This document is a Question & Answer Report for a Request for Proposal (RFP No. 1-26) issued by the City of Cheyenne Purchasing Department for a Compost Operations Plan. The RFP response deadline is set for September 15, 2025 at 3:00 pm, with the Q&A report dated September 4, 2025. Two questions were addressed during this reporting period, with the Purchasing Manager TJ Barttelbort providing responses to potential bidders.
The first question requested access to previous compost plans, to which Barttelbort indicated that a plan from 2012 is available and another report was redacted in 2019, with reference to Addendum Two. The second question sought clarification on the type of examples required in the Technical proposal, specifically whether project summary sheets or actual deliverables were preferred. Barttelbort responded that an example of an actual deliverable would be preferred for submission. No pricing, funding sources, or specific contract details were discussed in this Q&A report beyond the procedural clarifications for the RFP submission.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Cheyenne
Purchasing TJ Barttelbort, Purchasing Manager
2101 O'Neil Ave., Room 309, Cheyenne, WY 82001
(307) 773-1045
QUESTION & ANSWER REPORT
Request For Proposal - City of Cheyenne Compost Operations Plan
QUESTION & ANSWER REPORT
RFP No. RFP 1-26
City of Cheyenne Compost Operations Plan
RESPONSE DEADLINE: September 15, 2025 at 3:00 pm
Thursday, September 4, 2025
Approved, Unanswered Questions
Approved, Answers Provided
1. No subject
Sep 3, 2025 8:29 AM
Question: Can we get a copy of the previous plan that was completed?
Sep 3, 2025 8:29 AM
Answered by TJ Barttelbort: One previous plan is available from 2012 circa. A report/plan was also redacted in 2019. See Addendum Two.
Sep 4, 2025 2:25 PM
2. No subject
Sep 3, 2025 8:31 AM
Question: For Examples (section b of the Technical proposal outline) – are you looking for a project summary sheets or an example of a deliverable (the actual study)?
Sep 3, 2025 8:31 AM
Answered by TJ Barttelbort: An example of a deliverable would be preferred.
Sep 4, 2025 2:25 PM
File details come from the government source that posted it. Updated .