RFI NOTICE.pdf
PDF 634 KB Posted
- Solicitation number
- N62470-25-R-8009
About this file
This is a Request for Information (RFI) issued by NAVFAC Atlantic seeking market research information for a construction project for a Joint Maritime Facility in Newfoundland, Canada. The RFI aims to identify potential sources and gather information about challenges related to construction in Newfoundland, including base access, healthcare availability, local economy, skilled labor entry, harsh weather environments, materials procurement, supply chain movement, and Canadian port operations.
Interested parties must submit responses by 2:00 p.m. EST on January 6, 2025, to elizabeth.l.roberts31.civ@us.navy.mil. Responses must include company information, address the four items of interest, describe past relevant work outside CONUS (particularly regarding operations facilities and generator procurement/testing), and cannot exceed 5 single-sided pages using 12-point font. The RFI explicitly states it is not a solicitation and the government will not pay for information provided except as allowable costs under other contracts. Proprietary information must be clearly marked, and standard company brochures will not be reviewed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI NOTICE REVISION 02.pdf | ||
| RFI NOTICE REVISION 01.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Market Research/Request for Information (RFI) Naval Facilities Engineering Systems Command (NAVFAC) Atlantic
JOINT MARITIME FACILITY, NEWFOUNDLAND, CANADA
THIS IS A REQUEST FOR INFORMATION (RFI) NOTICE ONLY. THIS IS NOT A
REQUEST FOR PROPOSALS (RFP).
This market research tool is being issued for information purposes only and is not to be construed as a commitment by the Naval Facilities Engineering Systems Command (NAVFAC), implied or otherwise, to issue a solicitation or ultimately award a contract. In accordance with FAR 52.215- 3, Request for Information or Solicitation for Planning Purposes (Oct 1997):
(a) The Government does not intend to award a contract on the basis of this solicitation or to otherwise pay for the information solicited except as an allowable cost under other contracts as provided in subsection 31.205-18, Bid and proposal costs, of the Federal Acquisition Regulation.
(b) Although "proposal" and "offeror" are used in this Request for Information, your response will be treated as information only. It shall not be used as a proposal.
(c) This request for information notice is issued for the purpose of: identifying potential sources for a construction project for an Joint Maritime Facility at Newfoundland, Canada. All Djibouti host nation regulations will apply for construction.
The Government requests written information from the industry in the following areas:
1. Indicate particular challenges performing construction projects that involve construction within Newfoundland, Canada, including but not limited to base access, availability of health care, local economy, and entry of skilled labor into the country.
2. Indicate particular challenges performing construction activities within Newfoundland, Canada, including but not limited to, harsh weather environments, materials procurement, supply chain movement, material clearance through Canadian port operations, etc.
3. Indicate particular challenges associated with substantial upfront acquisition expenditure to obtain equipment needed to substantially complete construction requirements prior to invoicing, billing, or payment.
4. Provide any additional information that you feel relevant to the solicitation
Responses to this Request for Information Notice should reference ‘JOINT MARITIME FACILITY, NEWFOUNDLAND, CANADA and must include the following information in this format:
a. Brief description of company including:
i. Company Name, Address; Corporate website URL; point of contact name, phone number and email address.
ii. Business size (see http://www.sba.gov/size/indextableofsize.html).
b. Statements that address the four items of interest along with the basis for your responses.
c. Brief description of applicable past work performed that included construction of operation facilities and generator procurement and testing outside the Continental United States. Describe in the methodology of how you managed the requirement.
Describe the technical approach for construction material acquisition, document control and special requirements for the power plant construction.
d. Provide any additional information you believe will be relevant to a solicitation issued for the requirement.
Documentation of items (a-d) must be presented in sufficient detail for the Government to determine your company possesses the necessary functional area expertise and experience.
Standard company brochures WILL NOT be reviewed. You submission package is not to exceed five (5) single-sided pages (12-point font minimum).
Responses should be sent to the following email address by 2:00 p.m. EST no later than 6 January 2025. Responses sent after this time may not be considered by the government. Responders must mark proprietary data in order for it to be protected by the government.
Email: Elizabeth.l.roberts31.civ@us.navy.mil
Late responses will not be accepted.
NOTE: THE GOVERNMENT RESERVES THE RIGHT TO CANCEL ANY FUTURE
REQUIREMENT FOR THIS PROJECT. THE GOVERNMENT IS NOT RESPONSIBLE FOR
ANY COSTS INCURRED IN ORDER TO RESPOND TO THIS RFI, OR TO PARTICIPATE
IN ANY SUBSEQUENT PROCESS RELATED TO THE PROJECT STATED WITHIN THIS
RFI. ALL INFORMATION SUBMITTED IS AT THE OFFEROR’S OWN EXPENSE. ANY
RECOMMENDATIONS OR SUGGESTIONS PROVIDED IN RESPONSE TO THE MARKET
RESEARCH MAY BE UTILIZED WITHOUT ANY RESTRICTIONS WHATSOEVER OR
COST TO THE GOVERNMENT AND MAY BE INCLUDED IN A FUTURE PWS.
Proprietary information should be clearly marked. The requested information is for market research purposes only and will not be publicly released. Again, this is not a request for a proposal.
File details come from the government source that posted it. Updated .