This architectural drawing set documents the design for the Scale House building, a 814 gross square foot facility being constructed as part of the Dane County Department of Waste & Renewables Sustainability Campus project located at 4402 Brandt Road, Madison, Wisconsin. The Scale House is a single-story structure classified as a Mixed-Use occupancy (Group B - Business) with design loads including 22 PSF dead load on the roof (accounting for future solar panels), 20 PSF reducible live load on the roof, and variable snow and wind loads per Wisconsin Commercial Building Code based on 2021 IBC standards. The project includes comprehensive architectural, mechanical, electrical, plumbing, structural, landscape architecture, and technology and audiovisual design services provided by Strang Inc., MP-Squared Structural Engineers LLC, and Saiki Design Inc. Construction details encompass concrete slab-on-grade foundations with 6 inches of granular base, reinforced concrete footings, wood frame structural construction with roof trusses spaced at 24 inches on center, exterior wall systems utilizing brick veneer with insulation and metal panels, and interior finishes including sealed concrete floors, gypsum board partitions, and acoustical ceiling panels. The building contains five primary spaces: an observation deck (C101), corridor (C102), unisex restroom (C103), break room (C104), mechanical/janitorial area (C106), and electrical/IT room (C105), with an exit distance of 53 feet 2 inches and wheelchair turning space requirements throughout to meet ADA accessibility standards.
The Scale House design incorporates specialized systems for its function within the sustainability campus operations, including bullet-resistant storefront framing and glazing at transaction windows, RFID reader access control points, and mechanical equipment provisions for scale operations. The structure features multiple exterior elevations with metal panel systems in three finishes (clear anodized aluminum horizontal panels, woodgrain vertical panels, and charcoal horizontal panels), brick veneer sections, and factory-fabricated metal coping and flashing systems. Interior mechanical systems include HVAC units with heat pump capability, plumbing infrastructure with fixture provisions for office and restroom use, and electrical distribution with dedicated circuits and panel schedules. The drawings establish 4,000 PSI concrete compressive strength requirements for exterior foundation walls exposed to freezing conditions and 3,000 PSI for interior slabs, with all reinforcing steel meeting ASTM A615 Grade 60 specifications. Design compliance includes fire alarm initiation and notification devices, accessible route provisions to accessible parking stalls, and corner guard protection throughout accessible areas. The construction documents are dated March 31, 2026, with the project number 2024131, and include detailed specifications for all finishes, hardware, and equipment necessary for bid package development and construction administration.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARCHITECTURAL MECHANICAL
STRUCTURAL ELECTRICAL
ARCHITECTURAL DESIGN, MECHANICAL, ELECTRICAL, AND PLUMBING
ENGINEERING
STRANG, INC.
STRUCTURAL ENGINEERING
MP-SQUARED STRUCTURAL ENGINEERS, LLC
LANDSCAPE ARCHITECTURE
SAIKI DESIGN, INC.
TECHNOLOGY & AV DESIGN
NETWORK TECHNOLOGIES, INC.
DESIGN TEAM PROJECT IMAGE
SHEET INDEX
STAMPS
SITE LOCATION MAP
D R
A W
IN
G
S E
T
D A
T E
COPYRIGHT STRANG, INC. 2026
R E
V
IS
IO
N
S
P R
O
JE
C T
N O
4402 BRANDT ROAD
MADISON, WI 53718 PROJECT NO. : 2024131
DANE COUNTY DEPT OF WASTE & RENEWABLES - SCALE HOUSE
B R
A N
D T
R O
A D
M A
D
IS
O N
, W I
C D
/3
1/
T
IT
LE
S
H E
E T
D A
N E
C O
U N
T Y
D E
P T
O F
W A
S T
E
R E
N E
W A
B
LE
S
S C
A
LE
H O
U S
E
CG000
N
PROJECT LOCATION
MADISON
GENERAL
CG000 TITLE SHEET
CG001 GENERAL INFORMATION
CG002 LIFE SAFETY PLAN & CODE INFORMATION
STRUCTURAL
CS001 STRUCTURAL NOTES
CS101 FOUNDATION PLAN
CS301 WOOD FRAMING PLAN
CS501 CONCRETE DETAILS
CS901 WOOD DETAILS
CS902 WOOD DETAILS
ARCHITECTURAL
CA001 PARTITION, WALL & ROOF TYPES
CA002 INTERIOR FINISH SCHEDULE
CA003 DOOR AND FRAME TYPES, DETAILS AND HARDWARE SCHEDULE
CA004 STOREFRONT ELEVATIONS
CA201 FLOOR PLAN
CA210 ROOF PLANS
CA261 INTERIOR FINISH AND FURNITURE & EQUIPMENT PLANS
CA271 FIRST FLOOR SIGNAGE PLAN
CA301 REFLECTED CEILING PLAN
CA401 EXTERIOR ELEVATIONS
CA402 EXTERIOR ELEVATIONS
CA410 EXTERIOR SIGNAGE ELEVATIONS
CA501 BUILDING SECTIONS
CA502 WALL SECTIONS
CA503 WALL SECTIONS
CA701 INTERIOR ELEVATIONS
CA801 EXTERIOR DETAILS
CA802 EXTERIOR DETAILS
CA803 EXTERIOR DETAILS
CA804 EXTERIOR DETAILS
CA901 INTERIOR DETAILS
CA902 INTERIOR DETAILS
PLUMBING
CP001 PLUMBING SYMBOLS, ABBREVIATIONS AND GENERAL NOTES
CP200U UNDERSLAB PLUMBING PLAN - SCALE HOUSE
CP201 FIRST FLOOR PLUMBING WASTE PLAN - SCALE HOUSE
CP301 FIRST FLOOR PLUMBING SUPPLY PLAN - SCALE HOUSE
CP701 PLUMBING ISOMETRIC - SCALE HOUSE
CP801 PLUMBING DETAILS - SCALE HOUSE
CP901 PLUMBING SCHEDULES
MECHANICAL
CM001 MECHANICAL SYMBOLS, ABBREVIATIONS AND GENERAL NOTES
CM201 FIRST FLOOR MECHANICAL PLAN
CM801 MECHANICAL DETAILS & CONTROLS
ELECTRICAL
CE001 ELECTRICAL SYMBOLS, ABBREVIATIONS AND GENERAL NOTES
CE201 FIRST FLOOR ELECTRICAL LIGHTING PLAN
CE301 FIRST FLOOR ELECTRICAL POWER PLAN
CE401 FIRST FLOOR ELECTRICAL FIRE ALARM PLAN
CE501 ELECTRICAL SECTIONS, ELEVATIONS AND ENLARGED PLANS
CE601 SCALE ELECTRICAL POWER PLAN
CE701 ELECTRICAL ONE-LINE DIAGRAM
CE801 ELECTRICAL DETAILS
CE911 ELECTRICAL SCHEDULES
CE912 ELECTRICAL PANEL SCHEDULES
TECHNOLOGY
CT000 PROJECT REQUIREMENTS & SPECIFICATIONS
CT001 PROJECT REQUIREMENTS & SPECIFICATIONS
CT002 SYMBOLS & LEGENDS
CT003 SYMBOLS & LEGENDS
CT004 SYMBOLS & LEGENDS
CT005 COMPONENTS SPECIFICATIONS & NOTES
CT201 FIRST FLOOR PLAN
CT601 SCALE PLAN
CT800 ENLARGED EQUIPMENT ROOM LAYOUTS
CT900 EQUIPMENT RACK DETAILS
CT901 SECURITY SYSTEM DETAILS
CT902 INSTALLATION DETAILS
CT903 INSTALLATION DETAILS
N O
D
E S
C R
IP
T
IO
N
D A
T E
DETAIL REFERENCE
Detail Number
Sheet Number
SECTION REFERENCE
Section Number
Sheet Number
BUILDING SECTION REFERENCE
Building Section Number
Sheet Number
INTERIOR ELEVATION
Interior Elevation Number
Sheet Number
EXTERIOR ELEVATION
Exterior Elevation Number
Sheet Number
ROOM NAME/
ROOM NUMBER
PARTITION TYPE
SPECIFIC ELEVATION NOTE
SPECIFIC PLAN NOTE
CEILING HEIGHT
WINDOW/BORROWED LIGHT TYPE
VERTICAL ELEVATION
COLUMN GRID NUMBER
NEW DOOR
REVISION
(Cloud Around Revision)
NAME
ELEVATION
ROOM NAME
RM ##
BL-#
SPECIFIC DEMOLITION NOTE#
9' - 2"
ACP-1
C.W.-07
CW-A
EXTERIOR WINDOW TYPE
PRECAST CONCRETE
CONCRETE MASONRY UNIT (SECTION)
BRICK (SECTION)
STEEL (SECTION)
RIGID INSULATION (SECTION)
EXTERIOR INSULATION AND FINISH SYSTEM (ELEVATION)
PLYWOOD (SECTION)
GRANULAR FILL
SOIL, INFILL
SOIL, UNDISTURBED
6" MAX
3' - 0" MIN 3' - 6" MIN
12" MAX
T
.O . S
E A
T
1'
" 3'
A T
A C
C E
S S
IB
LE
U N
IT
1'
NOTE:
- ALL FIXTURE MOUNTING INSTALLATION & CLEARANCE DIMENSIONS SHALL MEET ALL ADA
ACCESSIBILITY STANDARDS AND NO ACCESSORY SHALL PROJECT MORE THAN 4" FROM WALL.
- PROVIDE BLOCKING IN WALLS FOR ALL WALL MOUNTED EQUIPMENT, ACCESSORIES, AND
CABINETRY AS REQUIRED; INCLUDING OWNER ITEMS.
- ALL ITEMS SHOWN ARE NOT NECESSARILY IN THIS PROJECT.
ELONGATED RIM
GRAB BAR (GB)
1' - 6 1/2"
18" GRAB BAR (GB)
WATER CLOSET URINAL
2'
3' - 5 1/2"
TOILET PAPER
DISPENSER (TPD)
GRAB BAR (GB)
3'
3' - 3 1/2"
T O
R E
F
LE
C T
IV
E
S U
R F
A C
E
3'
2'
0"
2'
/2
M
IN
MIRROR (MIR)
BOTTOM OF
APRON
INSULATE PIPE DRAIN &
HOT WATER SUPPLY @
ALL SINKS WHERE PLAM
PANEL IS NOT SHOWN
3'
SOAP DISPENSER (SD)
T O
O P
E R
A B
LE
C
O N
T R
O
LS
3'
M A
X
T O
O P
E R
A B
LE
C
O N
T R
O
LS
3'
M A
X
2'
PAPER TOWEL DISPENSER /
RECEPTACLE (PTD/R)
SANITARY NAPKIN DISPENSER (SND)
SANITARY NAPKIN
RECEPTACLE (SNR)
T O
S P
O U
T O
U T
LE
T
3'
M A
X
2'
M
IN
ELECTRIC WATER
COOLER (EWC)
ACCESSORIES
B .O
. C A
B
IN
E T
2'
FIRE EXTINGUISHER
CABINET (FEC)
5' -0
M
A X
0L B
4' -0
M
A X
0L B
FIRE
EXTINGUISHER (FE)
SANITARY NAPKIN
RECEPTACLE (SNR)
ARCHITECTURE
ENGINEERING
INTERIOR DESIGN
MADISON, WI | WAUKESHA, WI
D R
A W
IN
G
S E
T
D A
T E
R E
V
IS
IO
N
S
P R
O
JE
C T
N O
COPYRIGHT STRANG, INC. 2026
B R
A N
D T
R O
A D
M A
D
IS
O N
, W I
C D
/3
1/
G E
N E
R A
L
IN
F O
R M
A T
IO
N
D A
N E
C O
U N
T Y
D E
P T
O F
W A
S T
E
R E
N E
W A
B
LE
S
S C
A
LE
H O
U S
E
CG001
# POUND, NUMBER
& AND
< ANGLE
@ AT
A-100 A LABEL - 100 MINUTE FIRE RATING
B-90 B LABEL - 90 MINUTE FIRE RATING
C-45 C LABEL - 45 MINUTE FIRE RATING
D-20 D LABEL - 20 MINUTE FIRE RATING
Ø DIAMETER, ROUND, PHASE
AB ANCHOR BOLT
ABBR ABBREVIATION
ACB ACOUSTICAL CEILING BAFFLE
ACOUS ACOUSTICAL
ACP ACOUSTICAL CEILING PANEL
ACR ACRYLIC, ACRYLIC MARKER BOARD
ADJ ADJUSTABLE, ADJACENT
AFF ABOVE FINISH FLOOR
AFS AIR FLOW STATION
AGGR AGGREGATE
AHU AIR HANDLING UNIT
AL ALUMINUM
ALT ALTERNATE
AP ACCESS PANEL
APPROX APPROXIMATE
ARCH ARCHITECTURAL, ARCHITECT
ASPH ASPHALT
AV AIR VALVE
AWP ACOUSTICAL WALL PANEL
BAF BAFFLES
BD BOARD
BHD BULKHEAD
BITUM BITUMINOUS
BL BORROWED LITE
BLDG BUILDING
BLKG BLOCKING
BM BEAM
BN BULLNOSE
BO BOTTOM OF
BOT BOTTOM
BP BASE PLATE
BRG BEARING
BSC BIO-SAFETY CABINET
BTU BRITISH THERMAL UNITS
BTUH BRITISH THERMAL UNITS PER HOUR
BTW BETWEEN
BUR BUILT-UP ROOF
C CONVECTOR, CHANNEL
CAB CABINET
CB CATCH BASIN
CEM CEMENT
CER CERAMIC
CFCI CONTRACTOR FURNISHED, CONTRACTOR INSTALLED
CFM CUBIC FEET PER MINUTE
CG CORNER GUARD
CH COAT HOOK
CHBD CHALKBOARD
CJ CONTROL JOINT
CL CENTER LINE
CLG CEILING
CLOS CLOSET
CLR CLEAR
CMU CONCRETE MASONRY UNIT
COL COLUMN
CONC CONCRETE
CONJ CONSTRUCTION JOINT
CONN CONNECTION
CONST CONSTRUCTION
CONT CONTROL
CONTR CONTRACTOR
CORR CORRIDOR
CPT SHEET CARPETING
CR CARD READER
CS CAST STONE
CT CERAMIC TILE
CTR CENTER
CTSK COUNTERSINK
CU CONDENSING UNIT
CUH CABINET UNIT HEATER
CYL CYLINDER
D DEPTH
DBA DECK BEARING ANGLE
DBL DOUBLE
DEMO DEMOLITION, DEMOLISH
DEPT DEPARTMENT
DF DRINKING FOUNTAIN
DIA DIAMETER
DIAG DIAGONAL
DIM DIMENSION
DISP DISPENSER
DN DOWN
DO DO OVER, DITTO
DP DAMPPROOFING
DR DOOR
DS DOWNSPOUT
DSD DUCT SMOKE DETECTOR
DT DRAIN TILE
DTL DETAIL
DWG DRAWING
DWL DOWEL
E EAST
EA EACH, EXHAUST AIR
EC ELECTRICAL CONTRACTOR, EXPOSED CONCRETE
EF EXHAUST FAN
EHD ELECTRIC HAND DRYER
EIFS EXTERIOR INSULATION FINISH SYSTEM
EJ EXPANSION JOINT
EL ELEVATION
ABBREVIATIONS MATERIAL LEGEND
SYMBOL LEGEND
ELEC ELECTRICAL
ELEV ELEVATOR
EMER EMERGENCY
ENCL ENCLOSURE
EP ELECTRIC PANEL, EPOXY
EQ EQUAL
EQUIP EQUIPMENT
ES EXPOSED STRUCTURE
ETR EXISTING TO REMAIN
EW EACH WAY
EWC ELECTRIC WATER COOLER
EWH ELECTRIC WATER HEATER
EXH EXHAUST
EXP EXPANSION
EXPO EXPOSED
EXST EXISTING
EXT EXTERIOR
FA FIRE ALARM
FB FACE BRICK, FLOOR BOX
FCTY FACTORY
FD FLOOR DRAIN
FDN FOUNDATION
FE FIRE EXTINGUISHER
FEB FIRE EXTINGUISHER BRACKET
FEC FIRE EXTIINGUISHER CABINET
FF FINISH FLOOR
FFLR FITNESS FLOOR
FH FUME HOOD, FIRE HOSE
FHC FIRE HOSE CABINET
FIN FINISH
FIX FIXTURE
FL FLOOR
FLUOR FLUORESCENT
FO FINISHED OPENING
FOC FACE OF CONCRETE
FOS FACE OF STUD
FPRF FIREPROOFING
FRP FIBERGLASS REINFORCED PLASTIC, FIBERGLASS
REINFORCED PANELING
FRT FIRE RETARDANT
FRZ FREEZER
FT FOOT, FEET
FTG FOOTING
FURR FURRING
FUT FUTURE
FV FIELD VERIFY
G GAS
GA GAUGE
GALV GALVANIZED
GB GRAB BAR
GC GENERAL CONTRACTOR
GFRG GLASS FIBER REINFORCED GYPSUM
GL GLASS
GND GROUND
GWB GYPSUM WALL BOARD
GYP GYPSUM
H HIGH
HB HOSE BIBB
HBD HARDBOARD
HC HOLLOW CORE
HDWD HARDWOOD
HDWE HARDWARE
HM HOLLOW METAL
HORIZ HORIZONTAL
HP HORSEPOWER
HPC HIGH PERFORMANCE COATING
HR HOUR
HSS HOLLOW STRUCTURAL STEEL
HT HEIGHT
HVAC HEATING, VENTILATION, & AIR CONDITIONING
HWD HARDWOOD
ID INSIDE DIAMETER
IE INVERT ELEVATION
IF INSIDE FACE
IMP INSULATED METAL PANEL
INSUL INSULATION
INT INTERIOR
ITD IMPACT TRAFFIC DOOR
JAN JANITOR
JBE JOIST BEARING ELEVATION
JT JOINT
KIT KITCHEN
KO KNOCKOUT
KP KICK PLATE
KS KNEE SPACE
L LENGTH, ANGLE
LAB LABORATORY
LAM LAMINATE
LAV LAVATORY
LLH LONG LEG HORIZONTAL
LLV LONG LEG VERTICAL
LT LIGHT
LVT LUXURY VINYL TILE
LWC LIGHT WEIGHT CONCRETE
MATL MATERIAL
MAX MAXIMUM
MB MOP BASIN
MC MECHANICAL CONTRACTOR
MECH MECHANICAL
MEMB MEMBRANE
MEP MECHANICAL, ELECTRICAL, PLUMBING
MEZZ MEZZANINE
MFR MANUFACTURER
MH MANHOLE, MOP HOLDER
MIN MINIMUM
MIR MIRROR
MISC MISCELLANEOUS
ML&P METAL LATH & PLASTER
MO MASONRY OPENING
MTD MOUNTED
MTL METAL
MUL MULLION
N NORTH
NIC NOT IN CONTRACT
NO NUMBER
NOM NOMINAL
NP NON POTABLE WATER
NTS NOT TO SCALE
OA OVERALL, OUTSIDE AIR
OC ON CENTER
OD OUTSIDE DIAMETER
OFCI OWNER FURNISHED CONTRACTOR INSTALLED
OFF OFFICE
OFOI OWNER FURNISHED OWNER INSTALLED
OH OVERHEAD
OHCD OVERHEAD COILING DOOR
OHSD OVERHEAD SECTIONAL DOOR
OP OPERABLE PARTITION
OPG OPENING
OPNG OPENING
OPP OPPOSITE
OPP-H OPPOSITE HAND
PA PUBLIC ADDRESS
PC PLUMBING CONTRACTOR
PCON POLISHED CONCRETE
PDO POWER DOOR OPERATOR
PERP PERPENDICULAR
PL PLATE, PROPERTY LINE
PLAM PLASTIC LAMINATE
PLAM PLASTIC LAMINATE
PLAS PLASTER
PLBG PLUMBING
PLYWD PLYWOOD
PR PAIR
PT PAINT
PTD PAPER TOWEL DISPENSER
PTD/R PAPER TOWEL DISPENSER / RECEPTACLE
PTN PARTITION
PTR PAPER TOWEL RECEPTACLE
PVT PAVER TILE
QSM QUARTZ SURFACING MATERIAL
QT QUARRY TILE
R RADIUS, RISER
RA RETURN AIR
RB RESILIENT BASE
RBC RESILIENT BASE COVED
RBS RESILIENT BASE STRAIGHT
RD ROOF DRAIN
REF REFERENCE, REFRIGERATOR
REFR REFRIGERATOR
REINF REINFORCED
REM REMOVE
REQ REQUIRED
REQD REQUIRED
RF RESINOUS FLOORING
RM ROOM, RATED METAL
RO ROUGH OPENING
RSF RUBBER SHEET FLOORING
RSF RUBBER SHEET FLOORING
RT RUBBER TILE
RTF RUBBER TILE FLOORING
RUB RUBBER
RWD REDWOOD
S SOUTH, SINK, SUPPLY
S&V STAIN & VARNISH
SAB SOUND ATTENUATION BLANKET
SAN SANITARY
SB SOIL BORING
SC SOLID CORE
SCD SEAT COVER DISPENSER
SCHED SCHEDULE
SCON SEALED CONCRETE
SD SOAP DISPENSER
SECT SECTION
SF SQUARE FOOT
SH SHELF
SHR SHOWER
SHT SHEET
SIM SIMILAR
SND SANITARY NAPKIN DISPENSER
SNR SANITARY NAPKIN RECEPTACLE
SOG SLAB ON GRADE
SPEC SPECIFICATION
SQ SQUARE
SS STAINLESS STEEL
SSM SOLID SURFACE MATERIAL
ST STONE
STA STATION
STD STANDARD
STL STEEL
STOR STORAGE
STRUC STRUCTURAL
SUSP SUSPENDED
SWC SUSPENDED WOOD CEILING
SYM SYMMETRICAL
T TREAD, THRESHOLD
T&B TOP & BOTTOM
T&G TONGUE & GROOVE
TEL TELEPHONE
TEMP TEMPORARY, TEMPERATURE
TER TERRAZZO
THK THICK
TKBD TACK BOARD
TOB TOP OF BEAM
TOF TOP OF FOOTING
TOS TOP OF STEEL
TPD TOILET PAPER DISPENSER
TRANS TRANSPARENT
TRZ TERRAZZO
TV TELEVISION
TW TOP OF WALL
TYP TYPICAL
UH UNIT HEATER
UNF UNFINISHED
UNO UNLESS NOTED OTHERWISE
UR URINAL
V VENT, VOLT, VALVE
VAC VACUUM
VCT VINYL COMPOSITION TILE
VERT VERTICAL
VEST VESTIBULE
VIF VERIFY IN FIELD
VSF VINYL SHEET FLOORING
VTR VENT THROUGH ROOF
VWC VINYL WALL COVERING
TWC TACKABLE WALL COVERING
W WEST, WIDTH, WIDE, WATT, WASTE, WATER
W/ WITH
W/O WITHOUT
WB WOOD BASE
WC WATER CLOSET
WD WOOD
WF WIDE FLANGE
WM WIRE MESH
WP WATERPROOF, WEATHERPROOF, WALL PROTECTION
WR WATER RESISTANT, WATER RECEPTACLE
WT WEIGHT
WWF WELDED WIRE FABRIC
YD YARD
STANDARD MOUNTING HEIGHTS
N O
D
E S
C R
IP
T
IO
N
D A
NOT TO SCALE
LIFE SAFETY PLAN LEGEND
NOT TO SCALE
LIFE SAFETY PLAN LEGEND
FIRE EXTINGUISHER CABINET (FEC)
EGRESS WIDTH AND DIRECTION
67" Ø WHEELCHAIR TURNING SPACE
FEC
EXIT0"##
AED FA OFOI ITEMS: AUTOMATED
EXTERNAL DEFIBRILLATOR
(AED) AND FIRST AID KIT (FA)
30" x 52" CLEAR FLOOR SPACE
T-SHAPED TURNING SPACE 304.3.2.1(B)
CLASSIFICATION OF WORK:
New Building
BUILDING AREA:
First Floor 814 gross sq. ft.
BUILDING HEIGHT:
One story above grade plane 12' - 8" to highest point of roof
PRIMARY BUILDING USES: (IBC 2021 Chapter 3)
MIXED USE
Occupancies Occupancy group Floor area Office Areas Group B, Business 814 gsf
TYPE OF CONSTRUCTION: (IBC 2021 Chapter 6) 5B
FIRE SPRINKLER SYSTEM:
None
FIRE ALARM SYSTEM:
Fire Alarm Initiation and Notification Devices
ALLOWABLE AREA CALCULATIONS: (IBC 2021 Table 506.2) 9,000 sq. ft. Allowable Area per B Occupancy, Non-Sprinklered
ALLOWABLE HEIGHT CALCULATIONS: (IBC 2021 Tables 504.3 and 504.4) 1 story 40 feet Allowable Height per B Occupancy, Non-Sprinklered
FIRE RESISTANCE RATINGS: (IBC 2021 Table 601) Primary Structural Frame 0 Hour Bearing Walls, Exterior 0 Hour Bearing Walls, Interior 0 Hour Floor Construction 0 Hour Roof Construction 0 Hour
OCCUPANT LOAD CALCULATIONS: (IBC 2021 Table 1004.5) Business Areas 814 gsf / 150 = 6 persons
PLUMBING FIXTURE CALCULATIONS: (IBC 2021 Table 2902.1)
Type of Use Occupant load Water closets Lavatories Drinking Service fountains sink
Group B 6 0.25 0.15 0** 0***
Total required for 1 1 0 0 entire building
Total provided for entire building 1* 1* 0 1
Notes * Restroom facility for staff only. Restroom facilities for public convenience are provided in adjacent Education and Admin Center.
** IBC 2902.6
*** Table 2902.1, Footnote "e"
CODE INFORMATION
EXIT WIDTH CALCULATIONS: (IBC 2021 Section 1005.3.1 & 1005.3.2)
Non-Sprinkled
Stairs, Required Stairs, Provided Other Egress, Required Other Egress, Provided
N/A NA 6 persons x 0.2 = 1.2 inches 33 inches
APPLICABLE CODES:
Wisconsin Commercial Building Code Accessibility: ICC/ANSI A117.1-2017 Edition Commercial Building: 2021 IBC as amended Electrical: 2017 NEC as amended Energy Conservation: 2021 IECC as amended Fire Protection: 2021 IFC as amended Mechanical: 2021 IMC as amended Plumbing: 2021 IPC as amended
C101
OBSERVATION DECK
C102
CORRIDOR
C103
UNISEX
C105
ELECTRICAL / IT
EXIT DIST: 53' - 2"
E X
IT
33"
C106
MECH / JAN
ACCESSIBLE RESTROOM
FEC AEDFA
C104
BREAK ROOM
5' - 0"
5'
DN
ACCESSIBLE ENTRANCE
ARCHITECTURE
ENGINEERING
INTERIOR DESIGN
MADISON, WI | WAUKESHA, WI
D R
A W
IN
G
S E
T
D A
T E
R E
V
IS
IO
N
S
P R
O
JE
C T
N O
COPYRIGHT STRANG, INC. 2026
B R
A N
D T
R O
A D
M A
D
IS
O N
, W I
C D
/3
1/
LI
F
E S
A F
E T
Y P
LA
N
C
O D
E
IN
F O
R M
A T
IO
N
D A
N E
C O
U N
T Y
D E
P T
O F
W A
S T
E
R E
N E
W A
B
LE
S
S C
A
LE
H O
U S
E
CG002
GENERAL LIFE SAFETY PLAN NOTES
1 ALL DOOR LEAVES ARE 36" WIDE WITH 33" CLEAR EGRESS WIDTH, UNLESS NOTED
OTHERWISE.
2 WIDTHS NOTED ON LIFE SAFETY PLANS ARE CLEAR EGRESS WIDTHS
3 SEE SITE PLAN FOR ACCESSIBLE ROUTE TO ACCESSIBLE PARKING STALLS.
PNTN
SCALE: 1/4" = 1'-0"CG002
1 FIRST FLOOR LIFE SAFETY PLAN
N O
D
E S
C R
IP
T
IO
N
D A
LOADING
1. DESIGNED IN ACCORDANCE WITH THE CURRENT WISCONSIN COMMERCIAL BUILDING CODE BASED ON THE
2021 INTERNATIONAL BUILDING CODE.
2. DESIGN LOADS:
A. DEAD LOADS:
ROOF = 22 PSF (INCLUDES 5 PSF FOR FUTURE SOLAR PANELS)
B. LIVE LOADS:
ROOF = 20 PSF (REDUCEIBLE)
PRIVATE ROOMS AND CORRIDORS SERVING THEM = 40 PSF (REDUCIBLE)
PUBLIC ROOMS AND CORRIDORS SERVING THEM = 100 PSF
PARTITIONS = 15 PSF
C. DESIGN SNOW LOAD:
Pg = 30 PSF Pf = 0.7(Ce)(Ct)(I)(Pg) = 23.1 PSF Ce = 1.0 Cs = 1.0 Ct = 1.1 I = 1.0
DRIFTED SNOW, PER CODE: SEE PLAN
D. WIND DESIGN CRITERIA
ULTIMATE WIND SPEED = 107 MPH
NOMINAL WIND SPEED = 82.9 MPH
EXPOSURE = C
I = 1.0 Kzt = 1.0 GCpi = +/- 0.18
G. SEISMIC DESIGN CRITERIA
SEISMIC USE GROUP = II
SITE CLASS = D
SS = 0.076 S1 = 0.048
SDS = 0.081; SD1 = 0.077
SEISMIC DESIGN CATEGORY = B
SEISMIC RESISTING SYSTEM = LIGHT FRAME WALLS WITH SHEAR PANELS - OTHER
R = 2.0
DESIGN BASE SHEAR (FX)= 0.041*W
CONCRETE CONSTRUCTION
1. ALL CONCRETE DESIGN AND CONSTRUCTION SHALL CONFORM TO THE LOCAL BUILDING CODE REQUIREMENTS AND THOSE OF THE LATEST EDITION OF THE FOLLOWING STANDARDS: ACI 318, ACI 315, ACI 301, AND ACI 305 & 306.
2. ALL CONCRETE UNLESS SPECIFICALLY NOTED SHALL BE NORMAL WEIGHT (145 PCF) AND SHALL ACHIEVE A MINIMUM 28 DAY COMPRESSIVE STRENGTH (fc') AS FOLLOWS:
a. FOOTINGS BELOW FROST LINE: f'c = 3,000 PSI
b. EXTERIOR FOUNDATION WALLS AND GRADE BEAMS
THAT ARE EXPOSED TO FREEZING: f'c = 4,000 PSI
c. INTERIOR AND EXTERIOR SLAB ON GROUND: f'c = 4,000 PSI
e. CONCRETE BEAMS, JOIST, & COLUMNS: f'c = 4,000 PSI
f. ALL OTHER CONCRETE: f'c = 3,000 PSI
3. ALL CONCRETE SUBJECT TO EXTERIOR EXPOSURE SHALL BE AIR ENTRAINED TO 6% (+/- 1.5% ) AND HAVE A MAXIMUM 1.5” AGGREGATE. ALL CONCRETE WITHOUT SUPERPLASTICIZERS SHALL HAVE A MAXIMUM SLUMP OF 4” ± 1".
4. CONCRETE SLABS ON GROUND CONTAINING REINFORCEMENT SHALL PLACE ALL REINFORCING BARS AND WWF ON CHAIRS, TIED IN PLACE, AND LOCATED IN THE MIDDLE TO THE UPPER ONE-THIRD OF THE SLAB. LIFTING REINFORCING AFTER CONCRETE IS PLACED IS NOT CONSIDERED TO BE AN EFFECTIVE MEANS OF PLACEMENT AND SHALL NOT BE ALLOWED WITHOUT PRIOR WRITTEN CONSENT OF THE ENGINEER. WELDED WIRE REINFORCEMENT FABRIC SHALL BE SUPPORTED WITH APPROVED MATERIALS OR SUPPORTS AT SPACING NOT TO EXCEED 3 FEET OR IN ACCORDANCE WITH THE MANUFACTURER'S SPECIFICATIONS. WELDED PLAIN WIRE REINFORCEMENT FABRIC FOR CONCRETE SHALL CONFORM TO
ASTM A 185.
5. ALL CONCRETE MIX DESIGNS SHALL MINIMIZE SHRINKAGE AS MUCH AS IS PRACTICAL. INCLUDING SELECTION OF
AGGREGATE TYPE, SIZE, GRADATIONS W/ C RATIO AND ADD MIXTURES.
6. UNLESS THE MIX DESIGN INCLUDES THE USE OF SUPERPLASTICIZERS, CONCRETE WITH A SLUMP GREATER THAN 5” SHALL
BE REFUSED.
7. ALL CONCRETE REINFORCING STEEL TO BE ASTM A615 GRADE 60. ALL WELDED WIRE FABRIC (WWF) TO BE ASTM A - 185.
ALL REINFORCING SHALL BE DETAILED AND PLACED IN ACCORDANCE WITH ACI 315 AND 315R.
8. ALL REINFORCING BARS AND WWF SHALL BE SET ON CHAIRS AND TIED IN PLACE.
9. AFTER CONCRETING HAS STARTED, IT SHALL BE CARRIED ON AS A CONTINUOUS OPERATION UNTIL PLACING OF A PANEL OR SECTION, AS DEFINED BY ITS BOUNDARIES OR PREDETERMINED JOINTS, IS COMPLETED. CONCRETE SHALL BE DEPOSITED AS NEARLY AS PRACTICABLE TO ITS FINAL POSITION TO AVOID SEGREGATION DUE TO REHANDLING OR
FLOWING.
10. CONCRETING OPERATIONS SHALL BE CARRIED ON AT SUCH A RATE THAT THE CONCRETE IS AT ALL TIMES PLASTIC AND
FLOWS READILY INTO SPACES BETWEEN REINFORCEMENT.
11. CONCRETE SHALL BE THOROUGHLY CONSOLIDATED BY SUITABLE MEANS DURING PLACEMENT AND SHALL BE THOROUGHLY WORKED AROUND REINFORCEMENT AND EMBEDDED FIXTURES AND INTO CORNERS OF THE FORMS. THE TOP
SURFACES OF VERTICALLY FORMED LIFTS SHALL BE GENERALLY LEVEL.
12. CONCRETE SHALL BE CURED ABOVE 50°F (10°C) AND IN A MOIST CONDITION FOR AT LEAST THE FIRST SEVEN DAYS AFTER PLACEMENT. DO NOT PLACE CONCRETE WHEN DURING ANY POINT IN THE DAY THE MEAN DAYLIGHT TEMPERATURE
IS LESS THAN 20°F.
13. ALL FLAT WORK CONCRETE SHALL BE COVERED IMMEDIATELY FOLLOWING SAW CUTTING AND MAINTAINED CONTINUOUSLY WET FOR A MINIMUM OF 7-DAYS AFTER PLACING. CURING SHEETS ARE TO BE USED AND REMAIN IN PLACE. CURING COMPOUNDS MAY BE USED APPLIED MUST BE APPLIED PER THE MANUFACTURES RECOMMENDATIONS. SUBMIT PRODUCT
DATA TO A/E FOR APPROVAL.
14. RETEMPERED CONCRETE, CONCRETE THAT HAS BEEN REMIXED AFTER INITIAL SET OR PARTIALLY HARDENED SHALL NOT
BE USED IN THE STRUCTURE.
15. ALL LAPS SHALL BE “B” SPLICES UNLESS NOTED OTHERWISE ON THE DRAWINGS OR UNLESS SPECIAL CARE IS TAKEN FOR
THE REINFORCING TO BE DETAILED AND PLACED TO PROVIDE STAGGERED LAPS.
16. UNLESS OTHERWISE APPROVED, ALL EXPOSED CONCRETE WALLS SHALL BE CURED WITH FORMS LEFT IN PLACE FOR SEVEN DAYS. IF FORMS CAN NOT BE LEFT IN PLACE THE CONTRACTOR SHALL SUBMIT IN WRITING TO THE ENGINEER ALL
PROPOSED CURING METHODS.
17. WALL CRACKS DUE TO IMPROPER CURING METHODS, OR WEATHER PROTECTION SHALL BE THE RESPONSIBILITY OF THE
CONTRACTOR.
18. UNLESS NOTED OTHERWISE ON THE DRAWINGS ALL REINFORCING SHALL BE LAPPED TO DEVELOP ITS CAPACITY AS
FOLLOWS:
19. SLAB ON GRADE SHALL HAVE A CLASS "A" TOLERANCE.
20. A 10-MIL. (MIN.) POLYETHYLENE VAPOR BARRIER WITH JOINTS LAPPED NOT LESS THAN 6” SHALL BE PLACED BETWEEN
THE BASE COURSE OR SUBGRADE AND THE CONCRETE FLOOR.
21. CALCIUM CHLORIDE AND OR ADMIXTURES CONTAINING CALCIUM CHLORIDE SHALL NOT BE USED.
22. PLACING OF CONCRETE SHALL BE DONE IN CONFORMANCE WITH ACI-306 FOR COLD WEATHER AND ACI-305 FOR HOT
WEATHER.
23. FLOOR SLAB CONTROL JOINTS SHALL FOLLOW THE INTENT SHOWN ON THE PLAN BUT SHALL NOT EXCEED AN ASPECT RATIO OF 1.5 TO 1.0. ALL REENTRANT CORNERS SHALL HAVE CONTROL JOINTS EXTENDING OUT FROM THE INSIDE
CORNER. DEAD-END “T” CONTROL JOINTS INTO CONTINUOUS JOINTS SHALL BE AVOIDED.
24. NO TACK WELDING WILL BE PERMITTED ON ASTM A615 GRADE 40 OR 60 STEEL.
25. CONSTRUCTION JOINTS SHALL BE LOCATED AT CONTROL JOINTS OR CONTRACTION JOINTS.
26. ALL SLAB-ON-GRADE SHALL UTILIZE 1.5 INCH TOP AGGREGATE IN AN EVENLY DISTRIBUTED AGGREGATE GRADATION.
27. PIPE SLEEVES OVER 1 1/2" IN DIAMETER WHICH PASS THROUGH CONCRETE WALLS OR SLABS SHALL BE SCHEDULE 40 GALVANIZED STEEL PIPE. ALL OTHER SLEEVES SHALL BE 18 GAUGE SHEET METAL. SLEEVES SHALL BE ON SIZE LARGER THAN OUTSIDE DIAMETER OF THE PIPE PASSING THROUGH THE SLEEVE. VERIFY SIZE AND NUMBER WITH MECHANICAL, ELECTRICAL, AND PLUMBING CONTRACTOR.
28. ALUMINUM CONDUIT SHALL NOT BE EMBEDDED IN CONCRETE.
CONCRETE COMPRESSIVE STRENGTH f'c=3,000 PSI
#3
UNCOATED STANDARD & CLASS "B" TENSION LAP LENGTHS1, 5
CONCRETE COMPRESSIVE STRENGTH f'c=4,000 PSI
BAR
SIZE
BTM
BARS
TOP
BARS4
BTM
BARS
TOP
BARS4
STD DEVLOPMENT
LENGTH2
CLASS "B" TENSION
LAP LENGTH3
STD DEVLOPMENT
LENGTH2
CLASS "B" TENSION
LAP LENGTH3
BAR
SIZE
BTM
BARS
TOP
BARS4
BTM
BARS
TOP
BARS4
#4
#5
#6
#7
#8
#3
#4
#5
#6
#7
#8
17"
22"
28"
33"
48"
55"
22"
29"
36"
43"
63"
72"
22"
29"
36"
43"
63"
72"
28"
38"
47"
56"
81"
93"
15"
19"
24"
29"
42"
48"
19"
25"
31"
37"
54"
62"
19"
25"
31"
37"
54"
62"
25"
33"
41"
49"
71"
81"
NOTES:
1. BASED ON _d VALUES FROM SECTION 25.4.2.2 IN ACI 318-14:
1.1 GRADE 60 REINFORCEMENT BARS
1.2 NORMAL WEIGHT CONCRETE (_=1.0)
1.3 NON-EPOXY COATED BARS (_=1.0)
1.4 CLEAR COVER > 1.0db; CLEAR SPACING > 2.0db; NOTIFY ENGINEER IF COVER NOT MET.
2. STANDARD LAB SPLICES ARE TO BE USED WHEN < 50% OF BARS ARE LAPPED AT THE SAME LOCATION, INCLUDING TEMPERATURE AND SHRINKAGE LAP SPLICES.
2.1 PROVIDE CLASS B LAP SPLICES UNLESS DETAILED AND APPROVED BY ENGINEER.
3. CLASS B LAP SPLICES ARE TO BE USED WHEN > 50% OF BARS ARE LAPPED AT THE SAME LOCATION, INCLUDING TEMPERATURE AND SHRINKAGE LAP SPLICES.
4. HORIZONTAL (TOP) BARS HAVE MORE THAN 12" OF FRESH CONCRETE PLACED BELOW
REINFORCEMENT.SPLICE LENGTHS ARE ROUNDED UP TO THE NEAREST INCH.
GENERAL
1. THE CONTRACTOR SHALL FIELD VERIFY ALL DIMENSIONS AND EXISTING CONDITIONS PRIOR TO CONSTRUCTION. NOTIFY THE ENGINEER AND
ARCHITECT OF ANY DISCREPANCY IMMEDIATELY.
2. THE CONTRACTOR IS RESPONSIBLE FOR LIMITING THE AMOUNT OF CONSTRUCTION LOAD IMPOSED UPON NEW OR EXISTING STRUCTURAL FRAMING. CONSTRUCTION LOADS SHALL NOT EXCEED THE DESIGN CAPACITY OF THE FRAMING AT THE TIME THE LOADS ARE IMPOSED.
3. THE STRUCTURE IS DESIGNED TO FUNCTION AS A UNIT UPON COMPLETION. THE CONTRACTOR IS RESPONSIBLE FOR HAVING AN INDEPENDENT ENGINEER DESIGN AND FURNISH ALL TEMPORARY BRACING AND/ OR SUPPORT THAT MAY BE REQUIRED AS THE RESULT OF THE CONTRACTOR'S CONSTRUCTION METHODS AND/OR SEQUENCES. THE STRUCTURAL ENGINEER SEAL ON THESE DRAWINGS ASSUMES
NO LIABILITY FOR THE STRUCTURE DURING CONSTRUCTION.
4. THE CONTRACTOR IS RESPONSIBLE FOR ALL MEANS AND METHODS OF CONSTRUCTION AND ALL JOB SITE SAFETY.
5. THE CONTRACTOR IS RESPONSIBLE FOR COORDINATION OF ALL BUILDING MATERIALS AND COMPONENTS. COMPONENT LOCATIONS ARE SHOWN FOR DESIGN INTENT, NOT EXACT LOCATION, UNLESS NOTED SPECIFICALLY. INDEPENDENTLY PREPARED SHOP DRAWINGS ARE REQUIRED OF ALL TRADES FOR COORDINATION AND BEST PRACTICE. ERRORS OR OMISSIONS IN INSTALLATION DUE TO THE CONTRACTOR'S
FAILURE TO COORDINATE THE WORK WILL BE THE SOLE RESPONSIBILITY OF THE CONTRACTOR
6. THE CONTRACTOR SHALL BE RESPONSIBLE FOR FIELD VERIFICATION OF ALL CONDITIONS PRIOR TO BIDDING. THIS INCLUDES INSURING ERECTION CAN BE PERFORMED AS DETAILED ON THE PLANS. IF MODIFICATIONS ARE NEEDED TO FACILITATE ERECTABILITY THE BIDDING CONTRACTOR SHALL NOTIFY THE OWNER, ARCHITECT AND ENGINEER AND CLEARLY COMMUNICATE ASSUMPTIONS IN BID DOCUMENTS.
7. THE CONTRACTOR SHALL SUBMIT SHOP DRAWINGS.
a. ALL SHOP DRAWINGS MUST BE THOROUGHLY REVIEWED BY THE CONTRACTOR AND STAMPED AS REVIEWED PRIOR TO SUBMITTING TO
THE ENGINEER FOR FURTHER REVIEW.
b. THE CONTRACTOR SHALL PROVIDE THEIR REVIEWED SUBMITTAL TO THE ENGINEER IN PDF FORMAT.
c. THE OMISSION OF SHOP DRAWINGS OF ANY MATERIAL SHALL NOT RELIEVE THE CONTRACTOR OF THE RESPONSIBILITY OF FURNISHING
AND INSTALLING SUCH MATERIALS.
8. THIS BUILDING MEETS ALL OF THE EXEMPTIONS FOR SPECIAL INSPECTIONS.
MISCELLANEOUS
1. ALL DRAWINGS ARE OF EQUAL IMPORTANCE IN DEFINING THE WORK OF THE CONTRACT DOCUMENTS.
CONTRACTOR SHALL CAREFULLY REVIEW AND COMPARE ALL DRAWINGS DURING THE BIDDING PERIOD AND BEFORE INSTALLATION OF THEIR WORK. ANY INCONSISTENCIES IN THE DRAWINGS SHALL BE
REPORTED PROMPTLY TO THE ENGINEER AND ARCHITECT FOR CLARIFICATION.
2. EVERY EFFORT HAS BEEN MADE TO PROVIDE TO SCALE DRAWINGS, HOWEVER THE DRAWINGS ARE NOT
NECESSARILY TO SCALE - USE GIVEN DIMENSIONS.
3. ALL ANCHOR BOLTS SHOULD HAVE A MIN SPACING OF 6*BOLT DIAMETER FROM EACH OTHER AND EDGE
OF PIER/BUILDING LINE.
4. ALL WINDOW FRAMES SHALL BE INSTALLED TO ALLOW FOR A MINIMUM OF L/600 OR 1/2 INCH
VERTICAL DEFLECTION OF THE HEADER WHICHEVER IS LESS.
5. DIMENSIONS OF EXISTING CONSTRUCTION OR CONSTRUCTION IN PROGRESS SHALL BE VERIFIED AND
COORDINATED PRIOR TO FABRICATION OF STRUCTURAL COMPONENTS.
STRUCTURAL WOOD FRAMING
1. TIMBER DESIGN AND INSTALLATION SHALL CONFORM TO THE LATEST EDITION OF THE NATIONAL DESIGN
SPECIFICATION FOR WOOD CONSTRUCTION.
2. ALL WOOD FRAMING SHALL CONFORM TO THE FOLLOWING MINIMUM STRENGTH AND GRADING CRITERIA UNLESS SPECIFICALLY SHOWN DIFFERENT ON PLAN. IF SPECIFIC SPECIES AND GRADE OF LUMBER IS
UNAVAILABLE CONTACT MP-SQUARED STRUCTURAL ENGINEERS FOR SUITABLE SUBSTITUTIONS.
3. ALL CALCULATIONS HAVE BEEN BASED ON NAILS WITH PROPERTIES AS SHOWN IN THE TABLE BELOW.
NAIL SUBSTITUTIONS SHALL HAVE EQUAL OR GREATER DIAPHRAGM AND SHEAR CONNECTION
CAPACITIES PER LATEST ICC ESR - 1539 REPORTS.
8D MINIMUM REQUIRED FOR ALL ROOF CONSTRUCTION.
4. ALL CONNECTIONS IN CONTACT WITH PRESERVATIVE TREATED WOOD SHALL HAVE A HOT - DIP GALVANIZED COATING OR THE SPECIFIC COATING SHALL BE SUBMITTED TO AND APPROVED BY THE
PROJECT ARCHITECT.
5. ALL SIZES SHOWN FOR TIMBER MEMBERS ARE STANDARD NOMINAL DIMENSIONS.
6. PLYWOOD PANELS SHALL BE APA GRADED STRUCTURAL PLYWOOD OR OSB SHEATHING.
7. ALL EXTERIOR EXPOSED TIMBER MEMBERS, WOOD MEMBERS IN DIRECT CONTACT WITH FOUNDATIONS OR EXTERIOR MASONRY AND INTERIOR MEMBERS NOTED TO BE PRESSURE TREATED WITH A NON-
ARSENATE COMPOUNDS (ACQ PREFERRED).
8. SHOP DRAWINGS SHALL BE PROVIDED TO THE ARCHITECT AND ENGINEER OF RECORD.
9. ALL BOLTS, LAG SCREWS, SCREWS AND NAILS SHALL HAVE A HOT DIP GALVANIZED FINISH.
10. SIMPSON STRONG-TIE CONNECTORS ARE SPECIFICALLY REQUIRED TO MEET THE STRUCTURAL CALCULATIONS OF PLAN. BEFORE SUBSTITUTING ANOTHER BRAND, CONFIRM LOAD CAPACITY BASED ON RELIABLE PUBLISHED TESTING DATA OR CALCULATIONS. THE ENGINEER OF RECORD IS REQUIRED TO
EVALUATE AND GIVE WRITTEN APPROVAL FOR SUBSTITUTION PRIOR TO INSTALLATION.
11. ALL SIMPSON CONNECTORS SHALL BE ZMAX (G185) OR HOT - DIP GALVANIZED (HDG).
12. THE CONTRACTOR SHALL SUBMIT FOR REVIEW PRIOR TO CONSTRUCTION (1) ONE SET OF
CONSTRUCTION PLANS PROVIDED BY THE ROOF TRUSS PROVIDER
13. THE INSTALLATION OF BOLTS IN TIMBER MEMBERS SHALL MEET THE REQUIREMENTS OF ANSI/ASME
STANDARD B18.2.1
14. BOLT HOLES IN TIMBER MEMBERS SHALL BE A MINIMUM OF 1/32” TO A MAXIMUM OF 1/16” LARGER THAN THE BOLT DIAMETER. HOLES SHALL BE ACCURATELY ALIGNED IN MAIN AND SIDE MEMBERS.
BOLTS SHALL NOT BE FORCIBLY DRIVEN.
15. A STANDARD CUT WASHER, METAL PLATE OR STEEL STRAP OR PLATE, OF SIZE NOT LESS THAN THE
STANDARD CUT WASHER, SHALL BE BETWEEN THE WOOD AND THE BOLT HEAD AND BETWEEN THE
WOOD AND THE NUT.
USE GRADE Fb (psi) Fc (psi) E (psi)
STUDS SOLID SAWN SPF SELECT
CONSTRUCTION
1,000 1,400 1,300,000
STUDS
MANUFACTURED
TIMBERSTRAND
LSL
2,250 1,950 1,500,000
BEAM
2x4 - 2x10
SPF No. 1 / No. 2
875 1,150 1,400,000
BEAM 2x12 SPF No. 1 / No. 2
875 1,150 1,400,000
BEAM
MANUFACTURED
LVL OR PSL 2,600 2,500 2,000,000
NAIL TYPE LENGTH (in) DIAMETER (in) HEAD (in)
2 .099 .2666d
2.5 .113 .2978d
3 .128 .31210d
3.5 .135 .34416d
FABRICATED WOOD TRUSSES
1. FABRICATE, SUPPLY, AND ERECT WOOD TRUSSES AS SHOWN ON THE DRAWINGS AND AS SPECIFIED. WORK TO INCLUDE ANCHORAGE, BLOCKING, CURBING, MISCELLANEOUS INCIDENTAL FRAMING AND BRACING.
2. TRUSSES SHALL BE DESIGNED IN ACCORDANCE WITH NATIONAL DESIGN SPECIFICATION FOR WOOD CONSTRUCTION, AFPA, AND NATIONAL DESIGN STANDARD FOR METAL PLATE CONNECTED WOOD TRUSS CONSTRUCTION, ANSI/ TPI 1 - 2015, AND THE CURRENT WISCONSIN COMMERCIAL BUILDING CODE.
3. FABRICATOR SHALL FURNISH DESIGN DRAWINGS & LAYOUT DRAWINGS BEARING THE SEAL AND
REGISTRATION NUMBER OF DESIGN PROFESSIONAL LICENSED IN THE STATE OF WISCONSIN.
4. DRAWINGS SHALL BE APPROVED BY THE ARCHITECT AND ENGINEER PRIOR TO FABRICATION.
5. LUMBER USED SHALL BE IDENTIFIED BY GRADE MARK OF A LUMBER INSPECTION BUREAU OR AGENCY APPROVED BY BOARD OF REVIEW OF AMERICAN LUMBER STANDARDS COMMITTEE, AND SHALL BE SIZE, SPECIES, AND GRADE IN ACCORDANCE WITH DESIGN DRAWINGS, AS REQUIRED.
6. CONNECTOR PLATES SHALL MEET OR EXCEED ASTM A653 REQUIREMENTS FOR STRUCTURAL STEEL.
7. TRUSSES SHALL BE FABRICATED AS SET FORTH IN ANSI/ TPI 1 - 2015 IN ACCORDANCE WITH THE DESIGN
DRAWINGS BY AN ESTABLISHED FABRICATOR.
8. TRUSSES SHALL BE HANDLED DURING FABRICATION, DELIVERY, AND AT JOB SITE SO AS NOT TO BE
SUBJECTED TO EXCESSIVE LATERAL BENDING.
9. INSTALLATION SHALL BE IN ACCORDANCE WITH HANDLING, INSTALLING, AND BRACING WOOD TRUSSES, HIB- 91, TPI. TRUSSES SHALL BE SET AND SECURED LEVEL AND PLUMB, AND IN CORRECT LOCATION.
10. TRUSSES SHALL BE SUFFICIENTLY BRACED DURING INSTALLATION TO PREVENT TOPPLING OR DOMINOING.
INSTALL ALL BRACING BEFORE PLACING CONCENTRATED LOADS ATOP TRUSSES.
11. CUTTING AND ALTERING OF TRUSSES IS NOT PERMITTED.
STRUCTURAL ABBREVIATIONS
@ AT
AB ANCHOR BOLT
ACCOM ACCOMMODATE
AFF ABOVE FINISH FLOOR
AGG AGGREGATE
ALT ALTERNATE
ARCH ARCHITECT/ ARCHITECTURAL
B- B BACK- TO- BACK
BL BUILDING LINE
BLDG BUILDING
BLK BLOCK
BM BEAM
BOT BOTTOM
BRG BEARING
BS BOTH SIDES
C CHANNEL DESIGNATION
CB CATCH BASIN
C/ C CENTER- TO- CENTER
CG CENTER OF GRAVITY
CI CAST IRON
CIP CAST IN PLACE
CJ CONTRACTION OR
CONSTRUCTION JOINT
CL CENTERLINE
CLJ CONTROL JOINT
CLR CLEAR
CMU CONCRETE MASONRY UNIT
COL COLUMN
COMP COMPOSITE
CONC CONCRETE
CONN CONNECTION
CONT CONTINUOUS
CONTR CONTRACTOR
D DEPTH
Ø DIAMETER
DIA DIAMETER
DIM DIMENSION
DN DOWN
DTL DETAIL
DWG DRAWING
DWL DOWEL
EA EACH
EC ELECTRICAL CONTRACTOR
EJ EXPANSION JOINT
EL ELEVATION
ELEV ELEVATOR
ENG ENGINEER
EQ EQUAL
EW EACH WAY
E- W EAST- WEST DIRECTION
EXIST EXISTING
EXP EXPANSION
EXT EXTERIOR
FB FLANGE BRACE
FD FLOOR DRAIN
FDN FOUNDATION
FF FINISH FLOOR
F- F FACE- TO- FACE
FL FRAME LINE
FLG FLANGE
FUT FUTURE
FV FIELD VERIFY
FTG FOOTING
GA GAGE
GALV GALVANIZED
GC GENERAL CONTRACTOR
GL GRID LINE
HC HVAC CONTRACTOR
HK HOOK
HM HOLLOW METAL
HORIZ HORIZONTAL
HP HIGH POINT
HT HEIGHT
HVAC HEATING, VENTILATING, & AIR
CONDITIONING
HWS HEADED WELDED STUD
ID INSIDE DIAMETER
INSUL INSULATION
INT INTERIOR
JT JOINT
KB KNEE BRACE
L STEEL ANGLE DESIGNATION
LG LONG/ LENGTH
LGMF LIGHT GAGE METAL FRAMING
LLH LONG LEG HORIZONTAL
LLV LONG LEG VERTICAL
LP LOW POINT
LVL LAMINATED VENEER LUMBER
MAX MAXIMUM
MBW MASONRY BEARING WALL
MECH MECHANICAL
MFG MANUFACTURE
MIN MINIMUM
MISC MISCELLANEOUS
MTL METAL
NIC NOT IN CONTRACT
NOM NOMINAL
NTS NOT TO SCALE
N- S NORTH- SOUTH DIRECTION
OC ON CENTER
OD OUTSIDE DIAMETER
OH OVER HEAD
OPP OPPOSITE
OS ONE SIDE
PC PLUMBING CONTRACTOR
P/ C PRECAST/ PRESTRESSED
PDF POWDER DRIVEN FASTENER
PEMB PRE- ENGINEERED METAL
BUILDING
PERM PERIMETER
PJF PRE- FORMED JOINT FILLER
⅊ PLATE
PL PLATE
P/ T POST TENSIONED
PROJ PROJECTION
PVMT PAVEMENT
R RADIUS
R/ C REINFORCED CONCRETE
RD ROOF DRAIN
REINF REINFORCING
REQD REQUIRED
SCHED SCHEDULE
SIM SIMILAR
SHT SHEET
SPA SPACE/ SPACES
SPEC SPECIFICATION
SQ SQUARE
SSTL STAINLESS STEEL
STL STEEL
STR STRUCTURAL
TBE TRUSS BEARING ELEVATION
THK THICK
TO TOP OF
TC TOP OF CURB ELEVATION
TL TOP OF LEDGE ELEVATION
TP TOP OF PIER ELEVATION
TW TOP OF WALL ELEVATION
TOS TOP OF STEEL ELEVATION
TSL TOP OF SLAB ELEVATION
TYP TYPICAL
UNO UNLESS NOTED OTHERWISE
VERT VERTICAL
VIF VERIFY IN FIELD
W WIDTH
W/ WITH
W/ O WITHOUT
WCJ WALL CONTROL JOINT
WD WOOD
WF WIDE FLANGE
WP WORKING POINT
WSBW WOOD STUD BEARING WALL
WWF WELDED WIRE FABRIC
FOUNDATION
1. ALLOWABLE SOIL BEARING CAPACITY = 3,000 PSF
GEOTECHNICAL INFORMATION TAKEN FROM:
SOILS & ENGINEERING SERVICES, INC.
GEOTECHNICAL INVESTIGATION REPORT 25.001
DANE COUNTY SUSTAINABILITY CAMPUS
4402 BRANDT ROAD
MADISON, WI
AUGUST 12, 2025
2. PROJECT GEOTECHNICAL REPORT SUPERSEDES GEOTECHNICAL INFORMATION PROVIDED ON STRUCTURAL PLANS.
3. THE GENERAL CONTRACTOR (GC) SHALL BE RESPONSIBLE FOR ALL CONSTRUCTION PROCEDURES THAT MAY AFFECT ADJACENT EXISTING STRUCTURES, ROADS, OR OTHER SIGNIFICANT PROPERTY. IT IS THE RESPONSIBILITY OF THE GC TO RETAIN A SPECIALTY FOUNDATION DESIGN CONSULTANT, GEOTECHNICAL ENGINEER, OR OTHER ENGINEERING CONSULTANT BEFORE EXCAVATION & AS REQUIRED DURING CONSTRUCTION. THE CONSULTANT SHALL PROVIDE ENGINEERED SOIL RETENTION/STABILIZATION SYSTEM, INSTALLATION GUIDANCE, AND ADJACENT PROPERTY MONITORING AS NEEDED DURING CONSTRUCTION. THE ARCHITECT AND/OR EOR SHALL BE NOTIFIED IMMEDIATELY IF
ADJACENT PROPERTY (FOUNDATION MOVEMENT, CRACKING, ETC) IS DETECTED.
4. THE BUILDING FINISHED FLOOR ELEVATION IS 100.00 AND EQUALS EL 887.83 ON THE SITE PLAN.
5. GRADE AREAS IN ACCORDANCE WITH ELEVATIONS AND GRADES SHOWN ON THE SITE DRAWINGS AND AS REQUIRED FOR DRAINAGE.
6. SLAB ON GROUND TO BE CONSTRUCTED ON A MINIMUM OF 6” OF CRUSHED STONE OR GRANULAR FILL COMPACTED TO 95% MODIFIED PROCTOR
OR AS DIRECTED BY THE GEOTECHNICAL ENGINEER.
7. ALL FILL MATERIAL USED IN GRADING OPERATIONS SHALL BE GRANULAR MATERIAL AND BE FREE OF DEBRIS, BOULDERS OR ORGANIC MATERIAL.
FILL SHALL BE PLACED IN MAXIMUM OF 12” LIFTS AND COMPACTED TO 95% OF MODIFIED PROCTOR MAXIMUM DRY DENSITY OR AS DIRECTED BY
THE GEOTECHNICAL ENGINEER.
8. THE BOTTOM OF ALL EXTERIOR FOOTINGS SHALL BE A MINIMUM OF 4'- 0” BELOW FINISHED GRADE.
9. ALL FOUNDATIONS AND FOOTINGS SHALL BEAR ON NATIVE SOIL OR COMPACTED GRANULAR FILL HAVING A MINIMUM ALLOWABLE BEARING
CAPACITY EQUAL TO THE PRESUMPTIVE CAPACITY ABOVE.
10. THE ENGINEER SHALL BE NOTIFIED IF ACTUAL FIELD CONDITIONS DO NOT MEET BEARING REQUIREMENTS, OR IF QUESTIONABLE SOIL CONDITIONS
ARE DISCOVERED INCLUDING BUT NOT LIMITED TO PEAT AND OTHER HIGH ORGANIC SOILS.
11. ALL BEARING SOIL OR FILL MUST BE PROTECTED FROM FREEZING. THE CONTRACTOR SHALL PROVIDE PROTECTION TO PREVENT FROST PENETRATION BELOW THE CONCRETE BEARING ELEVATIONS. ANY FROZEN SOIL BELOW THE FOUNDATION BEARING LEVEL MUST BE REMOVED
PRIOR TO PLACING CONCRETE.
12. ALL SLABS ON GRADE AREAS SHALL BE PROOF ROLLED. ALL SOFT SPOTS SHALL BE REMOVED AND REPLACED WITH COMPACTABLE FILL.
13. WHEN IT IS POSSIBLE FOR GROUND WATER TO SEEP TOWARD SUBGRADE FOUNDATIONS AND RETAINING WALLS, THESE WALLS SHALL HAVE A POSITIVE DRAINAGE SYSTEM AT THE BASE OF THE WALL CONSISTING OF A PERFORATED DRAIN PIPE PROTECTED BY A GEOTEXTILE FABRIC SURROUNDED BY CONCRETE SAND (TORPEDO SAND). NEAR THE BASE OF THE WALL. OTHER BACK FILL MATERIAL SHALL BE SAND WITH LESS
THAN 12% PASSING THE #200 SIEVE.
14. DO NOT USE EXCESSIVE COMPACTION EFFORTS ADJACENT TO RETAINING WALLS. SUCCESSIVE PASSES OF HEAVY COMPACTION EQUIPMENT, SUCH AS ROLLERS, CAN RESULT IN WALL PRESSURE BUILD UP BEYOND THE DESIGN INTENT. HEAVY EQUIPMENT SHOULD BE KEPT A MINIMUM OF 10 FEET FROM THE TOP OF BASEMENT OR RETAINING WALLS. USE HAND-OPERATED COMPACTION EQUIPMENT SUCH AS VIBRATORY PLATES.
15. PROVIDE SUB-GRADE PREPARATION AS PER THE PLANS OR PROJECT GEOTECHNICAL REPORT.
ARCHITECTURE
ENGINEERING
INTERIOR DESIGN
MADISON, WI | WAUKESHA, WI
D R
A W
IN
G
S E
T
D A
T E
R E
V
IS
IO
N
S
P R
O
JE
C T
N O
COPYRIGHT STRANG, INC. 2025
B R
A N
D T
R O
A D
M A
D
IS
O N
, W I
C D
3/
/2
S T
R U
C T
U R
A L
N O
T E
S
D A
N E
C O
U N
T Y
D E
P T
O F
W A
S T
E
R E
N E
W A
B
LE
S
S C
A
LE
H O
U S
E
CS001
DRAWING INDEX
SHEET TITLE
CS001 STRUCTURAL NOTES
CS101 FOUNDATION PLAN
CS301 WOOD FRAMING PLAN
CS501 CONCRETE DETAILS
CS901 WOOD DETAILS
CS902 WOOD DETAILS
N O
D
E S
C R
IP
T
IO
N
D A
COLUMN PIER MARK (SEE PIER SCHEDULE)
CONCRETE FOOTING
CONCRETE PIER
TOP OF PIER ELEVATION
COLUMN GRID MARK
COLUMN FOOTING MARK (SEE FOUNDATION SCHEDULE)
TOP OF COLUMN FOOTING ELEVATION
CONCRETE WALL & FOOTING
TOP OF WALL FOOTING ELEVATION
TOP OF LEDGE ELEVATION
TOP OF WALL ELEVATION
FOOTING STEP
FOOTING MARK
EXPANSION JOINT-SEE NOTES FOR
WALL CONTROL JOINT SPACING
FOUNDATION LEGEND
F X X'-X" P X X'-X"
WX
TL=X'-X"
TW=X'-X"
COLUMN PIER MARK
TOP OF PIER ELEVATION
COLUMN FOOTING MARK
TOP OF COLUMN FOOTING
ELEVATION
F X X'-X" P X X'-X"
A
X'-X"
TF=X'-X"
1. SEE SHEET CS001 FOR ADDITIONAL NOTES.
2. CONTROL JOINTS: ALL CONCRETE SLABS SHALL BE SAW CUT AS SOON AS THE
CONCRETE WILL SUPPORT THE SAWING EQUIPMENT AND DOES NOT RAVEL
DURING THE SAWING OPERATION. ALL SAW CUTTING SHALL BE PERFORMED
THE SAME DAY THE CONCRETE IS PLACED. SAW CUTS SHALL BE 1/ 8" WIDE
WITH DEPTHS OF AT LEAST 25% OF THE SLAB THICKNESS. JOINTING PATTERN
SHALL BE IN A SQUARE PATTERN, WITH MAXIMUM SPACING OF 12' - 0" FOR 4"
THICK SLABS, 13' - 0" FOR 5" THICK SLABS & 14' - 6" FOR 6" THICK SLABS
UNLESS NOTED OTHERWISE.
3. CURING: ALL CONCRETE FLAT WORK SHALL BE COVERED IMMEDIATELY
FOLLOWING SAW CUTTING AND MAINTAINED CONTINUOUSLY WET FOR A
MINIMUM OF 7 DAYS AFTER PLACING. CURING SHEETS SHALL BE USED, AND
ARE TO REMAIN IN PLACE, DURING THIS PERIOD. CURING COMPOUND MAY BE
USED AND MUST BE APPLIED PER MANUFACTURER'S RECOMMENDATIONS.
4. VERIFY/COORDINATE ALL WALL OPENINGS AND WALL STEP LOCATIONS FOR
DOORS, GRADE CHANGES, PIPES, ETC. WITH ARCH AND MECHANICAL PLANS.
5. SEE UNDERGROUND PLUMBING DRAWINGS FOR ALL UNDERGROUND PLUMBING
REQUIREMENTS PRIOR TO POURING CONCRETE.
6. TOP OF BRICK LEDGE = SEE PLAN. VERIFY W/ ARCH PLANS PRIOR TO PLACING
FOUNDATION WALLS.
7. SEE 1 & 2/CS501 FOR FOOTING AND WALL CORNER REINFORCING
REQUIREMENTS.
8. SEE 3/CS501 FOR PIPE PENETRATIONS THROUGH FOUNDATION WALL.
9. SEE 4/CS501 FOR SLAB JOINT REQUIREMENTS. SLAB CONTROL JOINT SHALL
BE AS SHOWN ON PLAN OR SIMILAR. SLAB JOINT ASPECT RATIO SHALL NOT
EXCEED 1.5:1. SEE NOTE 2 ABOVE.
10. SEE 5/CS501 FOR ADDED REINFORCING AT REENTRANT CORNERS. PROVIDE
(2) #4 BARS AT ALL DEAD ENDS AND REENTRANT CORNERS, TYP.
11. SEE 11/CS501 FOR BRICK VENEER TIE BACK DETAIL.
PLAN NOTES
CS501
TF= 94'-8"
TW= 100'-0"
TF
4'
8"
TL
7'
8"
TW
0"
CS501
CS501
CS501
W 2.
7" 4'
4"
1'
0"
5'
4"
7"
16'-7" 34'-0"
CS501
50'-7"
9'-0" 41'-7"
CS501
4" CONC SLAB-ON-GROUND W/ 6x6 W2.0xW2.9 WWF ON 6" GRANULAR FREE
DRAINING GRAVEL BASE W/ VAPOR BARRIER.
TOP OF SLAB = 100'-0"
TL= 97'-8"
94'-8" F3.0
P1 99'-4" C1
94'-8" F3.0
P1 99'-4" C1
94'-8" F3.0
P1 99'-4" C1
94'-8" F3.0
P1 99'-4" C1
C1
C1
C1 C1
CS501
CS501
D D
A A
B B
C C
TW
0"
TW
9'
4"
TF
4'
8"
14"
W2.0
TF
4'
8"
TW
9'
4"
TF
4'
8"
TL
7'
8"
TW
0"
6" W 1.
14"
31'-1" 8'-2 1/2"
SL
OP
IN
G
TW= 96'-10"
TW= 94'-8"
CS902
TYP.
HD1
HD1
14"
W2.0
HD1
HD1
HD1
HD1
ARCHITECTURE
ENGINEERING
INTERIOR DESIGN
MADISON, WI | WAUKESHA, WI
D R
A W
IN
G
S E
T
D A
T E
R E
V
IS
IO
N
S
P R
O
JE
C T
N O
COPYRIGHT STRANG, INC. 2025
B R
A N
D T
R O
A D
M A
D
IS
O N
, W I
C D
3/
/2
F O
U N
D A
T
IO
N P
LA
N
D A
N E
C O
U N
T Y
D E
P T
O F
W A
S T
E
R E
N E
W A
B
LE
S
S C
A
LE
H O
U S
E
CS101
SCALE: 1/4" = 1'-0"CS101
1 FOUNDATION PLAN
1. CENTER FOOTING UNDER COLUMN. WHEN THE FOOTING IS
COMBINED WITH A STRIP FOOTING, SUCH AS A RETAINING
WALL, THE NET FOOTING SIZE MAY BE LARGER THAN EITHER
INDIVIDUAL FOOTING. COMBINE AS SHOWN.
F3.0 3'-0" x 3'-0" x 1'-0" 4-#5 EA WAY
FOOTING
MARK
FOOTING DIMENSION
(W x L x D)
FOOTING REINFORCING,
BOTTOM
FOOTING SCHEDULE
1. CENTER FOOTING UNDER WALL, UNO.
W2.0 2'-0" x 1'-0" 3-#5 CONT
W1.5 1'-6" x 1'-0" 2-#5 CONT
FOOTING
MARK
FOOTING DIMENSION
(W x D)
FOOTING REINF REMARKS
STRIP FOOTING SCHEDULE
1. CENTER PIER UNDER COLUMN OR UNDER BEAM BEARING UNLESS NOTED OTHERWISE.
2. SEE DETAIL X/S601 FOR TYPICAL PIER DETAILS.
3. PROVIDE DOWELS OF SAME SIZE & NUMBER AS VERTICAL REINFORCEMENT.
MINIMUM LAP PER GENERAL NOTES WITH STANDARD ACI HOOK INTO FOOTING.
4. PROVIDE THREE (3) SETS OF TIES AT 2"oc AT TOP OF PIER.
5. PIERS AT WALLS TO BE BUILT INTEGRAL WITH WALL. PIER LENGTH ABOVE INCLUDES
FOUNDATION WALL WIDTH.
P1 1'-4" x 1'-4"
4-#6 VERT W/ #3
TIES @ 12" OC
A
PIER
MARK
PIER DESCRIPTION
(W x L)
PIER RIENFORCING TYPE NOTES
PIER SCHEDULE
C1 HSS 3-1/2x3-1/2x1/4 BP1 - 9/CS501
COLUMN
MARK
SIZE BASE PLATE
COLUMN SCHEDULE
HD1 SIMPSON HDUE3-SDS2.5 5/8" Ø 2-2x6's
MARK TYPE
ANCHOR
BOLT SIZE
MIN END POST
HOLD-DOWN SCHEDULE
N O
D
E S
C R
IP
T
IO
N
D A
T
. 2026
WOOD BEARING WALL
MASONRY WALL
WOOD SHEAR WALL
WOOD SHEAR WALL DESIGNATION,
SEE SHEAR WALL SCHEDULE
WOOD FRAMING LEGEND
SWX
MWX
MASONRY WALL DESIGNATION,
SEE CMU WALL SCHEDULE
HOLDDOWN ANCHOR/STRAP, SEE
HOLDOWN SCHEDULE
HDX
PLAN NOTES
1. SEE CS501 FOR ADDITIONAL NOTES.
2. SEE SCS501 FOR HEADER AND BEAM SCHEDULE, AND WOOD BEARING WALL
SCHEDULE FOR STUD SIZE AND SPACING.
3. SEE CS501 FOR MINIMUM FASTENING SCHEDULE.
4. ROOF SHEATHING SHALL BE 1/2" APA 24/ 16 SPAN EXP 1 OSB. SEE
CS901 FOR FASTENING REQUIREMENTS.
5. SEE 2/CS501 FOR ALLOWABLE HOLE SIZES AND LOCATIONS FOR LVL &
PARALLAM BEAMS.
6. DESIGN GABLE END TRUSS FOR 25 PSF WIND ON FACE.
7. TRUSS-TO-TRUSS CONNECTIONS SHALL BE DESIGNED AND SUPPLIED BY
TRUSS SUPPLIER.
8. SEE ARCH FOR ALL WINDOW CANOPY/ AWNING/ SIGNAGE LOCATIONS.
PROVIDE BLOCKING AS REQUIRED FOR ATTACHMENT TO STUD WALL.
9. EXTERIOR WALLS TO BE SW1 SHEAR WALLS UNO.
10. TEMPORARY CONSTRUCTION BRACING TO REMAIN IN PLACE UNTIL WALL
SHEATHING & HOLDOWNS HAVE BEEN INSTALLED.
11. DESIGN UPLIFT ON ROOF TRUSSES AS INDICATED IN THE DESIGN DATA.
PROVIDE TIE DOWNS AT EACH TRUSS, AT EVERY POINT OF BEARING.
12. RTU LOCATION & WEIGHTS HAVE NOT BEEN PROVIDED TO MP2 AT THIS
TIME. VERIFY RTU LOCATION, WEIGHT AND SIZE PRIOR TO TRUSS
FABRICATION. TRUSSES TO BE DESIGNED FOR CONCENTRATED/ UNIFORM
LOADS AS REQUIRED. CONTRACTOR TO COORDINATE WITH MECHANICAL
ENGINEER, ARCHITECT, STRUCTURAL ENGINEER & TRUSS SUPPLIER.
CS902
CS902
CS902
CS902
CS902
MIN 1'-6" TRUSS
DEPTH AT THIS END
MIN 2'-6" TRUSS
DEPTH AT THIS END
9'-0" 18'-0" 22'-2"
B1
H
H2
H1
H
H
C1
C1
C1
CS902
CS902
C1
CS902
CS902
H1
D D
A A
B B
C C
TO
P
CH
OR
D
SL
OP
ED
W
OO
D
RO
OF
T
RU
SS
ES
4"
O C
1'
4" 1'
4"
1'
4" 1'
0"
TO
P
CH
OR
D
SL
OP
ED
W
OO
D
RO
OF
T
RU
SS
ES
, S
EE
S
PA
CI
N G
27'-0"
EDGE OF TRUSS/
PARAPET FRAMING,
TYPICAL.
6"
SP
AC
ES
0"
O C
6'
0"
ROOF TRUSS LOADING
TOP CHORD DL = 14 PSF
BOTTOM CHORD DL = 8 PSF
20 PSF REDUCIBLE
BALANCED SNOW = 23.1 PSF
SNOW DRIFT = SEE SNOW LOADING DIAGRAM BELOW
13.3 PSF GROSS UPLIFT FIELD
15.8 PSF GROSS UPLIFT PERIMETER
15.8 PSF GROSS UPLIFT CORNERS
L/ 240 LIVE/ SNOW
L/ 180 TOTAL
DEAD LOAD:
LIVE LOAD:
SNOW LOAD:
WIND LOAD:
DEFLECTION:
ARCHITECTURE
ENGINEERING
INTERIOR DESIGN
MADISON, WI | WAUKESHA, WI
D R
A W
IN
G
S E
T
D A
T E
R E
V
IS
IO
N
S
P R
O
JE
C T
N O
COPYRIGHT STRANG, INC. 2025
B R
A N
D T
R O
A D
M A
D
IS
O N
, W I
C D
3/
/2
W O
O D
F R
A M
IN
G
P
LA
N
D A
N E
C O
U N
T Y
D E
P T
O F
W A
S T
E
R E
N E
W A
B
LE
S
S C
A
LE
H O
U S
E
CS301
SCALE: 1/4" = 1'-0"CS301
1 ROOF FRAMING PLAN
1. WINDOWS/DOORS (ETC) TO ALLOW FOR MAX 3/8" VERT DEFLECTION OF HEADER
(TYPICAL ALL FLOORS). INSTALL WINDOWS AFTER ALL DEAD LOADS ARE IN PLACE.
2. SEE BEAM/ HEADER CONNECTION SCHEDULE FOR FASTENING REQUIREMENTS.
3. HEADER AND BEAMS DESIGNATED (HX-R) OR (BX) TO BE RAISED FLUSH w/
BOTTOM OF TRUSS ELEVATION. TRUSS SUPPLIER TO MODIFY HEEL HEIGHTS AS REQ'D
4. PRESSURE TREATED LUMBER TO BE SOUTHER YELLOW PINE No. 2.
B1 (3) 1.75"x11.875" LVL BEAM POCKET, FULL 5.5" BEARING 2,3,4
H2 (3) 1.75"x11.875" LVL SEE DETAIL FOR COLUMN CAP 1,2,3
H1 (3) 2x10 2 1 1,2,3
MARK DESCRIPTION SHOULDER STUDS NO. FULL HEIGHT... NOTES
WOOD BEAM/HEADER SCHEDULE
GENERAL SHEAR WALL NOTES:
1. SEE BEARING WALL SCHEDULE FOR STUD SPACING.
2. WHEN BLOCKING IS REQUIRED, USE 2x BLOCKING AT ALL PANEL EDGES, SAME DEPTH AS STUD, AND PROVIDE EDGE NAILING AT ALL SUPPORTS & PANEL EDGES.
3. APPLY SHEATHING PANELS EITHER VERTICALLY OR HORIZONTALLY IN 4'-0" OR WIDER SHEETS ONLY.
4. TOE NAILS SHALL BE COMMON OR GALVANIZED BOX NAILS. TOE NAILING MUST BE FROM OUTSIDE FACE OF RIMBOARD. IF OUTSIDE FACE IS NOT ACCESSIBLE USE SHEAR CLIP OPTION.
SW1
5/8" DENSGLASS
SHEATHING
11-GUAGE X
1-3/4" NAILS
4" oc 6" oc 1/2"Ø @ 4'-0" oc 16d @ 16" oc 10d @ 16" NO
MARK
(1) (2)
SHEATHING FASTENER SIZE
EDGE
SPACING
FIELD
SPACING
ANCHOR BOLTS SOLE PLATE NAILING
SHEAR CLIP OR TOE NAIL
(7) (8)
BLOCKING REQUIRED (3)
SHEAR WALL SCHEDULE
N O
D
E S
C R
IP
T
IO
N
D A
T
ADDED CORNER REINFORCING
(MATCH FTG REINF SIZE)
OPTIONAL KEY JOINT
REINF BARS
FOOTING INTERSECTION FOOTING CORNER
SEE PLAN SEE PLAN
HK
STD
LA
P
M
IN
CL
AS
S B
2'-0" MIN
CLASS B LAP
2'
0" M
IN
CL
AS
S B
LA
P
2'-0" MIN
CLASS B LAP
2'
0" M
IN
CL
AS
S B
LA
P
ADDED CORNER REINF TO
MATCH SIZE & SPACING OF
LARGEST HORIZ REINF
PLACE VERT WALL REINF @ INSIDE
CORNER OF HOOKS (OTHER VERT
REINF NOT SHOWN FOR CLARITY)
OPTIONAL KEY JOINT
REINFORCING BARS
SEE WALL SECTION
NOTES:
1. CONTRACTOR MAY EXTEND
HORIZ WALL REINF WITH 2'-0"
90° HOOK IN LIEU OF ADDED
CORNER REINFORCING.
2. NO VERT WALL CONSTRUCTION
JOINT WITHIN 5'-0" OF WALL
CORNER.
3. SIM FOR SINGLE HORIZ BAR.
WALL
INTERSECTION
WALL CORNER
LA
P
CL
AS
S B
PLAN
SEE
PLAN
SEE
PL
AN
SE
E
HK
STD
CONTROL JOINT
CONSTRUCTION JOINT
WWF TO BE PLACED IN TOP 1/3 OF
SLAB. CUT EVERY-OTHER WIRE TYP
WWF REINF CONT THRU JOINT
SAWCUT JOINT WITHIN 12 HRS
OF SLAB POUR. DEPTH = t/4
12" OF WELL -GRADED
GRANULAR MATERIAL WITH
LESS THAN 3% PASSING
THE No. 200 SIEVE. SEE
GEOTECH REPORT.
1 1/2" KEYWAY
t
WWF REINF DISCONTINUOUS
THRU JOINT
12" OF WELL -GRADED
GRANULAR MATERIAL WITH
LESS THAN 3% PASSING
THE No. 200 SIEVE. SEE
GEOTECH REPORT.
WWF TO BE PLACED IN TOP 1/3 OF
SLAB. CUT EVERY-OTHER WIRE TYP
M
IN
2" C
LR
FLOOR SLAB 2- #4 BARS x 2'-0"
FDN WALL REENTRANT/ INSIDE CORNER
T.O WALL = SEE PLAN
T.O SLAB = SEE PLAN
TYPICAL FOR EXTERIOR
DOOR LOCATIONS.
SLEEVE
FTG ELEVATION AS
INDICATED ON PLAN
ALL PIPES TO CLEAR SLEEVE
BY 1/2" ALL AROUND
CAULK WHERE NECESSARY
M
IN
NO PIPES TO
BE PLACED IN
THIS HEIGHT
WHERE PIPE WILL PENETRATE
FTG, STEP FTG AND SLEEVE
UTILITY LINE THRU FOUNDATION WALL
MIN.
1'-6"
NO DIGGING FOR PIPE TRENCH PARALLEL
TO FTG WITHIN THESE LINES (WALL FTG
SHOWN, COLUMN FTG SIMILAR)
PIPE
45° SLOPE
NOTES:
1. THIS DETAIL APPLIES WHEN PIPE WOULD PENETRATE THE FOOTING, THEN
FOOTING ELEVATION MUST BE DROPPED.
2. IF UTILITY LINE RUNNING PERPENDICULAR TO FOOTING IS MORE THAN
3'-0" BELOW BOTTOM OF FOOTING, IT IS NOT NECESSARY TO DROP FTG
AND SLEEVE LINE THRU WALL AS SHOWN ABOVE.
T.O. FTG
SEE PLAN
SE
E
PL
AN
T.O. WALL
SEE PLAN
CONC SLAB, SEE PLAN
#4 DOWEL W/ STD HOOK
@ 48"OC ALT DIRECTION
EVERY OTHER BAR
3" RIGID INSULATION,
SEE ARCH. 1" AT WALL
(2)#4 BARS BOT
FND REINF,
SEE SCHED
SUB-BASE PER GEOTECHNICAL
ENGR OR GENERAL NOTES.
EQ 1'-2" EQ
SEE PLAN
TREATED 2x SILL PL, MIN (2) ANCHORS
PER PIECE W/ (1) ANCHOR LOCATED
NOT MORE THAT 12" OR LESS THAN 4"
FROM EA END OF PIECE. OFFSET EDGE
OF FDN WALL 1½", TYP.
½"Ø SIMPSON TITEN HD
ANCHOR W/ 5¾" EMBED
@ 4'-0" OC
EXTERIOR SHEATHING
2x STUD WALL W/ (2) 2x
TOP PLATE, SEE SCHED
FOR GRADE & SPACING
6" 8"
BRICK, SEE ARCH
(2) #4 BARS TOP
T.O. LEDGE
SEE PLAN
#4 HORIZ BARS @ 24" OC
#4 VERTICAL @ 24" OC
RIGID INSULATION,
SEE ARCH
1 1/2"
1/
2"
10"
5" 5"
5" 5"
10"x10"x5/8" BASE PLATE
(4) 3/4" ANCHOR BOLTS
WITH OVERSIZED HOLES
HSS PER PLAN
1/4"
BP1
CL
SE
E
PL
AN
T.O. WALL
SEE PLAN
CONC SLAB, SEE PLAN
#4 DOWEL W/ STD HOOK
@ 48"OC ALT DIRECTION
EVERY OTHER BAR
(2)#4 BARS BOT
FND REINF, SEE SCHED
SUB-BASE PER GEOTECHNICAL
ENGR OR GENERAL NOTES.
EQ 1'-2" EQ
SEE PLAN
TREATED 2x SILL PL, MIN (2) ANCHORS
PER PIECE W/ (1) ANCHOR LOCATED
NOT MORE THAT 12" OR LESS THAN 4"
FROM EA END OF PIECE. OFFSET EDGE
OF FDN WALL 1½", TYP.
½"Ø SIMPSON TITEN HD
ANCHOR W/ 5¾" EMBED
@ 4'-0" OC
EXTERIOR SHEATHING
2x STUD WALL W/ (2) 2x
TOP PLATE, SEE SCHED
FOR GRADE & SPACING
BRICK, SEE ARCH
(2) #4 BARS TOP
#4 HORIZ BARS @ 24" OC
#4 VERTICAL @ 24" OC
RIGID INSULATION,
SEE ARCH
6" 6" 6"
1'-6"
(4) #5 BARS T&B ALL AROUND AND
DOWELED TO FOUNDATION WALL
6x6 W2.1xW2.1 WWF IN 4"
CONCRETE SLAB-ON-GRADE
#4 BARS @ 12"OC ALL AROUND
#4x12 DOWELS @ 12"OC
ALL AROUND
T.O. WALL
SEE PLAN
T.O. FTG
SEE PLAN
#4 x 12" DOWEL, DRILL AND
EPOXY INTO WALL @ 12" OC.
8" 4"
GUARD RAIL,
SEE ARCH
SLEEVE FORM w/
9" EMBED, TYP
(6) #4 @ TOP
AROUND GUARD RAIL
SE
E
PL
AN
T.O. WALL
SEE PLAN
CONC SLAB, SEE PLAN
#4 DOWEL W/ STD HOOK
@ 48"OC ALT DIRECTION
EVERY OTHER BAR
(2)#4 BARS BOT
FND REINF, SEE SCHED
SUB-BASE PER GEOTECHNICAL
ENGR OR GENERAL NOTES.
EQ 1'-2" EQ
SEE PLAN
#4 HORIZ BARS @ 24" OC
#4 VERTICAL @ 24" OC
RIGID INSULATION,
SEE ARCH
6" 6" 6"
1'-6"
(4) #5 BARS T&B ALL AROUND AND
DOWELED TO FOUNDATION WALL
6x6 W2.1xW2.1 WWF IN 4"
CONCRETE SLAB-ON-GRADE
#4 BARS @ 12"OC ALL AROUND
#4x12 DOWELS @ 12"OC
ALL AROUND
T.O. WALL
SEE PLAN
T.O. FTG
SEE PLAN
GUARD RAIL,
SEE ARCH
SLEEVE FORM w/
9" EMBED, TYP
(6) #4 @ TOP
AROUND GUARD RAIL
DOOR, SEE ARCH
T.O. SLAB
SEE PLAN
CONC SLAB, SEE PLAN
WALL BEYOND
6" 1'-4"
T.O. LEDGE
SEE PLAN
T.O. PIER
SEE PLAN
CL
1/2" PJF
CONC DIAMOND. FILL AROUND
COL AFTER FLOOR IS CAST &
COLUMNS ARE CARRYING FULL
DEAD LOAD
ANCHOR BOLT SIZE &
SPACING, SEE COLUMN
SCHEDULE
1 1/2" NON- SHRINK
NON-METALLIC GROUT TYP
AT CONTRACTORS OPTION
WALL EDGE BEYOND
(3) TIES IN TOP 8"
VERT BARS W/ STD
HOOK INTO FTG
TIE BARS, SEE SCHED
6 1/4" 9 3/4"
WOOD STUD
MIN W1.7 "VEE" TWO
PIECE GALV
ADJUSTABLE TIE.
ATTACH TO STUD W/
GALV #12 SCREWS
FND WALL,
SEE PLAN
BRICK VENEER
5/8"COVER MIN
EXTEND TIE MIN 1 1/2"
INTO VENEER BRICK
1. PROVIDE VENEER TIES AT MAX 16"OC VERT W/ (1) TIE PER 2-SQ FT.
2. PROVIDE ADDITIONAL TIES AROUND OPENINGS LARGER THAN 16".
3. PROVIDE VERT & HORIZ EXPANSION JOINTS. COORD W/ ARCH & FND WALL SPACING.
4. PROV W1.7 WIRE JOINT REINFORCEMENT AT 16"OC VERT IN CMU VENEER.
SCALE: 3/4" = 1'-0"CS501
1 FOOTING CORNER REINFORCING
SCALE: 3/4" = 1'-0"CS501
2 WALL CORNER REINFORCING
SCALE: 3/4" = 1'-0"CS501
4 SLAB JOINTS
SCALE: 3/4" = 1'-0"CS501
8 SLAB REINF AT REENTRANT CORNERS
SCALE: NTSCS501
3 PIPE PENETRATION AT FDN WALL
ARCHITECTURE
ENGINEERING
INTERIOR DESIGN
MADISON, WI | WAUKESHA, WI
D R
A W
IN
G
S E
T
D A
T E
R E
V
IS
IO
N
S
P R
O
JE
C T
N O
COPYRIGHT STRANG, INC. 2025
B R
A N
D T
R O
A D
M A
D
IS
O N
, W I
C D
3/
/2
C O
N C
R E
T E
D E
T A
IL
S
D A
N E
C O
U N
T Y
D E
P T
O F
W A
S T
E
R E
N E
W A
B
LE
S
S C
A
LE
H O
U S
E
CS501
SCALE: 3/4" = 1'-0"CS501
5 TYPICAL FOUNDATION WALL AT BRICK
SCALE: 3" = 1'-0"CS501
9 COLUMN BASE PLATES
SCALE: 3/4" = 1'-0"CS501
6 STOOP AT WALL
SCALE: 3/4" = 1'-0"CS501
7 STOOP AT DOOR
SCALE: 3/4" = 1'-0"CS501
10 TYPICAL PIER SECTION
SCALE: 1" = 1'-0"CS501
11 VENEER TIE BACK AT STUD WALL
N O
D
E S
C R
IP
T
IO
N
D A
T
LEDGER STRIP SUPPORTING JOISTS OR RAFTERS 3 - 16d COMMON EACH JOIST OR RAFTER, FACE NAIL
JOIST TO BAND JOIST OR RIM JOIST 3 - 16d COMMON END NAIL
MINIMUM FASTENING SCHEDULE (UNO)
3 - 8d COMMON
FASTENING
JOIST TO SILL, TOP PLATE, OR GIRDER
DOUBLE TOP PLATES
DOUBLE STUDS (NOT AT BRACED WALL PANELS)
CEILING JOIST TO PLATE
LOCATIONCONNECTION
BRIDGING OR BLOCKING TO JOIST, RAFTER OR TRUSS 2 - 8d COMMON TOENAIL EACH END
TOENAIL
1" x 6" SUBFLOOR OR LESS TO EACH JOIST 2 - 8d COMMON FACE NAIL
FACE NAIL16d @ 24" O.C
FACE NAIL16d @ 16" O.C
3 - 8d COMMON
ROOF RAFTERS TO RIDGE VALLEY OR HIP RAFTERS; OR ROOF
RAFTER TO 2-INCH RIDGE BEAM
FACE NAIL
TABLE 2308.7.3.1
3 - 10d COMMON
3 - 16d COMMON MINIMUM
(SEE SECTION 2308.7.3.1, TABLE 2308.7.3.1)
CEILING JOISTS TO PARALLEL RAFTERS
TOENAIL3 - 16d COMMONRAFTER OR TRUSS TO TOP PLATE
(SEE SECTION 2308.7.5, TABLE 2308.7.5)
FACE NAIL AT ENDS & AT EACH SPLICE
FACE NAIL AT TOP & BOTTOM STAGGERED
AND: 2 - 20d COMMON
20d COMMON 32" O.CBUILT-UP GIRDER & BEAMS
ON OPPOSITE SIDES
COLLAR TIE TO RAFTER
2" PLANKS
3 - 16d COMMON
29.
2 - 16d COMMON
2 - 16d COMMON
TOENAIL
END NAIL
FACE NAIL
AT EACH BEARING, FACE NAIL
PER 2021 IBC & WISCONSIN COMMERCIAL BUILDING CODE: TABLE 2304.10.1
3.
30.
24.
9.
13.
22.
5.
7.
27.
6.
8.
28.
26.
For SI: 1 inch = 25.4mm
a. NAILS SPACED AT 6 INCHES AT INTERMEDIATE SUPPORTS WHERE SPANS ARE 48 INCHES OR MORE. FOR NAILING OF WOOD STRUCTURAL PANEL AND PARTICLEBOARD DIAPHRAGMS AND SHEAR WALLS, REFER TO IBC SECTION 2305. NAILS FOR WALL SHEATHING ARE PERMITTED TO BE COMMON, BOX OR CASING.
b.…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .