01. RFI-2026-11-16-GP Attachment 1.docx

DOCX document 21 KB Posted

Attached to
Procurement and Installation of a Medium-Scale Superconducting Quantum Computer
Solicitation number
RFI-2026-11-16-GP
Issued by

About this file

This is a Request for Information (RFI) questionnaire issued by Battelle Memorial Institute, Pacific Northwest Division, on behalf of the Department of Energy, seeking industry input on the procurement and installation of a medium-scale superconducting quantum computing system for the Pacific Northwest National Laboratory in Richland, Washington. The RFI targets a multi-year lease agreement of three to five years with supplier support, with award anticipated in fiscal year 2027. Respondents must address technical specifications including processor architecture (qubit count, qubit type, coupler type, and lattice topology), system availability commitments, control electronics capabilities, integration with high-performance computing schedulers, security protocols, and remote-access architecture. The questionnaire also requires information on facility requirements such as system footprint, floor loading, vibration specifications, electrical requirements (voltage, phase, power draw), and cooling specifications for chilled water or air-cooled systems.

Additional response areas cover commercial and lease terms, including pricing structures accepted, what services are included in lease pricing, rough order-of-magnitude pricing for three- and five-year terms, performance guarantees and availability commitments, and lead times from award to delivery and delivery to acceptance. Respondents must also provide details on upgrade paths and hardware refresh cadence within the lease term, describe major installation and procurement challenges encountered, demonstrate capability for on-premises operation with no external network dependency, and confirm willingness to permit independent benchmarking with publication of results subject to factual accuracy review. Corporate experience questions require documentation of prior full-stack on-premises quantum computer installations in the United States with customer references, as well as descriptions of U.S. staffing and facilities. Export classification information, country of origin, and return/re-export management protocols must also be addressed.

View the file

Other files

File Type Posted
00. RFI-2026-11-16-GP.pdf PDF
01. RFI-2026-11-16-GP Attachment 1.docx DOCX document
00. RFI-2026-11-16-GP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BATTELLE MEMORIAL INSTITUTE, PACIFIC NORTHWEST DIVISION'S

REQUEST FOR INFORMATION NUMBER RFI-2026-11-16-GP

PROCUREMENT AND INSTALLATION OF A MEDIUM-SCALE SUPERCONDUCTING QUANTUM COMPUTER

ATTACHMENT 3, RFI QUESTIONNAIRE

It is understood that respondents may not have the knowledge or expertise to answer every question. Respondents should answer to the best of their ability.

A. System and Measured Performance A1. Describe the processor you would propose to deliver within the schedule in Section 4: qubit count, qubit type (e.g., fixed-frequency transmon, tunable transmon, fluxonium, other), coupler type, and lattice topology. Provide the connectivity graph.

A4. What system availability (percentage of scheduled time the system is executing user jobs at specification) do you commit to in on-premises contracts, and what has been achieved at existing installations over the past 12 months?

B. Access, Software, and Operation B1. Describe the control electronics (in-house or third-party), channel counts, real-time capability, and the level of access users have to pulse definition, waveform upload, and real-time control flow.

B2. Describe integration with an HPC scheduler (e.g., Slurm) and with classical compute co-located with the system, the classical-to-quantum latency achievable for tightly coupled hybrid workflows, and the recommended network topology.

B3. Can the system be operated fully on-site with no external network dependency? If not, identify the functions that require connectivity to supplier services.

B4. Will you permit Battelle to run independent benchmarks, including application-level benchmarks defined by Battelle, and to publish the results without vendor approval, subject to a reasonable review period for factual accuracy?

B5. What, if any, major issues and/or challenges have been encountered during quantum computer installations?

B6. What, if any, major issues and challenges have you encountered during the procurement of quantum computers?

C. Upgrade Path C1. What hardware refresh do you offer within a three to five year lease, at what cadence, at what cost, and with what downtime?

D. Security and Export Control D1. Describe the remote-access architecture used for calibration and diagnostics (protocols, endpoints, authentication, logging) and whether access can be limited to customer-initiated sessions.

D2. State the export classification of the proposed system (e.g., ECCN 4A906), its country of origin, and how you manage return, re-export, and remote technical-data transfer for systems installed in the United States.

E. Facility and Site Requirements E1. Provide the system footprint and an example layout with dimensions, including the refrigerator, gas handling, compressors, control electronics racks, classical compute, and service clearances.

E2. State floor loading (total and point loads), slab versus raised-floor requirements, and the vibration specification at the refrigerator location, including the vibration the system itself generates.

E3. Specify electrical requirements (voltage, phase, steady-state and peak draw by subsystem), identify which loads must be on UPS or generator to avoid a warm-up during a utility outage, and state how long the system can ride through an outage.

E4. Specify cooling requirements: chilled water flow, supply temperature, pressure, and heat rejection for compressors (or air-cooled alternatives), plus room air-conditioning load.

F. Commercial and Lease Terms F1. Which pricing structures do you accept for a multi-year on-premises engagement (operating lease, lease-to-own, on-premises quantum-as-a-service with usage pricing, purchase with service)?

F2. State what would be included in a lease price (hardware, installation, acceptance, support tier, software licenses, refresh, consumables, training, removal) and what is priced separately.

F3. Provide rough order-of-magnitude pricing for a three- and five-year term.

F4. Describe the performance guarantees, availability commitments, and remedies you offer, and how they are measured.

F5. State the lead time from award to delivery and from delivery to acceptance, and the site-readiness milestones Battelle must meet to hold that schedule. Are the targets in Section 4 achievable?

F6. What services do you offer for post procurement equipment support?

G. Corporate Experience and Standing G1. How many full-stack on-premises systems have you delivered and accepted, where, and at what qubit counts? Identify installations in the United States and provide customer references.

G2. Describe U.S. staffing (engineering, field service, support), and U.S. facilities.

RFI-2026-11-16-GP

Attachment 1

File details come from the government source that posted it. Updated .