RFB # P27-07R North Street Storm Sewer Replacement - Technical Specifications.pdf

PDF 2 MB Posted

Attached to
North Street Storm Sewer Replacement - Rebid
Solicitation number
323-P27-07R
Issued by
Henderson County, Charlotte City, North Carolina

About this file

This is a Technical Specifications document for a state and local construction contract issued by the Town of Chapel Hill, North Carolina, prepared by Ballentine Associates, P.A. Consulting Engineers. The project involves the replacement of a storm sewer system at 110 & 116 North Street, Chapel Hill, NC 27514 (Project #119016.06), with work to be conducted in a single phase under a stipulated price contract. The scope of work includes implementation of a three-phase erosion control program (perimeter controls, rough grading and drainage, and inlet protection), construction of private roads with striping and signage, construction of utilities and storm drainage infrastructure, and installation of lighting and landscaping. Construction activities are restricted to normal business hours of 7:00 a.m. to 7:00 p.m. Monday through Friday, 8:00 a.m. to 7:00 p.m. on Saturday, with no work permitted on Sundays or federal holidays. The contract establishes procedures for unit prices, with three identified unit price categories for removal and replacement of unsatisfactory soil, trench rock excavation, and mass rock excavation, each measured in cubic yards.

The specifications establish comprehensive administrative and procedural requirements for contract execution, including detailed provisions for payment procedures, change orders, substitutions, and progress documentation. A schedule of values must be submitted no later than the 15th of the month, with progress payments due by the 15th of each month covering work completed through the last day of the preceding month. The contractor is required to submit a cost-loaded Critical Path Method (CPM) schedule within 60 days of the Notice to Proceed, along with daily construction reports, material location reports, photographic documentation (minimum 20 photos monthly), and regular progress meeting minutes. Contract modifications are processed through Work Change Directives and Change Orders, with proposals for contractor-initiated changes requiring detailed cost and schedule impact analysis. Waivers of mechanic's liens must accompany each Application for Payment, and the contractor must maintain performance and payment bonds, certificates of insurance, and building permits. Final completion includes submission of project record documents, evidence of tax and fee payment, contractor affidavits of payment and lien release, and final liquidated damages settlement statements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Issue Dates Description

20 Feb 2026 Bid Set

SITEWORK

TECHNICAL SPECIFICATIONS

North Street Pipe Replacement

110 & 116 North Street

Chapel Hill, NC 27514

Attn: Town of Chapel Hill

6850 Milhouse Road

Chapel Hill, NC 27514

Prepared by:

Ballentine Associates, P.A.

Consulting Engineers

221 Providence Road

Chapel Hill, NC 27514

(919) 929-0481

Attn: Kenneth Judy, PE

BA Project # 119016.06

North Street Town of Chapel Hill

Pipe Replacement 119016.06

Bid Set 02/20/26

TABLE OF CONTENTS

TOC - 1

Division ....... Section Title .............................................................................................................................. Pages

011000 ......... SUMMARY

012200 ......... UNIT PRICES

012500 ......... SUBSTITUTION PROCEDURES

012600 ......... CONTRACT MODIFICATION PROCEDURES

012900 ......... PAYMENT PROCEDURES

013100 ......... PROJECT MANAGEMENT AND COORDINATION

013200 ......... CONSTRUCTION PROGRESS DOCUMENTATION

013233 ......... PHOTOGRAPHIC DOCUMENTATION

013300 ......... SUBMITTAL PROCEDURES

014000 ......... QUALTIY REQUIREMENTS

015000 ......... TEMPORARY FACITILIES AND CONTROLS

015639 ......... TEMPORARY TREE AND PLANT PROTECTION

016000 ......... PRODUCT REQUIREMENTS

017300 ......... EXECUTION

017419 ......... CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

017700 ......... CLOSEOUT PROCEDURES

017839 ......... PROJECT RECORD DOCUMENTS

024116 ......... STRUCTURE DEMOLITION

221313 ......... FACILITY SANITARY SEWERS

311000 ......... SITE CLEARING

312000 ......... EARTH MOVING

312319 ......... DEWATERING

315000 ......... EXCAVATION SUPPORT AND PROTECTION

321216 ......... ASPHALT PAVING

321313 ......... PORTLAND CEMENT CONCRETE PAVING

321373 ......... CONCRETE PAVING JOINT SEALANTS

334100 ......... STORM DRAINAGE UTILITY PIPING

..................... SITEWORK SUBMITTAL LOG

SECTION 011000 – SUMMARY

North Street 1 BA Project #119016.06

Pipe Replacement 011000 Issued for Bid – 02-20-2026

GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.02 SUMMARY

A. Section includes:

Project information.

2. Work covered by Contract Documents.

3. Phased construction.

4. Work under separate contracts.

5. Future work.

6. Access to site.

7. Work restrictions.

8. Specification and drawing conventions.

B. Related Section:

Division 01 Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1.03 PROJECT INFORMATION

A. Project Identification: 119016.06.

1. Project Location: 110 & 116 North Street.

B. Owner: Town of Chapel Hill .

1. Owner's Representative: Chad Brown

6850 Millhouse Road, Chapel Hill, NC 27514

Other Owner Consultants: The Owner has retained the following design professionals who have prepared designated portions of the Contract Documents:

1. Civil Engineering: Ballentine Associates, P.A.

221 Providence Road Chapel Hill, NC 27514

Engineer of Record: Kenneth Judy, P.E.

WORK COVERED BY CONTRACT DOCUMENTS

The Work of the Project is defined by the Contract Documents and consists of the following:

North Street 2 BA Project #119016.06

Pipe Replacement 011000 Issued for Bid – 02-20-2026

1. Implementation of an Erosion Control Program in 3 Phases.

1) Phase 1 – perimeter controls

2) Phase 2 – rough grading and drainage

3) Phase 3 – inlet protection

2. Construction of private roads, including striping and signage.

3. Construction of utilities and storm drainage.

4. Lighting and landscaping.

Type of Contract

Project will be constructed under a single prime contract (Stipulated Price).

Form of Agreement Between Owner and Contractor for Construction Contract

1.05 PHASED CONSTRUCTION

The Work shall be conducted in 1 phase.

WORK UNDER SEPARATE CONTRACTS

General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract or other contracts. Coordinate the Work of this Contract with work performed under separate contracts.

ACCESS TO SITE

General: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project.

WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work in the existing building to normal business working hours of

7:00 a.m. to 7:00 p.m., Monday through Friday, except as otherwise indicated.

1. Weekend Hours: 8:00 a.m. to 7:00 p.m. on Saturday. No construction activities on Sundays.

2. Holidays: No construction on federal holidays.

Controlled Substances: Use controlled substances on the Project site is not permitted.

North Street 3 BA Project #119016.06

Pipe Replacement 011000 Issued for Bid – 02-20-2026

SPECIFICATION AND DRAWING CONVENTIONS

Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

Drawing Coordination: Requirements for materials and products identified on the Drawings are described in detail in the Specifications. One or more of the following are used on the Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations scheduled on

Drawings.

3. Keynoting: Materials and products are identified by reference keynotes referencing

Specification Section numbers found in this Project Manual.

1.10 MISCELLANEOUS PROVISIONS

PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

SECTION 012200 – UNIT PRICES

Pipe Replacement 012200 Issued for Bid – 02-20-2026

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.02 SUMMARY

A. Section includes administrative and procedural requirements for unit prices.

B. Related Sections:

1. Division 01 Section "Contract Modification Procedures" for procedures for submitting and handling Change Orders.

2. Division 01 Section "Quality Requirements" for general testing and inspecting requirements.

1.03 DEFINITIONS

A. Unit price is an amount incorporated in the Agreement, applicable during the duration of the

Work a price per unit of measurement for materials, equipment, or services, or a portion of the

Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of

Work or estimated quantities of Work required by the Contract Documents are increased or decreased.

1.04 PROCEDURES

A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.

B. Measurement and Payment: Refer to individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.

C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor.

D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.

SECTION 012200 – UNIT PRICES

Pipe Replacement 012200 Issued for Bid – 02-20-2026

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.01 SCHEDULE OF UNIT PRICES

A. Unit Price 1: Removal of unsatisfactory soil and replacement with satisfactory soil material.

1. Description: Unsatisfactory soil excavation and disposal off site and replacement with satisfactory fill material or engineered fill from off site, as required, in accordance with

Division 31 Section "Earth Moving."

2. Unit of Measurement: Cubic yard of soil excavated, based upon survey of volume removed.

B. Unit Price 2: Trench Rock excavation and replacement with satisfactory soil material.

1. Description: Classified trench rock excavation and disposal off site and replacement with satisfactory fill material or engineered fill from off site, as required, in accordance with

Division 31 Section "Earth Moving."

2. Unit of Measurement: Cubic yard of rock excavated, based upon survey of volume removed.

C. Unit Price 3: Mass Rock excavation and replacement with satisfactory soil material.

1. Description: Classified mass rock excavation and disposal off site and replacement with satisfactory fill material or engineered fill from off site, as required, in accordance with

Division 31 Section "Earth Moving."

2. Unit of Measurement: Cubic yard of rock excavated, based upon survey of volume removed.

END OF SECTION 012200

SECTION 012500 – SUBSTITUTION PROCEDURES

Pipe Replacement 012500 Issued for Bid – 02-20-2026

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.02 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Sections:

1. Division 01 Section "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

2. Divisions 02 through 49 Sections for specific requirements and limitations for substitutions.

1.03 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.

2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to

Contractor or Owner.

1.04 SUBMITTALS

A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.

b. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Owner and separate contractors, that will be necessary to accommodate proposed substitution.

Pipe Replacement 012500 Issued for Bid – 02-20-2026

c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable specification section.

Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested.

f. Certificates and qualification data, where applicable or requested.

g. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners.

h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

i. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall

Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.

j. Cost information, including a proposal of change, if any, in the Contract Sum.

k. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

l. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

2. Engineer's Action: If necessary, Engineer will request additional information or documentation for evaluation within seven days of receipt of a request for substitution.

Engineer will notify Contractor of acceptance or rejection of proposed substitution within

15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order, Construction Change Directive.

b. Use product specified if Engineer does not issue a decision on use of a proposed substitution within time allocated.

1.05 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage qualified testing agency to perform compatibility tests recommended by manufacturers.

1.06 PROCEDURES

A. Coordination: Modify or adjust affected work as necessary to integrate work of the approved substitutions.

Pipe Replacement 012500 Issued for Bid – 02-20-2026

PART 2 - PRODUCTS

2.01 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately upon discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.

1. Conditions: Engineer will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Engineer will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Substitution request is fully documented and properly submitted.

c. Requested substitution will not adversely affect Contractor's construction schedule.

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: Engineer will consider requests for substitution if received within 60 days after the Notice to Proceed. Requests received after that time may be considered or rejected at discretion of Architect.

1. Conditions: Engineer will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Engineer will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities

Owner must assume. Owner's additional responsibilities may include compensation to Engineer for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.

b. Requested substitution does not require extensive revisions to the Contract

Documents.

c. Requested substitution is consistent with the Contract Documents and will produce indicated results.

d. Substitution request is fully documented and properly submitted.

e. Requested substitution will not adversely affect Contractor's construction schedule.

f. Requested substitution has received necessary approvals of authorities having jurisdiction.

g. Requested substitution is compatible with other portions of the Work.

h. Requested substitution has been coordinated with other portions of the Work.

North Street 4 BA Project #119016.06

Pipe Replacement 012500 Issued for Bid – 02-20-2026

i. Requested substitution provides specified warranty.

j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

END OF SECTION 012500

SECTION 012600 – CONTRACT MODIFICATION PROCEDURES

Pipe Replacement 012600 Issued for Bid – 02-20-2026

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.02 SUMMARY

A. Section includes administrative and procedural requirements for handling and processing

Contract modifications.

B. Related Sections:

1. Division 01 Section "Product Requirements" for administrative procedures for handling requests for substitutions made after Contract award.

1.03 MINOR CHANGES IN THE WORK

A. Engineer will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on a Work Change Directive form (C-940).

1.04 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Engineer will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Proposal Requests issued by Engineer are not instructions either to stop work in progress or to execute the proposed change.

2. Within time specified in Proposal Request after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and supervision directly attributable to the change.

d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

Pipe Replacement 012600 Issued for Bid – 02-20-2026

B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the

Contract, Contractor may initiate a claim by submitting a request for a change to Engineer.

1. Include a statement outlining reasons for the change and the effect of the change on the

Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the

Contract Time.

6. Comply with requirements in Division 01 Section "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.

1.05 ADMINISTRATIVE CHANGE ORDERS

A. Unit Price Adjustment: Refer to Division 01 Section "Unit Prices" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect measured scope of unit price work.

1.06 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Proposal Request, Engineer will issue a Change Order for signatures of Owner and Contractor on EJCDC Document, Change Order form C-941.

1.07 CONSTRUCTION CHANGE DIRECTIVE

A. Work Change Directive: Engineer may issue a Work Change Directive on

EJCDC Document C-940. Work Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Work Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the

Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of work required by the

Work Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

Pipe Replacement 012600 Issued for Bid – 02-20-2026

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012600

SECTION 012900 – PAYMENT PROCEDURES

Pipe Replacement 012900 Issued for Bid – 02-20-2026

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.02 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and process Applications for Payment.

B. Related Sections:

1. Division 01 Section "Unit Prices" for administrative requirements governing the use of unit prices.

2. Division 01 Section "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.

3. Division 01 Section "Construction Progress Documentation" for administrative requirements governing the preparation and submittal of the Contractor's construction schedule.

4. Division 01 Section "Submittal Procedures" for administrative requirements governing the preparation and submittal of the submittal schedule.

1.03 DEFINITIONS

A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract

Sum to various portions of the Work and used as the basis for reviewing Contractor's

Applications for Payment.

1.04 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule. Cost-loaded Critical Path Method Schedule may serve to satisfy requirements for the schedule of values.

1. Correlate line items in the schedule of values with other required administrative forms and schedules, including the following:

a. Application for Payment forms with continuation sheets.

b. Submittal schedule.

c. Items required to be indicated as separate activities in Contractor's construction schedule.

2. Submit the schedule of values to Engineer at earliest possible date but no later than the

15th of the month. Retain paragraph below; revise to suit Project. If desired, include a sample schedule of values at end of Section.

Pipe Replacement 012900 Issued for Bid – 02-20-2026

B. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the schedule of values:

a. Project name and location.

b. Name of Engineer.

c. Engineer’s project number.

d. Contractor's name and address.

e. Date of submittal.

2. Arrange the schedule of values in tabular form with separate columns to indicate the following for each item listed:

a. Related Specification Section or Division.

b. Description of the Work.

c. Name of subcontractor.

d. Name of manufacturer or fabricator.

e. Name of supplier.

f. Change Orders (numbers) that affect value.

g. Dollar value of the following, as a percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent.

1) Labor.

2) Materials.

3) Equipment.

3. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project

Manual table of contents. Provide multiple line items for principal subcontract amounts in excess of five percent of Contract Sum.

a. Include separate line items under Contractor and principal subcontracts for project closeout requirements in an amount totaling five percent of the Contract Sum and subcontract amount.

4. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

5. Provide a separate line item in the schedule of values for each part of the Work where

Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

a. Differentiate between items stored on-site and items stored off-site. If required, include evidence of insurance.

6. Provide separate line items in the schedule of values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

7. Allowances: Provide a separate line item in the schedule of values for each allowance.

Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities.

Pipe Replacement 012900 Issued for Bid – 02-20-2026

8. Purchase Contracts: Provide a separate line item in the schedule of values for each purchase contract. Show line-item value of purchase contract. Indicate owner payments or deposits, if any, and balance to be paid by Contractor.

9. Each item in the schedule of values and Applications for Payment shall be complete.

Include total cost and proportionate share of general overhead and profit for each item.

a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at Contractor's option.

10. Schedule Updating: Update and resubmit the schedule of values before the next

Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum.

1.05 APPLICATIONS FOR PAYMENT

A. Each Application for Payment shall be consistent with previous applications and payments as certified by Engineer and paid for by Owner.

1. Initial Application for Payment, Application for Payment at time of Substantial

Completion, and final Application for Payment involve additional requirements.

B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.

C. Payment Application Times: Progress payments shall be submitted to Engineer by the 15th day of the month. The period covered by each Application for Payment is one month, ending on the last day of the month.

1. Submit draft copy of Application for Payment 15 days prior to due date for review by

Engineer.

D. Application for Payment Forms: Use forms acceptable to Engineer and Owner for Applications for Payment. Submit forms for approval with initial submittal of schedule of values.

E. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Engineer will return incomplete applications without action.

1. Entries shall match data on the schedule of values and Contractor's construction schedule.

Use updated schedules if revisions were made.

2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.

3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

4. Indicate separate amounts for work being carried out under Owner-requested project acceleration.

Pipe Replacement 012900 Issued for Bid – 02-20-2026

F. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site.

1. Provide certificate of insurance, evidence of transfer of title to Owner, and consent of surety to payment, for stored materials.

2. Provide supporting documentation that verifies amount requested, such as paid invoices.

Match amount requested with amounts indicated on documentation; do not include overhead and profit on stored materials.

3. Provide summary documentation for stored materials indicating the following:

a. Materials previously stored and included in previous Applications for Payment.

b. Work completed for this Application utilizing previously stored materials.

c. Additional materials stored with this Application.

d. Total materials remaining stored, including materials with this Application.

G. Transmittal: Submit one signed and notarized copies of each Application for Payment to

Engineer by email and ensure receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

H. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from entities lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment.

1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.

2. When an application shows completion of an item, submit conditional final or full waivers.

3. Owner reserves the right to designate which entities involved in the Work must submit waivers.

4. Waiver Forms: Submit waivers of lien on forms, executed in a manner acceptable to

Owner.

I. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's liens from subcontractors, sub-subcontractors, and suppliers for construction period covered by the previous application.

1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.

2. When an application shows completion of an item, submit conditional final or full waivers.

3. Owner reserves the right to designate which entities involved in the Work must submit waivers.

4. Submit final Application for Payment with or preceded by conditional final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien.

5. Waiver Forms: Submit waivers of lien on forms, executed in a manner acceptable to

Owner.

North Street 5 BA Project #119016.06

Pipe Replacement 012900 Issued for Bid – 02-20-2026

J. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Schedule of values.

3. Contractor's construction schedule (preliminary if not final).

4. Combined Contractor's construction schedule (preliminary if not final) incorporating

Work of multiple contracts, with indication of acceptance of schedule by each Contractor.

5. Products list (preliminary if not final).

6. Schedule of unit prices.

7. Submittal schedule (preliminary if not final).

8. List of Contractor's staff assignments.

9. List of Contractor's principal consultants.

10. Copies of building permits.

11. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.

12. Initial progress report.

13. Report of preconstruction conference.

14. Certificates of insurance and insurance policies.

15. Performance and payment bonds.

16. Data needed to acquire Owner's insurance.

K. Application for Payment at Substantial Completion: After issuing the Certificate of Substantial

Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This application shall reflect Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work.

L. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

3. Updated final statement, accounting for final changes to the Contract Sum.

4. AIA Document G706, "Contractor's Affidavit of Payment of Debts and Claims."

5. AIA Document G706A, "Contractor's Affidavit of Release of Liens."

6. AIA Document G707, "Consent of Surety to Final Payment."

7. Evidence that claims have been settled.

8. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.

9. Final liquidated damages settlement statement.

North Street 6 BA Project #119016.06

Pipe Replacement 012900 Issued for Bid – 02-20-2026

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012900

SECTION 013100 – PROJECT MANAGEMENT AND COORDINATION

Pipe Replacement 013100 Issued for Bid – 02-20-2026

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.02 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. General project coordination procedures.

2. Administrative and supervisory personnel.

3. Coordination drawings.

4. Requests for Information (RFIs).

5. Project meetings.

B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.

C. Related Sections:

1. Division 01 Section "Construction Progress Documentation" for preparing and submitting Contractor's construction schedule.

2. Division 01 Section "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Division 01 Section "Closeout Procedures" for coordinating closeout of the Contract.

4. Division 01 Section "General Commissioning Requirements" for coordinating the Work with Owner's commissioning authority.

1.03 DEFINITIONS

A. RFI: Request from Owner, Engineer, or Contractor seeking information from each other during construction.

1.04 COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the

Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.

Pipe Replacement 013100 Issued for Bid – 02-20-2026

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Coordination: Each contractor shall coordinate its construction operations with those of other contractors and entities to ensure efficient and orderly installation of each part of the Work.

Each contractor shall coordinate its operations with operations, included in different Sections, that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other contractors to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

C. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their

Work is required.

D. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Preinstallation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

9. Project closeout activities.

E. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials. Coordinate use of temporary utilities to minimize waste.

1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. Refer to other Sections for disposition of salvaged materials that are designated as Owner's property.

Pipe Replacement 013100 Issued for Bid – 02-20-2026

1.05 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings in accordance with requirements in individual Sections, where installation is not completely shown on Shop

Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.

1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

a. Use applicable Drawings as a basis for preparation of coordination drawings.

Prepare sections, elevations, and details as needed to describe relationship of various systems and components.

b. Coordinate the addition of trade-specific information to the coordination drawings by multiple contractors in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review.

c. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

d. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

e. Show location and size of access doors required for access to concealed dampers, valves, and other controls.

f. Indicate required installation sequences.

g. Indicate dimensions shown on the Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Engineer indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

B. Coordination Digital Data Files: Prepare coordination digital data files in accordance with the following requirements:

1. File Preparation Format: Same digital data software program, version, and operating system as the original Drawings.

2. File Preparation Format: DWG, Version 2018, operating in Microsoft Windows operating system.

3. File Submittal Format: Submit or post coordination drawing files using Portable Data

File (PDF) format.

4. Engineer will furnish Contractor one set of digital data files of the Drawings for use in preparing coordination digital data files.

a. Engineer makes no representations as to the accuracy or completeness of digital data files as they relate to the Drawings.

b. Digital Data Software Program: The Drawings are available in DWG, version

2018.

Pipe Replacement 013100 Issued for Bid – 02-20-2026

1.06 KEY PERSONNEL

A. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home, office, and cellular telephone numbers and email addresses. Provide names, addresses, and telephone numbers of individuals assigned as standbys in the absence of individuals assigned to Project.

1. Post copies of list in temporary field office. Keep list current at all times.

1.07 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Engineer will return RFIs submitted to Engineer by other entities controlled by

Contractor with no response.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Project number.

3. Date.

4. Name of Contractor.

5. Name of Engineer.

6. RFI number, numbered sequentially.

7. RFI subject.

8. Specification Section number and title and related paragraphs, as appropriate.

9. Drawing number and detail references, as appropriate.

10. Field dimensions and conditions, as appropriate.

11. Contractor's suggested resolution. If Contractor's solution(s) impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

12. Contractor's signature.

13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Forms: Software-generated form with substantially the same content as indicated above, acceptable to Engineer.

D. Engineer's Action: Engineer will review each RFI, determine action required, and respond.

Allow seven working days for Engineer's response for each RFI. RFIs received by Engineer after 1:00 p.m. will be considered as received the following working day.

Pipe Replacement 013100 Issued for Bid – 02-20-2026

1. The following RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for coordination information already indicated in the Contract

Documents.

d. Requests for adjustments in the Contract Time or the Contract Sum.

e. Requests for interpretation of Engineer's actions on submittals.

f. Incomplete RFIs or inaccurately prepared RFIs.

2. Engineer's action may include a request for additional information, in which case

Engineer's time for response will date from time of receipt of additional information.

3. Engineer's action on RFIs that may result in a change to the Contract Time or the

Contract Sum may be eligible for Contractor to submit Change Proposal according to

Division 01 Section "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Engineer in writing within 7 days of receipt of the RFI response.

E. On receipt of Engineer's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Engineer within seven days if Contractor disagrees with response.

F. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.

Submit log weekly. Use Software log with not less than the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Engineer.

4. RFI number including RFIs that were dropped and not submitted.

5. RFI description.

6. Date the RFI was submitted.

7. Date Engineer's response was received.

8. Identification of related Minor Change in the Work, Construction Change Directive, and

Proposal Request, as appropriate.

9. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.

1.08 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Engineer of scheduled meeting dates and times.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

Pipe Replacement 013100 Issued for Bid – 02-20-2026

3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner and Engineer, within three days of the meeting.

B. Preconstruction Conference: Schedule and conduct a preconstruction conference before starting construction, at a time convenient to Owner and Engineer, but no later than 60 days after execution of the Agreement.

1. Conduct the conference to review responsibilities and personnel assignments.

2. Attendees: Authorized representatives of Owner and Engineer, and their consultants;

Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with

Project and authorized to conclude matters relating to the Work.

3. Agenda: Discuss items of significance that could affect progress, including the following:

a. Tentative construction schedule.

b. Phasing.

c. Critical work sequencing and long-lead items.

d. Designation of key personnel and their duties.

e. Lines of communications.

f. Procedures for processing field decisions and Change Orders.

g. Procedures for RFIs.

h. Procedures for testing and inspecting.

i. Procedures for processing Applications for Payment.

j. Distribution of the Contract Documents.

k. Submittal procedures.

l. Sustainable design requirements.

m. Preparation of record documents.

n. Use of the premises.

o. Work restrictions.

p. Working hours.

q. Owner's occupancy requirements.

r. Responsibility for temporary facilities and controls.

s. Procedures for moisture and mold control.

t. Procedures for disruptions and shutdowns.

u. Construction waste management and recycling.

v. Parking availability.

w. Office, work, and storage areas.

x. Equipment deliveries and priorities.

y. First aid.

z. Security.

aa. Progress cleaning.

4. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

North Street 7 BA Project #119016.06

Pipe Replacement 013100 Issued for Bid – 02-20-2026

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Engineer of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Review of mockups.

i. Possible conflicts.

j. Compatibility problems.

k. Time schedules.

l. Weather limitations.

m. Manufacturer's written recommendations.

n. Warranty requirements.

o. Compatibility of materials.

p. Acceptability of substrates.

q. Temporary facilities and controls.

r. Space and access limitations.

s. Regulations of authorities having jurisdiction.

t. Testing and inspecting requirements.

u. Installation procedures.

v. Coordination with other work.

w. Required performance results.

x. Protection of adjacent work.

y. Protection of…