RFP 01-26 Landscaping Services Summary
This is a Request for Proposal (RFP) issued by the Southeastern Public Service Authority (SPSA) of Virginia for comprehensive annual landscaping and grounds maintenance services across multiple facilities. SPSA seeks qualified professional turf and landscape management firms to provide services at 12 locations including the Regional Office Building in Chesapeake, nine transfer stations, a regional landfill, and two convenience centers serving over one million residents across eight jurisdictions (cities of Chesapeake, Franklin, Norfolk, Portsmouth, Suffolk, and Virginia Beach; counties of Isle of Wight and Southampton). Required services encompass turf maintenance with weekly mowing during growing season (March 1 to December 31) at 3-inch height, trimming, edging, fertilization, weed control, overseeding, tree and shrub maintenance including pruning and pest control, litter removal, and snow/ice removal on a per-occurrence basis at the Regional Office Building. The mandatory pre-bid conference is scheduled for April 20, 2026 at 10:00 A.M. at SPSA's Regional Office Building, with proposals due by 2:00 P.M. on May 8, 2026. Site visits are available by contacting designated representatives for each location. The initial contract term is one year with four optional one-year renewal periods, with price increases negotiable only at renewal.
Pricing shall be submitted on the SPSA-provided form with annual costs for each of the 12 locations and a per-occurrence price for snow and ice removal. The contractor will receive twelve equal monthly installments of the contract amount on the 25th of each month, with progress billing permitted. Proposals will be evaluated on experience (35 points), cost (25 points), owned equipment (25 points), and references (15 points). The contractor must maintain Commercial General Liability insurance of $1,000,000 per occurrence/$2,000,000 aggregate, Automobile Liability coverage of $1,000,000 combined single limit, and statutory workers' compensation coverage. SPSA reserves the right to cancel the contract with 60 days' written notice without penalty and may award to multiple offerors. All contractors must comply with SPSA's environmental management system (ISO 14001 conforming), attend a required environmental briefing, and adhere to safety requirements. The contract may be extended for use by other public bodies through cooperative procurement provisions.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL
for
Landscaping Services
RFP 01-26
Issued: April 13, 2026
Pre-Bid: April 20, 2026
Due Date: May 8, 2026
Southeastern Public Service Authority (SPSA) 723 Woodlake Drive, Chesapeake, VA 23320
757.420.4700 www.spsa.com
TABLE OF CONTENTS
SECTION I
PURPOSE
BACKGROUND
SCOPE OF WORK
SECTION II
PROPOSAL PREPARATION AND SUBMISSION INSTRUCTIONS
SECTION III
SPECIFIC PROPOSAL INSTRUCTIONS
SECTION IV
EVALUATION AND AWARD CRITERIA
SECTION V
GENERAL TERMS AND CONDITIONS
SECTION VI
SPECIAL TERMS AND CONDITIONS
SECTION VII
PROPOSAL FORM
SIGNATURE SHEET
PROOF OF AUTHORITY TO TRANSACT BUSINESS IN VIRGINIA
REFERENCE FORM
-1- RFP 01-26
SECTION I
PURPOSE
The purpose of this Request for Proposal (RFP) is to solicit sealed proposals from qualified professional turf and landscape management firms to provide annual landscape and grounds maintenance services according to best green industry practices to the Southeastern Public Service Authority of Virginia (SPSA) at its various locations.
BACKGROUND
SPSA is the regional solid waste collection and disposal agency for over one million residents in the cities of Chesapeake, Franklin, Norfolk, Portsmouth, Suffolk and Virginia Beach and the counties of Isle of Wight and Southampton, all located in the Commonwealth of Virginia. SPSA’s disposal system includes a Regional Landfill in Suffolk and nine transfer stations in various locations throughout the geographic territory served by SPSA, accompanied by a transportation operation, a fleet maintenance facility, a tire shredder facility, a white goods program, and a household hazardous waste program. Please see SPSA’s website for more information, available at www.spsava.gov.
SCOPE OF WORK
GENERAL
The contractor shall furnish all labor, supervision, equipment, tools, parts and materials, as necessary, to provide the identified sites with Comprehensive Landscape Services per contract. Landscaping areas are defined as any areas with lawns, shrubs, flowerbeds, trees.
MINIMUM SPECFICATIONS
1. Turf Maintenance: Maintain turf and street rights-of-way located on the property in a healthy, growing condition by performing the following tasks and other work incidental thereto:
(a) Mowing and Trimming: Turf shall be mowed using a reel or rotary type mower, at least once every seven (7) days during the growing season, generally between March 1 and December 31. Turf shall be mowed as otherwise necessary to maintain a neat and trimmed appearance.
(i) Mowing Height: Fescue or similar type grass is predominating. It shall be mowed to a 3” height.
(ii) Mowing will be accomplished as to not damage trees, shrubs, signs, etc.
-2- RFP 01-26
(iii) Clippings will be immediately removed from any roadway, walkway, parking area, curbing, drain, etc. after each mowing. Excessive clippings shall be removed from turf area as necessary to maintain a professional appearance and to prevent damage to the turf. Care shall be taken to prevent clippings from entering the mulched flower beds and any clipping entering these beds will be removed by the contractor after each mowing.
(iv) Trimming around trees, shrubs, flowers, utilities, signs, etc. shall be performed at each mowing using herbicide, hand labor and/or machine. Trimming shall be done as to not damage any surrounding plant life.
(b) Edging:
(c) Fertilizer:
(d) Weed Control:
(e) Over Seeding:
2. Trees, Shrubs and Beds: Maintain street trees, shrubs as well as any other individually planted tree or shrub on the property in a healthy and growing condition.
(a) Weeding:
(b) Pre-emergent Herbicide:
(c) Post-emergent Herbicide:
(d) Hand Weeding:
(e) Pruning:
(f) Insect and Disease Control: As needed, apply appropriate chemicals as directed by manufacturer’s recommendations to control all forms of pests and disease. Chemicals shall be applied by a qualified applicator.
(g) Fertilizer and Mulching:
-3- RFP 01-26
3. Litter Removal: Pick-up and remove all paper, plastic, metal, trash and other debris, and accumulated leaves, fallen branches, or other organic material from the landscaped beds and mowed turf areas and public right-of-ways to the curb.
Debris may be disposed of at no charge at the closest SPSA facility. Only debris originating from the SPSA facility is eligible for no cost disposal.
4. General Requirements:
(a) Contractor shall demonstrate adequate knowledge of plants, species, pests and diseases for all the plants found on the site and accordingly practice generally acceptable industry standards and techniques for landscape maintenance.
(b) Contractor accepts total responsibility for the replacement of materials, whether owned by SPSA or others, which SPSA judges to have been damaged or killed as a result of poor industry practice or lack of knowledge.
(c) The contractor shall ensure that their site supervisor is capable of clear and concise communication in the English language with the SPSA representative.
(d) Contractor will provide the necessary Personal Protective Equipment for all employees assigned to this contract.
(e) The contractor shall immediately remove any employee from the site that appears to be incompetent or behaving in a disorderly manner. If SPSA requests the removal of an employee from the work site, that employee shall not be allowed to return to the site without written permission from an authorized SPSA representative.
5. Specific Sites:
Regional Office Building 723 Woodlake Dr.
Chesapeake VA, 23320
Chesapeake Transfer Station 901 Hollowell Dr.
Chesapeake VA 23320
Norfolk Transfer Station 3136 Woodland Av.
Norfolk VA, 23504
Landstown Transfer Station 1825 Concert Dr.
VA Beach VA, 23453
Oceana Transfer Station 2025 VA Beach Blvd.
VA Beach VA, 23462
Operation Center 2 & 4 Victory Blvd.
Portsmouth VA, 23704
Victory Blvd Corridor Drawing B Victory Blvd.
Portsmouth VA, 23704
Regional Landfill 1 Bob Foeller Dr Suffolk, VA 23434
-4- RFP 01-26
Isle of Wight Transfer Station 13191 Four Square Road Smithfield, VA 23430
Ivor Convenience Center 36439 General Mahone Blvd.
Ivor, VA 23866
Boykins Convenience Center 18449 General Thomas HWY
Boykins, VA 23827
Franklin Transfer Station 30521 General Thomas HWY
Franklin, VA 23851
6. Hours of Service: Due to the number of visitors to the Regional Office Building and the uncertain schedule for large meetings at the facility, any services required under this agreement at this location requiring the use of power equipment should be scheduled before 8:00 AM or after 4:00 PM or on weekends. Other sites included in this RFP may be serviced at any other time during normal operating hours.
7. A per-occurrence price for snow and ice removal from the parking lots and sidewalks at 723 Woodlake Dr. shall be included. The area to be serviced during ice and snow events is identified on the attached drawing A.
8. Site Visits:
Interested bidders may arrange site visits through the following contact person for each site:
Regional Office Building Angie Hutchins 757-961-3562 Chesapeake Transfer Station Robbie Robinson 757-961-3942 Landstown Transfer Station Brian Ogle 757-961-3985 Norfolk Transfer Station Michael Debroux 757-961-3980 Oceana Transfer Station Dustin Plass 757-961-4052 Operations Center Kurt Prenger 948-999-3536 Franklin, Isle of Wight, Suffolk Duane Cooper 757-417-5365 Boykins & Ivor Duane Cooper 757-417-5365
In addition, you may visit our website at www.spsava.gov for information on operating hours at each location.
9. Payment: The contractor shall be paid in twelve equal monthly installments of the contract amount on the 25th of each month of the contract period as long as an invoice has been provided.
10. Other Requirements:
SPSA may request services ancillary to this contract but not included in price schedule. These will be invoiced per negotiated quotes and paid per invoice
-5- RFP 01-26
Attached: Drawing A
Highlighted area indicates the service area for 723 Woodlake Drive, Chesapeake, VA.
Bidders should only include the cost of service for the highlighted service area.
-6- RFP 01-26
Attached: Drawing B
Highlighted area indicates the service area for Victory Blvd. Corridor, Portsmouth, VA.
Bidders should only include the cost of service for the highlighted service area.
-7- RFP 01-26
SECTION II
PROPOSAL PREPARATION AND SUBMISSION INSTRUCTIONS
1. REQUEST FOR PROPOSAL (RFP) RESPONSE: Proposals will be received at the Purchasing Department of the Southeastern Public Service Authority of Virginia, in the Regional Office Building, 723 Woodlake Drive, Chesapeake, Virginia 23320, until 2:00 P.M. May 8, 2026, in accordance with the specifications and other terms and conditions set forth herein.
Proposals shall be delivered to SPSA in a sealed envelope showing on the outside the RFP number, time, date, and RFP description. OR
Offerors shall submit one (1) original and two (2) complete copies of their proposal to SPSA plus an electronic copy on a flash drive.
2. PRE-PROPOSAL CONFERENCE: A mandatory pre-proposal conference will be held at 723 Woodlake Dr Chesapeake, VA 23320, at 10 A.M on April 20, 2026, to clarify and answer any questions regarding this proposal. Any changes determined necessary which may affect the responses to this RFP will be formally addressed via addenda issued by SPSA.
3. PROPOSAL SOURCE/CHANGES TO THE RFP:
Any changes to the terms and conditions of this Request for Proposal determined necessary by SPSA, in its sole discretion, will be formally addressed via addenda issued by SPSA. No purported modification of any term or condition of this RFP shall be binding upon SPSA unless it is made in strict accordance with this paragraph. Please direct all questions to SPSA via email at purchasing@spsava.gov.
Offerors are solely responsible for ensuring that SPSA has valid contact information for the offeror, regardless of whether you received a copy of this RFP from SPSA or from any other source. If you receive a copy of this Request for Proposal from a source other than SPSA or eVA, please contact SPSA at the email address specified above (purchasing@spsava.gov) and provide your name, address, telephone number, and email address. Please reference the RFP Number in the subject line of the email. Thereafter, you will be added to the offerors list and will receive any addenda to the RFP.
4. PROPOSAL PREPARATION:
(a) Proposals shall be signed by an authorized representative of the offeror.
(b) All information requested in this RFP should be included as part of the proposal. Failure by any offeror to submit all information requested may result in SPSA requiring prompt submission of missing information by each
-8- RFP 01-26
such offeror and/or giving a lowered evaluation of the proposal to each such offeror. Proposals that are substantially incomplete or lack key information may be rejected.
(c) Proposals should be prepared simply and economically, providing a straightforward, concise description of capabilities to satisfy the requirements of this RFP.
(d) Proposals should be organized in the order in which the requirements are presented in Section III of this RFP (Specific Proposal Instructions). All pages of the proposal should be numbered. Each section in the proposal should reference the corresponding section of this RFP. Please also cite the paragraph number, subletter, and repeat the text of the requirement as it appears in this RFP. If a response covers more than one page, the paragraph number and subletter should be repeated at the top of the next page. The proposal should contain a table of contents which cross-references the applicable RFP requirements. Information which the offeror desires to present that does not fall within any of the requirements of this RFP should be clearly identified as additional material and inserted at an appropriate place or be attached at the end of the proposal. Proposals that are not organized in this manner risk elimination from consideration if SPSA is unable to determine whether or not (or where) the applicable RFP requirements are specifically addressed.
(e) As used in this RFP, the terms “must”, “shall”, “should” and “may” identify the criticality of requirements. “Must” and “shall” identify requirements whose absence will have a significant negative impact on the suitability of the proposal. Items labeled “should” or “may” are highly desirable and would be useful, although they are not necessary and their absence will have a material impact on the review of the proposal. Depending on the overall response to this RFP, some individual “must” and “shall” items may not be fully satisfied, but it is the intent to satisfy most, if not all, “must” and “shall” requirements. The inability of an offeror to satisfy a “must” or “shall” requirement does not automatically remove that offeror from consideration;
however, it may significantly affect the overall rating of the offerors’ proposal.
(f) Each copy of the proposal should be bound or contained in a single volume where practical. All documentation submitted with the proposal should be contained in that single volume.
(g) Ownership of all data, materials, and documentation originated and prepared for SPSA pursuant to this RFP shall belong exclusively to SPSA and be subject to public inspection in accordance with the Virginia Freedom of Information Act. Trade secrets or proprietary information submitted by an offeror shall not be subject to public disclosure under the Virginia Freedom of Information Act; however, the offeror must invoke the protections of § 2.2-
-9- RFP 01-26
4342F of the Code of Virginia, in writing, either before or at the time the data or other material is submitted. The written notice must specifically identify the data or materials to be protected and state the reasons why protection is necessary. The proprietary or trade secret material submitted must be identified by some distinct method such as highlighting or underlining and must indicate only the specific words, figures, or paragraphs that constitute trade secret or proprietary information. The classification of an entire proposal document, line-item prices, and/or total proposal prices as proprietary or trade secrets is not acceptable and will result in rejection of the proposal.
5. ORAL PRESENTATION: Offerors who submit a proposal in response to this RFP may be required to give an oral presentation of their proposal to SPSA. This provides an opportunity for the offeror to clarify or elaborate on the proposal. This is a fact finding and explanation session only and does not include negotiation.
Oral presentations are an option and may or may not be conducted, and SPSA’s Purchasing Department will schedule the time and location of these presentations to the extent (if at all) they are required.
-10- RFP 01-26
SECTION III
SPECIFIC PROPOSAL INSTRUCTIONS
Proposals shall be prepared in accordance with the format below and should be as thorough and detailed as possible so that SPSA may properly evaluate your capabilities to provide the required services. Offerors are required to and must submit the following items as a complete proposal:
1. A title page displaying the RFP subject, the name of the offeror’s firm, address, telephone number, email address, name of the contact person, and date.
2. A written narrative statement to include:
(a) Profile of offeror.
(b) Names, qualifications, experience and location of personnel to be assigned to provide the services.
(c) Examples of demonstrated experience in providing services similar to the services described herein.
3. Specific plans for providing the proposed services, and other matters relevant to provision of the services, including:
(a) Detailed descriptions of any services that may or will be subcontracted, including identities of and all relevant information with respect to actual or potential subcontractors.
(b) Demonstrated compliance with all current federal, state, and local regulations.
4. Proposed pricing terms indicated on Pricing Schedule provided in Appendix.
5. Proof of Authority to Transact Business in Virginia in the form provided in Appendix.
6. Signature Sheet in the form provided in Appendix.
7. List of References for similar services and associated project size in the form provided in Appendix.
-11- RFP 01-26
SECTION IV
EVALUATION AND AWARD CRITERIA
1. EVALUATION CRITERIA: Proposals shall be evaluated by SPSA using the following criteria and scoring:
(a) Experience: up to 35 total points.
(b) Cost to provide service: up to 25 total points.
(c) Owned Equipment: up to 25 total points.
(d) References: up to 15 total points.
2. AWARD TO MULTIPLE OFFERORS: Selection may be made of two or more offerors deemed to be fully qualified and best suited among those submitting proposals on the basis of the evaluation factors included in the Request for Proposals, including price, if so stated in the Request for Proposals. Negotiations shall be conducted with the offerors so selected. Price shall be considered, but need not be the sole determining factor. After negotiations have been conducted with each offeror so selected, SPSA shall select the offeror which, in its opinion, has made the best proposal, and shall award the contract to that offeror. SPSA reserves the right to make multiple awards as a result of this RFP. SPSA may cancel this Request for Proposals or reject proposals at any time prior to an award, and is not required to furnish a statement of the reasons why a particular proposal was not deemed to be the most advantageous (Code of Virginia, § 2.2-4359D).
Should SPSA determine in writing and in its sole discretion that only one offeror is fully qualified, or that one offeror is clearly more highly qualified than the others under consideration, a contract may be negotiated and awarded to that offeror.
The award document will be a contract incorporating by reference all the requirements, terms and conditions of the RFP and the contractor’s proposal as negotiated.
-12- RFP 01-26
SECTION V
GENERAL TERMS AND CONDITIONS
1. COMMONWEALTH OF VIRGINIA PUBLIC PROCUREMENT ACT AND SPSA
PROCUREMENT POLICY: This Request for Proposal (RFP) is subject to the provisions of the Virginia Public Procurement Act and the SPSA Procurement Manual, including any revisions thereto in effect at the time of this Request for Proposal.
2. APPLICABLE LAWS AND COURTS: This RFP and any resulting contract shall be governed in all respects by the laws of the Commonwealth of Virginia, and any litigation with respect thereto shall be brought in the courts of the Commonwealth.
The contractor shall comply with all federal, state and local laws, rules and regulations that are applicable to this RFP and any resulting contract.
3. EMPLOYMENT DISCRIMINATION BY CONTRACTOR PROHIBITED: By submitting a bid, offerors certify to SPSA that they will conform to the provisions of the Federal Civil Rights Act of 1964, as amended, as well as the Virginia Fair Employment Contracting Act of 1975, as amended, and, where applicable, the Virginians With Disabilities Act, the Americans With Disabilities Act and § 2.2-4311 of the VPPA.
If an award is made to a faith-based organization, the organization shall not discriminate against any recipient of goods, services, or disbursements made pursuant to the contract on the basis of the recipient’s religion, religious belief, refusal to participate in a religious practice, or on the basis of race, age, color, gender, sexual orientation, gender identity, or national origin and shall be subject to the same rules as other organizations that contract with public bodies to account for the use of the funds; provided, however, if the faith-based organization segregates public funds into separate accounts, only the accounts and programs funded with public funds shall be subject to audit by SPSA. (Va. Code § 2.2- 4343.1(E)).
(a) During the performance of the contract, the contractor agrees as follows:
i. The contractor will not discriminate against any employee or applicant for employment because of race, religion, color, sex, national origin, age, disability, or any other basis prohibited by state law relating to discrimination in employment, except where there is a bona fide occupational qualification reasonably necessary to the normal operation of the contractor. The contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of this nondiscrimination clause.
-13- RFP 01-26
ii. The contractor, in all RFPs or advertisements for employees placed by or on behalf of the contractor, will state that such contractor is an equal opportunity employer.
iii. Notices, advertisements and RFPs placed in accordance with federal law, rule or regulation shall be deemed sufficient for the purpose of meeting these requirements.
(b) The contractor will include the provisions of clause (a) above in every subcontract or purchase order over $10,000, so that the provisions will be binding upon each applicable subcontractor or vendor.
4. ETHICS IN PUBLIC CONTRACTING: By submitting their proposal, offerors certify that their proposal is made without collusion or fraud and that they have not offered or received any kickbacks or inducements from any other offeror, supplier, manufacturer or subcontractor in connection with their proposal, and that they have not conferred on any public employee having official responsibility for this procurement transaction any payment, loan, subscription, advance, deposit of money, services or anything of more than nominal value, present or promised, unless consideration of substantially equal or greater value was exchanged.
5. IMMIGRATION REFORM AND CONTROL ACT OF 1986: By entering into a written contract with SPSA, the contractor certifies that the contractor does not, and shall not during the performance of the contract; knowingly employ an unauthorized alien as defined in the federal Immigration Reform and Control Act of 1986.
6. DEBARMENT STATUS: By submitting their proposal, offerors certify that they are not currently debarred by the Commonwealth of Virginia from submitting bids or proposals on contracts for the type of goods and/or services covered by this RFP, nor are they an agent of any person or entity that is currently so debarred.
7. MANDATORY USE OF SPSA FORMS PROVIDED IN APPENDIX AND TERMS
AND CONDITIONS: Failure to submit a proposal on the SPSA form(s) provided for that purpose may be a cause for rejection of the proposal. Modification of or additions to the General and/or Special Terms and Conditions of the RFP may be cause for rejection of the proposal; however, SPSA reserves the right to decide, on a case by case basis, in its sole discretion, whether to reject such a proposal as nonresponsive. As a precondition to its acceptance, SPSA may, in its sole discretion, request that the offeror withdraw or modify nonresponsive portions of a proposal which do not affect quality, quantity, price, or delivery.
8. CLARIFICATION OF TERMS: If any prospective offeror has questions about the specifications in this RFP or other RFP documents, the prospective offeror should contact SPSA, via email, no later than five (5) working days before the due date for proposals. Any revisions to the RFP will be made only by addendum issued by
SPSA.
-14- RFP 01-26
9. PAYMENT:
(a) To Prime Contractor:
(i) Invoices for items ordered, delivered and accepted shall be submitted by the contractor directly to the payment address shown on the purchase order/contract. All invoices shall show the SPSA contract number and/or purchase order number. Payment shall be made following completion of project and acceptance by SPSA.
Progress billing may be provided.
(ii) Any payment terms requiring payment in less than 30 days will be regarded as requiring payment 30 days after invoice or delivery, whichever occurs last. This shall not affect offers of discounts for payment in less than 30 days, however.
(iii) All goods or services provided under this contract or purchase order, that is to be paid for with public funds, shall be billed by the contractor at the contract price.
(iv) The postmark date in all cases shall be deemed to be the date of payment.
(v) Unreasonable Charges. Under certain emergency procurements and for most time and material purchases, final job costs cannot be accurately determined at the time orders are placed. In such cases, contractors should be put on notice that final payment in full is contingent on a determination of reasonableness with respect to all invoiced charges. Charges which appear to be unreasonable will be researched and challenged, and that portion of the invoice held in abeyance until a settlement can be reached. Upon determining that invoiced charges are not reasonable, SPSA shall promptly notify the contractor, in writing, as to those charges which it considers unreasonable and the basis for the determination. A contractor may not institute legal action unless a settlement cannot be reached within thirty (30) days of notification.
(b) To Subcontractors:
(i) A contractor awarded a contract under this RFP is hereby obligated:
1. To pay the subcontractor(s) within seven (7) days of the contractor’s receipt of payment from SPSA for the proportionate share of the payment received for work performed by the subcontractor(s) under the contract; or
2. To notify SPSA and the subcontractor(s), in writing, of the contractor’s intention to withhold payment and the reason.
-15- RFP 01-26
(ii) The contractor is obligated to pay the subcontractor(s) interest at the rate of one percent per month (unless otherwise provided under the terms of the contract) on all amounts owed by the contractor that remain unpaid seven (7) days following receipt of payment from SPSA, except for amounts withheld as stated in (2) above. The date of mailing of any payment by U. S. Mail is deemed to be payment to the addressee. These provisions apply to each sub-tier contractor performing under the primary contract. A contractor’s obligation to pay an interest charge to a subcontractor may not be construed to be an obligation of SPSA.
(c) SPSA recognizes the importance of timely payments to our vendors.
Therefore, we offer our vendors the opportunity to enroll in our electronic fund transfer (EFT) program. This program allows us to make electronic fund transfer (EFT) payments to our vendors. Our EFT program is mutually beneficial and is our preferred method of payment. If you choose not to enroll in this program, payments will be made by check and mailed through the postal service which could impact how quickly you receive payments.
Payment(s) made through EFT are processed every two weeks as compared to monthly in the form of a check. Contractor is required to complete our EFT forms, ensuring faster payment transactions.
(d) For contracts for construction that provide for progress payments in installments based upon an estimated percentage of completion, the contractor shall be paid at least ninety-five percent of the earned sum when payment is due, with no more than five percent being retained to ensure faithful performance of the contract. All amounts withheld may be included in the final payment. Any subcontract for a public project that provides for similar progress payments shall be subject to the provisions of this section.
10. QUALIFICATIONS OF OFFERORS: SPSA may make such reasonable investigations as deemed proper and necessary to determine the ability of each offeror to perform the services solicited by this RFP, and the offeror shall furnish to SPSA all such information and data for this purpose as may be requested. SPSA reserves the right to inspect each offeror’s physical facilities prior to award to satisfy questions regarding the offeror’s capabilities. SPSA further reserves the right to reject any proposal if the evidence submitted by, or investigations of, an offeror fails to satisfy SPSA that such offeror is properly qualified to carry out the obligations of the contract and to provide the services contemplated therein.
11. TESTING AND INSPECTION: SPSA reserves the right to conduct any test/inspection it may deem advisable to ensure that goods and services provided under the contract conform to specifications.
12. ASSIGNMENT OF CONTRACT: The contract shall not be assignable by the contractor in whole or in part without the written consent of SPSA.
-16- RFP 01-26
13. CHANGES TO THE CONTRACT: The parties may agree in writing to modify the terms, conditions, or scope of the contract. Any additional goods or services to be provided shall be of a sort that is ancillary to the contract goods or services, or within the same broad product or service categories as were included in the contract award. Any increase or decrease in the price of the contract resulting from any such modification shall be agreed to by the parties as a part of their written agreement to modify the scope of the contract.
14. DEFAULT: In case of failure to deliver goods or services in accordance with the contract terms and conditions, SPSA, after due oral or written notice, may procure them from other sources and hold the contractor responsible for any resulting additional purchase and administrative costs. This remedy shall be in addition to any other remedies which SPSA may have.
15. TAXES: Sales to SPSA are normally exempt from State sales tax. State sales and use tax certificates of exemption, Form ST-12, will be issued upon request.
Deliveries against this contract shall usually be free of Federal excise and transportation taxes.
16. USE OF BRAND NAMES: Unless otherwise provided in this RFP, the name of a certain brand, make or manufacturer does not restrict offerors to the specific brand, make or manufacturer named, but conveys the general style, type, character, and quality of the article desired. Any article which the public body, in its sole discretion, determines to be the equivalent of that specified, considering quality, workmanship, economy of operation, and suitability for the purpose intended, shall be accepted. The offeror is responsible to clearly and specifically identify the product being offered and to provide sufficient descriptive literature, catalog cuts and technical detail to enable SPSA to determine if the product offered meets the requirements of the RFP. This is required even if offering the exact brand, make or manufacturer specified. Normally in competitive sealed bidding only the information furnished with the bid will be considered in the evaluation. Failure to furnish adequate data for evaluation purposes may result in declaring a bid nonresponsive. Unless the offeror clearly indicates in its bid that the product offered is an equivalent product, such bid will be considered to offer the brand name product referenced in the RFP.
17. TRANSPORTATION AND PACKAGING: By submitting their bids, all offerors certify and warrant that the price offered for FOB destination includes only the actual freight rate costs at the lowest and best rate and is based upon the actual weight of the goods to be shipped. Except as otherwise specified herein, standard commercial packaging, packing and shipping containers shall be used. All shipping containers shall be legibly marked or labeled on the outside with purchase order number, commodity description, and quantity.
8. INSURANCE: By signing and submitting a proposal under this RFP, the offeror certifies that, if awarded the contract, it will have the following insurance coverage at the time the contract is awarded. The offeror further certifies that the contractor
-17- RFP 01-26
and any subcontractors will maintain this insurance coverage during the entire term of the contract and that all insurance coverage will be provided by insurance companies authorized to sell insurance in Virginia by the Virginia State Corporation Commission.
(a) Employer’s Liability and Workers’ Compensation - Statutory requirements and benefits. Coverage is compulsory for employers of three or more employees, to include the employer. Contractors who fail to notify SPSA of increases in the number of employees that change their workers’ compensation requirements under the Code of Virginia during the course of the contract shall be in noncompliance with the contract.
(b) Commercial General Liability - $1,000,000 per occurrence and $2,000,000 in the aggregate. Commercial General Liability is to include bodily injury and property damage, personal injury and advertising injury, products and completed operations coverage. SPSA must be named as an additional insured and so endorsed on the policy.
(c) Automobile Liability - $1,000,000 combined single limit. Contractor must assure that the required coverage is maintained by the contractor (or third party owner of such motor vehicle.)
18. DRUG-FREE WORKPLACE: During the performance of the contract, the contractor agrees to (i) provide a drug-free workplace for the contractor’s employees; (ii) post in conspicuous places, available to employees and applicants for employment, a statement notifying employees that the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana is prohibited in the contractor’s workplace and specifying the actions that will be taken against employees for violations of such prohibition; (iii) state in all RFPs or advertisements for employees placed by or on behalf of the contractor that the contractor maintains a drug-free workplace; and (iv) include the provisions of the foregoing clauses in every subcontract or purchase order of over $10,000, so that the provisions will be binding upon each applicable subcontractor or vendor.
For the purposes of this section, “drug-free workplace” means a site for the performance of work done in connection with a specific contract awarded to a contractor, the employees of whom are prohibited from engaging in the unlawful manufacture, sale, distribution, dispensation, possession or use of any controlled substance or marijuana during the performance of the contract.
9. DISCRIMINATION PROHIBITED: No offeror or contractor shall be discriminated against in the RFP or award of any contract because of race, religion, color, sex, sexual orientation, gender identity, national origin, age, disability, status as a service disabled veteran, faith-based organization or any other basis prohibited by state law relating to discrimination in employment or because the offeror or contractor employs ex-offenders unless SPSA makes a written determination that employing ex-offenders on the contract is not in its best interest.
-18- RFP 01-26
SPSA will facilitate the participation of small businesses, businesses owned by women, minorities, and service-disabled veterans, and employment services organizations in procurement transactions. Whenever direct RFPs to potential offerors or contractors are made, SPSA shall include businesses selected from a list made available by the Department of Small Business and Supplier Diversity, which list shall include all companies and organizations certified by the Department.
19. AVAILABILITY OF FUNDS: It is understood and agreed between the parties herein that SPSA shall be bound hereunder and under the contract only to the extent of the funds available or which may hereafter become available for the purpose of the contract.
20. AUTHORIZATION TO CONDUCT BUSINESS IN THE COMMONWEALTH: A
contractor organized as a stock or nonstock corporation, limited liability company, business trust, or limited partnership or registered as a registered limited liability partnership shall be authorized to transact business in the Commonwealth as a domestic or foreign business entity if so required by Title 13.1 or Title 50 of the Code of Virginia or as otherwise required by law. Any business entity described above that enters into a contract with SPSA pursuant to the Virginia Public Procurement Act shall not allow its existence to lapse or its certificate of authority or registration to transact business in the Commonwealth, if so required under Title
13.1 or Title 50, to be revoked or cancelled at any time during the term of the contract. SPSA may void any contract with a business entity if the business entity fails to remain in compliance with the provisions of this section.
-19- RFP 01-26
SECTION VI
SPECIAL TERMS AND CONDITIONS
1. ACCEPTANCE PERIOD: Any proposal delivered in response to this RFP shall be valid for sixty (60) days (Acceptance Period). At the end of the Acceptance Period the proposal may be withdrawn at the written request of the offeror. If the proposal is not withdrawn at the end of the Acceptance Period, then it remains in effect until an award is made or the RFP is canceled.
2. BEST AND FINAL OFFER (BAFO): At the conclusion of negotiations, the offeror(s) may, in SPSA’s sole discretion, be asked to submit in writing a Best And Final Offer (BAFO). After the BAFO is submitted, no further negotiations shall be conducted with the offeror(s). In that event, each offeror’s proposal will be re-evaluated and the decision to award will be based on the BAFO.
3. RENEWAL OF CONTRACT: This contract may be renewed by SPSA for four successive one year periods under the terms and conditions of the original contract. Price increases may be negotiated only at the time of renewal unless previously approved and accepted by SPSA at the time the contract is executed.
Written notice of SPSA’s intention to renew shall be given approximately 90 days prior to the expiration date of each contract period.
4. CANCELLATION OF CONTRACT: SPSA reserves the right to cancel and terminate any contract, in part or in whole, without penalty, upon sixty (60) days written notice to the contractor. Any contract cancellation notice shall not relieve the contractor of the obligation to deliver and/or perform on all outstanding orders issued prior to the effective date of cancellation.
5. COOPERATIVE PROCUREMENT: This procurement is being conducted on behalf of the Southeastern Public Service Authority of Virginia (SPSA), and other public bodies in accordance with the provisions of §2.2-4304 of the Virginia Public Procurement Act.
A contract resulting from this procurement may be used by other public bodies to purchase at contract prices and in accordance with the contract terms, if approved by Contractor. The Contractor shall deal directly with any public body it approves to use the contract. Failure to extend a contract to another public body will have no effect on consideration of Contractor’s bid/proposal.
With the approval of the Contractor, any public body using the resultant contract has the option of executing a separate contract with the Contractor to add terms and conditions required by statute, ordinances, or regulations, or to remove terms and conditions which conflict with its governing statutes, ordinances, or regulations.
-20- RFP 01-26
SPSA, its officials and staff are not responsible for placement of orders, invoicing, payments, contractual disputes, or any other transactions between the Contractor and any other public body, and in no event shall the SPSA, its officials or staff be responsible for any costs, damages or injury resulting to any party from use of a SPSA contract. If, when preparing such a contract, the additional terms and conditions of a public body seeking to purchase pursuant to cooperative procurement are unacceptable to the Contractor, the Contractor may withdraw its consent to extension of the contract to that particular public body.
SPSA assumes no responsibility for any notification of the availability of the contract for use by other public bodies, but the Contractor may carry out such notification.
6. CONTRACTOR REGISTRATION: If a contract for construction, removal, repair or improvement of a building or other real property is for $120,000 or more, or if the total value of all such contracts undertaken by offeror within any 12-month period is $750,000 or more, the offeror is required under Title 54.1-1100, Code of Virginia (1950), as amended, to be licensed by the State Board of Contractors a “CLASS A CONTRACTOR.” If such a contract is for $10,000 or more but less than $120,000, or if the total value of all such contracts undertaken by offeror within any 12-month period is $150,000 or more, but less than $750,000 or more, the offeror is required to be licensed as a “CLASS B CONTRACTOR.” If such a contract is over $1,000 but less than $10,000, or if the contractor does less than $150,000 in business in a 12-month period, the offeror is required to be licensed as a “CLASS C CONTRACTOR.” The board shall require a master tradesmen license as a condition of licensure for electrical, plumbing and heating, ventilation and air conditioning contractors. The offeror shall place on the outside of the envelope containing the bid and shall place in the bid over his signature whichever of the following notations is appropriate, inserting his contractor license number:
Licensed Class A Virginia Contractor No. _____ Specialty __________
Licensed Class B Virginia Contractor No. _____Specialty __________
Licensed Class C Virginia Contractor No. _____Specialty __________
If the offeror shall fail to provide this information on his bid or on the envelope containing the bid and shall fail to promptly provide said contractor license number to SPSA in writing when requested to do so before or after the opening of bids, he shall be deemed to be in violation of § 54.1 1115 of the Code of Virginia (1950), as amended, and his bid will not be considered.
If a offeror shall fail to obtain the required license prior to submission of his bid, the bid shall not be considered.
7. INDEMNIFICATION: Contractor agrees to indemnify, defend and hold harmless SPSA, its officers, agents, and employees from any claims, damages and actions of any kind or nature, whether at law or in equity, arising from or caused by the use
-21- RFP 01-26
of any materials, goods, or equipment of any kind or nature furnished by the contractor and/or any services of any kind or nature furnished by the contractor, unless such liability is solely attributable to the gross negligence or willful misconduct of SPSA.
8. PRIME CONTRACTOR RESPONSIBILITIES: The contractor shall be responsible for completely supervising and directing the work under the contract and all subcontractors that it may utilize, using its best skill and attention. Subcontractors who perform work under the contract shall be responsible to the prime contractor.
The contractor is as fully responsible for the acts and omissions of its subcontractors and of persons employed by the subcontractors as it is for the acts and omissions of the contractor’s own employees.
9. WORK SITE DAMAGES: Any damage to existing utilities, equipment or finished surfaces resulting from the performance of this contract shall be repaired to SPSA’s satisfaction at the contractor’s expense.
10. STATE CORPORATION COMMISSION IDENTIFICATION NUMBER: Pursuant to Code of Virginia, §2.2-4311.2 subsection B, an offeror organized or authorized to transact business in the Commonwealth pursuant to Title 13.1 or Title 50 is required to include in its proposal the identification number issued to it by the State Corporation Commission (SCC). Any offeror that is not required to be authorized to transact business in the Commonwealth as a foreign business entity under Title
13.1 or Title 50 or as otherwise required by law is required to include in its proposal a statement describing why the offeror is not required to be so authorized. Indicate the above information on the SCC Form provided in Appendix. Contractor agrees that the process by which compliance with Titles 13.1 and 50 is checked during the RFP stage (including without limitation the SCC Form provided) is streamlined and not definitive, and SPSA’S use and acceptance of such form, or its acceptance of contractor’s statement describing why the offeror was not legally required to be authorized to transact business in the Commonwealth, shall not be conclusive of the issue.
11. HAZARD COMMUNICATION PROGRAM: The Southeastern Public Service Authority is required in accordance with 29 CFR 1910.1200 to inform all SPSA and contractor personnel that work centers within SPSA have hazardous chemicals on site. SPSA and contractor personnel may be exposed to these hazardous chemicals while working at SPSA work centers. A written Hazard Communication Program has been developed to inform personnel of the specific hazardous chemicals at the work centers and the related safety information, including protective measures, special precautions and emergency procedures to be observed. The Hazard Communication Program including Material Safety Data Sheets for each hazardous chemical at the work centers will be made available to contractors. Contractors are responsible for communicating the information contained in the Material Safety Data Sheets to their personnel working at each SPSA work center. Contractors or contractor personnel are in turn responsible for having Material Safety Data Sheets on any hazardous chemical that they will be
-22- RFP 01-26
using or storing at a SPSA facility. Furthermore, these Material Safety Data Sheets must be at the SPSA facility where they are being used and available for inspection by or on behalf of SPSA.
12. SPSA ENVIRONMENTAL PROCUREMENT POLICY: In 2003, SPSA implemented an environmental management system (EMS) that conforms to the elements of the ISO 14001 Environmental Standard. SPSA’s EMS is designed to assist it in managing and minimizing the environmental impacts of its processes and activities, which are called environmental aspects. SPSA will provide a list of the environmental aspects known to be associated with the planned/proposed activity in every RFP. Any contractor coming on any SPSA site to provide services to SPSA must comply with the policies, intent and/or procedures of SPSA’s EMS to manage these environmental aspects. This compliance will be demonstrated by the following:
(a) Agreeing in writing to comply with SPSA’s established emergency response procedures in the event of an incident that could adversely impact the environment; and
(b) Attending an environmental briefing prior to providing SPSA with any services. During this briefing, SPSA’s representatives and the contractor representative will collaboratively identify any planned activities, processes or products that could potentially impact the environment. Proactive measures designed to minimize these potential environmental impacts will be discussed. Results of this discussion will be documented on SPSA’s Contractor Environmental Briefing Form. The need for written procedures to manage those impacts will be determined at that time. If written procedures are required, the contractor representative shall:
(i) Provide SPSA copies of their existing written procedures (these procedures and/or instructions must be at least as stringent as SPSA’s established procedures for managing similar environmental aspects); OR
(ii) Agree in writing to follow the SPSA Standard Operating Procedures established to manage the identified environmental aspects.
13. SPSA’S CONTRACTOR SAFETY REQUIREMENTS: Contractor is required to adhere to SPSA’s Contractor Safety Requirements at all times. A copy of which may be obtained at https://www.spsava.gov/DocumentCenter/View/215/Contractors-Safety-Program-
2019--PDF.
-23- RFP 01-26
SECTION VII
Appendix: Forms
Proposal Form
Signature Sheet
Proof of Authority to Transact Business in Virginia
Reference Form
-24- RFP 01-26
The Offeror agrees to furnish and deliver to the Southeastern Public Service Authority of Virginia, at the place specified, the items or services in accordance with specifications herein at the prices quoted below.
Submit original (with original signature) and two (2) complete copies plus an electronic flash drive copy of bid on this form to address listed in Section II, Bid Preparation and Submission Instructions. Offeror is required to complete and sign all information.
Quantity
Location
Total Price
Annual Chesapeake Transfer Station $
Annual Landstown Transfer Station $
Annual Norfolk Transfer Station $ Annual Oceana Transfer Station $ Annual Operations Center $ Annual Regional Office Building $ Annual Victory Blvd Corridor Drawing B $
Annual Regional Landfill $
Annual Isle of Wight Transfer Station $
Annual Ivor Convenience Center $
Annual Boykins Convenience Center $
Annual Franklin Transfer Station $
GRAND TOTAL PRICE
Per Occurrence Snow & Ice Removal at the Regional Office Building based on Drawing A
The Offeror hereby acknowledges receipt of the following addenda:
ADDENDUM NO.
ADDENDUM DATE
PROPOSAL FORM
(Submit with Proposal)
Bid Item
RFP Landscaping Services
Proposal Number
Date
April 13, 2026
Bid Opening
N/A
Time
N/A
-25- RFP 01-26
Offeror:
Address: _____________________________________________________________
City, State, Zip Code: ___________________________________________________
Typed Name, Title: _____________________________________________________
Email Address:
Telephone # Fax #_____________________
Signature: Date:
-26- RFP 01-26
SIGNATURE SHEET
My signature certifies that the offeror’s proposal as submitted complies with all terms and conditions set forth in the RFP.
My signature also certifies that the accompanying proposal is not the result of, or affected by, any unlawful act of collusion with another person or company engaged in the same line of business or commerce, or any act of fraud punishable under Title 18.2, Chapter 12, Article 1.1 of the Code of Virginia, 1950, as amended. Furthermore, I understand that fraud and unlawful collusion are crimes under the Virginia Governmental Frauds Act, the Virginia Government Bid Rigging Act, and Virginia Antitrust Act, and Federal Law, and can result in fines, prison sentences, and civil damage awards.
My signature also certifies that this firm has no business or personal relationships with any other companies or persons that could be considered as a conflict of interest or potential conflict of interest to the Southeastern Public Service Authority, and that there are no principals, officers, agents, employees, or representatives of this firm that have any business or personal relationships with any other…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .