This is an Addendum to the Request for Bids (RFB945000-01) issued by the State of Iowa Department of Administrative Services for the Department of Corrections Mount Pleasant Correctional Facility North Parking Lot Replacement project. The addendum, issued May 12, 2025, supersedes portions of the original bidding documents dated January 17, 2025, and documents clarifications from the pre-bid meeting held May 8, 2025, at the facility located at 1200 E. Washington Street, Mount Pleasant, Iowa. The project scope involves removal and replacement of the existing north parking lot. Bids are due May 22, 2025, at 2:00 PM, with bid opening scheduled for 3:00 PM the same day via conference call. The construction schedule runs from July 2, 2025, through August 22, 2025, with substantial completion required by August 22, 2025, and project closeout through September 22, 2025. The pre-bid meeting was attended by representatives from McGough Construction, Mount Pleasant Correctional Facility, State of Iowa Department of Administrative Services, Bolton & Menk (engineer), and other prospective bidders. Key clarifications from the addendum include: standard work hours of 6:00 AM to 4:00 PM with prior approval required for deviations; ADA Detectable Warning pads to match existing pads; clean out casting to be poured integral to pavement per specifications; no utility depth information available; conventional seeding acceptable but hydroseeding preferred; and contractors must provide their own temporary facilities.
The 100% engineered estimate for the project totals $244,610. A bid security/bond of 5% of the total bid amount is required at submission. The Targeted Small Business (TSB) form is not required for bid submission, though the State of Iowa Department of Administrative Services encourages contractors using subcontractors to utilize certified TSB firms; however, this is not mandatory. The project is exempt from Iowa Sales Tax, and Davis Bacon Wages do not apply. Apparent low bidders must submit a subcontractor and supplier list within 48 hours of bid opening. Contractors will execute a modified ConsensusDocs 802 agreement and must provide project-specific Certificates of Insurance and Performance & Payment bonds prior to contract execution. All project management, submittals, invoicing, and RFIs will be conducted through Procore at no cost to trade contractors. The Schedule of Values must include a closeout line item representing at least 1% of total contract value, invoiceable only upon final completion certificate execution.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFB945000-01 - Notice to Bidders.pdf | ||
| RFB945000-01 - Drawings.pdf | ||
| RFB945000-01 - Project Manual.pdf | ||
| 1310487-event.pdf | ||
| RFB945000-01 - Bid Form.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
9450.00 DOC MPCF North Parking Lot Replacement Addendum 1
RFB945000-01 ADDENDUM #01
DATE: May 12, 2025
PROJECT: 9450.00 DOC MPCF North Parking Lot Replacement
BID DUE DATE: May 22, 2025 @ 2:00 pm
TO: All Contract Document Holders of Record.
This Addendum forms a part of the bidding and construction documents. This Addendum supersedes and supplements all portions of the original bidding and construction documents dated January 17, 2025, with which it conflicts. Please attach this Addendum to the Project Manual(s) in your possession.
ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE SPACE PROVIDED ON THE BID
FORM. FAILURE TO DO SO MAY SUBJECT BIDDER TO DISQUALIFICATION.
1. QUESTIONS/CLARIFICATIONS
a. Clarifications
i. MPCF has asked that the awarded contractor provide their own temporary facilities.
ii. See attached meeting minutes and sign-in sheet below from the pre-bid meeting held on
May 8, 2025.
Q1. What are the work hours?
A1. The typical hours of operation are 6:00 am to 4:00 pm. MPCF understands that the weather can cause irregular working hours. If the contractor thinks they will need to perform work outside of these hours, they should get prior approval from MPCF.
Q2. What color would you like the cast iron ADA Detectable Warning pad?
A2. Please match the existing ADA Detectable Warning pads. See the photo below for reference.
Q3. Would you like the clean out poured in the concrete or boxed out?
A3. Clean out casting to be poured integral to the parking lot pavement and include #4 rebar per Detail
6/B.01.
Q4. Do we know the depth of the utilities around the parking lot?
A4. No.
Q5. Can you provide an engineered estimate for the project?
A5. The 100% engineered bid day total estimate was $244,610.
Q6. Does the form in section 00 4116.02 – Targeted Small Business Information need to be filled out and entered with the bid submission?
A6. No, the TSB form is not required to be submitted with your bid. The State of Iowa Department of
Administrative Services (DAS) encourages contractors that are using subcontractors to utilize TSB, but it is not required.
Q7. Will this project utilize Davis Bacon Wages.
A7. This project is exempt from Iowa Sales Tax. Davis Bacon Wages will not apply to this project.
Q8. Would conventional seeding be acceptable in lieu of Hydroseeding?
A8. Conventional seeding is acceptable, but MPCF would prefer Hydroseeding.
9450.00 DOC MPCF North Parking Lot Replacement Addendum 1
State of Iowa - Department of Administrative Services 109 SE 13th St.
Des Moines, Iowa 50319 P: (515) 281-7260
Project: 9450.00 DOC MPCF North Parking Lot Replacement
1200 E. Washington St.
Mount Pleasant, Iowa 52641
RFB Pre-Bid Minutes: Meeting #1
Meeting Date May 8, 2025 Meeting Time 01:30 pm - 02:30 pm Central Time (US & Canada)
Meeting Location 1200 E Washington St. Mount Pleasant, Iowa 52641
Video Conferencing Link https://teams.microsoft.com/l/meetup-join/19%3ameeting_MzhjNjMxOWItMmE2MS00OD RmLTk3ZDAtZmIxMTMxNDFkZDA1%40thread.v2/0 ?context=%7b%22Tid%22%3a%22c6c429d4-d18c- 4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%2203997c 13-f223-4a6b-bb97-06276296bfeb%22%7d
Overview Meeting to allow prospective bidders to visit the site, when possible, and learn more about the project.
Notes
Attachments RFB945000-01_Project Manual_FINAL.pdf, RFB945000-01_Bid Drawings_FINAL.pdf
Scheduled Attendees
Name Company Phone Number Email Attendance
Forrest Martinson Bolton & Menk, Inc P: (507) 625-4171 forrest.martinson@bolton-menk.com Conference
Parker Badding McGough Construction parker.badding@mcgough.com Present
Greg Evans McGough Construction P: (515) 344-1625 greg.evans@mcgough.com Absent
Jeremy Howk Mount Pleasant Correctional Facility
P: (319) 385-9511 jeremy.howk@iowa.gov Present
Tony Kempker Mount Pleasant Correctional Facility
P: (319) 385-9511 ext.
anthony.kempker@iowa.gov Present
Brandon Adams State of Iowa - Department of Administrative Services brandon.adams@iowa.gov Conference
Introduction
No. Mtg Origin Title Assignment Due Date Priority Status
1.1 1 Introductions Open
Description Attendees
• McGough - Parker Badding, Greg Evans
• DAS - Brandon Adams
• MPCF - Jeremy Howk, Tony Kempker
• Bolton & Menk - Forrest Martinson
Official Documented Meeting Minutes Official Meeting Attendance
• McGough Construction: Construction Manager
State of Iowa - Department of Administrative Services Page 1 of 5 Printed On: May 9, 2025 09:33 AM CDT https://teams.microsoft.com/l/meetup-join/19%3ameeting_MzhjNjMxOWItMmE2MS00ODRmLTk3ZDAtZmIxMTMxNDFkZDA1%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%2203997c13-f223-4a6b-bb97-06276296bfeb%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MzhjNjMxOWItMmE2MS00ODRmLTk3ZDAtZmIxMTMxNDFkZDA1%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%2203997c13-f223-4a6b-bb97-06276296bfeb%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MzhjNjMxOWItMmE2MS00ODRmLTk3ZDAtZmIxMTMxNDFkZDA1%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%2203997c13-f223-4a6b-bb97-06276296bfeb%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MzhjNjMxOWItMmE2MS00ODRmLTk3ZDAtZmIxMTMxNDFkZDA1%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%2203997c13-f223-4a6b-bb97-06276296bfeb%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MzhjNjMxOWItMmE2MS00ODRmLTk3ZDAtZmIxMTMxNDFkZDA1%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%2203997c13-f223-4a6b-bb97-06276296bfeb%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MzhjNjMxOWItMmE2MS00ODRmLTk3ZDAtZmIxMTMxNDFkZDA1%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%2203997c13-f223-4a6b-bb97-06276296bfeb%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MzhjNjMxOWItMmE2MS00ODRmLTk3ZDAtZmIxMTMxNDFkZDA1%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%2203997c13-f223-4a6b-bb97-06276296bfeb%22%7d https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/companies/42578/01JTR4E6RQF4H3N4NPVJJAAZ6D?companyId=87524&projectId=2941114&sig=c87f24f9f97457992386d7d19031d294728edc25e1a1aadfdc13467f49606b0d https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/companies/42578/01JTR4E6QB18H8Q4A7V9M43SDQ?companyId=87524&projectId=2941114&sig=c60b5ca76c995052b09d26cee5943c4ea13306ded93301c9ccdac65f857fc7e1 o Parker Badding
• Mt. Pleasant Correctional Facility o Tony Kempker o Jeremy Howk
• Jones Contracting o Jennifer Wilcox
• Graystone Construction o Reed Chicken
• Mike Kilbride Construction o Mike Kilbride o Chadley Kilbride
• Bolton & Menk: Engineer o Forrest Martinson - Virtual
• DAS: Owner's Rep o Brandon Adams - Virtual
Project Overview
2.1 1 Project Description Open
Description
• Base Bid: Removal and replacement of the existing north parking lot at Mount Pleasant Correctional Facility, Mount Pleasant, Iowa, 52641.
• Alternates: N/A
• Unit Prices: See Bid Form on Project Manual for unit pricing.
• No questions or concerns.
2.2 1 Project Schedule Open
Description
• Contractor Bidding: 04/28 - 05/22
• Bids Due: 05/22 at 2:00 pm
• Contractor NOI to Award: 05/27
• Prepare & Execute Contracts: 05/28 - 06/10
• Submittals: 06/11 - 07/01
• Construction: 07/02 - 08/15
• Substantial Completion: 08/22
• Closeout: 08/25 - 09/22
If needed, a pull-plan session will be held with the successful bid package contractors to finalize the construction schedule.
Meeting #1 - RFB Pre-Bid Project: 9450.00 DOC MPCF North Parking Lot Replacement
State of Iowa - Department of Administrative Services Page 2 of 5 Printed On: May 9, 2025 09:33 AM CDT
State Holidays: Memorial Day, 4th of July, and Labor Day
• No questions or concerns with schedule.
2.3 1 Site Rules Open
Description
• Onsite supervision by Prime Contractor is required at all times when work by that contractor or their subcontractors/suppliers is taking place.
• Contractors shall provide daily logs for each day they are on site.
• Construction progress meeting will be established once construction starts.
• It is of the utmost importance to show respect and courtesy to all staff at all times.
• Clean all debris, materials, and bring all finishes back to existing conditions in the area they were working in prior to moving to the next area.
• No smoking, vaping, or smokeless tobacco use onsite.
Site Specific Rules
• Temporary Facilities - MPCF to advise
• Tool Control
• Cell Phones
• Background Checks / PREA Training
• Work Hours - MPCF to advise
• View Specification 01 1200 - Contract Summary for more information.
• Contractors to provide their own temporary restroom facilities.
RFB Overview
3.1 1 Bid Submission Open
Description
• Bids are due at 2:00 pm, Thursday, May 22, 2025.
• The bid shall be submitted to the Issuing Officer through the IMPACS Electronic Procurement System.
o Link and information is in the project manual o Contractors will need to register prior to bidding o Bidders will need to register regardless of whether it has already done business with the State of Iowa.
o Bidders should complete the registration process and ensure the ability to log in as soon as possible to ensure bids can be submitted on the due date.
o Please make sure the electronic documents submitted contain any required signatures. Digital signatures will be accepted.
• Bid Opening will be held via conference call at 3:00 pm, Thursday, May 22, 2025.
o More information regarding the Bid Opening can be found in the Project Manual in section 00 1113 - Notice to Bidders.
• Contractor shall reference section 00 0116 for the bid submittal checklist o Bid Proposal Information o Non Discrimination Clause Information
State of Iowa - Department of Administrative Services Page 3 of 5 Printed On: May 9, 2025 09:33 AM CDT o Contractor Targeted Small Business Enterprise Pre-Bid Contract Information o Bid Security – 5% of total Bid amount
• Apparent low bidder will be required to submit subcontractor/supplier list 48hrs after the bid opening.
Official Documented Meeting Minutes
• DAS encourages contractors that are using subcontractors to utilize TSB, but it is not required. The TSB form in the Project Manual is not required to be filled out with the bid submission.
3.2 1 Bid Schedule Open
Description
• Questions/Substitutions Due in Writing to Construction.Procurement@iowa.gov: 3:00 pm, Monday, May 12, 2025.
• Addendum Issued: On or before Wednesday, May 14, 2025.
• Bids Due: 2:00 pm, Thursday, May 22, 2025.
• Tentative NOI Issued: Tuesday, May 27, 2025.
3.3 1 Administrative Details Open
Description
• Contractors will sign a modified ConsensusDocs 802. Example in the project manual.
• Project-specific Certificate of Insurance must be provided prior to contract execution. Follow example in the project manual and limits in the 802.
• Project-specific P&P bonds must be provided prior to contract execution.
• Successful contractor must turn in their list of subcontractors and suppliers within 48 hours of the bid.
• DAS will provide tax exempt certificates upon request.
• Procore will be used for all project management, at no cost to the trade contractor.
o Submittals, Invoicing, RFIs, ASIs, PRs, RFQs o Contracts, Change Orders and Certificates of Substantial and Final Completion will also use Docusign
• Contractor Schedule of Values shall be broken out as specified in the project manual.
o SOV must contain a closeout line item for at least 1% of the total contract value.
o This line item can only be invoiced once the certificate of final completion has been signed by all parties.
State of Iowa - Department of Administrative Services Page 4 of 5 Printed On: May 9, 2025 09:33 AM CDT mailto:Construction.Procurement@iowa.gov:
3.4 1 Pre-Bid Site Visits Open
Description
• If you would like to schedule an additional pre-bid site visit please contact Tony Kempker at (319) 931-9460 or Jeremy Howk at (319) 201-0552.
Questions
4.1 1 Questions Open
Description
• Reminder: Submit all questions in writing to construction.procurement@iowa.gov.
Official Documented Meeting Minutes
• All questions that were asked during open discussion and site walkthrough to be answered via Addendum.
These meeting minutes are believed to be an accurate reflection of those items discussed and the conclusions that were reached during the referenced meeting.
Please contact State of Iowa - Department of Administrative Services if there are any discrepancies or questions with the content of these minutes.
State of Iowa - Department of Administrative Services Page 5 of 5 Printed On: May 9, 2025 09:33 AM CDT
File details come from the government source that posted it. Updated .