This is a Request for Proposal (RFP) issued by Lake Region State College, located in Devils Lake, North Dakota, for a 2025 Roof Rehabilitation & Replacement Project. The RFP seeks a contractor to perform roof renovation on multiple campus sections, covering approximately 134,000 sq. ft. of EPDM (Ethylene Propylene Diene Monomer) roof restoration using a fully reinforced liquid applied membrane. The project involves removing wet insulation, repairing perimeter failures, addressing drainage issues, sealing and flashing various roof components, and applying a two-coat polyurethane elastomeric fluid-applied roofing system. A mandatory site inspection is scheduled for August 4, 2025, at 12:00 PM CT, and proposals are due by August 15, 2025, at 12:00 PM CT. The contract term is anticipated to run from approximately September 1, 2025, until August 1, 2026.
The project requires a 25-year No Dollar Limit (NDL) Labor and Materials Warranty from the manufacturer. Contractors must be qualified, with a full-time on-site supervisor having a minimum of three years' experience installing similar products. The basis of design product is the Tremco AlphaGuard MTS System, which includes a base coat and top coat with specific performance requirements such as low VOC content, accelerated weathering resistance, and specific coating thickness. The evaluation will be conducted on a 100-point scale, with 60 points allocated to the technical proposal (40 points for Scope of Work Strategy and 20 points for Experience and Qualifications) and 40 points for the cost proposal. The state sales tax exemption number is E-5421, and the project is funded through existing appropriated funds.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF NORTH DAKOTA
LAKE REGION STATE COLLEGE
1801 N. COLLEGE DRIVE
DEVILS LAKE, ND 58301
REQUEST FOR PROPOSAL (RFP)
RFP Title: 2025 Roof Rehabilitation & Replacement Project
RFP Number: 100.06.18.2025
Issued: July 25, 2025
TABLE OF CONTENTS
SECTION ONE – INSTRUCTIONS
1.1 PURPOSE OF RFP
1.2 PROCUREMENT OFFICER CONTACT INFORMATION
1.3 DEFINITIONS
1.4 RFP SCHEDULE
1.5 ASSISTANCE TO INDIVIDUALS WITH A DISABILITY
1.6 SECRETARY OF STATE REGISTRATION REQUIREMENTS
1.7 BIDDERS LIST REGISTRATION
1.8 STATE PROCUREMENT WEBSITE (SPO ONLINE)
1.9 AMENDMENTS TO THE RFP
1.10 DEADLINE FOR QUESTIONS AND OBJECTIONS
1.11 SITE INSPECTION
1.12 OFFER HELD FIRM
1.13 OFFEROR RESPONSIBLE FOR COSTS
1.14 TAXES
1.15 F.O.B. POINT AND FREIGHT
1.16 PROPOSAL RECEIPT DEADLINE – LATE PROPOSALS REJECTED
1.17 PROPOSAL OPENING
1.18 AMENDMENT AND WITHDRAWAL OF PROPOSALS
1.19 NEWS RELEASES
1.20 CONFLICT OF INTEREST
1.21 ATTEMPT TO INFLUENCE PROHIBITED
1.22 COLLUSION PROHIBITED
1.23 PROTEST AND APPEAL
1.24 SPECIFICATIONS PREPARED BY NON-STATE PERSONNEL
1.25 SUPPLIER REGISTRATION (PAYEE)
SECTION TWO – BACKGROUND
2.1 BACKGROUND INFORMATION
2.2 BUDGET
SECTION THREE – SCOPE OF WORK
3.1 SCOPE OF WORK
3.2 APPLICABLE DIRECTIVES
3.3 REQUIREMENTS
A. Deliverables B. Location Of Work/Travel C. State-Furnished Property/Services D. Risk Management E. Access To Site F. Coordination With Occupants G. Work Restrictions H. Technical Exhibit I. Project Management Plan J. Contract Term, Schedule, and Deliverables
3.4 EXPERIENCE AND QUALIFICATIONS
A. Minimum Qualifications ............................................................................................... Error! Bookmark not defined.
SECTION FOUR – PROPOSAL INSTRUCTIONS
4.1 PROPOSAL PREPARATION
4.2 PROPOSAL SUBMISSION INSTRUCTIONS
4.3 PROPOSAL FORMAT
4.4 TECHNICAL PROPOSAL
4.5 COST PROPOSAL
4.6 SAMPLES
4.7 BONDS
SECTION FIVE – AWARD AND PROPOSAL EVALUATION
5.1 AWARD
5.2 RESPONSIVENESS
5.3 RESPONSIBILITY – SUPPLEMENTARY INVESTIGATION
5.4 EVALUATION CRITERIA
5.5 COST PROPOSAL EVALUATION
5.6 CLARIFICATIONS OF PROPOSALS – DISCUSSIONS
5.7 RIGHT OF REJECTION
5.8 PRESENTATIONS, DEMONSTRATIONS, AND SITE VISITS
5.9 BEST AND FINAL OFFERS
5.10 TIE PROPOSALS
5.11 NEGOTIATIONS
5.12 NOTICE OF INTENT TO AWARD
5.13 CONTRACT APPROVAL
5.14 EVALUATION DEBRIEFING
SECTION SIX – CONTRACT INFORMATION
6.1 NORTH DAKOTA CONTRACTUAL REQUIREMENTS – BACKGROUND
6.2 STATE CONTRACT TERMS AND CONDITIONS – OFFEROR’S PROPOSED CHANGES
6.3 CONTRACT PROVISIONS
A. Contract Type B. Payment Procedures C. Inspection & Modification D. Contract Changes – Unanticipated Amendments E. Purchasing Card
6.4 CONTRACTUAL TERMS AND CONDITIONS – NO MATERIAL CHANGES
6.5 SCOPE OF WORK
6.6 CONTRACT TERM
6.7 RIGHT TO INSPECT PLACE OF BUSINESS
ATTACHMENTS
3A – Technical Exhibit
3B – Technical Diagrams and Photographs
4A – Cost Proposal
5A – Technical Proposal Evaluation Worksheet
6A – Contract
SECTION ONE – INSTRUCTIONS
1.1 PURPOSE OF RFP
The State of North Dakota, acting through its Lake Region State College (the STATE) is soliciting proposals for roof rehabilitation and replacement.
1.2 PROCUREMENT OFFICER CONTACT INFORMATION
The Procurement Officer is the point of contact for this RFP. Offerors shall direct all communications regarding this RFP to the Procurement Officer. Do not add the Procurement Officer to any marketing distribution lists.
PROCUREMENT OFFICER: Sandi Lillehaugen EMAIL: Sandra.Lillehaugen@lrsc.edu
PHONE: 701-662-1543
A person or firm interested in submitting a proposal should ensure all communications related to the procurement are only with the designated point of contact. This section does not restrict communication with state officials or any member of the legislative assembly unless the state official or member of the legislative assembly is involved directly with the procurement for which the person is interested or has submitted a bid or proposal (N.D.C.C. § 54-44.4-01.1).
Engaging in unauthorized communication or seeking to obtain information about an open solicitation with any state employee or official other than the responsible Procurement Officer or designee is sufficient grounds for suspension or debarment. (N.D.A.C. § 4-12-05-04(7))
1.3 DEFINITIONS
For the purposes of this RFP, the acronyms and defined terms are as follows:
Acronym or Term Name or Definitions Contractor Entity that has an approved contract with the State of North Dakota
CT Central Time Zone
OMB Office of Management and Budget
RFP Request for Proposal
Solicitation Closing Deadline for receipt of proposals listed in the RFP Schedule
SPO Office of Management and Budget, State Procurement Office
SPO Online State Procurement Office Online system
1.4 RFP SCHEDULE
EVENT DATE and TIME
RFP issued July 25, 2025
Deadline for submission of Questions and Objections August 1, 2025 at 12:00PM, CT
Solicitation Amendment with responses to Questions issued approximately (if required)
August 5, 2025
Mandatory site inspections. August 4, 2025 at 12:00PM, CT
Deadline for receipt of proposals (Solicitation Closing) August 15, 2025 at 12:00PM, CT
Demonstrations or presentations (if needed). August 18, 2025
Proposal evaluation completed by approximately August 20, 2025
Notice of intent to award issued approximately August 22, 2025
Secretary of State Registration, if determined to be required.
Prior to Contract Signing
Contract start approximately Fall 2025 https://www.ndlegis.gov/cencode/t54c44-4.pdf http://www.legis.nd.gov/information/acdata/pdf/4-12-05.pdf?20130319105642
1.5 ASSISTANCE TO INDIVIDUALS WITH A DISABILITY
Contact the Procurement Officer, as soon as possible, if an individual with a disability needs assistance with the RFP, including any events in the RFP schedule, so reasonable accommodations can be made.
1.6 SECRETARY OF STATE REGISTRATION REQUIREMENTS
The North Dakota Secretary of State has registration requirements for individuals and businesses transacting business in North Dakota. If the successful Offeror is determined to have a registration requirement with the North Dakota Secretary of State, they must be registered before the contract award and registration must remain active for the duration of the contract period (N.D.C.C. § 54-44.4- 09.1)
• See the OMB Guidelines to Vendor Registry for more information.
Visit the Secretary of State's Vendor Registration webpage for information on registration requirements and fees. Visit FirstStop, the Secretary of State's business and licensing software, for online form options.
• Check the Business Records database to see if a business is registered.
• Contact Secretary of State's office by email or call 701-328-2900 (choose menu item 2, then option 1).
• If you need to register, fees apply.
• Vendors may need to obtain businesses licenses. See the list of licenses required of businesses in the State of North Dakota. The link includes information on who to contact, application fees, renewal dates, and the legal reference.
1.7 BIDDERS LIST REGISTRATION
Individuals or business entities desiring to be notified of bidding opportunities may apply to be placed on the Bidders List. (N.D.C.C. § 54-44.4-09) Bidders Lists are used to notify vendors when solicitations are issued on the State Procurement Office Online system (SPO Online). Placement on the Bidders List does not guarantee a vendor will receive notice of every solicitation (N.D.A.C. § 4-12-05-01). There are no fees to register as a bidder. The online application form requests contact information for the receipt of solicitation notices. The Bidders List application and SPO Online system use commodity codes to identify categories of goods, services, and information technology.
The commodity codes used for this solicitation are: 770-06, 770-23, 770-26, 770-45, 770-70, 770-93.
Visit the OMB website for instructions and the online Bidders List Application:
Bidders List Registration Website
For assistance with Bidders List Registration, contact State Procurement Help Desk at 701-328-1728 or infospo@nd.gov.
1.8 STATE PROCUREMENT WEBSITE (SPO ONLINE)
This RFP and any related amendments and notices will be posted on the North Dakota OMB website using SPO Online. Offerors are responsible for checking this website to obtain all information and documents related to this RFP: https://apps.nd.gov/csd/spo/services/bidder/main.htm
Select “Recent Solicitations”. Recent Solicitations are listed by close date.
Notices related to this RFP will be sent to the Bidders List for the needed commodity or service and other known potential Offerors.
https://www.ndlegis.gov/cencode/t54c44-4.pdf https://www.ndlegis.gov/cencode/t54c44-4.pdf https://www.omb.nd.gov/sites/www/files/documents/doing-business-with-the-state/procurement/vendor-reg-guidelines.pdf https://sos.nd.gov/business/vendors.html https://sos.nd.gov/firststop.html https://firststop.sos.nd.gov/search/business mailto:sos@nd.gov https://www.ndsu.edu/agriculture/extension/extension-topics/leadership-and-civic-engagement/business-leadership-and-resources-2 https://www.ndsu.edu/agriculture/extension/extension-topics/leadership-and-civic-engagement/business-leadership-and-resources-2 https://www.ndlegis.gov/cencode/t54c44-4.pdf https://www.ndlegis.gov/information/acdata/pdf/4-12-05.pdf https://www.omb.nd.gov/doing-business-state mailto:infospo@nd.gov https://apps.nd.gov/csd/spo/services/bidder/main.htm
Offerors not having completed the Bidders List registration may request to receive notices related to this RFP by contacting the Procurement Officer in writing with the following information: RFP title, business name, contact person, mailing address, telephone number, and email address.
1.9 AMENDMENTS TO THE RFP
If an amendment to this RFP is issued, it will be provided to all Offerors on the Bidders List for the solicitation and to those prospective Offerors who have contacted the Procurement Officer to receive notices related to the RFP. An Offeror shall include in their proposal any required acknowledgements of amendments to the RFP.
1.10 DEADLINE FOR QUESTIONS AND OBJECTIONS
Offerors should carefully review the RFP including all Attachments. Offerors may ask questions to obtain clarification and request additional information, or object to material in the RFP. Questions and objections must be submitted to the Procurement Officer in writing by the deadline identified in the RFP Schedule. If no deadline is specified, questions or objections must be received at least seven days prior to the Solicitation Closing deadline. The Procurement Officer may elect to respond to questions received after the deadline.
Questions and objections should include a reference to the applicable RFP section or subsection. Email is the preferred method of submission with the RFP number and title cited in the email subject line.
Responses to questions will be distributed as a solicitation amendment unless the question can be answered by referring the Offeror to a specific section of the RFP.
1.11 SITE INSPECTION
The STATE will hold a site inspection for the RFP. Participation is mandatory and only those Offerors in attendance are eligible to submit proposals, and proposals from Offerors not in attendance will be rejected. Questions and answers will be disseminated as a solicitation amendment to only those Offerors in attendance.
The site inspections will be held:
• Date: August 4, 2025
• Time: 12:00PM CST
• Location: Lake Region State College 1801 N. College Drive Devils Lake, ND 58301 Call Chad at 701-351-1521
1.12 OFFER HELD FIRM
Offerors must hold proposals firm for at least 180 days from the deadline for receipt of proposals (Solicitation Closing). The STATE may send a written request to all Offerors to hold their offer firm for a longer period of time.
1.13 OFFEROR RESPONSIBLE FOR COSTS
Offeror is responsible for all costs associated with the preparation, submittal, and evaluation of any proposal including any travel and per diem associated with demonstrations and presentations.
1.14 TAXES
The STATE is not responsible for and will not pay itemized local, state, or federal taxes. Purchases of tangible personal property made by a state government agency is exempt from sales tax. The state sales tax exemption number is E-5421, and certificates will be furnished upon request by the purchasing agency. The contractor must provide a valid Vendor Tax Identification Number as a provision of the contract.
The purchasing agency will determine if services provided under this contract are Form 1099 reportable. The purchasing agency may require the contractor to submit an IRS Form W-9.
The state tax exemption number should not be used by contractors in the performance of a contract.
A contractor or service provider performing any contract, including service contracts, for the United States Government, State of North Dakota, counties, cities, school districts, park board or any other political subdivisions within North Dakota is not exempt from payment of sales or use tax on materials, tangible personal property, and supplies used or consumed in carrying out contracts. In these cases, the contractor is required to file returns and pay sales and use tax just as required for contracts with private parties. Contact the North Dakota Tax Department at 701-328-1246 or visit their website at https://www.nd.gov/tax/tax-resources/ for more information.
A contractor performing any contract, including a service contract, within North Dakota is also subject to the corporation income tax, individual income tax, and withholding tax reporting requirements, whether the contract is performed by a corporation, partnership, or other business entity, or as an employee of the contractor. In the case of employees performing the services in the state, the contractor is required to withhold state income tax from the employees’ compensation and remit to the state as required by law. Contact the North Dakota Tax Department at 701-328-1248 or visit their website for more information.
1.15 F.O.B. POINT AND FREIGHT
All commodities purchased through this contract will be Free on Board (“F.O.B.”) final destination, freight prepaid. Unless specifically stated otherwise, all prices offered must include the delivery cost.
1.16 PROPOSAL RECEIPT DEADLINE – LATE PROPOSALS REJECTED
An Offeror is solely responsible for ensuring their proposal is received by the STATE prior to the Solicitation Closing deadline identified in the RFP schedule regardless of the method of submission. A solicitation amendment will be issued if this deadline is changed. An Offeror may contact the Procurement Officer to inquire whether their proposal has been received. Proposals delivered late will be rejected pursuant to N.D.A.C. § 4-12-08-13.
1.17 PROPOSAL OPENING
A public opening will not be held.
This is a formal sealed Request for Proposal (RFP) process. Proposals will be secured and held unopened until the Solicitation Closing deadline. Per N.D.A.C § 4-12-08-04, the openings may be made public at the discretion of the purchasing agency. If a public opening is held, only the names of Offerors that submitted proposals can be revealed at the opening, and each proposal will be opened in a manner to avoid disclosure of the contents to the competing Offerors.
1.18 AMENDMENT AND WITHDRAWAL OF PROPOSALS
Offeror may amend, supplement, or withdraw proposal prior to the Solicitation closing deadline. No changes will be accepted after the Solicitation closing deadline. After the Solicitation closing deadline, Offeror may make a written request to withdraw their proposal and shall provide evidence that a substantial mistake has been made, at which point the STATE may permit withdrawal.
1.19 NEWS RELEASES
Offerors shall not make any news releases related to this RFP without prior approval of the STATE.
1.20 CONFLICT OF INTEREST
Under state laws and rules, a state employee or official shall not participate directly or indirectly in a procurement when the state employee or official knows of a conflict of interest. Potential conflicts of interest include state employees or their immediate family members employed by the firm, seeking https://www.nd.gov/tax/tax-resources/ http://www.legis.nd.gov/information/acdata/pdf/4-12-08.pdf?20130424100739 https://www.legis.nd.gov/information/acdata/html/4-12.html employment with the firm, or with a financial interest in the firm. Potential conflicts of interest will be addressed in accordance with N.D.A.C. § 4-12-04-04. (N.D.C.C. § 12.1-13-03)
Persons employed by the State of North Dakota, or within one year thereafter, may be prohibited from acquiring a pecuniary interest in a public contract or transaction. Offerors should review N.D.C.C. § 12.1-13-02 to ensure compliance and avoid such conflict(s) of interest.
1.21 ATTEMPT TO INFLUENCE PROHIBITED
Offerors must not give or offer to give anything to a state employee or official that might influence or appear to influence procurement decisions. Suspected attempts to influence will be handled in accordance with N.D.A.C. § 4-12-04-05.
1.22 COLLUSION PROHIBITED
Offerors must prepare proposals independently, without collusion. Suspected collusion will be handled in accordance with N.D.A.C § 4-12-04-06.
1.23 PROTEST AND APPEAL
An interested party may protest a solicitation pursuant to N.D.C.C. § 54-44.4-12 and N.D.A.C. § 4-12- 14-01. When a solicitation contains a deadline for submission of questions and objections, protests of the solicitation will not be allowed if these faults have not been brought to the attention of the Procurement Officer before the specified deadline. If no deadline for questions is specified, protests based upon defects in the solicitation must be made at least seven calendar days before the deadline for receipt of proposals.
An Offeror that has submitted a response to a solicitation and is aggrieved may protest an award or notice of intent to award pursuant to N.D.C.C. § 54-44.4-12 and N.D.A.C. § 4-12-14-02. The protest must be submitted in writing to the Procurement Officer during the protest period, which is seven calendar days beginning the day after the notice of intent to award is issued.
The protestor may appeal the decision of the Procurement Officer to the Director of OMB or designee in writing within seven calendar days after receiving notice of the decision pursuant to N.D.C.C. § 54-44.4- 12 and N.D.A.C. § 4-12-14-03.
1.24 SPECIFICATIONS PREPARED BY NON-STATE PERSONNEL
When a purchasing agency has specifications prepared by someone other than a state employee or official on behalf of the STATE, that person or business entity must be excluded from submitting bids or proposals in accordance with N.D.A.C. § 4-12-06-06.
1.25 SUPPLIER REGISTRATION (PAYEE)
The successful Offeror will be required to complete Supplier Registration, if not already registered as a Supplier. Any individual or business who will be receiving payment from a state agency or higher education institution must complete a registration process to collect important financial and taxpayer information. Payments are generally made by check or automatic clearing house (ACH), and taxpayer information must be collected in compliance with IRS requirements. The State and North Dakota University System (NDUS) have separate financial systems and vendor registration processes.
http://www.legis.nd.gov/information/acdata/pdf/4-12-04.pdf?20140130144222 https://www.ndlegis.gov/cencode/t12-1c13.pdf https://www.legis.nd.gov/cencode/t12-1c13.html https://www.legis.nd.gov/cencode/t12-1c13.html http://www.legis.nd.gov/information/acdata/pdf/4-12-04.pdf?20140130144222 http://www.legis.nd.gov/information/acdata/pdf/4-12-04.pdf?20140130144222 http://www.legis.nd.gov/cencode/t54c44-4.pdf?20130417132347 http://www.legis.nd.gov/information/acdata/pdf/4-12-14.pdf?20130417132435 http://www.legis.nd.gov/information/acdata/pdf/4-12-14.pdf?20130417132435 http://www.legis.nd.gov/cencode/t54c44-4.pdf?20130417132347 http://www.legis.nd.gov/information/acdata/pdf/4-12-14.pdf?20130417132435 http://www.legis.nd.gov/cencode/t54c44-4.pdf?20130417132347 http://www.legis.nd.gov/cencode/t54c44-4.pdf?20130417132347 https://www.legis.nd.gov/information/acdata/pdf/4-12-14.pdf https://www.ndlegis.gov/information/acdata/pdf/4-12-06.pdf?20140130144222
SECTION TWO – BACKGROUND
2.1 BACKGROUND INFORMATION
At Lake Region State College, our motto is “We change lives!” and we live that motto every day. Our students are the heart of Lake Region State College. We strive to create an environment where students know they matter. The college’s dedicated staff and faculty are prepared to help you reach your goals.
Accredited since 1973, Lake Region State College serves a vital role in the community, region, state, and nation for preparing students for success. Specific programs like Nursing, Automotive Technology, and Fitness Trainer Technician have earned additional, industry-specific national accreditations.
We serve students wishing to start the first half of a bachelor’s degree to students eager to enter the workforce in the areas of technology, health care, energy, business, law enforcement, and many more trades and technical areas.
The mission of the Lake Region State College is to enhance lives and community vitality through quality education.
Our agency is conducting this solicitation because of roof leaks and continual deterioration of aged roof.
2.2 BUDGET
The funds for payment of this contract are already appropriated and identified.
SECTION THREE – SCOPE OF WORK
3.1 SCOPE OF WORK
Lake Region State College (STATE) is soliciting proposals for roof renovation on Main Campus sections 1,2,3,5,6A,6B,7,8,8A,10,11,11A,11C,12,13,15,14A,15A,16,17,18,19,20,21,22,23,24,25,26,31.
To be used in addition to detailed roof specifications. Approximately 134,000 sq. ft. of EPDM renovation with fully reinforced liquid applied membrane. Contractor to verify all measurements.
3.2 APPLICABLE DIRECTIVES
The contractor is responsible for identifying and complying with all state and federal requirements that apply to the contract.
3.3 REQUIREMENTS
A. Deliverables
The contractor will be required to provide the following to achieve the objective of this project roof renovation on Main Campus sections 1,2,3,5,6A,6B,7,8,8A,10,11,11A,11C,12,13,15,14A,15A,16,17,18,19,20,21,22,23,24,25,26,
31. To be used in addition to detailed roof specifications. Approximately 134,000 sq. ft. of EPDM renovation with fully reinforced liquid applied membrane. Contractor to verify all measurements:
1. Remove identified wet insulation identified in roof moisture survey completed in 2025. Areas are marked on roof. Wet insulation area is approximately 675 sq. ft.
2. Flash masonry roof wall that leaks dividing section 3 and 8 with EPDM membrane to completely encapsulate masonry wall.
3. Repair perimeter failure on roof section 17 located in SW Corner. Remove damaged metal and replace to match existing. Re-Adhere delaminated membrane at perimeter. Approximately 50 lineal ft of perimeter repair.
4. Rework and repair walkway roof area to ensure proper drainage on section 1 and remove tar from EPDM in this area.
5. Repair of expansion joints on sections 23 and 26.
6. Repair and re-caulk and damaged counter flashing to match existing.
7. Re-caulk counter flashing as required where caulking has failed.
8. Seal loose and broken wall flashing corners on sections 7 and 11C.
9. Remove and infill out of use curbs located on section 18. (3)
10. Pressure wash roof clean. Cleaning to be approved by manufacture’s rep that roof is suitable for coating.
11. Prime roof with compatible Membrane primer to promote adhesion of liquid membrane to
EPDM.
12. Detail and flash drains, perimeter, and roof penetrations with reinforcing polyester fabric and chemically cured polyurethane base coat.
13. Install field base coat and full fabric reinforcement to field of roof at minimum of 48 wet mils thick. Allow to cure.
14. Install chemically cured, aliphatic polyurethane top coat at 32 wet mils thick and allow to cure.
Top Coat color selected from range of manufactures colors.
Provide Manufactures 25 Year NDL Labor and Materials Warranty
B. Location Of Work/Travel The work is to be performed, completed, and managed at the following location: Devils Lake, North Dakota. The STATE shall not provide workspace for the contractor.
The contractor should include in its price proposal: transportation, lodging, and per diem costs sufficient for number of trip(s) to location. Travel to other locations will not be required.
C. State-Furnished Property/Services The STATE will provide the following personnel to support the project: Physical Plant Director Chad Estenson will be the lead contact for Lake Region State college on this project.
D. Risk Management The contractor will take appropriate measures to ensure the safety of their employees, state employees, the public, and property. The contractor must identify any potential risks, issues and problems associated with the project and identify ways to mitigate those potential risks.
E. Access To Site Use of site, limited. The contractor shall have limited use of project site for construction operations as indicated on drawings by the contract limits and as indicated by requirements of this section.
1. Use of Site: Limit use of project site to work in areas indicated and as directed by the STATE. Do not disturb portions of project site beyond areas in which the work is indicated, including designated lay-down areas.
2. Driveways, Walkways and Entrances: Keep driveways, facility loading areas, and entrances serving premises clear and available to the STATE, STATE's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
3. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period.
Repair damage caused by construction operations.
F. Coordination With Occupants Occupancy: The STATE will occupy site including existing and adjacent building(s) during entire construction period. Cooperate with STATE during construction operations to minimize conflicts and facilitate STATE usage. Perform the Work so as not to interfere with STATE's day-to-day operations. Maintain existing exits unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.
2. Notify the STATE not less than 72 hours in advance of activities that will affect the STATE’s operations.
G. Work Restrictions
1. Work Restrictions, General: Comply with restrictions on construction operations.
2. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by the STATE or others.
3. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to the occupancy with the STATE.
a. Notify the STATE not less than two days in advance of proposed disruptive operations.
b. Obtain the STATE’s written permission before proceeding with disruptive operations.
4. Nonsmoking Project: Use of tobacco products on STATE property is prohibited.
5. Controlled Substances: Use of controlled substances on STATE property is prohibited.
H. Technical Exhibit Please see Attachment 3A for technical exhibits.
I. Project Management Plan The contractor will be expected to use appropriate project management to ensure the work is accomplished on time, within budget, and meets quantity and quality standards.
1. The contractor will be required to collaborate with the STATE to agree upon the contract schedule, including a work breakdown, schedule of tasks and activities, and progress milestones.
2. The contractor will be required to coordinate with the STATE to develop a communication plan. Any problems or unforeseen events must be communicated timely to the STATE project manager and any changes must be agreed upon between the parties and set forth in a written amendment to the contract. If the STATE requires corrective action, the contractor will be notified in writing.
3. Contract Closeout Plan: When the contract is completed, the STATE and contractor will communicate regarding the contract closeout, including transition of any records. A contract closeout debrief may be performed at the discretion of the Procurement Officer or project manager designated by the STATE. The debriefing time and location will be negotiated between the STATE and contractor. The contractor must collaborate in the development of a Project Closeout Report to include feedback regarding the project implementation and any lessons learned.
J. Contract Term, Schedule, and Deliverables
1. Contract Term
The length of this contract will be from the date of award, approximately September 1st until completion, approximately August 1, 2026. See the attached contract for extension provisions.
2. Schedule and Deliverables
The STATE has identified the following deliverables which are significant work products or milestones in the project. The STATE requires these deliverables to be addressed in the Contract Schedule, at a minimum. The contractor shall develop a schedule for accomplishing the Scope of Work, including these specific deliverables. The final schedule shall be agreed upon between the STATE and the successful Offeror and incorporated into the contract. The approximate schedule for this contract is as follows:
a. Contract start: September 2025
b. “Kick off” meeting/conference call: TBD – September 2025
c. First contractor work period: TBD – September 2025
d. Contract Closeout Plan: August 1, 2026
3.4 EXPERIENCE AND QUALIFICATIONS
A. Installer Qualifications: An employer of workers trained and certified by manufacturer, including a full-time on-site supervisor with a minimum of three years' experience installing products similar to those specified, able to communicate verbally with Contractor, Architect, and employees, and the following:
1. Qualified by the manufacturer to install manufacturer's product and furnish warranty of type specified.
B. Manufacturer Qualifications: Primary product manufacturer that is UL listed for roofing system identical to that specified for this Project with minimum five years' experience in manufacture of comparable products in successful use in similar applications, and able to furnish warranty with provisions matching specified requirements.
1. Approval of Other Manufacturers and Comparable Products: Submit the following in accordance with project substitution requirements, within time allowed for substitution review:
a. Product data, including certified independent test data indicating compliance with requirements.
b. Detailed project specifications with detailed changes needed to specifications with substitution.
c. Samples of each component.
d. Sample submittal from similar project.
e. Project references: Minimum of five comparable installations in North Dakota of specified products not less than three years old, with Owner and Architect/Owner's Consultant contact information.
f. Sample Jobsite Inspection Report provided by manufacturer during installation
g. Sample warranty that includes in cost of warranty manufacturers periodic inspections listed in specifications and sample report and data base from manufacturers inspections accessible to owner.
C. Roofing Inspector Qualifications: A technical representative of manufacturer and experienced in the installation and maintenance of the specified roofing system, qualified to perform roofing observation and inspection specified in Field Quality Control Article, to determine Installer's compliance with the requirements of this Project, and approved by the manufacturer to issue warranty certification.
The Offeror must have and keep current any professional licenses and permits required by federal, state, and local laws for performance of this contract. Offerors that do not possess required licenses at the time proposals are due will be determined non-responsive to the RFP and will be rejected.
The Offeror must meet the above experience requirements to be considered for contract award.
A proposal from the Offeror that does not meet minimum experience requirements will be rejected.
SECTION FOUR – PROPOSAL INSTRUCTIONS
4.1 PROPOSAL PREPARATION
The STATE discourages overly lengthy and costly proposals. An Offeror must prepare their proposal using the prescribed proposal format and provide all the requested information; this will enable the proposal to be evaluated fairly and completely. If an Offeror submits more than one proposal, each proposal must be prepared in accordance with these instructions.
Each proposal will include a Technical Proposal and a Cost Proposal prepared in accordance with these instructions. The Technical Proposal and the Cost Proposal must be submitted as separate documents, clearly labeled with the name of the Offeror, and marked “Technical Proposal” and “Cost Proposal.” Costs must not be revealed in the Technical Proposal. Options may be discussed in the technical proposal, but all cost information must be in the Cost Proposal only. DO NOT submit documents that are embedded into proposal documents or that contain links to documents on an external website.
4.2 PROPOSAL SUBMISSION INSTRUCTIONS
Sealed proposals are required; therefore, proposals cannot be submitted by email to the Procurement Officer.
SUBMIT IN PERSON, BY MAIL, OR DELIVERY SERVICE
Offerors may submit proposals in person, by mail, or delivery service. Offerors may email proposals to a third party to place in a sealed envelope and deliver by the Solicitation Closing deadline.
Clearly address all envelopes or packages as follows:
RFP #: 100.06.18.2025
RFP Title: 2025 Roof Rehabilitation & Replacement Project ATTN: Sandi Lillehaugen Lake Region State College 1801 N. College Drive Devils Lake, ND 58301
The STATE assumes no responsibility for delays caused by any delivery service. Postmarking by the Solicitation Closing deadline shall not substitute for actual proposal receipt by the STATE. The STATE’s time of receipt will be used to determine timely receipt.
COPIES OF TECHNICAL AND COST PROPOSAL
Offeror shall submit one (1) copy of their Technical Proposal.
Offeror shall submit one (1) copy of the Cost Proposal in a separate, sealed envelope, clearly labeled “Cost Proposal.”
Offeror shall also submit their proposal in an electronic version (examples: Microsoft Word, Excel, or .pdf format) on a USB flash drive with the Technical Proposal and Cost Proposal saved as separate files.
4.3 PROPOSAL FORMAT
Prepare the Technical Proposal and Cost Proposal in accordance with these instructions.
Technical Proposal – Format the proposal with the following labeled sections:
Section 1 – Cover Letter Section 2 – RFP Amendments
Section 3 – Scope of Work Strategy Section 4 – Experience and Qualifications Section 5 – Contract Provisions Section 6 – Open Records and Confidentiality
Cost Proposal – The Cost Proposal must be a separate document. Format the Cost Proposal following the RFP instructions.
4.4 TECHNICAL PROPOSAL
SECTION 1 – COVER LETTER
Proposals shall include a cover letter that includes the following:
1. The name of the Offeror, name of the person to contact regarding the proposal, email address, telephone number, and mailing address.
2. Offerors are instructed to review the “Conflict of Interest” provisions in RFP Section 1 “Instructions.” If the firm, its employees, or subcontractors working on the contract have an apparent or actual conflict of interest, provide a statement disclosing the circumstances of the apparent or actual conflict of interest. Otherwise, provide a statement that your firm, employees, and subcontractors do not have a conflict of interest.
3. The cover letter must be signed by an individual with authority to bind the Offeror. By signing the cover letter, an Offeror certifies that it complies with:
a. All the requirements, terms, and conditions as set forth in this RFP.
b. The requirement that the Offeror’s proposal accurately describes the goods and services being offered to the STATE, and the proposal will be held firm for the period specified.
c. All local, state, and federal laws, rules, code laws, rules, code, regulation, and policies, including those relating to nondiscrimination, accessibility, civil rights, and equal employment.
d. The requirement that this proposal was prepared independently without collusion.
SECTION 2 – RFP AMENDMENTS
Provide signed copies of all Solicitation Amendments issued by the STATE that were required to be acknowledged by Offerors.
SECTION 3 –SCOPE OF WORK STRATEGY
Offeror must review the requirements and deliverables provided in RFP Section 3, Scope of Work.
1. Applicable Directives. The Offeror must identify any state and federal requirements that apply to the contract.
2. Strategy for Scope of Work Requirements. The Offeror must provide narrative statements to demonstrate their understanding of the scope of work requirements. Explain the proposed strategy to accomplish the scope of work, meet all requirements, and provide the deliverables described in the scope of work within the STATE’s project schedule.
3. Location of Work. The proposal must respond to the STATE’s Location of Work instructions within the RFP Scope of Work. Describe where the work will be performed and any proposed travel.
4. State Furnished Property and Services. Provide a detailed breakdown of the Offeror’s expectations for STATE resources that will be needed for the project, including number of staff, qualifications, roles and responsibilities, and time requirements for the various phases of the project.
5. Risk Management. Offerors must describe measures to be taken to ensure the safety of its employees, state employees, the public, and property. Offerors must also identify any pertinent issues and potential problems related to the project and describe how those potential issues and problems could be mitigated.
6. Project Management Plan. The proposal must describe how the contractor intends to manage the project to ensure the work is accomplished on time, within budget, and meet quantity and quality standards. Offerors may provide a narrative or organizational chart to illustrate the lines of authority and accountability.
7. Proposed Schedule and Deliverables. The proposal must provide a timeline for accomplishing the work, in consideration of the STATE’s Contract Schedule within the RFP Scope of Work.
SECTION 4 –EXPERIENCE AND QUALIFICATIONS
Mandatory Requirements. An Offeror must provide information to demonstrate meeting the Offeror Experience and Qualifications Requirement in RFP Section 3, Scope of Work, Experience and Qualifications.
Experience and Qualifications of the Firm Provide a brief history and describe the organization of the firm. Describe the number of years the Offeror has provided the type of work requested in this RFP. Describe specific experience of their firm in completing similar projects. Provide a description of the project, approximate time frame of the project, and contact information for the customer. Offerors may provide letters of reference from customers.
Experience and Qualifications of the Project Team Provide a narrative or organizational chart that describes the organization of the proposed project team. Provide information for key project team members, including:
1. Description of anticipated work they will perform and approximate estimated hours;
2. Resume or description of the relevant education, training, experience, skills, and qualifications;
3. Offeror must provide a designated executive level contact that will act as a point of contact for any issues that need escalation or to discuss the needs of the STATE. This point of contact will be required to participate in any requested demonstration or presentation requested during the RFP process. They will discuss how the contract will be supported and how the Offeror and STATE will work together to ensure a successful outcome;
4. If the Offeror has vacant positions, identify the job description and minimum qualifications for staff members to be recruited;
5. Subcontractors. If an Offeror intends to use subcontractors, the Offeror must identify in the proposal the names of the subcontractors and the portions of the work the subcontractors will perform. Provide a statement that the Offeror will ensure that the subcontractor has or will obtain any required licenses and registrations, including registration with the North Dakota Secretary of State; and
6. Joint Venture. If submitting a proposal as a joint venture, provide narrative statements that describe the roles and responsibilities of each party to the joint vendor. If available, submit a copy of the joint venture agreement that identifies the parties involved and their rights and responsibilities.
References Provide three (3) references for similar projects the Offeror has completed. Offerors must include the name of a contact person, address, email, and telephone number. Offerors are responsible for providing accurate reference contact information and are instructed to notify the reference that the STATE may be contacting them. Reference checks may begin within one (1) business day of the Solicitation Closing deadline. Evaluation may be impacted if the STATE is unable to contact the reference or the reference does not provide the requested information in a timely fashion.
SECTION 5 – CONTRACT PROVISIONS
Offeror shall review the RFP Section 6 and the STATE’s contract – Attachment 6A.
The proposal must indicate whether the Offeror accepts the terms and conditions in the STATE’s contract.
An Offeror may state that they accept the STATE’s contract as written.
An Offeror may state any objections or propose changes or additions to the STATE’s contract.
Describe the changes to the contract being proposed or provide a red-line of the STATE’s contract. Offeror is not to submit their own contract or standard terms and conditions with their proposals. Offeror should address the specific language in the attached contract and submit any proposed changes.
North Dakota procurement statutes, rules, and policies allow some negotiation of the terms and conditions. No changes to the terms and conditions will be permitted without prior written approval from the STATE.
SECTION 6 – OPEN RECORDS AND CONFIDENTIALITY
All proposals and other material submitted become the property of the STATE and may be returned only at the STATE’s discretion. The State of North Dakota has broad open records laws. Proposals received are exempt from open record requirements until an award is made, in accordance with N.D.C.C. § 54-44.4-10(2). After award, proposals are subject to the North Dakota open records laws. Proposals or portions of proposals may be confidential only if specifically stated in law.
Offerors are instructed not to mark their entire proposal as “confidential”.
Offeror must provide one of the following in their proposal:
• Provide a statement indicating that their proposal does not contain any confidential information, OR
• Make a written request to hold confidential any trade secrets and other proprietary data contained in their proposal. Offeror must clearly identify the material considered confidential and explain why the material is confidential. See the North Dakota Office of the Attorney General website for additional information at https://www.legis.nd.gov/cencode/t44c04.pdf and https://attorneygeneral.nd.gov/open-records-meetings
If the STATE receives a request for public information, the Procurement Officer, in consultation with the Office of the Attorney General, shall determine whether the information is an exception to the North Dakota open records laws, and the information shall be processed accordingly.
4.5 COST PROPOSAL
Cost Proposal Format. Cost proposals must be prepared as a separate document from the technical proposal, clearly labeled, “Cost Proposal”.
http://www.legis.nd.gov/cencode/t54c44-4.pdf?20131002103938 https://www.legis.nd.gov/cencode/t44c04.pdf https://attorneygeneral.nd.gov/open-records-meetings
Offeror must complete the Cost Proposal Format - Attachment 4-A or prepare a Cost Proposal following the same format.
Value-Added Options. Offeror may include pricing for any value-added options that are described in the Offeror’s proposal as options, but not included in the total cost. Any options must be within the scope of work. (e.g., an option for a higher level of service, equipment accessories, extended warranty options, etc.). Provide details related to initial cost, reoccurring costs, and options. The STATE shall not consider these costs as part of cost evaluation scoring.
All costs must be stated in U.S. currency. Any commodities being imported must be identified, and the price must include any applicable shipping and handling, customs, brokerage agency fees, and duties.
Offeror should describe any discount terms for prompt payment. Discounts for prompt payment will not be considered in evaluating costs.
4.6 SAMPLES
Offeror must provide a sample of the products being proposed for the purpose of ensuring compliance with solicitation requirements and evaluation. The Offeror is responsible for all costs associated with furnishing the sample, including transportation. Label the sample with the name of the Offeror. The sample must be submitted by the proposal submission closing date in the RFP Schedule listed in Section 1 of the RFP. Samples may be subject to examination and testing by the STATE. Samples offered by the successful Offeror may be retained for comparison to deliveries under the contract.
Upon request by the Offeror, samples not destroyed by examination or testing will be returned at the expense of the Offeror. If the Offeror does not request return of the sample, the sample will become property of the STATE (N.D.A.C. § 4-12-08-11).
4.7 BONDS
No bonds are required.
http://www.legis.nd.gov/information/acdata/pdf/4-12-08.pdf?20140211124607
SECTION FIVE – AWARD AND PROPOSAL EVALUATION
5.1 AWARD
The STATE intends to award a contract to the responsible Offeror whose proposal is determined to be responsive to the requirements of the solicitation and is determined to be the most advantageous in consideration of the RFP evaluation criteria.
5.2 RESPONSIVENESS
All proposals will be evaluated to determine if they are responsive to the requirements of the solicitation. The STATE reserves the right to waive minor informalities in accordance with N.D.A.C. chapter 4-12-10. Minor informalities are insignificant omissions or nonjudgmental mistakes that are matters of form rather than substance, evident from RFP document, with a negligible effect on price, quantity, quality, delivery, or contractual conditions that can be waived or corrected without prejudice to other Offerors. Responsive proposals will be evaluated by the Procurement Officer or evaluation committee using the evaluation criteria stated within the RFP.
5.3 RESPONSIBILITY – SUPPLEMENTARY INVESTIGATION
The STATE reserves the right to contact references, other customers, including state and local government agencies, regarding past experience with the Offeror. Prior experience of the state agency or institution with any prospective Offeror may also be taken into consideration during evaluation.
The STATE may, at any time, make a supplementary investigation as to the responsibility of any Offeror in accordance with N.D.A.C. § 4-12-11-04. This investigation may include, but is not limited to, financial responsibility, capacity to produce, sources of supply, performance record, or other matters related to the Offeror’s probable ability to deliver if a contract is awarded to the Offeror. If it is determined that an Offeror appears not to be sufficiently responsible, the proposal will be rejected.
5.4 EVALUATION CRITERIA
Proposals will be evaluated using a 100-point scale. The evaluation committee will award points based on the questions in the Technical Proposal Evaluation Worksheet – Attachment 5A. The Technical Proposal evaluation score and Cost Proposal evaluation score will be added together to determine the total evaluation score. After the initial evaluation, the evaluation committee may determine which proposals are reasonably susceptible for award and continue the evaluation process with only those Offerors. Offerors whose proposals are not selected for further evaluation may request a debrief from the Procurement Officer after an award notice is issued.
The final evaluation score will consider information received by the STATE, including but not limited to, discussions with Offerors, demonstrations, presentations, site visits, reference checks, and best and final offers.
The evaluation criteria and relative weight is as follows:
Technical Proposal Evaluation: 60 Points
A. Scope of Work Strategy – 40 Points B. Experience and Qualifications – 20 Points
Cost Proposal Evaluation: 40 Points
Preference Laws: Any applicable preference laws will be applied. For more information, refer to the Guidelines to Preference Laws.
http://www.legis.nd.gov/information/acdata/pdf/4-12-10.pdf?20130430132759 http://www.legis.nd.gov/information/acdata/pdf/4-12-11.pdf?20140130152917 https://www.omb.nd.gov/sites/www/files/documents/doing-business-with-the-state/procurement/guidelines-to-nd-purchasing-preference-laws.pdf
5.5 COST PROPOSAL EVALUATION
The STATE will calculate evaluation points awarded to Cost Proposals. Any prompt payment discount terms proposed by the Offeror will not be considered in evaluating cost.
The reciprocal preference law, N.D.C.C. § 44-08-01, was repealed effective August 1, 2023.
The cost amount used for evaluation may be affected by the application of other costs required to implement the proposed solution to determine the total cost of the solution (i.e. cost for ITD to host a STATE hosted solution).
The lowest Cost Proposal will receive the maximum number of points allocated…