RFB931600-01 - DHS CHMHI - Addendum #2.pdf
PDF 302 KB Posted
- Attached to
- DHS CHMHI New Parking Area
- Solicitation number
- 005-RFB-0630-2024
- Issued by
- Chickasaw County, Iowa
About this file
Addendum 2 for RFB931600-01 is an official document issued by the Iowa Department of Administrative Services (DAS) for the CHMHI New Parking Area project, dated 10/10/2023. The addendum addresses contractor questions and provides clarification for the bid process, specifically for a parking lot addition at the Cherokee Mental Health Institute. The document includes responses to three contractor questions regarding the project, including the designer's cost estimate of $140,000 for the base bid and $12,000 for the alternate, guidance on soil and concrete testing, and specifications for pavement markings.
The addendum includes an attachment of the sign-in sheet from the pre-bid meeting held on October 4th, 2023, which documents attendees from various construction companies. The designer's cost estimate suggests the project is relatively modest in scope, with the contractor responsible for coordinating owner-paid testing. The document references SUDAS 8020 for painted pavement markings, indicating adherence to standard specifications for infrastructure projects. The addendum serves to provide additional information and clarity to potential bidders, ensuring they have the most up-to-date details before submitting their proposals for the parking area construction project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum 2 for RFB931600-01
Project Name: CHMHI New Parking Area
DAS RFB #: 931600-01
DAS Project #: 9316.00 Date: 10/10/2023
CONTRACTOR QUESTIONS
Q1. Is there an engineer’s estimate?
A1. Designers cost estimate was $140,000 for base bid, with $12,000 for the alternate.
Q2. Who is soil, compaction, and concrete tests by?
A2. Contractor to coordinate Owner to pay.
Q3. Does the striping need to be epoxy based?
A3. No follow SUDAS 8020: Painted Pavement Markings.
ATTACHMENTS
1. Sign-In Sheet from Pre-Bid Meeting on Wednesday October 4th, 2023.
END OF ADDENDUM