RFB 216 ADDENDUM 1.pdf
PDF 963 KB Posted
- Attached to
- STANTON PARK REHABILITATION PHASE I & II
- Solicitation number
- S-C00100-00010883
- Issued by
- Douglas County, Canyonville City, Oregon
About this file
This document is an addendum to a Request for Bids (RFB) for the Stanton Park Rehabilitation Phase I & II project in Douglas County, Oregon. The addendum is issued by the Douglas County Parks Department to correct and clarify items in the original bid documents. Key changes include quantity adjustments to certain bid items, the addition of a new bid item, and revisions to various plan sheets. The bid submittal deadline remains unchanged. The project involves the rehabilitation of Stanton Park, including work on the sanitary sewer system, storm drainage, paving, and construction of new buildings and amenities. Bidders are instructed to use the revised bid schedule provided in the addendum and acknowledge receipt of the addendum on their bid forms.
The addendum also provides clarification on archaeological monitoring requirements and the designated waste disposal area for the project. Contractors are encouraged to consolidate excavation work to minimize the time an archaeologist needs to be on-site. Waste material may be hauled to the Herberts Pond area, with separate storage for aggregates, soil, and woody biomass. Overall, this addendum serves to update and clarify the bid documents for the Stanton Park Rehabilitation Phase I & II project in Douglas County, Oregon.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DOUGLAS COUNTY PARKS DEPARTMENT
RFB #216: STANTON PARK REHABILITATION PHASE I & II
ADDENDUM #1
Issued July 24, 2024
This addendum is issued to correct a number of items on the bid documents.
1.0 NOTICE TO ALL BIDDERS AND PLAN\HOLDERS
The Contract Documents for the above-referenced Project are modified as set forth in this Addendum. The original Contract Documents and any previously issued addenda remain in full force and effect, except as modified by this Addendum, which is hereby made part of the Contract Documents. Bidder shall take this Addendum into consideration when preparing and submitting a bid and shall acknowledge receipt of this Addendum in the space provided on the Bid Form.
2.0 BID SUBMITTAL DEADLINE
The bid submittal deadline remains the same and is not changed by this Addendum.
3.0 PROJECT BID BOOKLET
The following changes are made to the Project Bid Booklet:
1. The following changes are made to the Project Bid Items:
a. Quantity changes:
Quantity
Number Item Original New
25 3,000 GALLON SEPTIC TANK 3 2
b. Added items changes:
Number Item Unit Quantity
54 1,000 GALLON SEPTIC TANK EACH 1
Make a copy of and use the new attached Bid Schedule. A Bid not including this new Bid Schedule will be rejected as non-responsive.
3.0 PROJECT PLANS
The following changes are made to the Project Plans:
The following is a summary of revisions made to the plan sheets. Changes made have revision clouds.
Some minor changes such as adjustments to leader and number key locations are not noted.
1. Plan Sheet C.1
a. The sheet index has been updated with correct sheet numbering
b. General Notes:
i. Date updated in note 2.
ii. Staking responsibility updated in note 5. All staking is the responsibility of the Contractor.
c. Code references for dates and jurisdictions have been updated in the General Sanitary Sewer Notes.
d. Code references for dates and jurisdictions have been updated in the General Water Notes.
2. Plan Sheet C.2
a. Keyed Construction Note 4 text has been revised. The play structure is not to be removed. The structure and curbing shall be protected.
b. Utility poles were incorrectly numbered and have been updated.
c. The restroom was incorrectly number and has been updated.
3. Plan Sheet C.3
a. Keyed Construction Note 9 has been revised. The play structure is not to be removed.
b. Keyed Construction Note 15 has been revised. Correct pole size is 20’ long 4”x4”.
c. Sidewalk in front of the play structure has been modified.
4. Plan Sheet C.4
a. Grading has been revised in front of the play structure.
b. Concrete hatching has been removed from within the footprint of the restroom. No concrete pad is required below the restroom.
5. Plan Sheet C.5
a. Inverts and pipe lengths have been updated.
b. Keyed Construction Note 1 change to correct pipe size.
c. Keyed Construction Note 27 removed a bend not needed.
d. Keyed Construction Note 37 was revised to reference removal of the dump station.
e. Detail references were corrected for 29, 31, and 33.
f. Keyed Construction Note 43 pipe size corrected.
g. Keyed Construction Note 44 revised.
h. All septic tank inverts and rims were adjusted.
6. Plan Sheet SD.1
a. Wheel stop detail text updated for curb stop lengths.
7. Plan Sheet SD.2
a. Riser diameter for both septic tank details have been revised to 30” diameter for all risers based on the proposed tank depth.
8. Plan Sheet SD.3
a. WIFI Pole detail has been revised. The correct pole size is to be a minimum of a 4”x4”x20’ pressure treated timber.
9. Plan Sheet SD.4
a. No revisions.
5.0 CLARIFICATIONS
The following are provided as a matter of information to clarify issues raised or questions about the Contract Documents. To the extent that changes to the Contract Documents are required based on the questions received, the Contract Documents have been modified as noted above in the Project Bid Booklet and Project Plans sections of this Addendum.
6.0 ARCHAEOLOGICAL MONITORING
An Archaeologist is required onsite to monitor all initial excavation work. The County will hire and pay for the Archaeologist. County requests that the Contractor try and condense the required excavation work so as to minimize the time an Archeologist needs to be onsite.
7.0 WASTE MATERIAL
Waste material may be hauled to the designated waste area known as Herberts Pond located on the Tiller Trail Highway approximately 2.9 miles from the project. Waste material, including aggregate, soil, and woody biomass must be stored separately. Woody biomass should be piled for burning and other debris should be consolidated to minimize the area required to store it.
Contractor is free to haul the aggregate waste elsewhere if desired.
RFB #216 BID FORM (REVISED 07/24/2024)
Bid Item #
Item Description
UOM
Quantity
Unit Cost
Total Cost
MOBILIZATION
LS
EROSION CONTROL
TEMPORARY MULCHING, COMPOST
SQ YD
CONSTRUCTION ENTRANCE, TYPE 1
EACH
CONCRETE WASHOUT FACILITY
SEDIMENT FENCE
FOOT
INLET PROTECTION, TYPE 3
DECOMMISSION SEPTIC SYSTEM
CONSTRUCTION SURVEY WORK
REMOVAL OF STRUCTURES AND OBSTRUCTIONS
REMOVAL OF RESTROOM
CLEARING AND GRUBBING
GENERAL EARTHWORK
INTEGRATED GEOTEXTILE GEOGRID
SQYD
10,000
4 INCH SANITARY SEWER PIPE
2 INCH PRESSURE SANITARY SEWER PIPE
3 INCH IRRIGATION SLEEVES
3" RV CONNECTION
MAINLINE CLEANOUT
CARBON FILTER CLEANOUT
6 INCH STORM SEWER PIPE
8 INCH STORM SEWER PIPE
CONCRETE INLETS, TYPE G-2
8" INLINE DUCTILE IRON GRATE AND 6" ADAPTER
3,000 GALLON CONCRETE SEPTIC TANK
PUMP SYSTEM
CONTROL PANEL
CONNECTION TO EXISTING STRUCTURES
CONNECT TO EXISTING GRAVITY SEWER LATERAL
CONNECT TO EXISTING PRESSURE SEWER LATERAL
AGGREGATE BASE
TON
LEVEL 2, 1/2" DENSE GRADED HMAC
TON
STANDARD CURB
VALLEY GUTTER
CONCRETE WALKS AND PADS
SQFT
10500
Signature Date
Print Name and Title
Note: Douglas County requires Contractors to provide their Federal Employer Identification number (FEIN) or Social Security Number (SSN) prior to contract signing
PRECAST WHEEL STOP
BOLLARDS
LONGITUDINAL PAVEMENT MARKINGS - PAINT
PAVEMENT LEGEND, TYPE ADA PARKING
SIGNAGE w/ BASE, POLE, R7-8 and R7-8a SIGNS
3 INCH POTABLE WATER PIPE, FITTINGS AND COUPLINGS
2 INCH POTABLE WATER PIPE, FITTINGS AND COUPLINGS
1.5" INCH POTABLE WATER PIPE, FITTINGS AND COUPLINGS
44 3 INCH WATER CONNECTION TO EXISTING CHECK VALVE ASSEMBLY EACH 1 $ $
2 INCH WATER CONNECTION TO WATERLINE FOR LOWER RV PARK
46 3/4" WATER SERVICES AND CHECK VALVE EACH 26 $ $
47 1.5" WATER SERVICE WITH SHUTOFF VALVE AND CHECK VALVE EACH 2 $ $
2" WATER SERVICE WITH SHUTOFF VALVE AND CHECK VALVE TO
RESTROOM
49 CHEYENNE BUILDING, COMPLETE EACH 1 $ $
50 CORTEZ BUILDING, COMPLETE EACH 1 $ $
51 PAD MOUNTED POWER AND WATER RV PEDESTAL EACH 26 $ $
52 FIRE PITS EACH 26 $ $
53 COMPLETE ELECTRICAL SYSTEM, SHEETS E1, E2, E3 LS 1 $ $
54 1,000 GALLON CONCRETE SEPTIC TANK EACH 1 $ $
Total Bid $
This addendum can be found at: https://douglascounty-oregon.us/Bids.aspx
BIDDERS SHALL ACKNOWLEDGE RECEIPT OF T HIS ADDENDUM BY SIGNING BELOW
AND RETURNING THIS DOCUMENT ALONG WIT H T HE BID. FAILURE T O
ACKNOWLEDGE RECEIPT OF THIS ADDENDUM MAY RESULT IN BID REJECT ION.
Authorized Signature
Bidder Name
Date
File details come from the government source that posted it. Updated .