Oakland University has issued a Request for Proposal (RFP) for Construction Management (CM) and General Contractor (GC) Services for Small Projects. The RFP seeks a preferred supplier relationship for small general construction projects ranging up to $100,000, with the potential for expansion at the university's discretion. The initial contract term will commence on January 1, 2026, and remain in effect for three years through 2028, with an option to extend for two additional one-year periods through 2030. Proposals are due on October 15, 2025 by 2:00 PM EDT, with questions accepted until September 24, 2025. The university will work with the selected supplier during the design phase to execute construction using various methods including competitive bidding, design assist, negotiated scopes of work, and self-performance.
The RFP specifies that multiple vendors may be awarded preferred status, and all work is subject to prevailing wage provisions. Proposals will be evaluated on a 100-point scale, with points allocated across experience and qualifications (20 points), project approach and turn-around times (20 points), references (30 points), and cost (30 points). The university requires detailed documentation including organizational data, project experience, safety records, and a comprehensive project approach. Insurance requirements are substantial, including workers' compensation, commercial general liability, auto liability, and excess umbrella coverage, with the university reserving the right to request additional coverage based on project specifics. The university will not guarantee any business volume and notes this is their first time seeking this type of supplier relationship.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP 00147 - Schedule C - Cost Proposal.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Oakland University
REQUEST FOR PROPOSAL (RFP)
Construction Management and General Contractor Services
Small Projects
FILE 00147
Issue Date: September 10, 2025
Questions Due: September 24, 2025 by 5PM EDT
Addendum Issued October 1, 2025
Sealed Proposals Due: October 15, 2025 by 2PM EDT
Construction Management Services General Contractor Services
Contents
SECTION I – BACKGROUND
1.01 Oakland University Background Information
1.02 RFP Overview
SECTION II – SCOPE OF SERVICES
2.01 Statement of Work
SECTION III - RFP PROPOSAL REQUIREMENTS AND SPECIFICATIONS
3.01 Qualifications/Experience
3.02 University Liaison
3.03 Cost/Fees
3.04 Freedom of Information Act Requests
SECTION IV – EVALUATION
4.01 Evaluation of RFP Response and Selection Criteria
4.02 Presentations
4.03 Process for Award
SECTION V - PROCUREMENT PROCESS
5.01 Submission Method, Date and Time
5.02 Questions and Interpretations
5.03 Prevailing Wage
5.04 Withdrawal of Proposals
5.05 Price and Scope of Work Changes
5.06 Mistakes in Proposals
5.07 Execution of Proposals
5.08 Procurement Schedule
SECTION VI – GENERAL CONDITIONS
6.01 Terms and Conditions
6.02 Conflict of Interest
6.03 Cost of Proposal
6.04 Form of Purchase
6.05 Government Restrictions
6.06 Nonconformance to Conditions/Specifications/Scope of Services
Small Projects
6.07 Assignment or Transfer
6.08 Patents - Licenses and Royalties
6.09 Permits and Licenses
6.10 Taxes
6.11 Insurance Requirements
6.12 Proof of Insurance
6.13 Standards of Conduct
6.14 Removal of Employees
6.15 Supervision
6.16 Performance Evaluation Meeting
6.17 Federal, State and Local Reporting Compliance
6.18 Project Personnel
6.19 Notices
6.20 Cancellation
6.21 Travel
6.22 Non-Discrimination
SCHEDULE A – Addendum Acknowledgement
SCHEDULE B-INSURANCE REQUIREMENTS ACKNOWLEDGEMENT
SCHEDULE C-COSTS
Small Projects
SECTION I – BACKGROUND
1.01 Oakland University Background Information
Oakland University (University) is a world-class academic institution located on 1,443 acres of wooded hills and meadows in Rochester, MI. The university was established in 1957 through a generous donation from founders Alfred and Matilda Dodge Wilson. Oakland University celebrated the 50th anniversary of its founding in 2007. When it opened in 1959, 570 students were enrolled, and the charter class graduated in 1963 with 125 students receiving diplomas. Today, nearly 16,000 students attend classes at OU, and our alumni total has grown to approximately 100,000.
As a state-supported institution of higher education, Oakland University has been recognized and is classified as a doctoral research university by the Carnegie Foundation for the Advancement of Teaching. With 139 baccalaureate degree programs and 127 graduate degree and certificate programs, Oakland provides a distinct educational experience with flexible class schedules and state-of-the-art facilities, student services, classroom technologies, research labs, internships and research opportunities with corporate partners. Located in the heart of Oakland County's Automation Alley, the university has forged hundreds of partnerships with hospitals, Fortune 500 companies, cities, government agencies and educational institutions.
All questions regarding this Request for Proposal should be directed to:
Julie Hamilton Buyer Oakland University, Purchasing Department 411 Pioneer Drive Rochester, Michigan 48309 Phone No. 248-370-4199 Email: hamilton@oakland.edu
1.02 RFP Overview
Oakland University Facility Management is requesting quotes for a preferred supplier relationship for construction management (CM) and general contracting (GC) services for small projects. These services are meant for small general projects ranging up to $100,000, but may be expanded at the discretion of the university. The supplier and OU will work to execute projects using various methods including competitive bidding, design assist, negotiated scopes of work, and self-performance. OU may convert projects into other delivery methods such as design-build or construction phase only services.
The work will be covered by the CM/GC agreement
OU cannot guarantee any business, and no historical spend information is available as this is the first time OU is seeking this supplier relationship.
The University anticipates that the initial term of the contract will commence January 1, 2026, and will remain in effect for 3 years through 2028. Prices quoted and your responses to this RFP must be guaranteed for the entire three-year term of the agreement. Based on mutual agreement of Oakland University and the successful respondent, unless terminated, or canceled, as otherwise provided herein, the agreement has the option to extend for two additional one-year periods, through 2030. The University
Small Projects will not agree to auto renew clauses.
As a condition of the award, all work performed under this contract is subject to prevailing wages.
Multiple vendors may be awarded preferred status.
SECTION II – SCOPE OF SERVICES
2.01 Statement of Work
On a per project basis, OU will onboard a supplier during the design phase, and this supplier will collaborate as part of a team with OU and their designer, if designated, to execute construction. While competitive bidding of trade work is preferred, OU may consider other options to benefit the project such as competitive bids, design assist with GMP, negotiated work, and time and material. OU reserves the right to direct subcontractor selection and rejection. The supplier’s scope may include coordinating work with other OU contractors including abatement, low-voltage, networking, and moving. The supplier will be required to manage and maintain project information within Oakland University’s web-based enterprise project management system, Trimble Unity Construct, which includes real-time visibility of the project status, and a central repository for all project information. Facilities Management will provide the supplier with a login license and initial software training for the designated Project representative(s) at no cost to the supplier. Except for licenses and initial training, Oakland University assumes no responsibility for any real or potential costs associated with the use of the E-Builder product by the selected supplier.
SECTION III - RFP PROPOSAL REQUIREMENTS AND SPECIFICATIONS
3.01 Qualifications/Experience
Respondents shall provide experienced, qualified, and capable personnel to perform the functions and responsibilities as outlined in the Statement of Work. The Statement of Qualifications/Experience must clearly demonstrate the Proposer's relevant experience, proper licensing and bonding, and proper insurance as listed in Exhibit B.
All Respondents shall provide a Statement of Qualifications/Experience that addresses each of the following:
• Introduction o Organizational data that demonstrates the size scope and capability of the Supplier to handle the University’s specific requirements specified in this RFP o Describe Supplier’s experience with small projects under $100,000; include contact information for three references o Describe Supplier’s experience with mid-size projects up to $2,000,000; include contact information for three references o Safety EMR record for the past five years o Describe Supplier’s efforts to retain and support employees
Small Projects o Supplier’s claims and litigation history, including information on any past, current or anticipated claims; explain the litigation, the issue, and its outcome or anticipated outcome.
• Project Approach o Provide a detailed description of the process of how Supplier selects qualified subcontractors for bidding and manages them effectively.
o Provide a description of construction work that the project management team has capability to competitively bid and self-perform, including qualifications to do such.
Oakland University may, at its discretion, limit the types and amount of work the project management team bids and self-performs.
o Provide a description of how the project management team will approach creating the preconstruction estimate and the actual project estimate. Provide examples from prior projects indicating how similar these estimates were to actual construction costs.
o Provide a description of how the project management team will address and implement the following:
Conceptual estimating Value analysis Alternate solutions Cost/benefit analysis Use and management of allowances Timely buyout Managing contingency effectively to utilize all funding for the building with minimal savings at the end of construction Demonstrate how a high quality of workmanship is achieved Demonstrate your team’s ability to deal with issues of disruption at existing facilities, existing building systems, and keeping interruptions to OU operations to a minimum.
Responses must include the following OU required documents:
• A signed copy of the RFP indicating the Supplier agrees to the RFP in its entirety, including Oakland University’s Terms and Conditions
• Qualification Statement
• Schedule A - Addendum Acknowledgement
• Schedule B – Insurance Acknowledgement
• Schedule C – Cost Proposal in Excel format
Failure to submit information in accordance with the RFP requirements and procedures may be cause for disqualification.
3.02 University Liaison
The awarded Supplier shall designate and provide at no charge to Oakland University an official representative to serve as liaison with the University in overseeing the relationship between the Supplier and the University. Contact information for the liaison(s) should be provided and include name, title, phone/cell, and email address.
Small Projects
3.03 Cost/Fees
Proposals must include a fee schedule for the goods and/or services being proposed. The schedule should indicate all proposed costs will be held firm for a period of at least on hundred twenty (120) days following submission of the proposal.
Firms must clearly and unambiguously specify the cost of the services in their proposals. Any reimbursable fees should be identified separately.
Any other taxes, fees or commissions applicable to the proposed contract are the responsibility and liability of the proposer who must include these cost items in the price of the goods and services.
3.04 Freedom of Information Act Requests
The Supplier understands that the University complies with the Michigan Freedom of Information Act (“FOIA”) and that the University may provide Confidential Information to other persons or entities upon receipt of a FOIA request. Section “z” of the FOIA states that security information is exempt from disclosure.
A FOIA request must be submitted in writing to the FOIA Office (or Coordinator). The request may be transmitted in hard copy, by email, or by facsimile. Refer to Oakland University’s website for procedures and guidelines to submit a FOIA request - https://www.oakland.edu/policies-regulations/FOIA/.
SECTION IV – EVALUATION
4.01 Evaluation of RFP Response and Selection Criteria
Proposals will be evaluated by the University. If there are portions of any proposal the University finds unacceptable or otherwise in need of clarification or revision, the University reserves the right to negotiate with any or all Suppliers. Any exceptions to the specifications or any other special considerations or conditions requested or required by Supplier will be enumerated by the Supplier and submitted as part of its Proposal, together with an explanation as to the reason the specifications cannot be met. Each Supplier will be required and expected to meet the specifications in their entirety, except to the extent exceptions are expressly noted in its proposal.
The University will evaluate the proposals submitted in response to this RFP, based on the completeness of the information provided and the business and technical merits related to the goals and requirements of the University. The University will conduct a detailed review and evaluation of the company and/or team and all entities and/or organizations participating in providing the goods and services described in this RFP. The evaluation of proposals has one basic objective: to determine whether the proposer meets the requirements set forth in this RFP and has the best value proposal to the University.
After review of submitted proposals, OU reserves the right to request a demonstration of the product.
Proposals will be evaluated by the University against the criterion that follows:
https://www.oakland.edu/policies-regulations/FOIA/
Small Projects Criterion: Possible Points Experience and qualifications 20 Project approach and turn-around times 20 References 30 Cost 30
TOTAL: 100 POINTS
Proposals will be scored on a one hundred (100) point scale in accordance with the evaluation criteria set forth above. Each Respondent must indicate its fees in accordance with section 3.05. Fees must be reasonable and justifiable and must reflect the proposed approach/work plan. OU will award to the responsive and responsible Respondent(s) whose proposal conforms to this RFP and whose combined scores under this section provide the best value. Notwithstanding anything contained herein, OU reserves the right to make an award based on any other relevant considerations and in the best interest of OU.
4.02 Presentations
OU reserves the right to makes its award decision based solely on the written submitted proposals without any request for presentations, formal interviews, negotiations, or further discussions.
The objective of this presentation/discussion is to answer questions clarify issues, and/or provide additional information regarding a Respondent’s proposal and negotiate. Presentations will be evaluated according to criteria established by the evaluation committee. Respondents in the competitive range will be scored on a maximum 30-point scale. The resulting points will be added to their written proposal scores for a total score.
1. Oral Presentation 0-30 Points
Following the presentations, the evaluation committee will evaluate and summarize their findings for each firm that participates and will submit scores to the Procurement Officer. OU will award to the responsive and responsible Respondent(s) whose proposal conforms to this RFP and whose combined total score for price, compliance, technical factors, and oral presentations (if applicable) provides the best value to OU. Notwithstanding anything contained herein, OU reserves the right to make an award based on any other relevant considerations and in the best interest of OU.
4.03 Process for Award
Without limitation and at its sole option, OU reserves the right to accept or reject any or all proposals, to take exception to these RFP specifications, to negotiate with finalists, or to waive any informality. Firms may be excluded from further consideration for failure to fully comply with the specifications of this
RFP.
OU may decide to reject all proposals and/or to reissue this RFP with modifications.
OU will not award contracts to proposers that are debarred, suspended or otherwise determined ineligible by, nor to proposers that OU has determined to be non-responsible.
Small Projects OU reserves the right to make an award based solely on the original proposals received or to negotiate further with proposers. The proposer selected for the award will be chosen on the basis of an assessment of the greatest benefit to OU, not necessarily on the basis of lowest price. OU also reserves the right to negotiate and award any element of this RFP, make multiple awards, reject any or all proposals or waive any minor irregularities or technicalities in proposals received as the best interest of OU may require.
SECTION V - PROCUREMENT PROCESS
5.01 Submission Method, Date and Time
One (1) copy of the sealed proposal shall be submitted electronically. All responses must be submitted online via Grizzfiles. If you plan to submit a proposal, please request an upload link at least five days prior to the bid submittal by emailing hamilton@oakland.edu. Put the proposal number and name in the subject line. Proposals must be received October 15, 2025 @ 2:00 P.M. Eastern Time. Proposals will not be opened publicly. It is the firm’s responsibility to ensure that its proposal is delivered at the proper time and place.
The document shall be 8 ½” x 11” format, no smaller than 11-point font, up to 10 pages, and should not contain unnecessary elaborate brochures or other presentations beyond those minimally required to present a complete and effective quotation.
Expenses for developing and presenting responses to this RFP shall be the entire responsibility of the Supplier and shall not be chargeable to the University. All supporting documentation and manuals submitted with this proposal will become the property of the University.
Unless otherwise stated above, proposals submitted are to be in accordance with the outline and specifications contained and are to remain in effect a minimum of 120 days from the date of submission, and may be subject to further extensions as negotiated.
Submitted unit prices and labor costs are to be held for three years of the date of contract.
OU reserves the right to accept or reject any or all proposals, and may cancel this solicitation at any time for any reason at the university’s discretion.
5.02 Questions and Interpretations
All inquiries to this RFP must be submitted in writing to hamilton@oakland.edu by September 24, 2025 @ 5:00 P.M. Eastern Time. An Addendum will be issued October 1, 2025 with responses to all questions received.
5.03 Prevailing Wage
This Contract is subject to the prevailing wage provisions of Act No. 10 of Michigan Public Acts of 2023 (“The Act”) and the Contractor shall pay prevailing wages, that is, the rates of wages and fringe to be paid to each class of mechanics by the Contractor and all Subcontractors shall be not less than the wage and fringe benefit rates prevailing in the locality in which the work is to be performed. The prevailing wages and fringe benefits determined by the Michigan Department of Labor for the Project are attached hereto and made a part hereof by this reference
Small Projects and are a part of the Specification of the Work to be performed. If the Contract is not awarded or Work undertaken within ninety (90) days of the date of the Michigan Department of Labor’s wage and fringe benefit determination as shown on the attachment, the Michigan Department of Labor shall make a re-determination before the Contract is awarded and the new determination shall become part of the Specifications of the Work to be performed. Construction Mechanics are the intended beneficiaries of the contractual prevailing wage, fringe benefit, and nondiscrimination nonretaliation requirements of the Act. Any construction mechanic aggrieved by the failure of a contractor or subcontractor to pay prevailing wages or benefits as specified in the contract, or by a violation of section 7 of the Act, in addition to any other remedies provided in this act or by law, may bring an action in a court of competent jurisdiction against the contractor or subcontractor for damages or injunctive relief and may be awarded reinstatement or other appropriate relief, and all damages sustained, together with actual costs and attorney fees at trial and on appeal.
5.04 Withdrawal of Proposals
Proposals may be withdrawn by written notice to the prescribed OU Buyer, prior to the proposal deadline date. Negligence on the part of the Supplier in preparing the proposal confers no right of withdrawal or modification of the proposal after the proposal deadline has elapsed.
5.05 Price and Scope of Work Changes
All proposals should be firm and not subject to change by the Supplier for a period of one hundred twenty days (120) from the proposal deadline date. Note, however, OU reserves the option to negotiate prices downward and to negotiate additional scope of work and cost changes based on final negotiations with the selected Supplier.
5.06 Mistakes in Proposals
If a mistake in a proposal is suspected or alleged, the proposal may be corrected or withdrawn prior to the due date for this solicitation. If negotiations are not held, or if best and final offers have been received, the Firm may be permitted to correct a mistake in its proposal and the intended correct offer may be considered based on the conditions that follow:
The mistake and the intended correct offer are clearly evident on the face of the proposal.
The Firm submits written evidence which clearly and convincingly demonstrates both the existing offer, and such correction would not be contrary to the fair and equal treatment of other Firms.
Mistakes discovered after award shall not be corrected unless OU Counsel makes a written determination that it would be disadvantageous to OU not to allow the mistake to be corrected. The approval or disapproval of requests of this nature shall be in writing by OU’s Legal Counsel.
5.07 Execution of Proposals
The original proposal must contain a manual or electronic (date and time stamped) signature of an authorized representative of the Proposer. The proposal must be typed or printed in ink. All corrections made on the proposal sheets must be initialed by the authorized representative. The company name must appear on each sheet. The proposal must include all documents, materials and information required herein.
5.08 Procurement Schedule
The University intends to conduct the procurement process expeditiously. Proposers are expected to comply with the procurement schedule, including any modifications thereto which may be made by the University. The University will notify proposers of any and all such modifications. Proposers who fail to comply with the schedule may not receive further consideration.
The anticipated procurement schedule for the RFP process is as follows; the University will make every effort to adhere to the schedule, and at its discretion is subject to change:
Issue Request for Proposal September 10, 2025
Deadline for Written Questions Regarding the RFP September 24, 2025 @ 5:00 P.M.
Eastern Time
Addendum Issued by October 1, 2025
Proposal Submission October 15, 2025@ 2:00 P.M.
Eastern Time
Readiness for Service/Contract Commencement TBD
SECTION VI – GENERAL CONDITIONS
6.01 Terms and Conditions
Any contract resulting from this Request for Proposal is subject to and shall be performed in accordance with the University’s General Terms and Conditions for Agreement located at the following: OU Terms & Conditions.
The University’s preferred payment method is with a University credit card (Pcard). The University will not accept convenience fees or increased pricing due to Pcard payment. The University it tax exempt, State of Michigan tax is not applicable.
Any person, firm, corporation or association submitting a proposal shall be deemed to have read and understood all the terms, conditions and requirements in the specifications/scope of work.
Upon University request, the awarded supplier must agree to provide independently audited financial statements including its statement of financial position, statement of operations, and statement of cash flows for at least the past three years. Furthermore, the Contractor must agree to permit the University, upon request, to audit privileges, related to the University’s account. Failure to agree to this may result in disqualification of your bid.
Purchase Orders issued to the Supplier throughout the term of an agreement for services shall be subject to any and all of the provisions noted in this RFP. If there is a discrepancy between the information stated in this RFP and the University’s T&Cs, the T&Cs will apply.
https://www.oakland.edu/legal/legalforms/ https://www.oakland.edu/legal/legalforms/
Small Projects This RFP in no manner obligates the University to the eventual purchase of any products or services described, implied, or which may be proposed, and may be terminated by the University without penalty or obligation at any time.
Expenses for developing and presenting proposals will be the entire responsibility of the Supplier and will not be chargeable to the University. All supporting documentation and manuals with this proposal will become the property of the University.
The Supplier understands that the University complies with the Michigan Freedom of Information Act (“FOIA”) and that the University may provide Confidential Information to other persons or entities upon receipt of a FOIA request. Section “z” of the FOIA states that security information is exempt from disclosure.
Smoke Free Campus: Effective Fall 2013, the University is smoke-free. Contractors are responsible to ensure that all employees and all subcontractors’ employees are in compliance anytime they are on Oakland’s main, or extension center campuses. The complete policy can be found at Policy 475.
6.02 Conflict of Interest
The Supplier affirms that to the best of its knowledge there exists no actual or potential conflict-of-interest between the Supplier's family, business, or financial interests and providing the Services. The Supplier will not attempt to influence any University employee by the direct or indirect offer of anything of value. The Supplier also warrants that no officer or employee of the University has or will have a direct or indirect personal financial interest in the Agreement. The Supplier also affirms that neither the Supplier nor any of its employees has paid or agreed to pay any person, other than bona fide employees and consultants working solely for the Supplier, any fee, commission, percentage, brokerage fee, gift or any other consideration contingent upon or resulting from the execution of an Agreement.
In the event of change in either Supplier’s interests or Services under this Agreement, the Supplier will inform the University regarding all possible conflicts-of interest which may arise as a result of such change. The Supplier agrees that conflicts-of-interest will be resolved to the University’s satisfaction or the University may terminate the Agreement.
Oakland University reserves the following rights: to accept or reject any bid; to reject all bids’ to waive any formalities or irregularities contained in a bid that do not comply with the terms and conditions of the invitation to bid, any modifications to the invitation to bid, or any specifications; to select the bid and/or items that in the sole and absolute discretion of Oakland University are in Oakland University’s best interest whether or not the bid selected is the lowest monetary bid received.
6.03 Cost of Proposal
Suppliers are responsible for all their costs associated with the preparation of proposals, the demonstration and interview process and the contract negotiation process. All costs incurred, directly or indirectly, associated with the preparation of proposals shall be the sole responsibility of and shall be borne by the respondents.
6.04 Form of Purchase
The acceptance of the proposed Firm’s offer for the services specified herein will be made by issuance of a duly authorized contract or purchase order prepared by OU. Suppliers are cautioned to make no https://www.oakland.edu/policies/generalgovernance/475/
Small Projects assumptions or accept any representations by any employee, member, officer or representative of OU concerning the award until a contract agreement is executed.
6.05 Government Restrictions
In the event any governmental restrictions may be imposed which would necessitate alteration of the material, quality, workmanship or performance of the goods or services offered, it shall be the responsibility of the successful Firm to immediately notify OU in writing specifying the regulation which requires alteration. OU reserves the right to accept any such alteration, including any reasonable price adjustments occasioned thereby, or to cancel the contract at no expense to OU.
6.06 Nonconformance to Conditions/Specifications/Scope of Services Services will be inspected for compliance with specifications. Services not conforming to specifications may not be accepted at the Firm’s expense. Services not provided in accordance with the Scope of Services may result in the Firm being found in default. In the event of default all procurement costs may be charged against the Firm. Any violations of these stipulations may result in the Firm’s name being removed from OU’s proposal mailing list.
6.07 Assignment or Transfer
The successful Firm shall not assign or transfer any interest in any subsequent contract, in whole or part, without written approval of OU. Claims for sums of money due, or to become due from OU pursuant to the contract may be assigned to a bank, trust company or other financial institution. OU is hereby expressly relieved and absolved of any and all liability in the event a purported assignment or subcontracting of the contract is attempted in the absence of the Firm obtaining OU’s prior written consent.
6.08 Patents - Licenses and Royalties
The successful Firm shall indemnify and save harmless OU and its employees from liability of any kind, including cost and expenses for or on account of any copyrighted, patented, or not patented invention, process or article manufactured or used in the performance of the contract, including its use by OU. If the Supplier uses any design, device or material covered by letters, patent, or copyright, it is mutually agreed and understood that the proposal prices shall include all royalties or cost arising from the use of such design, device or materials involved in the work. Further all residual right to Patents, Licenses and Royalties (e.g., software and license to use same purchased) shall revert to OU at the end of the Agreement.
6.09 Permits and Licenses
The successful Firm shall obtain all permits and licenses that are required for performing its work. The Firm shall pay all related fees and costs in connection with required permits and licenses. Proof of ownership shall be made on all software used in the execution of the contract. The Firm will hold OU harmless for any violation of software licensing resulting from breaches by employees, owners, and agents of the Firm.
6.10 Taxes
The successful Firm is responsible for all state and federal payroll and/or social security taxes. The Firm shall hold OU harmless in every respect against tax liability.
Small Projects
6.11 Insurance Requirements
The awarded Supplier will be required to obtain insurance protecting Oakland University, Supplier and any subcontractor of Supplier performing services covered by the RFP. The awarded Supplier agrees to immediately comply with the insurance provisions and maintain insurance levels at its sole expense.
Supplier shall provide acknowledgement and evidence of such insurance prior to execution of the Contract, found in Schedule B. If you cannot currently meet the requirements, proposals must include a statement agreeing to meet these requirements at no additional cost by the time of contract signing.
Failure to meet this requirement may cause the proposal to be considered non-responsive and subject to disqualification.
6.12 Proof of Insurance
The successful Firm shall furnish to OU a certified copy of the policy or policies covering the work as required in the specifications as evidence that the insurance required will be maintained in force for the entire duration of the contract with OU. OU must be listed as an additional insured.
6.13 Standards of Conduct
The successful Firm shall be responsible for maintaining satisfactory standards of its employee’s competence, conduct, courtesy, appearance, honesty, and integrity. It shall be responsible for taking such disciplinary action with respect to any of its employees as may be necessary.
6.14 Removal of Employees
OU may request the successful Firm to immediately remove from assignment to OU and/or dismiss any employee found unfit to perform duties due to one or more of the following reasons:
1. Neglect of Duty.
2. Disorderly conduct, use of abusive or offensive language, quarreling, intimidation by words or actions or fighting.
3. Theft, vandalism, immoral conduct, or any other criminal action.
4. Selling, consuming, possessing, or being under the influence of intoxicants, including alcohol, or illegal substances while on assignment at OU.
6.15 Supervision
The successful Firm shall always provide adequate competent supervision during the performance of the contract. To that effect, a qualified consultant and one or more alternates shall be designated in writing to OU prior to contract start. The Firm or his designated representative shall be readily available to meet with OU personnel. The successful Firm shall provide the telephone numbers where its representative(s) can be reached.
6.16 Performance Evaluation Meeting
The selected Firm shall be readily available to meet with representatives of OU weekly during the first month of the contract and as often as necessary thereafter. A mutual effort will be made to resolve all performance problems identified at these meetings.
Small Projects
6.17 Federal, State and Local Reporting Compliance
The Firm shall provide such financial and programmatic information as required to comply with all Federal, State, and local law reporting requirements.
6.18 Project Personnel
Except as formally approved by OU, the key personnel identified in the accepted proposal shall be the individual who will complete the work, at the proposed levels of effort. Changes in staffing must be proposed in writing to OU and approved.
6.19 Notices
All written notices required to be given by either party under the terms of the contract(s) resulting from the contract award shall be addressed to the Firm at their legal business residence as given in the contract. Written notices to OU shall be addressed as provided in the contract.
6.20 Cancellation
Irrespective of any default hereunder, OU may also at any time at its discretion cancel any subsequent contract related to this solicitation, in whole or in part. In the event of cancellation, the Firm shall be entitled to receive equitable compensation for all work completed and accepted prior to such termination or cancellation as shall be indicated in the contract.
6.21 Travel
All travel and miscellaneous expenses related to this solicitation will be borne by the Firm unless otherwise provided in the contract for services.
6.22 Non-Discrimination
In accordance with the U.S. Constitution and all federal legislation and regulations governing fair employment practices and equal employment opportunity including, but not limited to Title VI (42 USC 2000d, et seq.) and Title VII )42 USC 2000e, et seq.) of the Civil Rights Act of 1964 (P.L. 88-352, 78 Stat.
241) and the U.S. Department of Justice regulations (28 CFR Part 42, et seq.) and the U.S. Department of Labor regulations (29 CFR Part 1601, et seq.) issued pursuant to those Titles, Executive Order 11246 (September 24, 1965) as amended, the Michigan Constitution and all state laws and regulations governing fair employment practices and equal employment opportunity, including but not limited to the Michigan Civil Rights Act (P.A. 1976 No. 453) and the Michigan Handicappers Civil Rights Act (P.A.
1976 No. 220), the Contractor agrees that it shall not discriminate against any employee or applicant for employment with respect to hire, tenure, terms, conditions or privileges of employment because of religion, race, color, national origin, age, sex, sexual orientation, height, weight, marital status or handicap that is unrelated to the individual’s ability to perform the duties of a particular assignment or position. The Contractor hereby recognizes the right of the United States and the State of Michigan to seek judicial enforcement of the foregoing covenant against discrimination, against itself or its subcontractors connected directly or indirectly with the performance of this Contract.
ACCEPTANCE
Please indicate your acceptance of Oakland University’s Terms and Conditions and the provisions stated in this RFP in the space provided below. Complete the information at the bottom of this document and return this signed page with your RFP response.
Thank you.
ACCEPTANCE ACKNOWLEDGEMENT:
I have reviewed and do accept Oakland University’s Terms and Conditions as stated on the University web page. I have read and agree to abide by the terms of this RFP. I also acknowledge that I am a legally authorized representative of the business entity noted below and, as such, have the authority to enter into agreements and make commitments on its behalf:
Company:_______________________________ Address:________________________________ Authorized Signature:_____________________ Date:___________________________________ Printed Name:___________________________ Title:____________________________________ Phone #: _______________________________ Email:___________________________________
NOTE: OAKLAND UNIVERSITY RESERVES THE FOLLOWING RIGHTS: TO ACCEPT OR REJECT ANY BID; TO REJECT ALL BIDS; TO WAIVE ANY FORMALITIES OR IRREGULARITIES CONTAINED IN A BID THAT DO NOT COMPLY WITH THE TERMS AND CONDITIONS OF THE INVITATION TO BID, ANY MODIFICATIONS TO THE INVITATION TO BID, OR ANY SPECIFICATIONS; TO SELECT THE BID AND/OR ITEMS THAT IN THE SOLE AND ABSOLUTE DISCRETION OF OAKLAND UNIVERSITY ARE IN OAKLAND UNIVERSITY’S BEST INTEREST
WHETHER OR NOT THE BID SELECTED IS THE LOWEST MONETARY BID RECEIVED.
SCHEDULE A – Addendum Acknowledgement
ADDENDA:
The undersigned affirms that the cost of all work covered by the following Addenda are included in the price of this proposal.
Addendum No._____ Date:________________ Addendum No.______ Date:_______________
Firm Name: ________________________________________________
Small Projects
SCHEDULE B-INSURANCE REQUIREMENTS ACKNOWLEDGEMENT
___________________________________, at its sole expense, shall cause to be issued and maintained in full effect for the term of this agreement, insurance as set forth hereunder:
Workers’ Comp: Statutory Limits & EL $1,000,000 Commercial General Liability: $1,000,000 per occurrence, $2,000,000 aggregate Auto Liability: $1,000,000 Excess (Umbrella): $2,000,000 per occurrence Builders All Risk: 100% of value of project
The University reserves the right to request additional coverage dependent on work to be performed. Additional coverage may include higher limits and/or additional line including but not limited to:
Contractors’ Pollution Liability $5,000,000 per occurrence Professional Liability $2,000,000 per occurrence, $4,000,000 aggregate
Respondents must provide an insurance certificate as part of their proposal submittal showing evidence of insurance. If you cannot currently meet the requirements proposals must include a statement agreeing to meet these requirements at no additional cost by the time of contract signing. Failure to meet this requirement in your RFP response may eliminate your company’s proposal.
1. Oakland University and its Board of Trustees must be listed as an “Additional Insured” on the
Certificate of Insurance. Sub-contractor endorsements must name Oakland University as an Additional Insured including completed operations coverage.
2. Supplier must provide an insurance certificate before commencing service delivery, must keep the certificate up-to-date, and must forward copies of all revised certificates of insurance to the Risk Management Department at Oakland University within thirty (30) days of the change.
3. Notice of cancellation must be submitted thirty (30) days prior to the termination of the insurance coverage.
4. Awarded Supplier shall notify the University of any Accidents and/or claims, including without limitation accidents or claims involving bodily injury, death or property damage, arising on or within the Licensed Premises. Such notice shall be provided in writing as soon as practicable, however in any event within five days of Awarded Supplier’s receipt of notice of the accident or claim.
5. Required insurance coverage and any self-insured retention may be required to be modified by the University if, in the sole judgment of the University, the levels of risk associated with Awarded Supplier’s operations require modification of such coverage.
6. Failure of the Awarded Supplier to obtain and maintain appropriate insurance as specified by the University, without gap, may be deemed a material breach of this license and at the sole discretion of the University may be cause for contract termination.
Exceptions to the above insurance requirements are to be approved, in writing, by the Office of Risk Management. Exceptions are determined by the type and nature of the contract and the individual contractor.
Small Projects
SCHEDULE C-COSTS
Supplier Name: ____________________________________________
All pricing should be completed in Schedule C Excel Sheet provided.
All items proposed by the Supplier should meet or exceed Oakland University’s requirements. The University reserves the right to reject any proposal at its sole discretion.
The undersigned, as bidder, declares that he/she having examined the specifications with related documents hereby proposes to furnish the equipment in accordance with the specifications, within the time set forth therein, and at the cost stated in Schedule C Excel Sheet.
Comments/Restrictions:
Submitted by:_______________________________________________________________________________
Signature:__________________________________________________________________________________
Title/Date:_______________________________________________________________________________ (Title) (Date) Phone:____________________________________________Email:___________________________________ hamilton Typewritten Text
IMPORTANT:
This contract involves prevailing wage rate jobs, and the applicable wages will be provided at contract award.
| SECTION I – BACKGROUND |
| 1.01 Oakland University Background Information |
| 1.02 RFP Overview |
| SECTION II – SCOPE OF SERVICES |
| 2.01 Statement of Work |
| SECTION III - RFP PROPOSAL REQUIREMENTS AND SPECIFICATIONS |
| 3.01 Qualifications/Experience |
| 3.02 University Liaison |
| 3.03 Cost/Fees |
| 3.04 Freedom of Information Act Requests |
| SECTION IV – EVALUATION |
| 4.01 Evaluation of RFP Response and Selection Criteria |
| 4.02 Presentations |
| 4.03 Process for Award |
| SECTION V - PROCUREMENT PROCESS |
| 5.01 Submission Method, Date and Time |
| 5.02 Questions and Interpretations |
| 5.03 Prevailing Wage |
| 5.04 Withdrawal of Proposals |
| 5.05 Price and Scope of Work Changes |
| 5.06 Mistakes in Proposals |
| 5.07 Execution of Proposals |
| 5.08 Procurement Schedule |
| SECTION VI – GENERAL CONDITIONS |
| 6.01 Terms and Conditions |
| 6.02 Conflict of Interest |
| 6.03 Cost of Proposal |
| 6.04 Form of Purchase |
| 6.05 Government Restrictions |
| 6.06 Nonconformance to Conditions/Specifications/Scope of Services |
| 6.07 Assignment or Transfer |
| 6.08 Patents - Licenses and Royalties |
| 6.09 Permits and Licenses |
| 6.10 Taxes |
| 6.11 Insurance Requirements |
| 6.12 Proof of Insurance |
| 6.13 Standards of Conduct |
| 6.14 Removal of Employees |
| 6.15 Supervision |
| 6.16 Performance Evaluation Meeting |
| 6.17 Federal, State and Local Reporting Compliance |
| 6.18 Project Personnel |
| 6.19 Notices |
| 6.20 Cancellation |
| 6.21 Travel |
| 6.22 Non-Discrimination |
| SCHEDULE A – Addendum Acknowledgement |
| SCHEDULE B-INSURANCE REQUIREMENTS ACKNOWLEDGEMENT |
| SCHEDULE C-COSTS |
| Company: |
| Address: |
| Date: |
| Printed Name: |
| Title: |
| Phone: |
| Email: |
| Addendum No: |
| Date_2: |
| Addendum No_2: |
| Date_3: |
| Addendum No_3: |
| Date_4: |
| Addendum No_4: |
| Date_5: |
| Addendum No_5: |
| Date_6: |
| Addendum No_6: |
| Date_7: |
| Firm Name: |
| at its sole expense shall cause to be issued and: |
| Supplier Name: |
| CommentsRestrictions 1: |
| CommentsRestrictions 2: |
| Submitted by: |
| TitleDate: |
| Phone_2: |
| Email_2: |
File details come from the government source that posted it. Updated .