About this file

This Request for Proposal (RFP) is issued by Oakland University for preferred supplier(s) for asbestos, lead paint, and mold abatement and remediation services. The RFP seeks to establish a contract for comprehensive environmental remediation services across the university's campus and off-campus locations, covering Classes I through III asbestos abatement work, as well as lead paint and mold remediation. The initial contract term will run from July 2025 through 2028, with the option to extend for two additional one-year periods through 2030. Proposals are due by July 1, 2025 at 2 PM EST, with questions accepted until June 18, 2025. The university anticipates multiple contractors may be selected to handle different classes of work, with historical spend averaging approximately $145,000 over the past three years.

The RFP requires detailed proposals including unit pricing, references, company experience, licensing, insurance certificates, and employee accreditation information. Proposers must provide comprehensive pricing that includes portal-to-portal travel, materials, equipment, waste transport, and disposal costs. The university will evaluate proposals based on a 100-point scoring system that considers service delivery approach, cost structure, ability to meet criteria, past performance, customer service, and employee training programs. Insurance requirements are substantial, including workers' compensation, commercial general liability, contractors pollution liability, auto liability, and an umbrella policy with specific coverage limits. Prevailing wage requirements apply, and contractors must submit certified payroll with each invoice.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Oakland University

REQUEST FOR PROPOSAL (RFP)

Preferred Supplier(s) for Asbestos, Lead Paint, and Mold Abatement and Remediation Services

FILE 00202

Issue Date: June 11, 2025

Questions Due: June 18, 2025 by 2PM EST

Addendum Issued by June 20, 2025

Sealed Proposals Due: July 1, 2025 by 2PM EST

RFP Preferred Supplier(s) for Asbestos, Lead Paint, and Mold Remediation and Abatement Services

Contents

SECTION I – BACKGROUND

1.01 Oakland University Background Information

1.02 RFP Overview

SECTION II – SCOPE OF SERVICES

2.01 Specifications

SECTION III - RFP PROPOSAL REQUIREMENTS

3.01 Qualifications/Experience

3.02 University Liaison

3.03 Cost/Fees

3.04 Freedom of Information Act Requests

SECTION IV – EVALUATION

4.01 Evaluation of RFP Response and Selection Criteria

4.02 Process for Award

SECTION V - PROCUREMENT PROCESS

5.01 Submission Method, Date and Time

5.02 Questions and Interpretations

5.03 Prevailing Wage

5.04 Withdrawal of Proposals

5.05 Price and Scope of Work Changes

5.06 Mistakes in Proposals

5.07 Execution of Proposals

5.08 Procurement Schedule

SECTION VI – GENERAL CONDITIONS

6.01 Terms and Conditions

6.02 Conflict of Interest

6.03 Cost of Proposal

6.04 Form of Purchase

6.05 Government Restrictions

6.06 Nonconformance to Conditions/Specifications/Scope of Services

6.07 Assignment or Transfer

6.08 Patents - Licenses and Royalties

6.09 Permits and Licenses

6.10 Taxes

6.11 Insurance Requirements

6.12 Proof of Insurance

6.13 Standards of Conduct

6.14 Background Checks and Debarment

6.15 Removal of Employees

6.15 Supervision

6.17 Performance Evaluation Meeting

6.18 Federal, State and Local Reporting Compliance

6.19 Project Personnel

6.20 Notices

6.21 Cancellation

6.22 Travel

6.23 Non-Discrimination

SCHEDULE A – Addendum Acknowledgement

SCHEDULE B-INSURANCE REQUIREMENTS ACKNOWLEDGEMENT

SCHEDULE C-COSTS

SECTION I – BACKGROUND

1.01 Oakland University Background Information

Oakland University (University) is a world-class academic institution located on 1,443 acres of wooded hills and meadows in Rochester, MI. The university was established in 1957 through a generous donation from founders Alfred and Matilda Dodge Wilson. Oakland University celebrated the 50th anniversary of its founding in 2007. When it opened in 1959, 570 students were enrolled, and the charter class graduated in 1963 with 125 students receiving diplomas. Today, nearly 16,000 students attend classes at OU, and our alumni total has grown to approximately 100,000.

As a state-supported institution of higher education, Oakland University has been recognized and is classified as a doctoral research university by the Carnegie Foundation for the Advancement of Teaching. With 139 baccalaureate degree programs and 127 graduate degree and certificate programs, Oakland provides a distinct educational experience with flexible class schedules and state-of-the-art facilities, student services, classroom technologies, research labs, internships and research opportunities with corporate partners. Located in the heart of Oakland County's Automation Alley, the university has forged hundreds of partnerships with hospitals, Fortune 500 companies, cities, government agencies and educational institutions.

All questions regarding this Request for Proposal should be directed to:

Maria Ebner-Smith Buyer Oakland University, Purchasing Department 411 Pioneer Drive Rochester, Michigan 48309 Phone No. 248-370-4423 Email ebnersmi@oakland.edu

1.02 RFP Overview

Oakland University Facility Management is requesting quotes for a preferred supplier relationship for Asbestos abatement services.

The work covered by the asbestos, lead paint, and mold remediation and abatement agreement includes supervision, labor, equipment, materials, insurance and the transportation and disposal of asbestos waste as necessary for the legal and safe remediation of friable and non-friable asbestos containing materials throughout the OU Campus and off-campus locations. Asbestos Abatement work in Classes I through III may be completed as part of this blanket. Abatement and remediation of lead paint and mold may also be completed as part of this contract. Multiple contractors may be chosen for different classes of work.

Although the University cannot guarantee any business, historical spend on average for asbestos abatement services has been approximately $145K in the last 3 years.

The initial term of the contract will commence July 2025, and will remain in effect for 3 years through 2028. Prices quoted and your responses to this RFP must be guaranteed for the entire three-year term of the agreement. Based on mutual agreement of Oakland University and the successful respondent, unless terminated, or canceled, as otherwise provided herein, the agreement has the option to extend for two additional one-year periods, through 2030. The University will not agree to auto renew clauses.

Prevailing Wages apply to this contract award. Contractor will need to provide certified payroll and is required to submit the Prevailing Wage Submittal Form (Attachment A) with each invoice.

Multiple vendors may be awarded preferred status.

SECTION II – SCOPE OF SERVICES

2.01 Specifications

The agreement requires the contractor to provide the following:

Asbestos:

1. The contractor shall comply with industry and regulatory standards and use accepted state-of-the-art or better materials and products throughout all phases of the project.

2. Supervision of the project shall be performed by an accredited Competent Person (as defined by OSHA 29 CFR 1926.1101) employed by the contractor at all times.

3. The contractor shall complete all appropriate asbestos project notifications and pay all notification fees.

4. The contractor shall furnish all labor, materials, equipment, services, insurance and incidentals necessary to remove all asbestos in the project specification.

5. The contractor is responsible for restoring the work area and auxiliary areas utilized during the asbestos abatement project to conditions equal to or better than original. This typically does not include re-insulating the areas.

Lead Paint:

1. Abatement- Removal of lead containing paint materials from the designated areas, proper engineering controls and enclosures as required by project specification or applicable regulations and as necessary to control airborne lead release from lead containing paint.

2. Encapsulation- Procedures as required per project specifications or necessary to apply and encapsulant to lead containing painting surfaces after the cleansing of the lead dust surfaces to control the possible release of lead into the ambient air.

3. Stabilization- processes and procedures necessary to return damaged lead containing painted surfaces to a stable, non-lead releasing condition.

4. Proper cleanup of lead dust and debris associated with the disturbance of lead containing paint.

5. Proper transportation and disposal of the lead containing materials in compliance with all state and federal regulations at appropriate disposal sites. Manifests will be required. The Contractor will be responsible for any and all penalties/fines for improper transportation and disposal

Mold:

1. Remediation- Removal of mold impacted building materials from the designated areas, proper engineering controls and enclosures as required by project specification or applicable regulations and as necessary to control airborne mold spore release from wet or mold impacted material.

2. Encapsulation- Procedures as required per project specifications or necessary to apply and encapsulant to lead containing painting surfaces after the cleansing of the lead dust surfaces to control the possible release of mold into the ambient air.

3. Proper containment and clean-up of mold contaminated building materials, ensuring that areas outside the impacted area’s do not become contaminated while remediation takes place.

4. Proper disposal of mold impacted building materials in compliance with industry standards.

A. Regulatory References

All work shall be performed in compliance with current federal and state regulations, including U.S.

EPA, OSHA, MIOSHA, MDEQ and all accepted industry standards. The most current edition of relevant regulations, standards, documents or codes shall be in effect including:

• Michigan Asbestos Worker Accreditation Act – Act 440 of 1988, as amended

• Michigan Asbestos Abatement Contractors Licensing Act – Act 135 of 1986, as amended

• Michigan Occupational Safety and Health Act – Act 154 of 1974, as amended

• Michigan Occupational Safety and Health Administration (MIOSHA), Construction Safety and Health , Asbestos Program, Asbestos Standards for Construction, Part 602 (OSHA standard 29 CFR 1926.1101)

• MIOSHA, Asbestos for General Industry, Part 305 (OSHA 29 CFR 1910.1001)

• MIOSHA, Respiratory Protection Standard, Part 451 (OSHA 29 CFR 1910.134)

• MIOSHA Personal Protection Equipment, Part 433

• MIOSHA Hazard Communication Standard, Part 421 (OSHA 29 CFR 1910.1200)

• Michigan Department of Environmental Quality (MDEQ) Air Quality Division NESHAP (National Emissions Standards for Hazardous Air Pollutants) Asbestos Program, (Subject to 40 CFR, Part 61, Subpart M)

• U.S. EPA Regulations for Asbestos, Title 40 CFR, Part 61, National Emissions Standards for Hazardous Air Pollutants, Subparts A & M.

• U.S. EPA Asbestos Worker Protection (65 FR 69210 November 15, 2000)

• U.S. Department of Transportation (DOT), Title 49, CFR Parts 171 and 172.

• Contractors are required to have a written Confined Space Entry Program in compliance with

OSHA 1910.146.

B. Project Planning

Oakland University requires the contractor to submit the following prior to beginning work on the specified project:

1. Documentation of required, timely notification(s) and payment of fees to the State and Federal regulators.

2. Development of a detailed asbestos, lead paint, or mold remediation or abatement plan, which describes the procedures used for complying with the project specifications. The plan should include the following:

a. The location and layout of decontamination areas.

b. The sequencing of asbestos, lead paint, or mold work and methods to be used to assure the safety of building occupants, workers and visitors to the site.

c. Methods for controlling visible emissions in the work and the containerization of asbestos, lead paint, or mold debris.

3. List of material and equipment available for the work

4. Material Safety Data Sheets (MSDSs) for all chemicals that will be used or that will be present at the job site.

5. Documentation that contractor is currently licensed by the State of Michigan.

6. Certification of accreditation for each employee of the contractor who will be on-site. Certificates shall be current and within the last 12 months.

7. Documentation of respirator training and fit testing for each employee of the contractor who will be on-site. Fit test documentation shall be current and within the 6 months of the end of the project.

8. Proof of medical surveillance program including a copy of the physicians written opinion [1926.1101(m)(4)] for each employee of the contractor who will be on-site.

9. A letter from U.S. EPA and Michigan DEQ approving disposal site to be used indicating that the Asbestos Containing Material removed from the site will be accepted for disposal.

10. A brief written description of any U.S. EPA, OSHA, MIOSHA, MDEQ or other regulatory agency citations.

11. A brief written description of any legal proceedings, lawsuits or claims which have been filed or levied against the contractor or any of their present or past employees for asbestos related activities.

C. Project Conclusion

The following documents shall be submitted at the conclusion of the project:

• A copy of third-party air monitoring and clearance reports.

• Proof of landfill disposal at a DEQ approved class II landfill (asbestos waste manifest).

SECTION III - RFP PROPOSAL REQUIREMENTS

3.01 Qualifications/Experience

Respondents shall provide experienced, qualified, and capable personnel to perform the functions and responsibilities as outlined in the Scope of Services. The Statement of Qualifications/Experience must clearly demonstrate the Proposer's relevant experience in installation of each type of flooring listed, proper licensing if required, proper insurance as listed in Exhibit B, ability to provide design assistance and product samples and capacity and willingness to manage different size projects and installations.

All Respondents shall provide a Statement of Qualifications/Experience that addresses the following:

Supplier Requirements – Please respond to each requirement.

Companies interested in bidding on this preferred agreement should include in their proposal the following information:

1. Completed unit pricing schedule for the items described (attached)

a. All rates are to include portal to portal travel. Additional travel costs will not be paid or reimbursed. All removal rates must include material, equipment, waste transport, material disposal and any other costs associated to removal of asbestos abatement.

Additional charges will not be accepted.

2. Three references which include description of work completed, contact name, phone number and email address. Description should be listed by Class I, II and III. Contractors may provide projects within one to three of the classes as multiple contractors may be chosen for different size projects.

3. Describe your prior work experience as it relates to the RFP. This should include an explanation of demonstrated experience by Class level.

4. Submission of appropriate licenses and certifications per Act 135

5. List of all previous violations and subsequent corrective actions of said violations

6. Provide average response time to a request for asbestos abatement

7. Describe company safety program and employee education

8. Number of employees accredited (per the Asbestos Workers Accreditation Act, 440 of 1988) as follows:

a. Asbestos, Lead, Paint, Mold Inspectors

b. Asbestos, Lead, Paint, Mold Management Planners

c. Asbestos, Lead, Paint, Mold Abatement Project Designers

d. Asbestos, Lead, Paint, Mold Abatement Contractors and Supervisors

e. Asbestos, Lead, Paint, Mold Abatement Workers

Responses must include the following OU required documents:

• A signed copy of the RFP indicating the Supplier agrees to the RFP in its entirety, including Oakland University’s Terms and Conditions

• Schedule A - Addendum Acknowledgement

• Schedule B – Insurance Acknowledgement and Certificate (Informational Only)

• Response to Qualifications/Experience

• Schedule C – Cost Proposal in Excel format

• Health and Safety Forms

Failure to submit information in accordance with the RFP requirements and procedures may be cause for disqualification. Not submitting the insurance certificate may cause your company to be disqualified.

3.02 University Liaison

The awarded Supplier shall designate and provide at no charge to Oakland University an official representative to serve as liaison with the University in overseeing the relationship between the Supplier and the University. Contact information for the liaison(s) should be provided and include name, title, phone/cell, and email address.

3.03 Cost/Fees

Proposals must include a fee schedule for the goods and/or services being proposed. The schedule should indicate all proposed costs will be held firm for a period of at least on hundred twenty (120) days following submission of the proposal.

Firms must clearly and unambiguously specify the cost of the services in their proposals. Any reimbursable fees should be identified separately.

Any other taxes, fees or commissions applicable to the proposed contract are the responsibility and liability of the proposer who must include these cost items in the price of the goods and services.

3.04 Freedom of Information Act Requests

The Supplier understands that the University complies with the Michigan Freedom of Information Act (“FOIA”) and that the University may provide Confidential Information to other persons or entities upon receipt of a FOIA request. Section “z” of the FOIA states that security information is exempt from disclosure.

A FOIA request must be submitted in writing to the FOIA Office (or Coordinator). The request may be transmitted in hard copy, by email, or by facsimile. Refer to Oakland University’s website for procedures and guidelines to submit a FOIA request - https://www.oakland.edu/policies-regulations/FOIA/.

SECTION IV – EVALUATION

4.01 Evaluation of RFP Response and Selection Criteria

Proposals will be evaluated by the University. If there are portions of any proposal the University finds unacceptable or otherwise in need of clarification or revision, the University reserves the right to negotiate with any or all Suppliers. Any exceptions to the specifications or any other special considerations or conditions requested or required by Supplier will be enumerated by the Supplier and submitted as part of its Proposal, together with an explanation as to the reason the specifications cannot be met. Each Supplier will be required and expected to meet the specifications in their entirety, except to the extent exceptions are expressly noted in its proposal.

The University will evaluate the proposals submitted in response to this RFP, based on the completeness of the information provided and the business and technical merits related to the goals and requirements of the University. The University will conduct a detailed review and evaluation of the company and/or team and all entities and/or organizations participating in providing the goods and services described in this RFP. The evaluation of proposals has one basic objective: to determine whether the proposer meets the requirements set forth in this RFP and has the best value proposal to the University.

https://www.oakland.edu/policies-regulations/FOIA/

After review of submitted proposals, OU reserves the right to request a demonstration of the product.

Proposals will be evaluated by the University against the criterion that follows:

Criterion: Possible Points Approach of delivery of service, and makeup of team 15

Cost of Structure and Services 25 Ability to meet listed criteria 30 Experience, past performance and references 10 Flexibility and willingness to expeditiously enter into contractual agreement, and deliver quality services

Customer Service Plan 5 Training program for employees (safety, cleaning, etc.) 10

TOTAL: 100 POINTS

Proposals will be scored on a one hundred (100) point scale in accordance with the evaluation criteria set forth above. Each Respondent must indicate its fees in accordance with section 3.05. Fees must be reasonable and justifiable and must reflect the proposed approach/work plan. OU will award to the responsive and responsible Respondent(s) whose proposal conforms to this RFP and whose combined scores under this section provide the best value. Notwithstanding anything contained herein, OU reserves the right to make an award based on any other relevant considerations and in the best interest of OU.

4.02 Process for Award

Without limitation and at its sole option, OU reserves the right to accept or reject any or all proposals, to take exception to these RFP specifications, to negotiate with finalists, or to waive any informality. Firms may be excluded from further consideration for failure to fully comply with the specifications of this

RFP.

OU may decide to reject all proposals and/or to reissue this RFP with modifications.

OU will not award contracts to proposers that are debarred, suspended or otherwise determined ineligible by, nor to proposers that OU has determined to be non-responsible.

OU reserves the right to make an award based solely on the original proposals received or to negotiate further with proposers. The proposer selected for the award will be chosen on the basis of an assessment of the greatest benefit to OU, not necessarily on the basis of lowest price. OU also reserves the right to negotiate and award any element of this RFP, make multiple awards, reject any or all proposals or waive any minor irregularities or technicalities in proposals received as the best interest of OU may require.

SECTION V - PROCUREMENT PROCESS

5.01 Submission Method, Date and Time

One (1) copy of the sealed proposal shall be submitted electronically. All responses must be submitted online via Grizzfiles. If you plan to submit a proposal, please request an upload link at least five days prior to the bid submittal by emailing ebnersmi@oakland.edu. Put the proposal number and name in the subject line. Proposals must be received by July 1, 2025 @ 2 P.M. Eastern Time. Proposals will not be opened publicly. It is the firm’s responsibility to ensure that its proposal is delivered at the proper time and place.

The document shall be 8 ½” x 11” format, no smaller than 11-point font, up to 35 pages, and should not contain unnecessary elaborate brochures or other presentations beyond those minimally required to present a complete and effective quotation.

Expenses for developing and presenting responses to this RFP shall be the entire responsibility of the Supplier and shall not be chargeable to the University. All supporting documentation and manuals submitted with this proposal will become the property of the University.

Unless otherwise stated above, proposals submitted are to be in accordance with the outline and specifications contained and are to remain in effect a minimum of 120 days from the date of submission, and may be subject to further extensions as negotiated.

Submitted unit prices and labor costs are to be held for three years of the date of contract.

OU reserves the right to accept or reject any or all proposals, and may cancel this solicitation at any time for any reason at the university’s discretion.

5.02 Questions and Interpretations

All inquiries to this RFP must be submitted in writing to ebnersmi@oakland.edu by June 18, 2025 @ 2 P.M. Eastern Time. An Addendum will be issued by June 20, 2025 with responses to all questions received.

5.03 Prevailing Wage

This Contract is subject to the prevailing wage provisions of Act No. 10 of Michigan Public Acts of 2023 (“The Act”) and the Contractor shall pay prevailing wages, that is, the rates of wages and fringe to be paid to each class of mechanics by the Contractor and all Subcontractors shall be not less than the wage and fringe benefit rates prevailing in the locality in which the work is to be performed. The prevailing wages and fringe benefits determined by the Michigan Department of Labor for the Project are attached hereto and made a part hereof by this reference and are a part of the Specification of the Work to be performed. If the Contract is not awarded or Work undertaken within ninety (90) days of the date of the Michigan Department of Labor’s wage and fringe benefit determination as shown on the attachment, the Michigan Department of Labor shall make a re-determination before the Contract is awarded and the new determination shall become part of the Specifications of the Work to be performed. Construction Mechanics are the intended beneficiaries of the contractual prevailing wage, fringe benefit, and nondiscrimination nonretaliation requirements of the Act. Any construction mechanic aggrieved by the failure of a contractor or subcontractor to pay prevailing wages or benefits as specified in the contract, or by a violation of section 7 of the Act, in addition to any other remedies provided in this act or by law, may bring an action in a court of competent jurisdiction against the contractor or subcontractor for damages or injunctive relief and may be awarded reinstatement or other appropriate relief, and all damages sustained, together with actual costs and attorney fees at trial and on appeal.

5.04 Withdrawal of Proposals

Proposals may be withdrawn by written notice to the prescribed OU Buyer, prior to the proposal deadline date. Negligence on the part of the Supplier in preparing the proposal confers no right of withdrawal or modification of the proposal after the proposal deadline has elapsed.

5.05 Price and Scope of Work Changes

All proposals should be firm and not subject to change by the Supplier for a period of one hundred twenty days (120) from the proposal deadline date. Note, however, OU reserves the option to negotiate prices downward and to negotiate additional scope of work and cost changes based on final negotiations with the selected Supplier.

5.06 Mistakes in Proposals

If a mistake in a proposal is suspected or alleged, the proposal may be corrected or withdrawn prior to the due date for this solicitation. If negotiations are not held, or if best and final offers have been received, the Firm may be permitted to correct a mistake in its proposal and the intended correct offer may be considered based on the conditions that follow:

The mistake and the intended correct offer are clearly evident on the face of the proposal.

The Firm submits written evidence which clearly and convincingly demonstrates both the existing offer, and such correction would not be contrary to the fair and equal treatment of other Firms.

Mistakes discovered after award shall not be corrected unless OU Counsel makes a written determination that it would be disadvantageous to OU not to allow the mistake to be corrected. The approval or disapproval of requests of this nature shall be in writing by OU’s Legal Counsel.

5.07 Execution of Proposals

The original proposal must contain a manual or electronic (date and time stamped) signature of an authorized representative of the Proposer. The proposal must be typed or printed in ink. All corrections made on the proposal sheets must be initialed by the authorized representative. The company name must appear on each sheet. The proposal must include all documents, materials and information required herein.

5.08 Procurement Schedule

The University intends to conduct the procurement process expeditiously. Proposers are expected to comply with the procurement schedule, including any modifications thereto which may be made by the University. The University will notify proposers of any and all such modifications. Proposers who fail to comply with the schedule may not receive further consideration.

The anticipated procurement schedule for the RFP process is as follows; the University will make every effort to adhere to the schedule, and at its discretion is subject to change:

Issue Request for Proposal June 11, 2025

Deadline for Written Questions Regarding the RFP June 18, 2025@ 2 P.M. Eastern Time

Addendum Issued by By June 20, 2025

Proposal Submission July 1, 2025 @ 2 P.M. Eastern Time

Readiness for Service/Contract Commencement Immediately upon award in July

SECTION VI – GENERAL CONDITIONS

6.01 Terms and Conditions

Any contract resulting from this Request for Proposal is subject to and shall be performed in accordance with the University’s General Terms and Conditions for Agreement located at the following: OU Terms & Conditions.

The University’s preferred payment method is with a University credit card (Pcard). The University will not accept convenience fees or increased pricing due to Pcard payment. The University it tax exempt, State of Michigan tax is not applicable.

Any person, firm, corporation or association submitting a proposal shall be deemed to have read and understood all the terms, conditions and requirements in the specifications/scope of work.

Upon University request, the awarded supplier must agree to provide independently audited financial statements including its statement of financial position, statement of operations, and statement of cash flows for at least the past three years. Furthermore, the Contractor must agree to permit the University, upon request, to audit privileges, related to the University’s account. Failure to agree to this may result in disqualification of your bid.

Purchase Orders issued to the Supplier throughout the term of an agreement for services shall be subject to any and all of the provisions noted in this RFP. If there is a discrepancy between the information stated in this RFP and the University’s T&Cs, the T&Cs will apply.

This RFP in no manner obligates the University to the eventual purchase of any products or services described, implied, or which may be proposed, and may be terminated by the University without penalty or obligation at any time.

Expenses for developing and presenting proposals will be the entire responsibility of the Supplier and will not be chargeable to the University. All supporting documentation and manuals with this proposal will become the property of the University.

The Supplier understands that the University complies with the Michigan Freedom of Information Act (“FOIA”) and that the University may provide Confidential Information to other persons or entities upon receipt of a FOIA request. Section “z” of the FOIA states that security information is exempt from disclosure.

https://wwwp.oakland.edu/Assets/upload/docs/General-Counsel/Forms/General-Terms-and-Conditions-for-Agreements.pdf https://wwwp.oakland.edu/Assets/upload/docs/General-Counsel/Forms/General-Terms-and-Conditions-for-Agreements.pdf

Smoke Free Campus: Effective Fall 2013, the University is smoke-free. Contractors are responsible to ensure that all employees and all subcontractors’ employees are in compliance anytime they are on Oakland’s main, or extension center campuses. The complete policy can be found at Policy 475.

6.02 Conflict of Interest

The Supplier affirms that to the best of its knowledge there exists no actual or potential conflict-of-interest between the Supplier's family, business, or financial interests and providing the Services. The Supplier will not attempt to influence any University employee by the direct or indirect offer of anything of value. The Supplier also warrants that no officer or employee of the University has or will have a direct or indirect personal financial interest in the Agreement. The Supplier also affirms that neither the Supplier nor any of its employees has paid or agreed to pay any person, other than bona fide employees and consultants working solely for the Supplier, any fee, commission, percentage, brokerage fee, gift or any other consideration contingent upon or resulting from the execution of an Agreement.

In the event of change in either Supplier’s interests or Services under this Agreement, the Supplier will inform the University regarding all possible conflicts-of interest which may arise as a result of such change. The Supplier agrees that conflicts-of-interest will be resolved to the University’s satisfaction or the University may terminate the Agreement.

Oakland University reserves the following rights: to accept or reject any bid; to reject all bids’ to waive any formalities or irregularities contained in a bid that do not comply with the terms and conditions of the invitation to bid, any modifications to the invitation to bid, or any specifications; to select the bid and/or items that in the sole and absolute discretion of Oakland University are in Oakland University’s best interest whether or not the bid selected is the lowest monetary bid received.

6.03 Cost of Proposal

Suppliers are responsible for all their costs associated with the preparation of proposals, the demonstration and interview process and the contract negotiation process. All costs incurred, directly or indirectly, associated with the preparation of proposals shall be the sole responsibility of and shall be borne by the respondents.

6.04 Form of Purchase

The acceptance of the proposed Firm’s offer for the services specified herein will be made by issuance of a duly authorized contract or purchase order prepared by OU. Suppliers are cautioned to make no assumptions or accept any representations by any employee, member, officer or representative of OU concerning the award until a contract agreement is executed.

6.05 Government Restrictions

In the event any governmental restrictions may be imposed which would necessitate alteration of the material, quality, workmanship or performance of the goods or services offered, it shall be the responsibility of the successful Firm to immediately notify OU in writing specifying the regulation which requires alteration. OU reserves the right to accept any such alteration, including any reasonable price adjustments occasioned thereby, or to cancel the contract at no expense to OU.

https://www.oakland.edu/policies/generalgovernance/475/

6.06 Nonconformance to Conditions/Specifications/Scope of Services Services will be inspected for compliance with specifications. Services not conforming to specifications may not be accepted at the Firm’s expense. Services not provided in accordance with the Scope of Services may result in the Firm being found in default. In the event of default all procurement costs may be charged against the Firm. Any violations of these stipulations may result in the Firm’s name being removed from OU’s proposal mailing list.

6.07 Assignment or Transfer

The successful Firm shall not assign or transfer any interest in any subsequent contract, in whole or part, without written approval of OU. Claims for sums of money due, or to become due from OU pursuant to the contract may be assigned to a bank, trust company or other financial institution. OU is hereby expressly relieved and absolved of any and all liability in the event a purported assignment or subcontracting of the contract is attempted in the absence of the Firm obtaining OU’s prior written consent.

6.08 Patents - Licenses and Royalties

The successful Firm shall indemnify and save harmless OU and its employees from liability of any kind, including cost and expenses for or on account of any copyrighted, patented, or not patented invention, process or article manufactured or used in the performance of the contract, including its use by OU. If the Supplier uses any design, device or material covered by letters, patent, or copyright, it is mutually agreed and understood that the proposal prices shall include all royalties or cost arising from the use of such design, device or materials involved in the work. Further all residual right to Patents, Licenses and Royalties (e.g., software and license to use same purchased) shall revert to OU at the end of the Agreement.

6.09 Permits and Licenses

The successful Firm shall obtain all permits and licenses that are required for performing its work. The Firm shall pay all related fees and costs in connection with required permits and licenses. Proof of ownership shall be made on all software used in the execution of the contract. The Firm will hold OU harmless for any violation of software licensing resulting from breaches by employees, owners, and agents of the Firm.

6.10 Taxes

The successful Firm is responsible for all state and federal payroll and/or social security taxes. The Firm shall hold OU harmless in every respect against tax liability.

6.11 Insurance Requirements

The awarded Supplier will be required to obtain insurance protecting Oakland University, Supplier and any subcontractor of Supplier performing services covered by the RFP. The awarded Supplier agrees to immediately comply with the insurance provisions and maintain insurance levels at its sole expense.

Supplier shall provide acknowledgement and evidence of such insurance prior to execution of the Contract, found in Schedule B. If you cannot currently meet the requirements, proposals must include a statement agreeing to meet these requirements at no additional cost by the time of contract signing.

Failure to meet this requirement may cause the proposal to be considered non-responsive and subject to disqualification. You must submit an insurance certificate (informational only) with your bid response.

6.12 Proof of Insurance

The successful Firm shall furnish to OU a certified copy of the policy or policies covering the work as required in the specifications as evidence that the insurance required will be maintained in force for the entire duration of the contract with OU. OU must be listed as an additional insured.

6.13 Standards of Conduct

The successful Firm shall be responsible for maintaining satisfactory standards of its employee’s competence, conduct, courtesy, appearance, honesty, and integrity. It shall be responsible for taking such disciplinary action with respect to any of its employees as may be necessary.

6.14 Background Checks and Debarment

Contractor has performed a police records check and/or criminal background check and that neither the Contractor nor any of its directors, members, officers, employees, volunteers, servants, agents, representatives and designees, and subcontractors, properly appear on the Michigan Public Sex Offender Registry or has been convicted of a felony, criminal sex offense, forcible assault or any crime against a minor or any other person; and (ix) Contractor is not suspended, debarred, proposed for debarment, declared ineligible or voluntarily excluded from the award of contracts from United States federal government programs and/or agencies and is not listed in the List of Parties Excluded from Federal Procurement or Non-procurement Programs (collectively “Not-Debarred”) pursuant to Executive Order 12549 and the regulations promulgated thereunder, 2 CFR 180, and any additional regulations promulgated by an applicable federal agency, and will obtain identical certifications from Contractor’s lower tier contractors and suppliers that they are also Not-Debarred.

6.15 Removal of Employees

OU may request the successful Firm to immediately remove from assignment to OU and/or dismiss any employee found unfit to perform duties due to one or more of the following reasons:

1. Neglect of Duty.

2. Disorderly conduct, use of abusive or offensive language, quarreling, intimidation by words or actions or fighting.

3. Theft, vandalism, immoral conduct, or any other criminal action.

4. Selling, consuming, possessing, or being under the influence of intoxicants, including alcohol, or illegal substances while on assignment at OU.

6.15 Supervision

The successful Firm shall always provide adequate competent supervision during the performance of the contract. To that effect, a qualified consultant and one or more alternates shall be designated in writing to OU prior to contract start. The Firm or his designated representative shall be readily available to meet with OU personnel. The successful Firm shall provide the telephone numbers where its representative(s) can be reached.

6.17 Performance Evaluation Meeting

The selected Firm shall be readily available to meet with representatives of OU weekly during the first month of the contract and as often as necessary thereafter. A mutual effort will be made to resolve all performance problems identified at these meetings.

6.18 Federal, State and Local Reporting Compliance

The Firm shall provide such financial and programmatic information as required to comply with all Federal, State, and local law reporting requirements.

6.19 Project Personnel

Except as formally approved by OU, the key personnel identified in the accepted proposal shall be the individual who will complete the work, at the proposed levels of effort. Changes in staffing must be proposed in writing to OU and approved.

6.20 Notices

All written notices required to be given by either party under the terms of the contract(s) resulting from the contract award shall be addressed to the Firm at their legal business residence as given in the contract. Written notices to OU shall be addressed as provided in the contract.

6.21 Cancellation

Irrespective of any default hereunder, OU may also at any time at its discretion cancel any subsequent contract related to this solicitation, in whole or in part. In the event of cancellation, the Firm shall be entitled to receive equitable compensation for all work completed and accepted prior to such termination or cancellation as shall be indicated in the contract.

6.22 Travel

All travel and miscellaneous expenses related to this solicitation will be borne by the Firm unless otherwise provided in the contract for services.

6.23 Non-Discrimination

In accordance with the U.S. Constitution and all federal legislation and regulations governing fair employment practices and equal employment opportunity including, but not limited to Title VI (42 USC 2000d, et seq.) and Title VII )42 USC 2000e, et seq.) of the Civil Rights Act of 1964 (P.L. 88-352, 78 Stat.

241) and the U.S. Department of Justice regulations (28 CFR Part 42, et seq.) and the U.S. Department of Labor regulations (29 CFR Part 1601, et seq.) issued pursuant to those Titles, Executive Order 11246 (September 24, 1965) as amended, the Michigan Constitution and all state laws and regulations governing fair employment practices and equal employment opportunity, including but not limited to the Michigan Civil Rights Act (P.A. 1976 No. 453) and the Michigan Handicappers Civil Rights Act (P.A.

1976 No. 220), the Contractor agrees that it shall not discriminate against any employee or applicant for employment with respect to hire, tenure, terms, conditions or privileges of employment because of religion, race, color, national origin, age, sex, sexual orientation, height, weight, marital status or handicap that is unrelated to the individual’s ability to perform the duties of a particular assignment or position. The Contractor hereby recognizes the right of the United States and the State of Michigan to seek judicial enforcement of the foregoing covenant against discrimination, against itself or its subcontractors connected directly or indirectly with the performance of this Contract.

ACCEPTANCE

Please indicate your acceptance of Oakland University’s Terms and Conditions and the provisions stated in this RFP in the space provided below. Complete the information at the bottom of this document and return this signed page with your RFP response.

Thank you.

ACCEPTANCE ACKNOWLEDGEMENT:

I have reviewed and do accept Oakland University’s Terms and Conditions as stated on the University web page. I have read and agree to abide by the terms of this RFP. I also acknowledge that I am a legally authorized representative of the business entity noted below and, as such, have the authority to enter into agreements and make commitments on its behalf:

Company: Address:

Authorized Signature:__________________ Date:

Printed Name: Title:

Phone #: Email:

NOTE: OAKLAND UNIVERSITY RESERVES THE FOLLOWING RIGHTS: TO ACCEPT OR REJECT ANY BID; TO REJECT ALL BIDS; TO WAIVE ANY FORMALITIES OR IRREGULARITIES CONTAINED IN A BID THAT DO NOT COMPLY WITH THE TERMS AND CONDITIONS OF THE INVITATION TO BID, ANY MODIFICATIONS TO THE INVITATION TO BID, OR ANY SPECIFICATIONS; TO SELECT THE BID AND/OR ITEMS THAT IN THE SOLE AND ABSOLUTE DISCRETION OF OAKLAND UNIVERSITY ARE IN OAKLAND UNIVERSITY’S BEST INTEREST

WHETHER OR NOT THE BID SELECTED IS THE LOWEST MONETARY BID RECEIVED.

SCHEDULE A – Addendum Acknowledgement

ADDENDA:

The undersigned affirms that the cost of all work covered by the following Addenda are included in the price of this proposal.

Addendum No. Date: Addendum No. Date:

Firm Name:

SCHEDULE B-INSURANCE REQUIREMENTS ACKNOWLEDGEMENT

You must submit an insurance certificate (informational only) with your bid response.

, at its sole expense, shall cause to be issued and maintained in full effect for the term of this agreement, insurance as set forth hereunder:

Workers’ Comp: Statutory Limits & EL $1,000,000 Commercial General Liability $1,000,000 per occurrence, $2,000,000 aggregate including completed operations coverage Contractors Pollution Liability: $5,000,000 per claim Auto Liability: $1,000,000 Excess (Umbrella): $5,000,000 per occurrence

Respondents must provide an insurance certificate as part of their proposal submittal showing evidence of insurance. If you cannot currently meet the requirements proposals must include a statement agreeing to meet these requirements at no additional cost by the time of contract signing. Failure to meet this requirement in your RFP response may eliminate your company’s proposal.

1. Oakland University and its Board of Trustees must be listed as an “Additional Insured” on the

Certificate of Insurance.

2. Supplier must provide an insurance certificate before commencing service delivery, must keep the certificate up-to-date, and must forward copies of all revised certificates of insurance to the Risk Management Department at Oakland University within thirty (30) days of the change.

3. Notice of cancellation must be submitted thirty (30) days prior to the termination of the insurance coverage.

4. Awarded Supplier shall notify the University of any Accidents and/or claims, including without limitation accidents or claims involving bodily injury, death or property damage, arising on or within the Licensed Premises. Such notice shall be provided in writing as soon as practicable, however in any event within five days of Awarded Supplier’s receipt of notice of the accident or claim.

5. Required insurance coverage and any self-insured retention may be required to be modified by the University if, in the sole judgment of the University, the levels of risk associated with Awarded Supplier’s operations require modification of such coverage.

6. Failure of the Awarded Supplier to obtain and maintain appropriate insurance as specified by the University, without gap, may be deemed a material breach of this license and at the sole discretion of the University may be cause for contract termination.

Exceptions to the above insurance requirements are to be approved, in writing, by the Office of Risk Management. Exceptions are determined by the type and nature of the contract and the individual contractor.

SCHEDULE C-COSTS

Supplier Name: ____________________________________________

All pricing should be completed in Schedule C Excel Sheet provided.

All items proposed by the Supplier should meet or exceed Oakland University’s requirements. The University reserves the right to reject any filter at its sole discretion.

The undersigned, as bidder, declares that he/she having examined the specifications with related documents hereby proposes to furnish the equipment in accordance with the specifications, within the time set forth therein, and at the cost stated below.

All pricing should be completed in Schedule C Excel Sheet provided.

Comments/Restrictions:

Submitted by:_______________________________________________________________________________

Signature:__________________________________________________________________________________

Title/Date:_______________________________________________________________________________ (Title) (Date) Phone:____________________________________________Email:___________________________________

SECTION I – BACKGROUND
1.01 Oakland University Background Information
1.02 RFP Overview
SECTION II – SCOPE OF SERVICES
2.01 Specifications
SECTION III - RFP PROPOSAL REQUIREMENTS
3.01 Qualifications/Experience
3.02 University Liaison
3.03 Cost/Fees
3.04 Freedom of Information Act Requests
SECTION IV – EVALUATION
4.01 Evaluation of RFP Response and Selection Criteria
4.02 Process for Award
SECTION V - PROCUREMENT PROCESS
5.01 Submission Method, Date and Time
5.02 Questions and Interpretations
5.03 Prevailing Wage
5.04 Withdrawal of Proposals
5.05 Price and Scope of Work Changes
5.06 Mistakes in Proposals
5.07 Execution of Proposals
5.08 Procurement Schedule
SECTION VI – GENERAL CONDITIONS
6.01 Terms and Conditions
6.02 Conflict of Interest
6.03 Cost of Proposal
6.04 Form of Purchase
6.05 Government Restrictions
6.06 Nonconformance to Conditions/Specifications/Scope of Services
6.07 Assignment or Transfer
6.08 Patents - Licenses and Royalties
6.09 Permits and Licenses
6.10 Taxes
6.11 Insurance Requirements
6.12 Proof of Insurance
6.13 Standards of Conduct
6.14 Background Checks and Debarment
6.15 Removal of Employees
6.15 Supervision
6.17 Performance Evaluation Meeting
6.18 Federal, State and Local Reporting Compliance
6.19 Project Personnel
6.20 Notices
6.21 Cancellation
6.22 Travel
6.23 Non-Discrimination
SCHEDULE A – Addendum Acknowledgement
SCHEDULE B-INSURANCE REQUIREMENTS ACKNOWLEDGEMENT
SCHEDULE C-COSTS

File details come from the government source that posted it. Updated .