RFISS-180 QA.pdf

PDF 89 KB Posted

Attached to
Undersea Submergence Buoy
Solicitation number
RFISS-180
Issued by

About this file

This is a Questions and Answers document for RFISS-180, a Request for Information/Sources Sought regarding an Undersea Submergence Buoy. The government seeks vendor capability information for manufacturing the buoy weldment specified in drawing 1845687 only, with no internal electronic components or associated capabilities required as part of this solicitation.

The procurement will follow a phased approach. The Initial Phase requires 1 to 3 prototype or qualification units for testing and evaluation purposes. The Production Phase, contingent upon successful validation of both the vendor and product, anticipates an estimated requirement of 24 to 50 production units. This document does not establish binding contract terms, pricing, delivery schedules, or award information, serving instead as a market research tool to identify qualified potential sources for future procurement action.

View the file

Other files

File Type Posted
RFISS-180 QA.pdf PDF
RFISS-180_Questionnaire_for_Industry.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS

REQUEST FOR INFORMATION SOURCES SOUGHT: RFISS-180

TITLE: Undersea Submergence Buoy

INQUIRIES: (Government Responses are provided in red.)

Question 1: Is there an estimated production or procurement quantity available for this Sources Sought?

The government anticipates a phased procurement approach as follows:

Initial Phase: A limited prototype or qualification quantity of 1 to 3 units will be required for tests and evaluation.

Production Phase: Following successful validation of both the vendor and the product, the estimated requirement is 24 to 50 production units.

Question 2: Is the RFI for the buoy housing only, or including any necessary internal electronic components and capabilities?

It is only for the weldment shown by drawing 1845687 only. We are not asking for associated internal components.