, or representative of your company, participate in the evaluation of the proposals received in response to this
RFP?
If you entered “YES”, you are not eligible for contract award or to work as a subcontractor for the awarded vendor.
5. State of Michigan Experience and Prior Experience Does your company have experience working with the State of Michigan? If so, please provide a list (including the contract number) of the contracts you hold or have held with the State for the last 10 years.
Describe at least 3 relevant experiences from the last 5 years supporting your ability to successfully manage a contract of similar size and scope for the work described in this RFP.
Experience 1 Company name Contact name Contact role at time of project Contact phone Contact email City State Zip
1. Project name and description of the scope of the project
2. What role did your company play?
3. How is this project experience relevant to the subject of this RFP?
Dollar value Start and end date (mm/yy – mm/yy) Status (completed, live, other – specify phase) Results obtained Experience 2 Company name Contact name Contact role at time of project Contact phone Contact email City State Zip
1. Project name and description of the scope of the project
2. What role did your company play?
3. How is this project experience relevant to the subject of this RFP?
Dollar value Start and end date (mm/yy – mm/yy) Status (completed, live, other – specify phase) Results obtained Experience 3 Company name Contact name Contact role at time of project Contact phone Contact email City State Zip
1. Project name and description of the scope of the project
2. What role did your company play?
3. How is this project experience relevant to the subject of this RFP?
Dollar value Start and end date (mm/yy – mm/yy) Status (completed, live, other – specify phase) Results obtained
6. Standard Contract Terms Bidder must affirm agreement with the attached Contract Terms. If not in agreement, written exceptions in accordance with Section 8 Evaluation Process must be provided with Bidder’s proposal.
7. Other Abusive Labor Practices. The Contractor certifies that it will not furnish any Deliverable that was produced fully or partially by forced labor, forced or indentured child labor, or indentured servitude.
Enter YES or NO.
Certification of Michigan Business- Public Act 431 of 1984, Sec. 268. I certify that the company has, pursuant to the provisions of Sec 268 of Public Act 431 of 1984, filed a Michigan Business Tax Corporate Income Tax Return. I certify that the company has, pursuant to the provisions of Sec 268 of Public Act 431 of 1984, filed a Michigan Income Tax return showing income generated in, or attributed to the State of Michigan. I certify that the company has, pursuant to the provisions of Sec 268 of Public Act 431 of 1984, withheld Michigan Income Tax from compensation paid to the company’s owners and remitted the tax to the Michigan Department of Treasury.
Iran Linked Business- Public Act 517 of 2012. I certify that the Company is not an Iran-Linked business as defined by Public Act 517 of 2012.
Enter YES or NO.
Clean Corporate Citizen. I certify that the Company is a Clean Corporate Citizen as defined by the Environmental Protection Act, 1994 PA 451.
Enter YES or NO.
Convict Labor. The Contractor certifies that if using convict labor, it is complying with all applicable state and federal laws and policies.
Enter YES or NO.
SOM Debt/Tax Payment. All SOM tax/debts. I certify that all applicable State of Michigan taxes are paid, and that no outstanding debt is owed to the State of Michigan.
Enter YES or NO.
Authorization to Verify Information provided by Vendor. I authorize the State to verify that all information provided in this registration, in bidding and contracting documents, and any attachments or supplement documents and processes are accurate.
Bidder must enter company name here.
Version 2 Revised Date: 2/2019
Request For Proposal No. 190000002527 Construction of Open Pavilion at Camp Grayling JMTC
SCHEDULE A
STATEMENT OF WORK
CONTRACT ACTIVITIES
This schedule identifies the anticipated requirements of any Contract resulting from this RFP. The term “Contractor” in this document refers to a bidder responding to this RFP.
The Contractor must respond to each requirement or question and explain how it will fulfill each requirement. Attach any supplemental information and appropriately reference within your response.
BACKGROUND
The State of Michigan Department of Military and Veterans Affairs, Camp Grayling Joint Maneuver Training Center in Grayling MI is seeking a State of Michigan licensed residential builder to provide all labor, materials, equipment and permits to construct an open pavilion over an existing concrete pad located in the cantonment area of Camp Grayling Joint Maneuver Training Center.
SCOPE
The awarded Contractor is responsible for providing all permits, labor, materials and equipment to construct a 40x30 pavilion over an existing slab that is 30 ft. x 36 ft. and nominal thickness of 4 inches according to the attached specification while following local building codes. No electrical or plumbing work required
REQUIREMENTS
1. General Requirements
1.1. Structural and Site Specifications:
• Contractor must provide all labor, materials and equipment necessary to construct the open pavilion according the RFP specifications and requirements.
• The open Pavilion detailed in this RFP must be constructed according to State and Local building codes.
• Contractor must be a licensed residential builder within the State of Michigan
• Contractor is required to pull and pay for all required building permits
• Camp Grayling JMTC staff will mark all utilities.
• Low pitch beams – Structural glue laminated timber shall be in conformance with AITC Standard Species.
Laminating lumber shall be kiln-dried, architectural grade, sealed and wrapped. The roof system must be designed to withstand a minimum 30 PSF live load, 115 MPH wind load and 50 PSF ground snow load. The roof slope shall be 5/12.
• Support Columns – All vertical support columns shall be spaced not more than 8 ft. apart. Columns shall be 5” tubular structural steel, powder coated (color-black) with welded bracket on top to connect to laminate beam. Bottom of support column shall have s Steel Base Shoe (powder coated) w/ ¾” Anchor Bolts F1554 Headed Anchors
• Footings – To avoid having to saw cut existing slab, new 24” x 48” footers shall be placed along outside perimeter of existing slab. (see attached detail). Column footings and beam connections to be designed and sealed by professional engineer.
• Connector Plates – Plates shall be fabricated from structural steel ASTM-A-36. Plates to be powder coated black. Hardware: A-325 zinc plated machine bolts and nuts.
• Roof Decking – 2” x 6” (nominal), #1 grade, single tongue and groove with V-joint on bottom face, kiln dried southern yellow pine, maximum moisture content shall be less than 19% or less selected for decking.
Specified lengths, with all joints over supports. All laminate beams shall have three coats of clear satin polyurethane.
• Shingles – Class “A” fire rated, architectural grade, laminated fiberglass shingle with a 30 year limited warranty. To be installed over 30 lb. felt. Roof application as per manufacturer’s specifications. Color to be Burnt Sienna. Fasteners shall be conventional barb shanked roofing nails (11 or 12 gauge) with 3/8” diameter heads, 6 each per shingle.
Version 2 Revised Date: 2/2019
• Fascia – 2”x8” nom Cedar, “D”/Better Grade, kiln-dried, surfaced on four sides.
• Welding – All plates and brackets shall be welded in accordance with the American Welding Society (AWS), Structural Welding Code-Steel (AWS) standards.
• Landscaping – A 4’ x 4” border of washed stone shall be placed around perimeter of the structure to prevent erosion. Washed stone, 1” to 3”, shall be placed on top of woven geotextile.
• All site prep and cleanup shall be performed by contractor. All site clean up to be performed daily.
• See attached drawing for more details.
• BIDDER ACKNOWLEDGEMENT: By initialing below, Bidder acknowledges, understands and agrees to the above Requirements.
1.2 Bid Submission Requirements:
The Contactor MUST provide the following items with bid submission. If these items are not included in the bid submission the Contractor’s bid may be disqualified and not reviewed:
• A copy of State of Michigan Residential Builders License
• Detailed Bill of Materials for entire project (include quantities, description, grade, colors, etc.)
• Project Plan with Project time- line detailing major milestones.
• Disclosure of subcontractors and all items detailed in Section 3.7 (below)
BIDDER ACKNOWLEDGEMENT: By initialing below, Bidder acknowledges, understands and agrees to provide the above items at time of bid submission.
1.3. Warranties
Describe any warranties included in the bid and explain the process for reporting warranty issues and how the Contractor will handle any repairs or replacements.
The State reserves the right to require additional warranties other than those identified by the Contractor in its response to this RFP.
BIDDER ACKNOWLEDGEMENT: Please, detail warranties below or attach on a separate page.
Version 2 Revised Date: 2/2019
2. Service Levels
2.1. Time Frames
All Contract Activities must be delivered within 90 days from receipt of order. The receipt of order date is pursuant to Section 2, Notices, of the Standard Contract Terms.
2.2. Installation
Installation will be expected within 30 of the project start date. Installation will be considered complete when Camp Grayling JMTC Project Manager accepts the pavilion as complete and signs invoice..
2.3. Meetings
The Contractor must attend the following meetings:
A kickoff meeting within two weeks of receipt of order unless otherwise notified by Camp Grayling JMTC Project Manager.
The State may request other meetings as it deems appropriate.
3. Staffing
3.1. Contractor Representative
The Contractor must appoint a Project Manager specifically assigned to State of Michigan accounts, that will respond to State inquiries regarding the Contract Activities, answering questions related to ordering and delivery, etc. (the “Contractor Representative”).
3.2. Key Personnel
The Contractor must appoint a Project Manager (can be same as Contractor Representative) who will be directly responsible for the day to day operations of the Contract (“Key Personnel”). Key Personnel must be specifically assigned to the State account, be knowledgeable on the contractual requirements, and respond to State inquires within 2 hours.
Contractor’s Key Personnel must be on-site during all construction activities
The Contractor may not remove or assign Key Personnel without the prior consent of the State. Prior consent is not required for reassignment for reasons beyond the Contractor’s control, including illness, disability, death, leave of absence, personal emergency circumstances, resignation, or termination for cause. The State may request a résumé and conduct an interview before approving a change. The State may require a 30 calendar day training period for replacement personnel.
The Contractor must identify the Key Personnel, indicate where they will be physically located, describe the functions they will perform, and provide current chronological résumés.
3.3. Non-Key Personnel
The Contractor must notify the Contract Administrator at least 10 calendar days before removing or assigning non-key personnel.
3.4. Disclosure of Subcontractors
If the Contractor intends to utilize subcontractors, the Contractor must disclose the following:
The legal business name; address; telephone number; a description of subcontractor’s organization and the services it will provide; and information concerning subcontractor’s ability to provide the Contract Activities.
The relationship of the subcontractor to the Contractor.
Whether the Contractor has a previous working experience with the subcontractor. If yes, provide the details of that previous relationship.
A complete description of the Contract Activities that will be performed or provided by the subcontractor.
COPY OF THE SUBCONTRACTORS BUILDERS LICENSE MUST BE SUBMITTED WITH CONTRACT BID
Version 2 Revised Date: 2/2019
3.8. Security
It is the Contractors responsibility to ensure that the materials at the site are kept secure, at all time. the State of Michigan DMVA Camp Grayling will not responsible for materials necessary for the construction of this pavilion that are lost or stolen.
It is the Contractors responsibility to ensure that the work area is kept clean an organized so as not to cause an eye sore or safety issue for visitors to Camp Grayling JMTC
The Contractor must explain any additional security measures in place to ensure the security of State facilities.
The bidder’s staff may be required to make deliveries to or enter State facilities. The bidder must: (a) explain how it intends to ensure the security of State facilities, (b) whether it uses uniforms and ID badges, etc., (c) identify the company that will perform background checks, and (d) the scope of the background checks. The State may require the Contractor’s personnel to wear State issued identification badges.
4. Pricing
4.1. Price Term
Pricing is firm for the entire length of the Contract.
5. Ordering
5.1. Authorizing Document
The appropriate authorizing document for the Contract will be a Purchase Order
5.2 Order Verification
The Contractor must have internal controls, approved by Central Procurement Services, to verify abnormal orders and to ensure that only authorized individuals place orders.
6. Delivery
6.1. Delivery Programs
The Contractor must explain in detail its delivery programs (e.g., standard delivery and quick-ship), including any limitations such as quantity.
The Contractor must explain the transportation method (e.g., UPS, FedEx, Contractor fleet, or other third party carrier) it intends on utilizing in delivery of the Contract Activities.
6.2. Packaging and Palletizing
Packaging must be optimized to permit the lowest freight rate. Shipments must be palletized whenever possible using manufacturer's standard 4-way shipping pallets.
7. Acceptance
7.1. Final Acceptance
Final acceptance will be given by the Camp Grayling JMTC Project Manager by signing off on final documents and invoices.
8. Invoice and Payment
8.1. Invoice Requirements
All invoices submitted to the State must include: (a) date; (b) purchase order; (c) quantity; (d) description of the Contract Activities; (e) unit price; (f) shipping cost (if any); and (g) total price.
8.2. Payment Methods
The State will make payment for Contract Activities via EFT.
9. Project Plan
Version 2 Revised Date: 2/2019
The Contractor will carry out this project under the direction and control of the Program Manager. Within 10 calendar days of the Effective Date, the Contractor will submit a project plan to the Program Manager for final approval. The plan must include: (a) the Contractor's organizational chart with names and title of personnel assigned to the project, which must align with the staffing stated in accepted proposals; and (b) the project breakdown showing sub-projects, tasks, and resources required.
10. Licensing Agreement The Contractor must provide a copy of any applicable licensing agreement.
12. Additional Requirements
12.1. Environmental and Energy Efficient Products
The Contractor must identify any energy efficient, bio-based, or otherwise environmental friendly products used in the products. Contractor must include any relevant third-party certification, including the verification of a United States department of agriculture certified bio based product label.
12.2. Hazardous Chemical Identification
In accordance with the federal Emergency Planning and Community Right-to-Know Act, 42 USC 11001, et seq., as amended, the Contractor must provide a Material Safety Data Sheet listing any hazardous chemicals, as defined in 40 CFR §370.2, to be delivered. Each hazardous chemical must be properly identified, including any applicable identification number, such as a National Stock Number or Special Item Number.
The Contractor must identify any hazardous chemicals that will be provided under any resulting contract.
12.3. Mercury Content
Pursuant to MCL 18.1261d, mercury-free products must be procured when possible. The Contractor must explain if it intends to provide products containing mercury, the amount or concentration of mercury, and whether cost competitive alternatives exist. If a cost competitive alternative does exist, the Contractor must provide justification as to why the particular product is essential. All products containing mercury must be labeled as containing mercury.
12.4. Brominated Flame Retardants
The State prefers to purchase products that do not contain brominated flame retardants (BFRs) whenever possible.
The Contractor must disclose whether the products contain BFRs.
Asphalt Shingles
42'-5"
PROPOSED NEW
CLASSROOM PAVILION
SCHEDULE A-EXHIBIT 1
30'
2'
4'
36'-5"
8'
2x8 nom Cedar
Fascia Board
4' x 4" Border of Washed Stone
Woven Geotextile Fabric
Side View
Existing 30' x 36' concrete slab
4 ' x 4" Border of 2" washed stone
5" x .5" Tubular Steel
Powder Coated (Black)
Footing and Column Layout
#6 Vertical Ties
6 Equally Spaced
#4 Horiz Tie
8" O.C.
2'
4'
4"
Existing Concrete Slab
1'
Steel Base Shoe (Powder Coated) w/
" Galvanized Steel Anchor Bolts and Washers
3"
3"
8'
5" x .5" Tubular Steel Column
Powder Coated (Black)
Footing Detail
Enter company name here.
Version 1 Revised Date: 7/28/2017
Request For Proposal No. 190000002527 Construction of Open Pavilion at Camp Grayling JMTC
SCHEDULE B
PRICING MATRIX
1. The Contractor must provide a pricing schedule for the proposed Contract Activities using the spreadsheet below. The pricing schedule should be submitted in a modifiable format (e.g.. Microsoft Word or Excel);
however, you may also submit an additional pricing schedule in a non-modifiable format (e.g., PDF). Failure to complete the pricing schedule as requested may result in disqualification of your proposal.
2. Price proposals must include all costs, including but not limited to, any one-time or set-up charges, fees, and potential costs that Contractor may charge the State (e.g., shipping and handling, per piece pricing, and palletizing).
3. The Contractor is encouraged to offer quick payment terms. The number of days must not include processing time for payment to be received by the Contractor's financial institution.
Quick payment terms: ________ % discount off invoice if paid within ________ days after receipt of invoice.
4. By submitting its proposal, the Contractor certifies that the prices were arrived at independently, and without consultation, communication, or agreement with any other Contractor.
Description Total Amount** Construction, including but not limited to all labor, materials, equipment and permits, of an open pavilion at Camp Grayling JMTC per Schedule A specifications and Exhibit 1 drawings.
*Must include all costs associated with the construction and completion of the work activities detailed in the associated RFP
Version 6 (2/2019) 1
This STANDARD CONTRACT (“Contract”) is agreed to between the State of Michigan (the “State”) and [Insert Company Name] (“Contractor”), a [Insert State & Entity Status, e.g., a Michigan corporation or a Texas limited liability company]. This Contract is effective on July 15, 2019 (“Effective Date”), and unless terminated, expires on July 1, 2020.
The parties agree as follows:
1. Duties of Contractor. Contractor must perform the services and provide the deliverables described in Schedule A – Statement of Work (the “Contract Activities”). An obligation to provide delivery of any commodity is considered a service and is a Contract Activity.
Contractor must furnish all labor, equipment, materials, and supplies necessary for the performance of the Contract Activities, and meet operational standards, unless otherwise specified in Schedule A.
Contractor must: (a) perform the Contract Activities in a timely, professional, safe, and workmanlike manner consistent with standards in the trade, profession, or industry; (b) meet or exceed the performance and operational standards, and specifications of the Contract; (c) provide all Contract Activities in good quality, with no material defects; (d) not interfere with the State’s operations; (e) obtain and maintain all necessary licenses, permits or other authorizations necessary for the performance of the Contract; (f) cooperate with the State, including the State’s quality assurance personnel, and any third party to achieve the objectives of the Contract; (g) return to the State any State-furnished equipment or other resources in the same condition as when provided when no longer required for the Contract; (h) not make any media releases without prior written authorization from the State; (i) assign to the State any claims resulting from state or federal antitrust violations to the extent that those violations concern materials or services supplied by third parties toward fulfillment of the Contract; (j) comply with all State physical and IT security policies and standards which will be made available upon request; and (k) provide the State priority in performance of the Contract except as mandated by federal disaster response requirements. Any breach under this paragraph is considered a material breach.
Contractor must also be clearly identifiable while on State property by wearing identification issued by the State, and clearly identify themselves whenever making contact with the State.
2. Notices. All notices and other communications required or permitted under this Contract must be in writing and will be considered given and received: (a) when verified by written receipt if sent by courier; (b) when actually received if sent by mail without verification of receipt; or (c) when verified by automated receipt or electronic logs if sent by facsimile or email.
If to State: If to Contractor:
Elizabeth Noffsinger Camp Grayling JMTC 1000 M-93 Building 4, Headquarters Grayling, MI 49738 989-344-6190 noffsingere@michigan.gov
[Name] [Street Address] [City, State, Zip] [Email] [Phone]
3. Contract Administrator. The Contract Administrator for each party is the only person authorized to modify any terms of this Contract, and approve and execute any change under this Contract (each a “Contract Administrator”):
State: Contractor:
State: Elizabeth Noffsinger [Name]
STANDARD CONTRACT TERMS
Version 6 (2/2019) 2
Camp Grayling JMTC 1000 M-93 Building 4, Headquarters Grayling, MI 49738 989-344-6190 noffsingere@michigan.gov
[Street Address] [City, State, Zip] [Email] [Phone]
4. Program Manager. The Program Manager for each party will monitor and coordinate the day-to-day activities of the Contract (each a “Program Manager”):
State: Contractor:
Byron Smith Camp Grayling JMTC 1000 M-93 Building 36, DPW Grayling, MI 49738 989-344-6764 Byron.a.smith.mil@mail.mil
[Name] [Street Address] [City, State, Zip] [Email] [Phone]
5. Performance Guarantee. Contractor must at all times have financial resources sufficient, in the opinion of the State, to ensure performance of the Contract and must provide proof upon request. The State may require a performance bond (as specified in Schedule A) if, in the opinion of the State, it will ensure performance of the Contract.
6. Insurance Requirements. Contractor must maintain the insurances identified below and is responsible for all deductibles. All required insurance must: (a) protect the State from claims that may arise out of, are alleged to arise out of, or result from Contractor's or a subcontractor's performance; (b) be primary and non-contributing to any comparable liability insurance (including self-insurance) carried by the State; and (c) be provided by a company with an A.M. Best rating of "A-" or better, and a financial size of VII or better.
Required Limits Additional Requirements Commercial General Liability Insurance
Minimum Limits:
$1,000,000 Each Occurrence Limit $1,000,000 Personal & Advertising Injury Limit…