This is a Request for Information (RFI) issued by Battelle Memorial Institute, Pacific Northwest Division, on behalf of the Department of Energy, regarding the procurement and installation of a medium-scale superconducting quantum computer system for the Pacific Northwest National Laboratory (PNNL) in Richland, Washington. This RFI does not constitute a formal solicitation and is issued for market research purposes under FAR 15.201(e) and FAR Part 10. The anticipated future contract will be structured as a multi-year lease agreement lasting three to five years with supplier support, with award targeted for fiscal year 2027. No financial responsibility is assumed by Battelle for response costs, and not responding does not preclude participation in any future solicitation.

Battelle seeks full-stack, on-premises superconducting quantum computing systems with approximately 50 to 150 physical superconducting qubits, median two-qubit gate fidelity at or above 99.5 percent, and a complete system including processor, dilution refrigerator, cryogenic infrastructure, control electronics, classical compute, and software stack supporting circuit-level and pulse-level programming. The system must be capable of fully on-site operation by Battelle staff with remote supplier support subject to cybersecurity requirements and must include installation, acceptance testing, maintenance, training, and a defined hardware refresh path. The intended use encompasses application-driven feasibility studies in chemistry and materials science, independent benchmarking, hybrid quantum-classical workflow development with PNNL high-performance computing resources, and collaborative hardware-software co-design. Battelle's current planning targets are RFP issuance in Quarter 1 or early Quarter 2 of fiscal year 2027, award in fiscal year 2027, and system delivery, installation, and acceptance in Quarter 4 2027. Responses are due by 4:00 p.m. Pacific Time on December 8, 2026, submitted as a single PDF not exceeding 15 pages to garrett.prather@pnnl.gov. Questions may be submitted by November 23, 2026. Responses must include organization information, primary point of contact details, SAM.gov Unique Entity ID and CAGE code if registered, business size and socioeconomic designation, and a capability statement tailored to the RFI.

View the file

Other files

File Type Posted
00. RFI-2026-11-16-GP.pdf PDF
01. RFI-2026-11-16-GP Attachment 1.docx DOCX document
01. RFI-2026-11-16-GP Attachment 1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI-2026-11-16-GP

BATTELLE MEMORIAL INSTITUTE, PACIFIC NORTHWEST DIVISION'S

REQUEST FOR INFORMATION NUMBER RFI-2026-11-16-GP

PROCUREMENT AND INSTALLATION OF A MEDIUM-SCALE

SUPERCONDUCTING QUANTUM COMPUTER

1. INTRODUCTION

Battelle Memorial Institute, Pacific Northwest Division (Battelle), Management and Operating Contractor of the Pacific Northwest National Laboratory (PNNL) on behalf of the Department of Energy (DOE), is issuing this Request for Information (RFI) to gather industry input on the procurement, installation, and operation of a medium-scale superconducting quantum computing system to be installed on the PNNL campus in Richland, Washington. Through this RFI, Battelle seeks industry input to inform the procurement strategy, technical requirements, facility requirements, and commercial terms for a future solicitation. The anticipated contract is expected to be a multi-year lease agreement (3 to 5 years) with supplier support, with award targeted in fiscal year 2027.

THERE IS NO SOLICITATION AT THIS TIME. This RFI does not constitute a formal solicitation or Request for proposal (RFP), and submission of information in response to this request is voluntary. This RFI is issued consistent with FAR 15.201(e), Exchanges with Industry Before Receipt of Proposals, and FAR Part 10, Market Research. Nothing in this request shall be interpreted as a commitment on the part of Battelle to enter into a contract with any respondent.

Battelle assumes no financial responsibility for any costs incurred in responding.

Battelle will use the information received to assess market capacity, candidate system configurations, technical and facility requirements, schedule feasibility, commercial structures, and interested suppliers. All inquiries to this RFI shall be submitted via email to the Procurement Representative identified. Telephone inquiries will not be accepted. No feedback or evaluation will be provided to respondents regarding their submissions.

Not responding to this RFI does not preclude participation in any future solicitation, should one be issued.

2. INTENDED USE

Battelle intends to operate the system as a scientific instrument in support of the Laboratory's quantum computing objectives. Anticipated uses include:

• application-driven feasibility studies in chemistry, materials science, and data science;

• independent benchmarking and verification of hardware performance;

• development of hybrid quantum-classical workflows coupled to PNNL high-performance computing resources; and

• end-to-end co-design of applications, software, and hardware in collaboration with the supplier.

Battelle staff and collaborators will require programmatic access at the circuit level and at the pulse level. The system will be operated by Battelle staff with supplier support, in an unclassified research facility, and results of research performed on the system will be published.

The installation site is an existing unclassified research facility on the PNNL campus in Richland, Washington.

3. CAPABILITY CLASS SOUGHT

Battelle is interested in full-stack, on-premises superconducting quantum computing systems with the following general characteristics. These are planning parameters for market research and are neither minimum requirements nor a specification. Respondents whose systems differ from these parameters are highly encouraged to respond and to explain the differences.

• On the order of 50 to 150 physical superconducting qubits in the configuration that would be delivered within the schedule in Section 4, with a described path to larger processors during the term of the lease.

• Median two-qubit gate fidelity at or above 99.5 percent, with single-qubit and readout fidelities, coherence times, and whole-system benchmarks reported as described in Attachment 1.

• Delivered as a complete system: processor, dilution refrigerator and cryogenic infrastructure, control electronics, classical control and compute, and a software stack supporting circuit-level and pulse-level programming, multi-user access, and integration with an HPC scheduler.

• Capable of fully on-site operation by Battelle staff, with supplier remote support subject to Battelle’s cybersecurity requirements.

Prather, Garrett T Is it beneficial to describe the potential site, or is that too much information for an RFI?

Paulsen, Samuel S Too much info.

• Supported under a multi-year lease or equivalent arrangement that includes installation, acceptance testing, maintenance, training, and a defined hardware refresh path.

Respondents offering systems based on other qubit modalities may respond and should clearly identify the modality and any respects in which the questions in Attachment 1 do not apply.

4. SCHEDULE TARGETS

Battelle's current planning targets are:

• Issue RFP in Quarter 1 or early Quarter 2 of fiscal year 2027,

• Award in fiscal year 2027, and

• delivery, installation, and acceptance of the system in Quarter 4 2027.

The federal fiscal year 2027 runs from October 1, 2026, through September 30, 2027. Respondents are asked in Attachment 1, group F, whether these targets are achievable and what site-readiness and contractual milestones would be required of Battelle to meet them.

5. SUBMISSION INSTRUCTIONS

Interested parties who consider themselves experienced, knowledgeable, and well-versed in the design, delivery, installation, and support of superconducting quantum computing systems are invited to submit a response and capability statement.

Responses to this RFI are due no later than 4:00 p.m. Pacific Time, on Tuesday, December 8, 2026. Responses shall be emailed to Garrett Prather at garrett.prather@pnnl.gov with the subject line "RFI Response: Superconducting Quantum Computer."

Questions regarding this RFI may be submitted by email to the same address no later than 4:00 p.m. Pacific Time on Monday, November 23, 2026. Battelle may revise this RFI posting to provide a consolidated list of answers to the questions received without identifying the source. Battelle may, at its discretion, invite respondents to one-on-one virtual capability briefings after the response date.

mailto:garrett.prather@pnnl.gov Warner, Marvin G Why and would we have to offer that to all respondents?

Paulsen, Samuel S If we don't want it, delete it.

Prather, Garrett T I believe this language is intended to allow Battelle the ability to have discussions with individual respondents, if needed. I can see it necessary for clarifications on their response. It is not mandatory and may be removed if you believe it to be unnecessary.

Warner, Marvin G No, I think that would be just fine to have in there.

At a minimum, responses shall contain the following:

• Organization name, address, and website.

• name, title, email address, and telephone number of the primary point of contact(s) for this RFI.

• SAM.gov Unique Entity ID (UEI) and CAGE code, if registered. Identification of the U.S. legal entity that would contract with Battelle, if the parent company is foreign.

• Business size (large or small) and socioeconomic type (e.g., HUBZone, Service-Disabled Veteran-Owned, 8(a), Woman-Owned) and which NAICS code(s) this designation applies to.

• A capability, qualification, and experience statement tailored to this RFI.

• Responses should be formatted as described in Section 6.

6. RESPONSE FORMAT

Response shall follow the following response format:

• Submit a single PDF. The body of the response, consisting of the capability statement and answers to Attachment 1, should not exceed 15 pages.

Appendices do not count against the page limit.

• Answer each question under its number. Where a question does not apply or the respondent chooses not to answer, state "no response" under that number.

Partial responses are welcome and will be considered.

• Supporting documentation, diagrams, and references are encouraged.

• It is recommended that attachments with file sizes exceeding 25MB be compressed (i.e., zipped) to ensure message delivery.

Responses should be prepared simply and economically, and provide a straightforward, concise delineation of the information requested. Emphasis should be on completeness and clarity.

7. USE OF INFORMATION AND PROPRIETARY DATA

Respondents should avoid including classified, business confidential, or proprietary information in their response. If a respondent must submit such information, the information shall be clearly marked, and the respondent must provide sufficient justification as to why the information is business confidential or proprietary.

8. ATTACHMENTS

1. RFI Questionnaire