This Request for Bids (RFB No. 27-0007) is issued by the Columbus Consolidated Government's Purchasing Division in Columbus, Georgia, for the procurement of protective fire clothing and accessories for the Columbus Fire & EMS Department. The solicitation seeks to establish contracts with both a Primary and Secondary contractor to provide firefighters with body protection against extreme temperature, sharp objects, steam and water penetration, hot particles, and other hazards encountered during structural firefighting operations. The City anticipates purchasing approximately 30 sets of clothing on an as-needed basis, with items including structural firefighting coats, pants, suspenders, protective hoods, gloves, helmets, and boots. All protective clothing and accessories must meet current NFPA standards. Sealed bids are due on October 14, 2026, at 2:30 PM Eastern Time, with a virtual bid opening scheduled during the 3:00 PM hour. The contract term is for two years with the option to renew for three additional twelve-month periods, contingent upon mutual agreement and funding appropriation by City Council.
Awards will be made to the two lowest responsive and responsible vendors who best meet the specifications. All pricing must be fixed for the initial two-year term, with any price escalation requests after the initial term limited to five percent and requiring full documentation from manufacturers. Bidders must submit bids electronically via OpenBids and include required documentation such as the E-Verify Affidavit, Conflict of Interest Affidavit, manufacturer warranty information, product literature and specifications, and acknowledgment of any addenda. The City is exempt from state retail tax and federal excise tax. All freight, shipping, and handling charges must be included in the bid price, with payment typically occurring net 30 days after satisfactory delivery. The City reserves the right to request product demonstrations or site visits at the bidder's expense, to reject any or all bids, and to cancel contracts if items do not perform as specified. Questions concerning specifications must be submitted in writing at least five working days prior to the bid due date.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFB No. 27-0007 PROTECTIVE FIRE CLOTHING AND ACCESSORIES (ANNUAL CONTRACT) Page 1 of 57
$50
FINANCE DEPARTMENT
PURCHASING DIVISION COLUMBUS CITY HALL
1111 FIRST AVENUE, COLUMBUS, GEORGIA 31901
P. O. BOX 1340, COLUMBUS, GEORGIA 31902-1340
706-225-4087 | www.columbusga.org
Date: September 22, 2026
REQUEST
FOR BIDS:
RFB NO. 27-0007
Qualified vendors are invited to submit sealed bids, subject to conditions and instructions as specified, for the sale of:
PROTECTIVE FIRE CLOTHING AND ACCESSORIES
(ANNUAL CONTRACT)
GENERAL SCOPE
It is the intent of the Columbus Consolidated Government ( the City) to establish an annual contract with a Primary and a Secondary contractor to provide firefighters with body protection against extreme temperature, sharp objects, steam water penetration, hot particles, and other hazards encountered during structural firefighting. These items will be procured on an "as needed" basis and are to be utilized by the Columbus Fire & EMS Department and will be awarded to both a Primary Contractor, and a Secondary Contractor.
The contract term will be for two years with the option to renew for three additional twelve-month periods.
DUE DATE
OCTOBER 14, 2026 – 2:30 PM (Eastern) Responses must be submitted via OpenBids on or before the due date. A virtual opening will be held during the 3:00 PM hour of the due date. Responding vendors are not required but are invited to attend the opening.
If you wish to attend the virtual opening, use one of the Microsoft Teams meeting options: Click here to join the meeting or call in (audio only) +1 478-239-0725,,855808406# United States, Macon Phone Conference ID: 855 808 406# Find a local number | Reset PIN. Note: Columbus Consolidated Government is not responsible for technical issues that may arise during the virtual opening.
BID SUBMISSION
REQUIREMENTS
DemandStar is now OpenBids See Appendix A for Submission Requirements, Submission Requirements Checklist, and OpenBids Registration and Submission Instructions.
ADDENDA IMPORTANT INFORMATION
The Purchasing Division will post addenda (if any) for this project at https://www.columbusga.gov/finance-2/bid-opportunities. It is the vendors’ responsibility to periodically visit the web page for addenda, before the due date and prior to submitting a proposal.
“NO BID”
RESPONSE Refer to the form on page 3 if you are not interested in this invitation.
Andrea J. McCorvey Purchasing Division Manager
COLUMBUS CONSOLIDATED GOVERNMENT
Georgia’s First Consolidated Government http://www.columbusga.org/ https://gcc02.safelinks.protection.outlook.com/ap/t-59584e83/?url=https%3A%2F%2Fteams.microsoft.com%2Fl%2Fmeetup-join%2F19%253ameeting_ZDBhMjU0OWQtNzhmMC00MWI3LWFmYTUtMWE5Mzg1MjYzNjJh%2540thread.v2%2F0%3Fcontext%3D%257b%2522Tid%2522%253a%2522f6bad3c9-1001-44da-acff-b25808ccd0c4%2522%252c%2522Oid%2522%253a%252231b993f8-2ba4-4447-8595-e9bd2a9237bb%2522%257d&data=04%7C01%7CDLewis%40columbusga.org%7C76679aafcef641b2945608d8c307fdd1%7Cf6bad3c9100144daacffb25808ccd0c4%7C1%7C0%7C637473786378728883%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=EtqSxTlQyxV6y%2Fbuj7jQhhssFaCviAFruPTKL665iPk%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/ap/t-59584e83/?url=https%3A%2F%2Fteams.microsoft.com%2Fl%2Fmeetup-join%2F19%253ameeting_ZDBhMjU0OWQtNzhmMC00MWI3LWFmYTUtMWE5Mzg1MjYzNjJh%2540thread.v2%2F0%3Fcontext%3D%257b%2522Tid%2522%253a%2522f6bad3c9-1001-44da-acff-b25808ccd0c4%2522%252c%2522Oid%2522%253a%252231b993f8-2ba4-4447-8595-e9bd2a9237bb%2522%257d&data=04%7C01%7CDLewis%40columbusga.org%7C76679aafcef641b2945608d8c307fdd1%7Cf6bad3c9100144daacffb25808ccd0c4%7C1%7C0%7C637473786378728883%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=EtqSxTlQyxV6y%2Fbuj7jQhhssFaCviAFruPTKL665iPk%3D&reserved=0 tel:+14782390725,,855808406#%20 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fdialin.teams.microsoft.com%2F59f93fad-7434-42f9-b866-29ac5c89c046%3Fid%3D855808406&data=04%7C01%7CDLewis%40columbusga.org%7C76679aafcef641b2945608d8c307fdd1%7Cf6bad3c9100144daacffb25808ccd0c4%7C1%7C0%7C637473786378728883%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=VVDIVins36aPwsCTcm3xO81%2FChUT7B5Np0mgAp9rAas%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fmysettings.lync.com%2Fpstnconferencing&data=04%7C01%7CDLewis%40columbusga.org%7C76679aafcef641b2945608d8c307fdd1%7Cf6bad3c9100144daacffb25808ccd0c4%7C1%7C0%7C637473786378738837%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=B3EFQGocYOaZ%2FWJeJvvy0qfiZu309O0I%2BWBqssG8iuo%3D&reserved=0 https://www.columbusga.gov/finance-2/bid-opportunities
RFB No. 27-0007 PROTECTIVE FIRE CLOTHING AND ACCESSORIES (ANNUAL CONTRACT) Page 2 of 57
IMPORTANT INFORMATION
e-Notification
The City uses the Georgia Procurement Registry e-notification system. You must register with GA@WORK (formerly Team Georgia Marketplace) to receive future procurement notifications via: https://doas.ga.gov/state-purchasing/getting-started-supplier.
If you have any questions or encounter any problems while registering, please contact the State Purchasing Division:
Telephone: 404-657-6000
Email: procurementhelp@doas.ga.gov https://doas.ga.gov/state-purchasing/getting-started-supplier mailto:procurementhelp@doas.ga.gov
RFB No. 27-0007 PROTECTIVE FIRE CLOTHING AND ACCESSORIES (ANNUAL CONTRACT) Page 3 of 57
STATEMENT OF “NO BID”
Complete and return this form immediately if you do NOT intend to Bid:
Email: BidOpportunities@columbusga.org Attn: Ryky Decembre, Buyer Mail: Columbus Consolidated Government Purchasing Division P.O. Box 1340 Columbus, GA 31902-1340
We, the undersigned decline to bid on your RFB No. 27-0007, for Protective Fire Clothing and Accessories (Annual Contract) for the following reason(s):
Specifications too "tight", i.e. geared toward one brand or manufacturer only (explain below) There is insufficient time to respond to the Requests for Bids.
We do not offer this product or service.
We are unable to meet specifications.
We are unable to meet bond requirements.
Specifications are unclear (explain below).
We are unable to meet insurance requirements.
Other (specify below)
Remarks:
COMPANY NAME: ______________________________________________
AGENT: ______________________________________________
DATE: ______________________________________________
TELEPHONE NUMBER: ______________________________________________
EMAIL ADDRESS: ______________________________________________
mailto:BidOpportunities@columbusga.org
RFB No. 27-0007 PROTECTIVE FIRE CLOTHING AND ACCESSORIES (ANNUAL CONTRACT) Page 4 of 57
GENERAL PROVISIONS
The provisions of the Procurement Ordinance for the Consolidated Government of Columbus, Georgia as adopted and amended by Council shall apply to all invitations for bids and award of all contracts and is specifically incorporated herein by this reference.
A copy of the ordinance is on file in the Purchasing Division.
1. TERM “CITY”. The term “City” as used throughout these documents will mean Consolidated Government of Columbus, Georgia.
2. PREPARATION OF FORM. Bid proposals shall be submitted on the forms provided by the City. All figures must be written in ink or typewritten. Figures written in pencil or erasures are not acceptable. However, mistakes may be crossed out, corrections inserted adjacent thereto, initialed in ink by the person signing the proposal. If there are discrepancies between unit prices quoted and extensions, the unit price will prevail. Failure to properly sign forms, in ink, will render bid incomplete.
3. EXECUTION OF THE BID PROPOSAL. Execution of the bid proposal will indicate the bidder is familiar and in compliance withall local laws, regulations, ordinances, site inspections, licenses, dray tags, etc.
4. BID DUE DATE. The bid submission must arrive in the Purchasing Division on or before the stated due date and time. Upon receipt, bids will be time and date stamped. Bids will remain sealed and secured until the stated due date and time for the bid opening.
5. BID OPENING. Bids shall be opened publicly in the presence of one or more witnesses at the time and place stated in the public notice. The amount of each bid, the bidder's name and such other relevant information as the Purchasing Manager deems appropriate shall be recorded and retained in accordance with Georgia law. The record and each bid shall be open to the public in accordance with Article 3. 301A of the Procurement Ordinance (Public Access to Procurement Information).
6. LATE BIDS. It is the responsibility of the bidder to ensure bids are submitted by the specified due date and time. Bids received after the stated date and time will be returned, unopened, to the bidder. The official clock to determine the date and time will be the time/date stamp located in the Finance Department. All bids received will be time and date stamped by the official clock. The City will not be held responsible for the late delivery of bids due to the U.S. Mail Service, or any other courier service.
7. RECEIPT OF ONE SEALED BID. In the event only one sealed bid is received, no formal bid opening shall take place. First, the Purchasing Division shall conduct a survey of vendors to inquire of “no bid” responses and non-responsive vendors. If, from the survey, it is determined by the Purchasing Division that specifications need revision, the one bid received will be returned, unopened, to the responding vendor, with a letter of explanation and a new bid solicitation prepared. If it is determined that other vendors need to be contacted, the bid due date will be extended, and the one bid received will remain sealed until the new bid opening date. The vendor submitting the single bid will receive a letter of explanation.
If it is determined the one bid received is from the only responsive, responsible bidder, then the bid shall be opened by the Purchasing Division Manager or designee, in the presence of at least one other witness. The single bid will be evaluated by the using agency for award recommendation.
8. RECEIPT OF TIE BIDS. In the event multiple responsive, responsible bidders are tied for the lowest price and all other terms and requirements are met by all tied bidders, the award recommendation shall be resolved in the order of the preferences listed below:
1. Award to the local bidder whose principal place of business is located in Columbus, Georgia.
2. Award to bidder previously awarded based on favorable prior experience.
3. Award to bidder whose principal place of business is located in the State of Georgia.
4. If feasible, divide the award equally among the bidders.
5. If it is not feasible to award equally and only two bidders are tied, perform a coin toss in the presence of the two bidders, either in person or virtually.
6. If the above preferences are insufficient to resolve the tie, all bid responses will be rejected and the bid will be re-advertised.
9. RECEIPT OF MULTIPLE BIDS. Unless otherwise stated in the bid specifications, the City will accept one and only one bid per vendor. Any unsolicited multiple bid(s) will not be considered. If prior to the bid opening, more than one bid is received from the same vendor, the following will occur: (1) the bidder will be contacted and required to submit written acknowledgment of the bid to be considered; (2) the additional bid(s) will be returned to the bidder unopened. If at the bid opening more than one bid is enclosed in a single bid package, the City will consider the vendor non-responsive and bids will be returned to the bidder.
10. CONDITIONS AND PACKAGING. Unless otherwise defined in the bid specifications, it is understood and agreed that any item offered or furnished shall be new, in current production and in first class condition, that all containers shall be new and suitable for storage or shipment, and that prices include standard commercial packaging.
11. FREIGHT/SHIPPING/HANDLING CHARGES. All freight, shipping, and handling charges shall be included in the bid price. The City will pay no additional charges.
12. CORRECTION OR WITHDRAWAL OF BIDS; CANCELLATION OF AWARDS
Correction or withdrawal of inadvertently erroneous bids before bid opening, or cancellation of awards or contracts based on such bid mistakes, may be permitted where appropriate. Mistakes discovered before bid opening may be modified or withdrawn by written notice received in the Purchasing Division.
RFB No. 27-0007 PROTECTIVE FIRE CLOTHING AND ACCESSORIES (ANNUAL CONTRACT) Page 5 of 57
After bid opening, corrections in bids shall be permitted only to the extent that the bidder can show by clear and convincing evidence that a mistake of a nonjudgmental character was made, the nature of the mistake and the bid price actually intended. After bid opening, no changes in bid prices or other provisions of bids prejudicial to the interest of the City or fair competition shall be permitted. In lieu of bid correction, a low bidder alleging a material mistake of fact may be permitted to withdraw its bid if the mistake is clearly evident on the face of the bid document but the intended correct bid is not similarly evident, or if the bidder submits evidence which clearly and convincingly demonstrate that a mistake was made.
All decisions to permit correction or withdrawal of bids or to cancel awards of contracts based on bid mistakes will be supported by the Purchasing Manager's written determination.
13. ADDENDA AND INTERPRETATIONS. If it becomes necessary to revise any part of this bid, a written addendum will be provided to all bidders. The City is not bound by any oral representations, clarifications, or changes made to the written specifications by City employees, unless such clarification or change is provided to the bidders in written addendum form from the Purchasing Officer. Bidders will be required to acknowledge receipt of the addenda (if applicable) in their sealed bid proposal. The vendor may provide an initialed copy of each addendum or initial the appropriate area on the bid form (pricing page). Failure to acknowledge receipt of the addenda (when applicable) will render bid incomplete. It is the bidder’s responsibility to ensure that they have received all addenda.
14. BID RECEIPT AND EVALUATION. Bids shall be unconditionally received without alteration or correction except as authorized in the City's Procurement Ordinance. Bids shall be evaluated based on requirements set forth in the Invitation for Bid, which may include criteria to determine acceptability such as inspection, testing, quality, workmanship, delivery, and suitability for a particular purpose. Those criteria that will affect the bid price and be considered in evaluation for award shall be objectively measurable, such as discounts, transportation cost, and total or life-cycle costs. The specifications presented in the Invitation for Bids shall represent the evaluation criteria. No other criteria may be used to evaluate bids.
15. TIME FOR CONSIDERATION. Bids must remain in effect for at least ninety (90) days after date of receipt to allow for evaluation.
16. BID SECURITY
(1) Requirement for Bid Security. Bid security shall be required for all competitive sealed bids for construction contracts when the price is estimated by the Purchasing Manager to exceed $50,000. Bid security shall be a bond provided by a surety company authorized to do business in the State, or other form satisfactory to the City. Such bonds may also be required on construction contracts under $50,000 or other procurement contracts when circumstances warrant.
(2) Amount of Bid Security. Bid security shall be in an amount equal to at least five percent (5%) of the bid amount.
(3) Rejection of Bids for Noncompliance with Bid Security Requirements. When the invitation for Bids requires security, noncompliance with such requirement shall force rejection of a bid.
(4) Withdrawal of Bids. If a bidder is permitted to withdraw its bid before award as provided in Section 3-108 Subsection (G) (Competitive Sealed Bidding – Correction or Withdrawal of Bids: Cancellation of Awards), no action shall be had against the bidder or the bid security.
17. CONTRACT PERFORMANCE AND PAYMENT BONDS
(1) When Required: Amounts. When a construction contract is awarded in excess of $50,000, the following bonds or security shall be delivered to the City, and shall be binding on the parties upon the execution of the contract:
a. a performance bond satisfactory to the City executed by a surely company authorized to do business in the State, or otherwise secured in a manner satisfactory to the City, amounting to one hundred percent (100%) of the price specified in the contract; and
b. a payment bond satisfactory to the City executed by a surety company authorized to do business in the State or otherwise secured in a manner satisfactory to the City, to protect all persons supplying labor and material to the contractor or its subcontractors for the performance of the work provided for in the contract, amounting to one hundred percent (100%) of the price specified in the contract.
At the discretion of the Purchasing Manager, this same condition may be placed on awards of any amount.
(2) Authority to Require Additional Bonds. Nothing in this Section shall be construed to limit the authority of the City to require a performance bond or other security in addition to the bonds, in circumstances other than the circumstances described in Subsection (1) above.
18. SUBCONTRACTING. Should bidder intend to subcontract all or any part of the work specified, name(s) and address(es) of sub-contractor(s) must be provided in bid proposal (use additional sheet if necessary). The bidder shall be responsible for subcontractor(s) full compliance with the requirements of the bid specifications. THE COLUMBUS CONSOLIDATED GOVERNMENT WILL NOT BE
RESPONSIBLE FOR PAYMENTS TO SUBCONTRACTORS.
19. DISQUALIFICATION OF BIDDERS AND REJECTION OF BIDS. Bidders may be disqualified and rejection of bid proposals may be recommended by the City for any (but not limited) to the following reasons:
(A) Receipt after the time limit for receiving bid proposals as stated in the bid invitation.
(B) Any irregularities contrary to the General Provisions or bid specifications.
(C) Unbalanced unit price or extensions.
(D) Unbalanced value of items.
(E) Failure to use the proper forms furnished by the Consolidated Government.
(F) Failure to complete the proposal properly
RFB No. 27-0007 PROTECTIVE FIRE CLOTHING AND ACCESSORIES (ANNUAL CONTRACT) Page 6 of 57
(G) Omission of warranty, product literature, samples, acknowledgment of addenda or other items required to be included with bid proposal.
(H) Failure to properly sign forms in ink.
The City reserves the right to waive any minor informality or irregularity. The City reserves the right to reject any and all bids.
20. BRAND NAMES “OR EQUAL”. Whenever in this invitation any particular material, process and/or equipment are indicated or specified by patent, proprietary or brand name of manufacturer, such wording will be deemed to be used for the purpose of facilitating description of the material, process and/or equipment desired by the City. It is not meant to eliminate bidders or restrict competition in any bid process.
Any manufacturers’ names, drawings, trade names, brand names, specifications and/or catalog numbers used herein are for the purpose of description and establishing general quality levels. Bidders may propose equivalent equipment, services or manufacturer. Any proposal that is equivalent to or surpasses stated specifications will be considered. Determination of equivalency shall rest solely with the City.
Please Note: Due to existing equipment, specific manufacturers may be required to facilitate compatibility.
21. ASSIGNMENT OF CONTRACTUAL RIGHTS. It is agreed that the successful bidder will not assign, transfer, convey or otherwise dispose of the contract or its right, title or interest in or to the same, or any part thereof, without previous consent of the City and any sureties.
22. DISCOUNTS. Terms of payments offered will be reflected in the space provided on the bid proposal form. Cash discounts will be considered net in the bid evaluation process. All terms of payment (cash discounts) will be taken and computed from the date of delivery of acceptable material or services, or the date of receipt of the invoice, whichever is later.
23. TAXES. The City is exempt from State Retail Tax and Federal Excise Tax. Tax Exemption No. GA Code Sec. 48-8-3. Federal ID No.
58-1097948.
24. FEDERAL, STATE AND LOCAL LAWS. All bidders will comply with all Federal, State, and Local laws and ordinances, relative to conducting business in Columbus, Georgia.
25. BID INCLUSIONS. When bid inclusions are required, such as warranty information, product literature/specifications, references, etc.
The inclusions should reference all aspects of the specific equipment or service proposed by the bidder. Do not include general descriptive catalogs. References to literature or other required inclusions submitted previously does not satisfy this provision. Bids found to be in non-compliance with these requirements will be subject to rejection.
26. NON-COLLUSION. By signing and submitting this bid, bidder declares that its agents, officers or employees have not directly or indirectly entered into any agreements, participated in any collusion or otherwise taken any action in restraint of free competitive bidding in connection with this bid. In the event, said bidder is found guilty of collusion, the company and agents will be removed from the City’s bid list for one full year and any current orders will be canceled.
27. INDEMNITY. The successful bidder agrees, by entering into this contract, to defend, indemnify and hold City harmless from any and all causes of action or claims of damages arising out or under this contract.
28. DISADVANTAGED BUSINESS ENTERPRISE. Disadvantaged Business Enterprises (minority or women owned businesses) will be afforded full opportunity to submit proposals in response to this invitation and will not be discriminated against on the grounds of race, color, creed, sex, sexual orientation, gender identity or national origin in consideration for an award. It is the policy of the City that disadvantaged business enterprises and minority business enterprises have an opportunity to participate at all levels of contracting in the performance of City contracts to the extent practical and consistent with the efficient performance of the contract.
29. AFFIRMATIVE ACTION PROGRAM - NON-DISCRIMINATION CLAUSE. The Consolidated Government of Columbus, Georgia (“the City”) is committed to using Disadvantaged Business Enterprises (DBEs) (small, women-owned and minority business enterprises) to the greatest extent practical in all solicitations and day-to-day procurement needs of the City and to taking specific affirmative actions to meet these commitments.
The City has an Affirmative Action Program in connection with Equal Employment Opportunities. The successful bidder will comply with all Federal and State requirements concerning fair employment and employment of the handicapped, and concerning the treatment of all employees, and will not discriminate between or among them by reason of race, color, age, religion, sex, sexual orientation, gender identity, national origin or physical handicap.
30. AWARDS TO LOCAL BUSINESSES. Except for construction contracts, Federally funded projects, Request for Proposals and Request for Qualifications, awards will be made to responsive and responsible local businesses proposing a cost not more than two percent (2%) above the low bid or quote for contracts involving an expenditure less than or equal to $50,000.00; and made to responsive and responsible local businesses proposing a cost not more than one percent (1%) above the low bid or quote for contracts involving an expenditure greater than $50,000.00.
31. RIGHT TO PROTEST.
(1) Right of Protest. Any actual or prospective bidder offeror, or contractor who is aggrieved in connection with a solicitation or award of a contract may protest to the Purchasing Manager initially. All protests shall be filed in the manner prescribed herein. Protests that do not comply with the following rules shall be deemed invalid and of no effect.
(2) The protest must be in writing, executed by a company officer that is authorized to execute agreements on behalf of the bidder or offeror or provided by an authorized legal representative of the protestor.
(3) A protest with respect to an invitation for Bids or Request for Proposals shall be submitted in writing no less than five (5) business days prior to the opening of bids or the closing date of proposals or qualification statements.
RFB No. 27-0007 PROTECTIVE FIRE CLOTHING AND ACCESSORIES (ANNUAL CONTRACT) Page 7 of 57
(4) Stay of Procurement During Protests. If there is a timely protest submitted as described above, the Purchasing Manager shall not proceed further with the solicitation or award of the contract until all administrative remedies have been exhausted or until the City Council, Mayor, or City Manager makes a determination on the record that the award of the contract without delay is necessary to protect substantial interests of the City.
32. FAILURE TO BID. Vendors choosing not to submit a bid are requested to return a Statement of “No Bid”.
33. PRODUCT/EQUIPMENT DEMONSTRATION - SITE VISIT. During the evaluation of bids, the City reserves the right to request a demonstration or site visit of the product, equipment or service offered by a bidder. The demonstration or site visit shall be at the expense of the bidder. Bidders who fail to provide demonstration or site visit, as requested, will be considered non-responsive.
34. CANCELLATION PROVISIONS. An Invitation for Bid, Request for Proposal, or other solicitation may be canceled, or any or all bids, proposals or responses rejected in whole or in part, at the discretion of the City for any reason whatsoever. The reasons for the cancellation shall be sent to all businesses solicited or that responded. The notice shall identify the solicitation, give the reasons for the cancellation, and when appropriate state that an opportunity will be given to compete on any re-solicitation or similar procurement in the future. Reasons for rejection will be provided to unsuccessful bidders or offerors.
When such action is in the best financial interest of the City, contracts for supplies to be purchased or services to be rendered under an annual (term) contract basis may be canceled and re-advertised at the discretion of the Purchasing Officer and in accordance with contract terms.
After the receipt of a product or piece of equipment, it is found that said item does not perform as specified and required, payment for said product or equipment will be withheld. The successful vendor will be notified of the non-performance in writing. After notification, the successful vendor will have ten (10) calendar days, from the date of notification, to deliver product or equipment which performs satisfactorily.
If a satisfactory product is not delivered within 10 calendar days, from the notification date, the City will cancel the contract (purchase order) and award to the next low, responsive, responsible bidder. The vendor will be responsible for the pick-up or shipment of the unsatisfactory equipment or product.
35. QUESTIONS: Questions concerning specifications must be submitted, in writing, at least 5 (five) working days (Monday-Friday) prior to receipt date. Questions received less than five working days prior to receipt date will not be considered.
36. SAMPLES: When samples are required to be included with the proposal response, the bidder will be responsible for the following:
1) Unless otherwise specified, bidders are required to submit exact samples of item(s) bid. Do not submit sample of “like” item(s).
2) Affix an identification label to each individual sample to include bidder’s name, bid name and number.
3) Make arrangements for the return of sample after the bid award. All shipping costs will be the responsibility of the bidder. If bidder does not make arrangements for return of sample, within 60 days after award, the sample will be discarded.
37. GOVERNING LAW: The parties agree that this Agreement shall be governed by the laws of Georgia, both as to interpretations and performance.
38. PAYMENT DEDUCTIONS: The City reserves the right to deduct, from payments to awarded vendor(s), any amount owed to the City for various fees, to include, but not limited to: False Alarm fees, Ambulance fees, Occupation License Fees, Landfill fees, etc.
39. PAYMENT TERMS: The City's standard payment term is usually net 30 days, after successful receipt of goods or services. Payment may take longer if invoice is not properly documented or not easily identifiable, goods/services are not acceptable, or invoice is in dispute.
40. FINAL CONTRACT DOCUMENTS: If a formal contract is required as a result of the Request for Bid; the final contract shall include the following: 1) The RFB; 2) Addenda; 3) Awarded Vendors(s) Bid response; 4) Awarded Vendor(s) Clarifications; and 5) Awarded Vendor(s) Business Requirements.
NOTICE TO VENDORS
Sec. 2-3.05. - Submitting bids to Consolidated Government, etc.—By mayor or councilmembers.
Neither the mayor nor any member of the Columbus Council shall submit any bid to the consolidated government, nor shall the mayor or any member of the Columbus Council own or have a substantial pecuniary interest in any business that submits a bid to the consolidated government. (Ord. No. 92-60, 6-23-92)
Sec. 2-3.06. - Same—By members of boards, authorities, commissions.
No member of any board or authority or commission or other independent or subordinate entity of the consolidated government shall submit any bid to the consolidated government or have a substantial pecuniary interest in any business that submits a bid to the consolidated government if such bid pertains to the board or authority or commission on which such person holds such membership. (Ord. No. 92-61, 6-23-92)
RFB No. 27-0007 PROTECTIVE FIRE CLOTHING AND ACCESSORIES (ANNUAL CONTRACT) Page 8 of 57
DO YOU HAVE QUESTIONS, CONCERNS OR NEED
CLARIFICATION ABOUT THIS SOLICITATION?
COMMUNICATION CONCERNING ANY SOLICITATION CURRENTLY
ADVERTISED MUST TAKE PLACE IN WRITTEN FORM AND ADDRESSED TO
THE PURCHASING DIVISION.
ALL QUESTIONS OR CLARIFICATIONS CONCERNING THIS SOLICITATION
SHALL BE SUBMITTED IN WRITING. THE CITY WILL NOT ORALLY OR
TELEPHONICALLY ADDRESS ANY QUESTION OR CLARIFICATION
REGARDING BID/PROPOSAL SPECIFICATIONS. IF A VENDOR VISITS OR CALLS
THE PURCHASING DIVISION WITH SUCH QUESTIONS, HE OR SHE WILL BE
INSTRUCTED TO SUBMIT THE QUESTIONS IN WRITING.
ALL CONTACT CONCERNING THIS SOLICITATION SHALL BE MADE
THROUGH THE PURCHASING DIVISION. BIDDERS SHALL NOT CONTACT
CITY EMPLOYEES, DEPARTMENT HEADS, USING AGENCIES, EVALUATION
COMMITTEE MEMBERS OR ELECTED OFFICIALS WITH QUESTIONS OR ANY
OTHER CONCERNS ABOUT THE SOLICITATION. QUESTIONS,
CLARIFICATIONS, OR CONCERNS SHALL BE SUBMITTED TO THE
PURCHASING DIVISION IN WRITING. IF IT IS NECESSARY THAT A TECHNICAL
QUESTION NEEDS ADDRESSING, THE PURCHASING DIVISION WILL FORWARD
SUCH TO THE USING AGENCY, WHO WILL SUBMIT A WRITTEN RESPONSE.
THE PURCHASING DIVISION WILL FORWARD WRITTEN RESPONSES TO THE
RESPECTIVE BIDDER OR IF IT BECOMES NECESSARY TO REVISE ANY PART OF
THIS SOLICITATION, A WRITTEN ADDENDUM WILL BE ISSUED TO ALL
BIDDERS.
THE CITY IS NOT BOUND BY ANY ORAL REPRESENTATIONS,
CLARIFICATIONS, OR CHANGES MADE TO THE WRITTEN SPECIFICATIONS BY
CITY EMPLOYEES, UNLESS SUCH CLARIFICATION OR CHANGE IS PROVIDED
TO THE BIDDERS IN A WRITTEN ADDENDUM FROM THE PURCHASING
MANAGER.
BIDDERS ARE INSTRUCTED TO USE THE ENCLOSED
“QUESTION/CLARIFICATION FORM” TO FAX OR EMAIL QUESTION.
ANY REQUEST, AFTER A SOLICITATION HAS CLOSED AND PENDING AWARD
MUST ALSO BE SUBMITTED IN WRITING TO THE PURCHASING DIVISION.
RFB No. 27-0007 PROTECTIVE FIRE CLOTHING AND ACCESSORIES (ANNUAL CONTRACT) Page 9 of 57
QUESTION/CLARIFICATION FORM
DATE:
TO: Ryky Decembre, Buyer Email: BidOpportunities@columbusga.org
RE: Protective Fire Clothing & Accessories; RFB No. 27-0007
(Questions/clarification requests must be submitted at least five (5) business days before the due date.)
From: __________________________________
Company Name Website
Representative Email Address
Complete Address City State Zip
Telephone Number
RFB 27-0007 PROTECTIVE FIRE CLOTHING AND ACCESSORIES (ANNUAL CONTRACT) Page 10 of 57
GENERAL SPECIFICATIONS
PROTECTIVE FIRE CLOTHING AND ACCESSORIES
(ANNUAL CONTRACT); RFB NO. 27-0007
I. SCOPE
These specifications describe minimum requirements for Protective Fire Clothing and Accessories for firefighters. The Fire Department will purchase approximately 30 sets of clothing on an “as needed” basis. The quantities specified are based on an estimated usage. The City may purchase some, all, more or none of the items. ALL PROTECTIVE CLOTHING AND ACCESSORIES MUST MEET NFPA STANDARDS. The City reserves the right to add additional related items during the term of the contract.
Primary and Secondary Contractors will be selected based on the two lowest responsive, responsible vendors, who best meet the specifications. The City will be the judge of the factors and will make the award accordingly. The Primary Contractor will be contacted first. If the Primary Contractor is unable to provide the required vehicle(s), then the City will contact the Secondary Contractor to render the needed services.
See Technical Specifications on Page 14-31.
II. TERM OF CONTRACT
A. The term of contract shall be for two (2) years, with the option to renew for three (3) additional twelve-month periods. Contract renewal will be contingent upon the mutual agreement of the City and the Contractor.
Notice of intent to renew will be given to the contractor in writing by the Purchasing Division Director, normally sixty days before the expiration date of the current contract. This notice shall not be deemed to commit the City to a Contract renewal.
It should be noted that multi-year contracts may be continued each fiscal year only after funding appropriations and programs approval has been granted by the Council of the Consolidated Government of Columbus, Georgia. In the event that the necessary funding is not approved, then the affected multi-year contract becomes null and void, effective July 1st of the fiscal year for which such approval has been denied.
B. Termination for Convenience
For the protection of both parties, either party giving 30 days prior notice in writing to the other party may cancel this contract.
III. ESCALATION CLAUSE
Contract pricing shall remain fixed for the initial two (2) year term of the contract. After the initial term, Contractor may request a price escalation by submitting a fully documented request (i.e.
documentation from manufacturers illustrating the necessity to implement price increases).
Request for price increases, without documentation, shall not be considered. Such escalation shall not exceed a five percent (5%) increase. The using department(s) and the
RFB 27-0007 PROTECTIVE FIRE CLOTHING AND ACCESSORIES (ANNUAL CONTRACT) Page 11 of 57
Purchasing Manager will review the request and shall approve or disapprove the increases based on budget constraints and other price comparisons.
If for any reason the contractor has a price increase that exceeds five percent (5%), the price increase will be evaluated on a case-by-case basis. The City and the Contractor will have the option to discuss and make adjustments to the requested increase. If either party declines approval of the adjustments, the contract will be considered cancelled on the scheduled expiration date of the contract.
IV. BRAND NAMES
It is not the intent of Columbus Consolidated Government (City) to restrict competition in any purchasing process. However, due to the fire protective clothing and accessories already in use by the Fire Department and to remain compatible, it is requested that bid proposals be submitted only for the brand name given in the specifications for “Protective Fire Clothing and Accessories”.
V. QUESTIONS/ADDENDA
Questions and requests for clarification must be submitted within five (5) business days of the due date (see pages 8 & 9). Changes to the specifications (if any) will be provided in the form of an addendum, which will be posted on the web page of the Finance Department/Purchasing Division of Columbus Consolidated Government at https://columbusga.gov/finance/bid-opportunities. It is the vendors’ responsibility to periodically visit the web page for addenda before the due date and prior to submitting a quote.
VI. INDEMNITY CLAUSE
The Contractor covenants to save, defend, hold harmless, and indemnify the City, and all of its officers, departments, agencies, agents, and employees (collectively the "City") from and against any and all claims, losses, damages, injuries, fines, penalties, costs (including court costs and attorney’s fees), charges, liability, or exposure, however caused, resulting from, arising out of, or in any way connected with the Contractor’s intentional, negligent, or grossly negligent acts or omissions in performance or nonperformance of its work called for by the Contract Documents.
VII. BID SUBMISSION REQUIREMENTS
See Appendix A for Submission Requirements, Submission Requirements Checklist, and DemandStar Registration and Submission Instructions.
Each bidder shall include the following information with bid submission. Bidder shall submit ONE (1) ELECTRONIC BID RESPONSE VIA DEMANDSTAR. Submissions will be deemed incomplete/non-responsive if the following required documents are not included, as prescribed within the specifications: E-Verify Affidavit, Conflict of Interest Affidavit, and Communication Concerning This Solicitation form. However, the City reserves the right to request any other omitted information, WHICH DOES NOT AFFECT THE SUBMITTED BID PRICE. Bidders shall be notified, in writing, and shall have two (2) days, after notification to submit the omitted information. If the omitted information is not received within two (2) days, the Bidder shall be deemed non-responsive and the Bid Submission will be deemed “Incomplete”:
https://columbusga.gov/finance/bid-opportunities https://columbusga.gov/finance/bid-opportunities
RFB 27-0007 PROTECTIVE FIRE CLOTHING AND ACCESSORIES (ANNUAL CONTRACT) Page 12 of 57
A. Bid Form (Form 1) B. Detailed Technical Specifications (Pages 14-31) C. Pricing Form (Form 2) D. Communication Concerning This Solicitation (Form 3) This page must be included in bid submission.
E. Conflict of Interest Affidavit (Form 4) This page must be included in bid submission.
F. Federal Compliance (Form 5) G. Manufacturer Warranty H. Product Literature / Specifications I. Addenda Acknowledgement Page (Form 6) Vendors must include acknowledgment of receipt of addenda (if any) in their sealed bid. Provide an initialed copy of each addendum or initial the appropriate area on bid form (pricing page). Addenda will be posted at https://columbusga.gov/finance/bid-opportunities. Vendors are responsible for periodically visiting the web page, to check for addenda, prior to the bid due date and before submitting a bid.
J. Contract Signature Page (Form 8) K. Business License: Vendors located in Muscogee County shall submit a current copy of their City of Columbus Business License (Occupation License). If the business is not located in Muscogee County and has proof of being properly licensed by a municipality in Georgia, and paid applicable occupation taxes in that city, the vendor will not be required to pay occupation taxes in Columbus, Georgia.
If the business location is not in Georgia, vendor must provide a current copy of their active Articles of Incorporation from the State and/or a current business license from the City/State in which business is located.
If you have questions regarding this requirement, please contact the Revenue Division at 706-225-3780.
L. Form W-9 Complete and return Page 1 of Form W-9 (https://www.irs.gov/pub/irs-pdf/fw9.pdf Form revised March 2024
VIII. AWARD/ORDERING/DELIVERING/INVOICE
A. Award: This bid will be awarded to a Primary and a Secondary Contractor. The Primary and Secondary Contractors will be selected based on the two lowest responsive, responsible vendors, who best meet the specifications. The Consolidated Government of Columbus The (City) shall be the judge of the factors and will make the award in the best interest of the City.
Should the successful bidder not be able to supply the required item(s), the City reserves the right to purchase from other sources. The City reserves the right to reject any/or all bids. After award of this bid, the successful vendors will be required to sign a contract for the project.
B. Ordering: The items will be procured on an “as needed” basis by phone, email, purchase orders, or the vendor’s website. It is the Vendor’s responsibility to notify the City, at the time an order is placed, if delivery cannot be met in the specified time.
C. Delivery: Deliveries shall be made to the applicable address indicated on the purchase order.
It will be the responsibility of the Vendor to deliver orders as specified to the address shown on the purchase orders. Inability to make delivery within specified time will authorize the City to purchase from other sources that meet specifications.
All shipping, delivery, and/or freight charges must be included in the unit cost. The Columbus Consolidated Government will pay no additional shipping, delivery, freight charges, and/or any additional add-on fees.
https://columbusga.gov/finance/bid-opportunities https://www.irs.gov/pub/irs-pdf/fw9.pdf https://www.irs.gov/pub/irs-pdf/fw9.pdf
RFB 27-0007 PROTECTIVE FIRE CLOTHING AND ACCESSORIES (ANNUAL CONTRACT) Page 13 of 57
D. Invoices: After receipt of goods/services and upon satisfactory delivery, the successful vendor shall forward itemized invoice(s) to the following address:
Columbus Consolidated Government Accounting Division – Accounts Payable P. O. Box 1340 Columbus, Georgia 31902-1340
The invoice(s) shall reference the bid number (RFB No. 27-0007) and/or purchase order number.
IX. TERMINATION OF CONTRACT
A. Default: If the contractor refuses or fails to perform any of the provision of this contract with such diligence as will ensure its completion within the time specified in this contract, or any extension thereof, otherwise fails to timely satisfy the contract provisions, or commits any other substantial breach of this contract, the Purchasing Division Director may notify the contractor in writing of the delay or non-performance and if not cured within ten (10) days or any longer time specified in writing by the Purchasing Division Director, such director may terminate the contractor's right to proceed with the contract or such part of the contract as to which there has been delay or a failure to properly perform.
In the event of termination in whole or in -part the Purchasing Division Director may procure similar supplies or services, from other sources, in a manner and upon terms deeded appropriate by the Purchasing Division Director. The contractor shall continue performance of the contract to the extent it is not terminated and shall be liable for excess costs incurred in procuring similar goods or services.
B. Compensation: Payment for completed supplies delivered and accepted by the City shall be at the contract price. The City may withhold from amounts due the contractor such sums as the Purchasing Division Director deem necessary to protect the City against loss because of outstanding liens or claims of former lien holders and to reimburse the City for the excess costs incurred in procuring similar goods and services.
C. Excuses for Nonperformance or Delayed Performances: Except with respect to defaults of subcontractors, the contractor shall not be in default by reason of any failure in performance of this contract in accordance with its terms, if the contractor has notified the Purchasing Division Director within 15 days after the cause of the delay and the failure arises out of causes such as: acts of God; acts of public enemy; acts of the City and any other governmental entity in its sovereign or contractual capacity; fires;
floods; epidemics; quarantine restrictions; strikes or other labor disputes; freight embargoes; or unusually severe weather. If the failure to perform is caused by the failure of a subcontractor to perform or to make progress, and if such failure arises out of causes similar to those set forth above, the contractor shall not be deeded in default, unless the supplies or services to be furnished by the subcontractor were reasonably obtainable from other sources in sufficient time to permit the contractor to meet the contract requirements.
Upon request of the contractor, the Purchasing Division Director shall ascertain the facts and extent of such failure, and, if such director determines that any failure to perform was occasioned by any one or more of the excusable causes, and that, but for the excusable cause, the contractor's progress and performance would have met the terms of the contact, the delivery schedule shall be revised accordingly.
RFB 27-0007 PROTECTIVE FIRE CLOTHING AND ACCESSORIES (ANNUAL CONTRACT) Page 14 of 57
DETAILED TECHNICAL SPECIFICATIONS
PROTECTIVE FIRE CLOTHING AND ACCESSORIES
(ANNUAL CONTRACT); RFB NO. 27-0007
Procurement intent These requirements define the City’s minimum safety, performance, fit, interface, durability, documentation, and training needs without requiring a particular manufacturer, model, material trade name, construction patent, distributor, or certification organization. Equivalent designs are acceptable when the bidder demonstrates equal or better performance and full compliance with the applicable current NFPA requirements.
1. SCOPE
1.1 Intended Use
The protective clothing and accessories shall be designed and certified for structural firefighting operations where personnel may be exposed to flame, heat, physical hazards, liquids, and other hazards addressed by the applicable standard. The equipment may also be used during rescue operations, emergency medical operations, victim extrication, and related emergency-response duties within the limitations stated by the manufacturer and the applicable certification.
The solicitation may include structural firefighting coats, pants, suspenders, protective hoods, structural firefighting gloves, and associated options. Each item shall be new, unused, current production, and supplied in the sizes and configurations ordered by the City.
BIDDER RESPONSE: YES [ ] NO [ ] EXCEPTION [ ] PROPOSAL PAGE / COMMENTS: ___________________________________
1.2 Complete and Compatible System
Coats, pants, hoods, gloves, suspenders, and ordered accessories shall be mutually compatible with the City’s structural firefighting ensemble, including helmets, SCBA facepieces and harnesses, footwear, communications equipment, and other normally worn equipment. Interfaces shall maintain required overlap and shall not create avoidable gaps, pressure points, entanglement hazards, or restrictions to normal movement.
BIDDER RESPONSE: YES [ ] NO [ ] EXCEPTION [ ] PROPOSAL PAGE / COMMENTS: ___________________________________
2. BRAND-NEUTRAL AND EQUIVALENCY REQUIREMENTS
2.1 No Brand or Model Requirement
No manufacturer, distributor, product family, model number, proprietary fabric, membrane, coating, thread, trim, closure system, training platform, or certification mark is required by these specifications. Any manufacturer’s product that satisfies every mandatory requirement is eligible for consideration.
BIDDER RESPONSE: YES [ ] NO [ ] EXCEPTION [ ] PROPOSAL PAGE / COMMENTS: _________________________________
2.2 Equivalent Designs
Dimensions and construction descriptions are intended to communicate the required form, fit, function, coverage, interface, and operational capacity. A bidder may offer an alternative construction, geometry, attachment method, or material system when the finished product is certified to the applicable current standard and the bidder provides objective documentation showing that the alternative provides equal or better safety, durability, mobility, and function.
RFB 27-0007 PROTECTIVE FIRE CLOTHING AND ACCESSORIES (ANNUAL CONTRACT) Page 15 of 57
The bidder shall identify every exception or alternative in a separate exceptions schedule. Silence shall be interpreted as full compliance. Product literature alone does not replace a written response to these specifications.
BIDDER RESPONSE: YES [ ] NO [ ] EXCEPTION [ ] PROPOSAL PAGE / COMMENTS: _________________________________
2.3 Configuration Control and Substitutions
The manufacturer, model, material package, options, and certification configuration offered shall be clearly identified. After award, no material, component, certification configuration, model, or manufacturing location that could affect compliance or performance may be substituted without advance written approval from the City and supporting current certification documentation.
BIDDER RESPONSE: YES [ ] NO [ ] EXCEPTION [ ] PROPOSAL PAGE / COMMENTS: _________________________________
3. APPLICABLE STANDARDS AND CERTIFICATION
Current-edition requirement “Current edition” means the latest edition published and effective on the bid due date, together with all effective Tentative Interim Amendments (TIAs), errata, and formally issued corrections. When an NFPA document has been consolidated, renumbered, or superseded, the current successor document shall govern.
Edition numbers shown below are the editions current when this revision was prepared and do not limit the City to an obsolete edition.
3.1 NFPA Standards
At the time of this revision, the principal applicable standards are NFPA 1970, 2025 edition, for structural firefighting…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .